CN107385138A - A kind of method for improving coal gas of converter pipe network system and protecting energy supply power - Google Patents
A kind of method for improving coal gas of converter pipe network system and protecting energy supply power Download PDFInfo
- Publication number
- CN107385138A CN107385138A CN201710530296.1A CN201710530296A CN107385138A CN 107385138 A CN107385138 A CN 107385138A CN 201710530296 A CN201710530296 A CN 201710530296A CN 107385138 A CN107385138 A CN 107385138A
- Authority
- CN
- China
- Prior art keywords
- gas
- converter
- pipeline
- valve
- blast furnace
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000003034 coal gas Substances 0.000 title claims abstract description 34
- 238000000034 method Methods 0.000 title claims abstract description 14
- 239000007789 gas Substances 0.000 claims abstract description 66
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical group C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 claims abstract description 44
- 239000003345 natural gas Substances 0.000 claims abstract description 22
- 230000006835 compression Effects 0.000 claims abstract description 4
- 238000007906 compression Methods 0.000 claims abstract description 4
- 238000010438 heat treatment Methods 0.000 claims description 3
- 230000007306 turnover Effects 0.000 claims description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 abstract description 10
- 229910000831 Steel Inorganic materials 0.000 abstract description 8
- 239000010959 steel Substances 0.000 abstract description 8
- 229910052742 iron Inorganic materials 0.000 abstract description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 5
- 238000012423 maintenance Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
Classifications
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21C—PROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
- C21C5/00—Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
- C21C5/28—Manufacture of steel in the converter
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21B—MANUFACTURE OF IRON OR STEEL
- C21B5/00—Making pig-iron in the blast furnace
- C21B5/06—Making pig-iron in the blast furnace using top gas in the blast furnace process
-
- C—CHEMISTRY; METALLURGY
- C21—METALLURGY OF IRON
- C21C—PROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
- C21C5/00—Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
- C21C5/28—Manufacture of steel in the converter
- C21C5/42—Constructional features of converters
- C21C5/46—Details or accessories
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P10/00—Technologies related to metal processing
- Y02P10/10—Reduction of greenhouse gas [GHG] emissions
- Y02P10/143—Reduction of greenhouse gas [GHG] emissions of methane [CH4]
Landscapes
- Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Manufacturing & Machinery (AREA)
- Materials Engineering (AREA)
- Metallurgy (AREA)
- Organic Chemistry (AREA)
- Carbon Steel Or Casting Steel Manufacturing (AREA)
- Feeding And Controlling Fuel (AREA)
Abstract
A kind of method for improving coal gas of converter pipe network system and protecting energy supply power, belongs to iron and steel enterprise's field of mechanical technique.Blast furnace gas and gas discharge are pressed 7:1‑9:1 range scale is mixed, and meets each coal gas of converter user technological requirement;A set of gas mi xture system and control system are set up between converter gas cabinet and compression system, coal gas mixing station is made up of two-way pipeline, it is natural gas line all the way, another way is blast furnace gas pipeline, and the mixed gas of the hybrid station is confessed pipeline and is directly connected with Pressure Unit inlet manifold;Open the high pneumoelectric of hybrid station and move two inclined valves, open return valve, slow to drive hybrid station natural gas electric control valve, control sends out pressure and meets that user requires.Advantage is:The guarantor for effectively increasing converter gas system energizes power and stability, it is ensured that main flow production process normally produces.
Description
Technical field
The invention belongs to iron and steel enterprise's field of mechanical technique, more particularly to a kind of coal gas of converter pipe network system that improves protects energy supply
The method of power.Production suitable for integrated iron and steel works' coal gas system supplies with protecting.
Background technology
General iron and steel enterprise coal gas of converter pipe network is usually that single seat gas chamber is connected in converter gas system, this kind of mode
Small investment, plant maintenance amount relatively less, system operation it is simple.But turn gas holder need to stop the supple of gas or steam overhaul when, it is necessary to pipe network disconnect, turn
Producer gas pipe network will stop supplying, and reduce the guarantor's energy supply power for turning gas pipe network system.Each coal gas of converter user needs to stop production;It is precious
The TECHNIQUE TO LARGE INTEGRATED STEEL WORKS coal gas of converter pipe network system such as steel, Shoudu Iron and Steel Co employs the method for operation of double gas holders gas storage arranged side by side, the party
The advantages of formula is because of single seat overhaul gas container or will not to move back pipe network operation and influence to turn the overall operation of gas system, coal gas of converter pipe
There is net system stronger guarantor to energize power.But the shortcomings that double cabinet gas storage methods of operation is that system cost is higher, maintenance is larger, behaviour
Make complicated.
The content of the invention
It is an object of the invention to provide a kind of method for improving coal gas of converter pipe network system and protecting energy supply power, solves coal gas
When cabinet failure or maintenance out of service, the problem of coal gas of converter user is unable to normal use.Enhance coal gas of converter pipe network system
Guarantor energize power.
A kind of method for improving coal gas of converter pipe network system and protecting energy supply power, specific steps and parameter are as follows:
1st, blast furnace gas calorific value 3300-3800kJ/m3, heating value of natural gas 33000-36000kJ/m3, by blast furnace gas and day
Right throughput presses 7:1-9:1 range scale is mixed, mixed gas calorific value 7000-9000 kJ/m3, with coal gas of converter calorific value
It is close, meet each coal gas of converter user technological requirement.
2nd, a set of gas mi xture system and control system are set up between converter gas cabinet and compression system, i.e. coal gas mixes
Stand.Coal gas mixing station is made up of two-way pipeline, is all the way natural gas line, and natural gas blank-plate valve 1, natural balloon are installed on pipeline
Valve 2 and natural gas electric control valve 3;Another way is blast furnace gas pipeline, and high gas blank-plate valve 4 and high pneumoelectric dynamic two are installed on pipeline
Inclined valve 5.The mixed gas of the hybrid station is confessed pipeline and is directly connected with Pressure Unit inlet manifold.
3rd, open the high pneumoelectric of hybrid station and move two inclined valves 5, pressuring machine power-on operation is performed by related code.
4th, return valve is opened, slow to open turnover panel before pressuring machine machine, control sends out pressure in the range of 16-20kpa.
5th, delay and drive hybrid station natural gas electric control valve 3, blast furnace gas and gas discharge are pressed 7:1-9:1 scope ratio
Example is mixed;Control sends out pressure and meets that user requires.
The advantage of the invention is that:The Pressure Unit inlet manifold of coal gas of converter pipe network system is additionally arranged coal gas mixed stocker
System, the hybrid system can be put into operation at any time, and the flow and calorific value of mixed gas, the mixing are controlled by regulating valve and flowmeter
Stand using blast furnace gas system as support, its stable equivalent to one large-scale gas chamber of gas supply capacity.When converter gas pipeline system
System recovers normal, it is only necessary to closes contacting for the i.e. cut-off hybrid station of blank-plate valve and converter gas system.Effectively increase converter
The guarantor of coal gas system energizes power and stability, it is ensured that main flow production process normally produces.Content is most in blast furnace gas three kinds
Gas is respectively N2、CO、CO2, three kinds of most gases of content are respectively CO, N in coal gas of converter2、CO2。N2With CO2It is inertia
Gas, therefore blend a small amount of natural gas in blast furnace gas and improve calorific value, exhaust gas components produce without large change to gas equipment
Technique is without considerable influence.Present invention design is simple and practical, is adapted in steel industry, especially to only having the converter of single seat gas chamber
Promote, use in gas piping system.
Brief description of the drawings
Fig. 1 is position view of the present invention in coal gas of converter pipe network.Wherein, natural gas blank-plate valve 1, natural gas ball valve
2nd, natural gas electric control valve 3, high gas blank-plate valve 4, high pneumoelectric move two inclined valves.
Embodiment
A kind of method for improving coal gas of converter pipe network system and protecting energy supply power, specific steps and parameter are as follows:
1st, as blast furnace gas calorific value 3300kJ/m3, heating value of natural gas 33000kJ/m3, by blast furnace gas and gas discharge
By 7:1 ratio is mixed, mixed gas calorific value 7000kJ/m3, it is close with coal gas of converter calorific value, it can meet that each coal gas of converter is used
Family technological requirement.
2nd, a set of gas mi xture system and control system are set up between converter gas cabinet and compression system, i.e. coal gas mixes
Stand.Coal gas mixing station is made up of two-way pipeline, is all the way natural gas line, and natural gas blank-plate valve, natural balloon are installed on pipeline
Valve and natural gas electric control valve;Another way is blast furnace gas pipeline, and high gas blank-plate valve is installed on pipeline and high pneumoelectric dynamic two is inclined
Valve.The mixed gas of the hybrid station is confessed pipeline and is directly connected with Pressure Unit inlet manifold.
3rd, open the high pneumoelectric of hybrid station and move two inclined valves 5, pressuring machine power-on operation is performed by related code.
4th, return valve is opened, slow to open turnover panel before pressuring machine machine, pressure 18kpa is sent out in control.
5th, delay and drive hybrid station natural gas electric control valve 3, blast furnace gas and gas discharge are pressed 7:1 ratio is mixed
Close;Control sends out pressure and meets that user requires, notifies that user resumes production by igniting use.
Claims (1)
- A kind of 1. method for improving coal gas of converter pipe network system and protecting energy supply power, it is characterised in that specific steps and parameter are as follows:1) blast furnace gas calorific value 3300-3800kJ/m3, heating value of natural gas 33000-36000kJ/m3, by blast furnace gas and natural gas Flow presses 7:1-9:1 range scale is mixed, mixed gas calorific value 7000-9000kJ/m3, meet each coal gas of converter user work Skill requirement;2) a set of gas mi xture system and control system, i.e. coal gas mixing station are set up between converter gas cabinet and compression system; Coal gas mixing station is made up of two-way pipeline, is all the way natural gas line, and natural gas blank-plate valve (1), natural balloon are installed on pipeline Valve (2) and natural gas electric control valve (3);Another way is blast furnace gas pipeline, and high gas blank-plate valve (4) and high gas are installed on pipeline Electronic two inclined valve (5);The mixed gas of the hybrid station is confessed pipeline and is directly connected with Pressure Unit inlet manifold;3) open the high pneumoelectric of hybrid station and move two inclined valves (5), pressuring machine power-on operation is performed by related code;4) return valve is opened, slow to open turnover panel before pressuring machine machine, control sends out pressure in the range of 16-20kpa;5) delay and drive hybrid station natural gas electric control valve (3), blast furnace gas and gas discharge are pressed 7:1-9:1 range scale enters Row mixing;Control sends out pressure and meets that user requires.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710530296.1A CN107385138A (en) | 2017-06-30 | 2017-06-30 | A kind of method for improving coal gas of converter pipe network system and protecting energy supply power |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710530296.1A CN107385138A (en) | 2017-06-30 | 2017-06-30 | A kind of method for improving coal gas of converter pipe network system and protecting energy supply power |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107385138A true CN107385138A (en) | 2017-11-24 |
Family
ID=60334202
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710530296.1A Pending CN107385138A (en) | 2017-06-30 | 2017-06-30 | A kind of method for improving coal gas of converter pipe network system and protecting energy supply power |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107385138A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111766909A (en) * | 2019-03-31 | 2020-10-13 | 上海梅山钢铁股份有限公司 | Control system for full-automatic operation of coal mixing process of metallurgical enterprise |
CN113832340A (en) * | 2021-10-21 | 2021-12-24 | 南京钢铁股份有限公司 | Method for improving pressure of client-side blast furnace gas node |
CN114134265A (en) * | 2021-11-30 | 2022-03-04 | 天津市新天钢联合特钢有限公司 | Converter and blast furnace gas supply method |
CN114657317A (en) * | 2022-03-24 | 2022-06-24 | 鞍山市恒成设备制造有限公司 | Low-carbon metallurgy method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201735344U (en) * | 2010-07-15 | 2011-02-09 | 中冶东方工程技术有限公司 | Gas mixing device |
CN102095073A (en) * | 2010-12-16 | 2011-06-15 | 山西太钢不锈钢股份有限公司 | Conveying and distributing method of industrial gas |
CN103409588A (en) * | 2013-08-02 | 2013-11-27 | 江苏永钢集团有限公司 | Interconnection intercommunication device for two converting furnace gas chambers |
CN104043375A (en) * | 2013-03-15 | 2014-09-17 | 宝山钢铁股份有限公司 | Mixing equipment for high pressure natural gas and low pressure coal gas and mixing method |
CN205170903U (en) * | 2015-10-23 | 2016-04-20 | 首钢京唐钢铁联合有限责任公司 | Converter gas chamber parallel operation system |
-
2017
- 2017-06-30 CN CN201710530296.1A patent/CN107385138A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201735344U (en) * | 2010-07-15 | 2011-02-09 | 中冶东方工程技术有限公司 | Gas mixing device |
CN102095073A (en) * | 2010-12-16 | 2011-06-15 | 山西太钢不锈钢股份有限公司 | Conveying and distributing method of industrial gas |
CN104043375A (en) * | 2013-03-15 | 2014-09-17 | 宝山钢铁股份有限公司 | Mixing equipment for high pressure natural gas and low pressure coal gas and mixing method |
CN103409588A (en) * | 2013-08-02 | 2013-11-27 | 江苏永钢集团有限公司 | Interconnection intercommunication device for two converting furnace gas chambers |
CN205170903U (en) * | 2015-10-23 | 2016-04-20 | 首钢京唐钢铁联合有限责任公司 | Converter gas chamber parallel operation system |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111766909A (en) * | 2019-03-31 | 2020-10-13 | 上海梅山钢铁股份有限公司 | Control system for full-automatic operation of coal mixing process of metallurgical enterprise |
CN111766909B (en) * | 2019-03-31 | 2022-03-15 | 上海梅山钢铁股份有限公司 | Control system for full-automatic operation of coal mixing process of metallurgical enterprise |
CN113832340A (en) * | 2021-10-21 | 2021-12-24 | 南京钢铁股份有限公司 | Method for improving pressure of client-side blast furnace gas node |
CN114134265A (en) * | 2021-11-30 | 2022-03-04 | 天津市新天钢联合特钢有限公司 | Converter and blast furnace gas supply method |
CN114657317A (en) * | 2022-03-24 | 2022-06-24 | 鞍山市恒成设备制造有限公司 | Low-carbon metallurgy method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107385138A (en) | A kind of method for improving coal gas of converter pipe network system and protecting energy supply power | |
CN205170903U (en) | Converter gas chamber parallel operation system | |
CN201269402Y (en) | Gas inlet and outlet device for gas cabinet | |
CN204240050U (en) | A kind of blast furnace gas low energy consumption direct-supplying device | |
CN202509094U (en) | Gas spread tower anti-leakage control device | |
CN105567902A (en) | Regulating device and method for gas chamber bypass pipe network | |
CN207230598U (en) | Oxygen-enriched combustion system of generator set | |
CN102095073A (en) | Conveying and distributing method of industrial gas | |
CN202303323U (en) | Boiler system with steam recovering device | |
CN204369822U (en) | A kind of energy saver of fixed bed coal gas producer steam | |
CN205807374U (en) | A kind of thermodynamic steam generator | |
CN211199258U (en) | Blast furnace top charging bucket pressure-equalizing coal gas full-recovery system | |
CN211953244U (en) | High-temperature oxygen-enriched heating furnace for extracting vanadium and titanium from vanadium-titanium slag | |
CN204958964U (en) | Converter gas recovery and balancing device | |
CN202101252U (en) | Coal gas diffusing device capable of diffusing various kinds of coal gas | |
CN203212590U (en) | Oxygen coal rifle coolant regulation and control system | |
CN102563201A (en) | Device for eliminating leakage risk of gas gate valve online | |
CN206398366U (en) | A kind of oxyhydrogen continuous casting billet numerical control cutting machine intelligent gas-supplying system | |
CN206754806U (en) | A kind of acetylene cylinder air supply system | |
CN204627797U (en) | A kind of gas electricity unit blending LNG fuel apparatus | |
CN104728593A (en) | Gas cabinet position adjusting system | |
CN204325279U (en) | A kind of gasification chilling train | |
CN216513946U (en) | Process device for improving recovery of converter gas | |
CN106704831A (en) | Oxyhydrogen gas continuous casting billet numerical control cutting machine intelligent gas supply system | |
CN202469209U (en) | Device for eliminating harm of leakage of gas gate valve on line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190325 Address after: 063200 Iron and Steel Power Park, Caofeidian Industrial Zone, Tangshan City, Hebei Province Applicant after: Shougang Jingtang United Iron & Steel Co., Ltd. Address before: 066326 Duzhuang, Haigang District, Qinhuangdao City, Hebei Province Applicant before: QINHUANGDAO SHOUQIN METAL MATERIAL Co.,Ltd. |
|
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20171124 |