CN107387006A CN201710532686.2A CN201710532686A CN107387006A CN 107387006 A CN107387006 A CN 107387006A CN 201710532686 A CN201710532686 A CN 201710532686A CN 107387006 A CN107387006 A CN 107387006A
Authority
CN
China
Prior art keywords
hanger
running tool
giving
boss
central tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710532686.2A
Other languages
Chinese (zh)
Other versions
CN107387006B (en
Inventor
王玥
张恒
陈世春
徐学军
杨文领
张镇
刘洋
于学良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Petroleum Corp
CNPC Bohai Drilling Engineering Co Ltd
Original Assignee
CNPC Bohai Drilling Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CNPC Bohai Drilling Engineering Co Ltd filed Critical CNPC Bohai Drilling Engineering Co Ltd
Priority to CN201710532686.2A priority Critical patent/CN107387006B/en
Publication of CN107387006A publication Critical patent/CN107387006A/en
Application granted granted Critical
Publication of CN107387006B publication Critical patent/CN107387006B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B23/00Apparatus for displacing, setting, locking, releasing or removing tools, packers or the like in boreholes or wells
    • E21B23/08Introducing or running tools by fluid pressure, e.g. through-the-flow-line tool systems
    • E21B23/10Tools specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/12Packers; Plugs
    • E21B33/127Packers; Plugs with inflatable sleeve
    • E21B33/1277Packers; Plugs with inflatable sleeve characterised by the construction or fixation of the sleeve
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/10Sealing or packing boreholes or wells in the borehole
    • E21B33/12Packers; Plugs
    • E21B33/129Packers; Plugs with mechanical slips for hooking into the casing
    • E21B33/1295Packers; Plugs with mechanical slips for hooking into the casing actuated by fluid pressure

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Infusion, Injection, And Reservoir Apparatuses (AREA)

Abstract

The invention discloses a kind of running tool and the large diameter hanger of the running tool is installed;The setting hydraulic pressure actuating system of running tool integrated installation hanger, it can realize that hydraulic pressure, machinery are double and give up;Running tool is linked together with hanger body by left-hand thread, it has been fully integrated into due to setting with function of giving up on running tool, hanger body only retains suspension sealing system and deblocking system, so that hanger body structure more simplify it is compact, to obtain bigger latus rectum, instrument is allowed to meet the requirement of expandable screen completion and other various completion practices.The hanger, which also has, simultaneously can salvage function, and it is provided with the fishing tool of hook by bottom, using machine driving, realize and salvage.

Description

Running tool and the large diameter hanger for being provided with the running tool
Technical field
The present invention relates to completion practice field of tool, specially a kind of running tool and the big logical of the running tool is installed Footpath hanger.
Background technology
For current existing hydraulic setting hanger mostly by design of Hydraulic System on hanger body, hanger body is empty Between it is limited, along with the structure of complexity, easily gone wrong in use, and excessively complicated structure has a strong impact on that hanger leads to Footpath, conventional hanger can not be competent at as expandable screen or expansion tube completion need later stage tripping in large scale it is swollen cone it is expanding Completion construction, small latus rectum returns later stage operation and brings Risks.
The content of the invention
In order to solve the above-mentioned technical problem, the present invention provides a kind of running tool and is provided with the big orifice of the running tool Hanger, the running tool are provided directly with hydraulic tool, do not interfere with the diameter of hanger, and the big orifice that meets the requirements uses ring The requirement in border, and matched hanger is additional can salvage function, is provided convenience for subsequent job, adds instrument The scope of application.
Therefore, technical scheme is as follows:
A kind of running tool, including running tool central tube, piston, top connection, fluid cylinder, power transmission set, promotion set, control lock Block, control set, limitation closing piece, non-return ring, helmet, stop collar of giving up, block set of giving up, give up block and ball seat;
The inner surface of the top connection bottom is connected with running tool basepipe seal, and outer surface is tightly connected with fluid cylinder; The outer tube wall of the running tool central tube is provided with first boss, and the first boss is located at the lower edge of fluid cylinder;The liquid Formed with the first cavity between cylinder and running tool central tube;The piston seal is arranged in first cavity, and it is divided into Put power transmission set;There is space between the top of the piston and top connection, corresponding to the space on the tube wall of running tool central tube It is provided with multiple through holes;The downside of the piston is formed with boss, and when at descent of piston to first boss, the boss is stuck in Prevent piston from continuing traveling downwardly at the first boss, now, gap is formed between the outer wall of the piston and fluid cylinder bottom;
Power transmission set is from top to bottom divided into three sections according to internal diameter difference, epimere internal diameter is minimum, and stage casing internal diameter is maximum;Institute The first paragraph for stating power transmission set is fixed in the first boss by the first shear pin;It is described to promote set to be fixed on by the second shear pin The outside of the power transmission set;
The power transmission set is fixed on the running tool central tube by the first shear pin;What first shear pin can be born Power is less than the power that the second shear pin can be born;
Described to control set be tubular, formed with second boss on the downside of it;The control set top is by controlling closing piece to be stuck in Between the first boss and the 3rd section of power transmission set;First boss correspondingly controls the installed position of closing piece to set groove, should The depth of groove is less than power transmission set second segment and the 3rd section of semidiameter;Limit unilateral, the opposite side tangent with first boss of closing piece Protrude second boss;During the control set slide downward, control closing piece slides from first boss, and it protrudes the portion of second boss Divide and submerge in second boss;
The ball seat is screwed onto the bottom of running tool central tube;Block set of giving up is screwed onto on ball seat;Give up block, leaf spring peace In block set of giving up;The outer surface of the block of giving up is provided with left-hand thread screw thread;Stop collar of giving up is arranged at running tool center Between block of managing and give up set, and give up stop collar and block set of giving up are fixed by the 3rd shear pin;The stop collar top spiral shell of giving up It is connected to helmet;Installation non-return ring inside the helmet, the inwall of non-return ring is provided with gingival cyst of mucous gland in the newborn button, corresponding, at running tool center Corresponding position in pipe outer wall is provided with the structure to match with the gingival cyst of mucous gland in the newborn button, and the stop collar that can prevent from giving up moves up;
Described give up is additionally provided with sealing device between block set and ball seat;
The vertical section of the block of giving up is the concave being rotated by 90 °, its projecting surface inwardly, the stop collar of giving up it is outer Surface is provided with the groove I to match with the block of giving up;When the stop collar of giving up is descending, block of giving up can be caught in groove I.
A kind of large diameter hanger for being provided with as above running tool, including:Hanger central tube, setting set, packing element set, Packing element, adapter sleeve, packing element cap bag, upper cone, spacing ring, tub slips, lower cone, salvaging adapter sleeve and lower contact;
Left-hand thread internal thread is set at the top of the hanger central tube, with the left-hand thread screw thread given up set by the outer surface of block Match;Be provided with from top to bottom on the outer wall of the hanger central tube packing element set, adapter sleeve, upper cone, tub slips, under Cone, salvage adapter sleeve and lower contact;The upper end for salvaging adapter sleeve is screwed onto the tail end of lower cone, lower end and lower contact spiral shell Connect;
The packing element set top is connected by shear pin and setting set;Packing element set end installation packing element cap bag;The packing element set Cap is made up of two cylinders of different-diameter, and one section of major diameter is enclosed on the packing element and put, one section of minor diameter and hanger center Manage tangent;The packing element cap bag is arranged on the inside of the adapter sleeve, and both are connected by the 4th shear pin;The packing element is arranged on glue On jacket casing;
The top of the setting set promotes the outside of set positioned at described, and can block formed with step, the step on its inwall On the control closing piece for protruding the control set second boss;
Lock ring is installed, lock ring is provided with mutual with hanger central tube tube wall between the hanger central tube and setting set The gingival cyst of mucous gland in the newborn button of matching, can prevent packing element set from moving up;
The spacing ring is arranged between the upper cone and hanger central tube, the inwall of spacing ring and hanger center The outer wall of pipe is provided with the gingival cyst of mucous gland in the newborn button being mutually matched, for preventing upper cone from moving up;
The both ends of the tub slips are connected with upper cone, lower cone by the 5th shear pin respectively.
Further, it is provided with screw thread claw between the hanger central tube and salvaging adapter sleeve;The screw thread claw with Adapter sleeve is salvaged to be spirally connected;The hanger central tube is arranged with salvaging stop collar;The salvaging stop collar is tubular, wherein The internal diameter in portion is more than the internal diameter at both ends;The inner surface of the lower contact rides over formed with step, the tail end for salvaging stop collar The upper end of the lower contact, salvaging stop collar can slide along the inner surface of lower contact, and slide downward can be by the platform of lower contact Rank prevents;The salvaging stop collar is fixed on by shear pin to be salvaged on adapter sleeve;The tail end of the screw thread claw rides over salvaging limit Position is put.
Further, the power that the 4th shear pin can bear is more than the power that the 5th shear pin can bear.
Further, the power that the power that the second shear pin can bear is more than the 4th shear pin, the 5th shear pin can bear.
The running tool and the large diameter hanger of the running tool is installed had the following advantages that:
1) hydraulic pressure power transmission, it is double to give up, it is integrated in anti-extension defencive function of sitting on running tool, so as to so that hanger master Body structure more concision and compact, the interior latus rectum of hanger meet that expandable screen and other completions are made than conventional hanger increase 20% Industry construction requirement;
2) it is easy to operate, it is possible to achieve to bore for one time to sit and hang, set, testing envelope and give up etc. and operate;
3) suspension and packing function integration, are designed with the tub slips of packing element, Bidirectional cone and elastic dilatation, meet each The needs of kind operation;
4) it is designed with that hydraulic pressure, back-off are double to give up, hanger is all can be used under the hole condition of 0-90 ° of hole angle;
5) the anti-seat for being designed with closing piece control hangs system, and avoiding instrument, use is safer because mechanical external force sits extension in advance;
6) salvaging function is designed with, is easy to later stage operation, applicability is wider, and this hanger is complete in expandable screen or expansion tube The application of well field is optimal, additionally can be used for the suspension liner completion operation of straight well, inclined shaft, horizontal well, extended reach well.
Brief description of the drawings
Fig. 1 is the semi-cutaway of running tool;
Fig. 1 a are the enlarged drawing of Fig. 1 top halfs;
Fig. 1 b are the enlarged drawing of Fig. 1 the latter half;
Fig. 2 is the semi-cutaway of large diameter hanger;
Fig. 2 a are the enlarged drawing of Fig. 2 top halfs;
Fig. 2 b are the enlarged drawing of Fig. 2 the latter half;
Fig. 3 a are the semi-cutaway for being provided with the large diameter hanger of running tool first paragraph from top to bottom;
Fig. 3 b are the semi-cutaway for being provided with the large diameter hanger of running tool second segment from top to bottom;
Fig. 3 c are to be provided with the large diameter hanger of running tool the 3rd section of semi-cutaway from top to bottom;
Fig. 3 d are to be provided with the large diameter hanger of running tool the 4th section of semi-cutaway from top to bottom;
Fig. 3 e are the A-A faces sectional view for the large diameter hanger for being provided with running tool;
Fig. 3 f are the B-B faces sectional view for the large diameter hanger for being provided with running tool;
Fig. 3 g are the C-C faces sectional view for the large diameter hanger for being provided with running tool;
Fig. 4 a fishing tools insert the state diagram of stop collar;
Fig. 4 b fishing tools press to stop collar and cut shear pin, and stop collar falls into the state diagram of lower contact;
Fig. 4 c fishing tools press downwards, and lower cone leaves the state diagram of tub slips.
Embodiment
Technical scheme is described in detail below in conjunction with the drawings and specific embodiments.
A kind of running tool, including running tool central tube 103, piston 104, top connection 101, fluid cylinder 102, power transmission set 105th, set 109, control closing piece 108, control set 110, limitation closing piece 111, non-return ring 112, helmet 113, stop collar of giving up are promoted 114th, block of giving up set 118, give up block 115 and ball seat 120;
The inner surface of the bottom of top connection 101 is tightly connected with running tool central tube 103, and outer surface seals with fluid cylinder 102 Connection;The outer tube wall of running tool central tube 103 is provided with first boss, and first boss is located at the lower edge of fluid cylinder 102;Fluid cylinder Formed with the first cavity between 102 and running tool central tube 103;Piston 104 is sealingly mounted in the first cavity, its lower setting Power transmission set 105;There is space between the top of piston 104 and top connection 101, running tool central tube 103 corresponding to the space Multiple through holes are provided with tube wall;The downside of piston 104 is formed with boss, when piston 104 is come downwards at first boss, boss Being stuck at first boss prevents piston 104 from continuing traveling downwardly, now, between being formed between the outer wall of piston 104 and the bottom of fluid cylinder 102 Gap;
Power transmission set 105 is from top to bottom divided into three sections according to internal diameter difference, epimere internal diameter is minimum, and stage casing internal diameter is maximum;Pass The first paragraph of power set 105 is fixed in first boss by the first shear pin 107;Set 109 is promoted to be fixed on by the second shear pin 106 The outside of power transmission set 105;
Power transmission set 105 is fixed on running tool central tube 103 by the first shear pin 107;What the first shear pin 107 can be born Power is less than the power that the second shear pin 106 can be born;
Control set 110 is tubular, and its downside is formed with second boss;The top of control set 110 is by controlling closing piece 108 to be stuck in Between first boss and the 3rd section of power transmission set 105;First boss correspondingly controls the installed position of closing piece 108 to set groove, The depth of the groove is less than power transmission and covers 105 second segments and the 3rd section of semidiameter;Limit the one side of closing piece 111 and first boss phase Cut, opposite side protrusion second boss;During control 110 slide downward of set, control closing piece 111 slides from first boss, and it protrudes The part of second boss is submerged in second boss;
Ball seat 120 is screwed onto the bottom of running tool central tube 103;Block of giving up set 118 is screwed onto on ball seat 120;Give up Block 115, leaf spring 116, which are arranged on, gives up in block set 118;The give up outer surface of block 115 is provided with left-hand thread screw thread;Give up stop collar 114 are arranged at running tool central tube 103 between block set 118 of giving up, and give up stop collar 114 and block set 118 of giving up pass through 3rd shear pin 117 is fixed;The top of stop collar 114 of giving up is bolted with helmet 113;The inside of helmet 113 installation non-return ring 112, non-return The inwall of ring 112 is provided with gingival cyst of mucous gland in the newborn button, corresponding, and the corresponding position on the outer wall of running tool central tube 103 is provided with and gingival cyst of mucous gland in the newborn The structure that matches is detained, the stop collar 114 that can prevent from giving up moves up;
Sealing device 119 is additionally provided between block of giving up set 118 and ball seat 120;
The give up vertical section of block 115 is the concave being rotated by 90 °, its projecting surface inwardly, the appearance for stop collar 114 of giving up Face is provided with the groove I to match with block 115 of giving up;When stop collar 114 of giving up is descending, block 115 of giving up can be caught in groove I.
A kind of large diameter hanger for being provided with as above running tool, including:Hanger central tube 204, it is setting set 201, Packing element set 203, packing element 205, adapter sleeve 206, packing element cap bag 208, upper cone 209, spacing ring 210, tub slips 212, lower cone Body 213, salvage adapter sleeve 214 and lower contact 218;
The top of hanger central tube 204 sets left-hand thread internal thread, with the left-hand thread screw thread phase given up set by the outer surface of block 115 Matching;Packing element set 203, adapter sleeve 206, upper cone 209, tub are provided with the outer wall of hanger central tube 204 from top to bottom Slips 212, lower cone 213, salvage adapter sleeve 214 and lower contact 218;The upper end for salvaging adapter sleeve 214 is screwed onto lower cone 213 Tail end, lower end is spirally connected with lower contact 218;
Packing element covers 203 tops and is connected by shear pin with setting set 201;Packing element covers 203 ends installation packing element cap bag 208;Glue Jacket casing cap 208 is made up of two cylinders of different-diameter, and one section of major diameter is enclosed on packing element set 203, and one section of minor diameter is with hanging Device central tube 204 is tangent;Packing element cap bag 208 is arranged on the inner side of adapter sleeve 206, and both are connected by the 4th shear pin 207;Packing element 205 are arranged on packing element set 203;
The top of setting set 201 can be stuck in positioned at the outside of promotion set 109 on its inwall formed with step, the step On the control closing piece 111 of protrusion control 110 second boss of set;
Lock ring 202, lock ring 202 and hanger central tube 204 are installed between hanger central tube 204 and setting set 201 Tube wall is provided with the gingival cyst of mucous gland in the newborn button being mutually matched, and can prevent packing element set 203 from moving up;
Spacing ring 210 is arranged between upper cone 209 and hanger central tube 204, the inwall and hanger of spacing ring 210 The outer wall of central tube 204 is provided with the gingival cyst of mucous gland in the newborn button being mutually matched, for preventing upper cone 209 from moving up;
The both ends of tub slips 212 are connected with upper cone 209, lower cone 213 by the 5th shear pin 211 respectively.
In order to realize the function of salvaging of the large diameter hanger, between hanger central tube 204 and salvaging adapter sleeve 214 It is provided with screw thread claw 215;Screw thread claw 215 is spirally connected with salvaging adapter sleeve 214;Being arranged with for hanger central tube 204 is beaten Drag for stop collar 217;Salvaging stop collar 217 is tubular, and the internal diameter in the middle part of it is more than the internal diameter at both ends;The inner surface of lower contact 218 Formed with step, the tail end for salvaging stop collar 217 rides over the upper end of lower contact 218, and salvaging stop collar 217 can be along lower contact 218 inner surface slides, and slide downward can be prevented by the step of lower contact;Stop collar 217 is salvaged to be fixed on by shear pin 216 Salvage on adapter sleeve 214;The tail end of screw thread claw 215, which rides over, to be salvaged on stop collar 217.
In specifically installation shear pin, the power that the 4th shear pin 207 can bear is more than the power that the 5th shear pin 211 can bear.
Further, the power that the second shear pin 106 can bear is more than the 4th shear pin 207, the 5th shear pin 211 can bear Power.
The installation method of running tool and large diameter hanger is during use:Hanger needs before mounting seat big envelope 201 Running tool is first connected, running tool is not installed joint 101, fluid cylinder 102, piston 104, power transmission set 105, second temporarily and cut Nail 106, set 109 is promoted, running tool is corresponding with the upper end of hanger central tube 204 by the left-hand thread screw thread on block 115 of giving up Left-hand thread is threaded togather, and is inserted in setting set 201 afterwards, then installation promotes the shear pin 106 of set 109 and second successively, is inserted in work Plug 104, fluid cylinder 102 and top connection 101 are finally installed, complete the installation of hanger complete machine.Now, sealing device 119 forms ball Sealing between seat 120 and hanger central tube 204;
The course of work is described as follows:Top connection 101 connects drill string, and lower contact 218 connects expandable screen or other completion tubulars String, instrument is sent into well by drill string, under in place after pitching establish pipe interior sealing environment to the position of ball seat 120, connect pump truck and beat Pressure, pressure are passed in running tool by drill string, and pressure is set multiple logical on the tube wall by running tool central tube 103 Hole is acted on piston 104, and hydraulic coupling is passed to power transmission set 105 by piston 104, and hydraulic coupling reaches the first shear pin after certain value 107 cuttings, power transmission set 105 move downward, and control closing piece 108 enters the second segment of power transmission set 105, control closing piece 108 from feeding The second segment into power transmission set 105 is skidded off in tool focus pipe 103;The unblock of control set 110, as power transmission covers 105 slide downwards, Control closing piece 111 slides from the first boss of running tool central tube 103, and it protrudes the part of second boss, and to submerge second convex In platform, setting set 201 is unlocked;Promotion set 109 pusher seat big envelope, the 201 setting hanger body in the outside of power transmission set 105, specifically such as Under:The setting drive of set 201 packing element set 203, packing element cap bag 208, adapter sleeve 206 and upper cone 209 move downward, the 5th shear pin 211 are cut, and inclined-plane of the tub slips 212 along upper cone 209 and lower cone 213 extends out expansion, stings tight set tube wall, are realized to sit and are hung Function.The power that setting set 201 provides further increases, and cuts the 4th shear pin 207, and packing element set 203 continues to move downward, packing element 205 packing element cover 203 inclined-planes in the presence of be in bowl-shape expansion, be adjacent to internal surface of sleeve pipe and realize sealing function.Simultaneously under packing element set 203 The packing element cap bag 208 of end connection can be moved and pushed up on upper cone 209, further be pressed by the conical surface to tub slips 2-12, Increase the anchorage force of hanger.Setting set 201 is locked, it is ensured that work while action by the step-by-step movement of lock ring 202 with gingival cyst of mucous gland in the newborn button Tool will not unseal in advance.
Hanger is sat hang after the completion of, further increase the pressure in running tool central tube 103, cut promote set 109 with The second shear pin 106 between power transmission set 105, power transmission set 105 can move forward, power are transmitted into helmet 113, then transmitted To stop collar 114 of giving up, the stress of stop collar 114 of giving up is cut the 3rd shear pin 117 and moved downward, and block 115 of now giving up can be in plate Inwardly retracted into the presence of spring 116 in the groove I for stop collar 114 of giving up, release give up block 115 and hanger central tube Connection between 204, realize by the function of giving up of fluid power, while when piston 104 moves to the bottom of fluid cylinder 102, piston 104 Gap between fluid cylinder 102 releases sealing, abrupt pressure reduction occurs and give up signal and to establish circulation.If hydraulic releasing not into Work(, the threaded connection of give up block 115 and hanger central tube 204 by rotating forward drill string, can also be released, realize that machinery is given up work( Energy.
The hanger to salvage function implementation process as follows:Later stage tripping in specific purpose tool salvages hanger, specific purpose tool It is inserted into hanger central tube 204 to establish with its left-hand thread screw thread and connects, specific purpose tool lower end is provided with hook, can hook salvaging limit The inner groovy at the middle part of position set 217, hook are moved downward by hydraulic coupling, are transmitted the force to and are salvaged stop collar 217, cut shear pin 216, salvaging stop collar 217, which moves downward, drops down onto the position of lower contact 218, and stop collar 217 promotes lower contact 218, drives the company of salvaging Female connector 214 moves downward, and because screw thread claw 215 loses the support of stop collar 217, its underpart is hanging, salvages adapter sleeve 214 Screw thread claw 215 bounces back when moving downward, and is disengaged with salvaging adapter sleeve 214;Now salvage adapter sleeve 214 and drive lower cone 213 Move downward, the lower end of tub slips 212 releases grappling to contract.Then specific purpose tool is above carried, drives hanger central tube 204 Motion upwards, hanger central tube 204 drive the motion upwards of setting set 201, while drive the motion upwards of packing element set 203, packing element 205 lose the backward contract deblocking of support of packing element set 203, while the packing element cap bag 208 being connected on packing element set 203 drives and connected Female connector 206 is moved upwards with upper cone 209, and the upper end of tub slips 212 releases grappling to contract.Continue above to carry specific purpose tool, Hanger is salvaged into well.

Claims (5)

  1. A kind of 1. running tool, it is characterised in that:Including running tool central tube (103), piston (104), top connection (101), Fluid cylinder (102), power transmission set (105), promotion cover (109), control closing piece (108), control set (110), limit closing piece (111), stop Winding (112), helmet (113), stop collar of giving up (114), block set (118) of giving up, block of giving up (115) and ball seat (120);
    The inner surface of top connection (101) bottom is tightly connected with running tool central tube (103), outer surface and fluid cylinder (102) it is tightly connected;The outer tube wall of the running tool central tube (103) is provided with first boss, and the first boss is located at At the lower edge of fluid cylinder (102);Formed with the first cavity between the fluid cylinder (102) and running tool central tube (103);The work Plug (104) is sealingly mounted in first cavity, its lower setting power transmission set (105);The top of the piston (104) is with above connecing There is space between head (101), multiple through holes are provided with the tube wall of running tool central tube (103) corresponding to the space;It is described The downside of piston (104) is formed with boss, and when piston (104) is come downwards at first boss, the boss is stuck in described first Piston (104) is prevented to continue traveling downwardly at boss, now, between being formed between the outer wall of the piston (104) and fluid cylinder (102) bottom Gap;
    The power transmission set (105) is from top to bottom divided into three sections according to internal diameter difference, epimere internal diameter is minimum, and stage casing internal diameter is maximum; The first paragraph of the power transmission set (105) is fixed in the first boss by the first shear pin (107);It is described to promote set (109) The outside of the power transmission set (105) is fixed on by the second shear pin (106);
    The power transmission set (105) is fixed on the running tool central tube (103) by the first shear pin (107);Described first The power that shear pin (107) can be born is less than the power that the second shear pin (106) can be born;
    The control set (110) is tubular, and its downside is formed with second boss;Locked at the top of the control set (110) by controlling Block (108) is stuck between the first boss and the 3rd section of power transmission set (105);First boss correspondingly controls closing piece (108) Installed position sets groove, and the depth of the groove is less than power transmission set (105) second segment and the 3rd section of semidiameter;Limit closing piece (111) it is unilateral tangent with first boss, opposite side protrusion second boss;During described control set (110) slide downward, closing piece is controlled (111) slid from first boss, it protrudes the part of second boss and submerged in second boss;
    The ball seat (120) is screwed onto the bottom of running tool central tube (103);Block set (118) of giving up is screwed onto ball seat (120) On;Block (115), leaf spring (116) give up in block set (118) of giving up;The outer surface of the block of giving up (115) is provided with instead Detain screw thread;Stop collar (114) of giving up is arranged at running tool central tube (103) between block set (118) of giving up, and it is spacing to give up Set (114) and block set (118) of giving up are fixed by the 3rd shear pin (117);Stop collar of giving up (114) top is bolted with helmet (113);Installation non-return ring (112) inside the helmet (113), the inwall of non-return ring (112) is provided with gingival cyst of mucous gland in the newborn button, corresponding, Corresponding position on running tool central tube (103) outer wall is provided with the structure to match with the gingival cyst of mucous gland in the newborn button, can prevent from giving up Stop collar (114) moves up;
    Described give up is additionally provided with sealing device (119) between block set (118) and ball seat (120);
    The vertical section of the block of giving up (115) is the concave being rotated by 90 °, its projecting surface inwardly, the stop collar of giving up (114) outer surface is provided with the groove I to match with the block of giving up (115);When the stop collar of giving up (114) is descending, lose Hand block (115) can be caught in groove I.
  2. A kind of 2. large diameter hanger for being provided with running tool as claimed in claim 1, it is characterised in that including:In hanger Heart pipe (204), setting set (201), packing element set (203), packing element (205), adapter sleeve (206), packing element cap bag (208), upper cone (209), spacing ring (210), tub slips (212), lower cone (213), salvaging adapter sleeve (214) and lower contact (218);
    Left-hand thread internal thread is set at the top of the hanger central tube (204), it is and anti-set by the outer surface of the block of giving up (115) Button screw thread matches;Packing element set (203), adapter sleeve are provided with from top to bottom on the outer wall of the hanger central tube (204) (206), upper cone (209), tub slips (212), lower cone (213), salvaging adapter sleeve (214) and lower contact (218);It is described The upper end for salvaging adapter sleeve (214) is screwed onto the tail end of lower cone (213), and lower end is spirally connected with lower contact (218);
    Packing element set (203) top is connected by shear pin with setting set (201);Packing element set (203) end is installed by packing element cap bag (208);The packing element cap bag (208) is made up of two cylinders of different-diameter, and one section of major diameter is enclosed on the packing element set (203) On, one section of minor diameter is tangent with hanger central tube (204);The packing element cap bag (208) is arranged in the adapter sleeve (206) Side, both are connected by the 4th shear pin (207);The packing element (205) is arranged on packing element set (203);
    The top of the setting set (201) covers the outside of (109) positioned at described promote, and formed with step on its inwall, this Rank can be stuck on the control closing piece (111) for protruding described control set (110) second boss;
    Lock ring (202) is installed between the hanger central tube (204) and setting set (201), lock ring (202) with hanger Heart pipe (204) tube wall is provided with the gingival cyst of mucous gland in the newborn button being mutually matched, and can prevent packing element set (203) from moving up;
    The spacing ring (210) is arranged between the upper cone (209) and hanger central tube (204), spacing ring (210) The outer wall of inwall and hanger central tube (204) is provided with the gingival cyst of mucous gland in the newborn button being mutually matched, for preventing upper cone (209) from moving up;
    The both ends of the tub slips (212) are connected with upper cone (209), lower cone (213) by the 5th shear pin (211) respectively Connect.
  3. 3. large diameter hanger as claimed in claim 2, it is characterised in that:The hanger central tube (204) and salvaging connection Screw thread claw (215) is provided between set (214);The screw thread claw (215) is spirally connected with salvaging adapter sleeve (214);It is described outstanding Stop collar (217) is salvaged in being arranged with for hanging device central tube (204);The salvaging stop collar (217) is tubular, interior in the middle part of it Footpath is more than the internal diameter at both ends;The inner surface of the lower contact (218) is formed with step, the tail end for salvaging stop collar (217) The upper end of the lower contact (218) is ridden over, salvaging stop collar (217) can slide along the inner surface of lower contact (218), and downwards Sliding can be prevented by the step of lower contact;The salvaging stop collar (217) is fixed on salvaging adapter sleeve by shear pin (216) (214) on;The tail end of the screw thread claw (215), which rides over, to be salvaged on stop collar (217).
  4. 4. large diameter hanger as claimed in claim 2, it is characterised in that:The power that 4th shear pin (207) can bear is more than the The power that five shear pins (211) can bear.
  5. 5. large diameter hanger as claimed in claim 2, it is characterised in that:The power that second shear pin (106) can bear is more than the The power that four shear pins (207), the 5th shear pin (211) can bear.
CN201710532686.2A 2017-07-03 2017-07-03 Running tool and the large diameter hanger for being equipped with the running tool Active CN107387006B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710532686.2A CN107387006B (en) 2017-07-03 2017-07-03 Running tool and the large diameter hanger for being equipped with the running tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710532686.2A CN107387006B (en) 2017-07-03 2017-07-03 Running tool and the large diameter hanger for being equipped with the running tool

Publications (2)

Publication Number Publication Date
CN107387006A true CN107387006A (en) 2017-11-24
CN107387006B CN107387006B (en) 2019-07-23

Family

ID=60334889

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710532686.2A Active CN107387006B (en) 2017-07-03 2017-07-03 Running tool and the large diameter hanger for being equipped with the running tool

Country Status (1)

Country Link
CN (1) CN107387006B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989570A (en) * 2018-01-09 2018-05-04 高云东 A kind of sump packer
CN110017109A (en) * 2019-04-28 2019-07-16 宝鸡石油机械有限责任公司 A kind of long-range hydraulically-controlled type boll-weevil hanger tripping in recycling tool
CN110630227A (en) * 2019-10-22 2019-12-31 东营市瑞丰石油技术发展有限责任公司 Running tool, layered oil production pipe column and layered oil production pipe column running method
CN111088957A (en) * 2020-01-15 2020-05-01 思达斯易能源技术(集团)有限公司 Tail pipe hanger feeding tool for hydraulic machinery releasing hand
CN111622698A (en) * 2020-05-19 2020-09-04 中国石油天然气股份有限公司 Hydraulic throwing tool for underground restrictor and use method thereof
CN111636862A (en) * 2020-07-10 2020-09-08 北京同永亨科技有限公司 Five-claw positioning hanger for well logging
CN114575773A (en) * 2020-12-01 2022-06-03 中国石油化工股份有限公司 Tail pipe suspension device with top packer and tail pipe suspension assembly
WO2024179495A1 (en) * 2023-02-28 2024-09-06 中国石油化工股份有限公司 Liner hanger system, liner hanger and using method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4393931A (en) * 1981-04-27 1983-07-19 Baker International Corporation Combination hydraulically set hanger assembly with expansion joint
CN201276995Y (en) * 2008-10-22 2009-07-22 大港油田集团有限责任公司 Tail pipe hanger with control lock
US20130133878A1 (en) * 2011-11-30 2013-05-30 Baker Hughes Incorporated Setting Subterranean Tools with Flow Generated Shock Wave
US20140008080A1 (en) * 2011-01-06 2014-01-09 Halliburton Energy Services, Inc. Low Equivalent Circulation Density Setting Tool
CN104989306A (en) * 2015-08-06 2015-10-21 中国石油集团长城钻探工程有限公司 Releasable screen tube hanger
CN204782879U (en) * 2015-06-08 2015-11-18 山东胜利石油装备产业技术研究院 Hydraulic pressure releasing tool that can salvage
CN204804727U (en) * 2015-05-19 2015-11-25 中国石油天然气股份有限公司 Hanger, unsealing and lifting device and feeding and sealing device
CN205743795U (en) * 2016-07-06 2016-11-30 荆州市赛瑞能源技术有限公司 A kind of double acting is given up hydraulic setting tool

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4393931A (en) * 1981-04-27 1983-07-19 Baker International Corporation Combination hydraulically set hanger assembly with expansion joint
CN201276995Y (en) * 2008-10-22 2009-07-22 大港油田集团有限责任公司 Tail pipe hanger with control lock
US20140008080A1 (en) * 2011-01-06 2014-01-09 Halliburton Energy Services, Inc. Low Equivalent Circulation Density Setting Tool
US20130133878A1 (en) * 2011-11-30 2013-05-30 Baker Hughes Incorporated Setting Subterranean Tools with Flow Generated Shock Wave
CN204804727U (en) * 2015-05-19 2015-11-25 中国石油天然气股份有限公司 Hanger, unsealing and lifting device and feeding and sealing device
CN204782879U (en) * 2015-06-08 2015-11-18 山东胜利石油装备产业技术研究院 Hydraulic pressure releasing tool that can salvage
CN104989306A (en) * 2015-08-06 2015-10-21 中国石油集团长城钻探工程有限公司 Releasable screen tube hanger
CN205743795U (en) * 2016-07-06 2016-11-30 荆州市赛瑞能源技术有限公司 A kind of double acting is given up hydraulic setting tool

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107989570A (en) * 2018-01-09 2018-05-04 高云东 A kind of sump packer
CN107989570B (en) * 2018-01-09 2024-04-12 东营市昌瑞石油机械配件有限责任公司 Sand setting packer
CN110017109A (en) * 2019-04-28 2019-07-16 宝鸡石油机械有限责任公司 A kind of long-range hydraulically-controlled type boll-weevil hanger tripping in recycling tool
CN110630227A (en) * 2019-10-22 2019-12-31 东营市瑞丰石油技术发展有限责任公司 Running tool, layered oil production pipe column and layered oil production pipe column running method
CN110630227B (en) * 2019-10-22 2024-05-03 东营市瑞丰石油技术发展有限责任公司 Running tool, layered oil production string and layered oil production string running method
CN111088957A (en) * 2020-01-15 2020-05-01 思达斯易能源技术(集团)有限公司 Tail pipe hanger feeding tool for hydraulic machinery releasing hand
CN111622698A (en) * 2020-05-19 2020-09-04 中国石油天然气股份有限公司 Hydraulic throwing tool for underground restrictor and use method thereof
CN111622698B (en) * 2020-05-19 2024-01-30 中国石油天然气股份有限公司 Downhole choke hydraulic delivery tool and use method thereof
CN111636862A (en) * 2020-07-10 2020-09-08 北京同永亨科技有限公司 Five-claw positioning hanger for well logging
CN114575773A (en) * 2020-12-01 2022-06-03 中国石油化工股份有限公司 Tail pipe suspension device with top packer and tail pipe suspension assembly
CN114575773B (en) * 2020-12-01 2024-08-16 中国石油化工股份有限公司 Tail pipe suspension device with top packer and tail pipe suspension assembly
WO2024179495A1 (en) * 2023-02-28 2024-09-06 中国石油化工股份有限公司 Liner hanger system, liner hanger and using method thereof

Also Published As

Publication number Publication date
CN107387006B (en) 2019-07-23

Similar Documents

Publication Publication Date Title
CN107387006B (en) Running tool and the large diameter hanger for being equipped with the running tool
CN108386146A (en) Deepwater drilling casing head and annular space sealing device tripping in tool and its application method
CN204804727U (en) Hanger, unsealing and lifting device and feeding and sealing device
US3223170A (en) Hydraulic pressure-set liner hanger
CN104213868B (en) Desirable bore anchor packer
CN101614117B (en) Expansion pipe type tail pipe hanger
CN101482001B (en) Rubber plug system used for drilling liner cementing of horizontal well
CN104963652B (en) From sealed compression packer
CN102953698B (en) A kind of expansion-type rotatable tail pipe hanger
CN104989306B (en) One kind can unseal screen pipe hanger
CN102606107B (en) Halfway cementing well completion tube column and halfway cementing method
CN109653695A (en) Bearing assembly and tubing string for tubing string
CN108301785B (en) Sand prevention well completion pipe string and method
CN204436320U (en) A kind of hydraulic releasing big orifice packer
CN207122297U (en) Large-drift-diameter drilling-free bridge plug with setting releasing function
CN107542421A (en) A kind of Hydraulic Anchorage whipstock of band circulation by-passing valve
CN103628834B (en) Locking type expansion liner hanger
CN202832323U (en) Locking type expansion liner hanger
CN209908438U (en) Disposable type tail pipe hanger
CN108547589A (en) The electronic method for setting flow string under recyclable hanging packer no killing well
CN108425655A (en) Retrievable hanging packer for flow string under no killing well
CN208734311U (en) A kind of permanent type well completion packer that mechanical can be given up
CN208184692U (en) Deepwater drilling casing head and annular space sealing device tripping in tool
CN201443351U (en) Novel packer
CN107724991A (en) Buckling type tail pipe hanger with slips

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210219

Address after: 100007 No. 9 North Main Street, Dongcheng District, Beijing, Dongzhimen

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC Bohai Drilling Engineering Co.,Ltd.

Address before: 300457 Tianjin Binhai New Area Development Zone Second Avenue 83, China Petroleum Tianjin building Bohai Drilling Engineering Co., Ltd.