CN107368996B - Method/system for problem handling/supervision of field project, storage medium, terminal - Google Patents

Method/system for problem handling/supervision of field project, storage medium, terminal Download PDF

Info

Publication number
CN107368996B
CN107368996B CN201710432781.5A CN201710432781A CN107368996B CN 107368996 B CN107368996 B CN 107368996B CN 201710432781 A CN201710432781 A CN 201710432781A CN 107368996 B CN107368996 B CN 107368996B
Authority
CN
China
Prior art keywords
project
event
field
icon
building model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710432781.5A
Other languages
Chinese (zh)
Other versions
CN107368996A (en
Inventor
黄健
詹生锐
邢雷兵
王卓
潘强
苏威
王峰
徐雨祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jaso Group Co ltd
Original Assignee
Shanghai Jaso Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jaso Group Co ltd filed Critical Shanghai Jaso Group Co ltd
Priority to CN201710432781.5A priority Critical patent/CN107368996B/en
Publication of CN107368996A publication Critical patent/CN107368996A/en
Application granted granted Critical
Publication of CN107368996B publication Critical patent/CN107368996B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention provides a problem processing method/system of a field project, a supervision method/system of the field project, a storage medium and a terminal, wherein the problem processing system of the field project comprises: the problem creating module is used for marking project problems on a building model, starting a problem event input interface by intercepting the building model pictures marked with the project problems, and inputting information data about the project problems by using the problem event input interface to generate problem events. The problem processing method/system of the field project, the supervision method/system of the field project, the storage medium and the terminal can bring the construction management personnel with a feeling of being personally on the scene, the experience feeling is better, the management efficiency of the construction personnel is improved, and paperless project management is realized.

Description

Method/system for problem handling/supervision of field project, storage medium, terminal
Technical Field
The invention belongs to the field of application management of constructional engineering, relates to a processing/supervising method and a system, and particularly relates to a problem processing/supervising method/system, a storage medium and a terminal for a field project.
Background
BIM (Building Information Modeling) is another important computer application technology appearing in the engineering construction industry after CAD (computer aided design) technology, and is leading to a complete revolution of unprecedented cases in the construction industry. The technology utilizes digital modeling software, improves the efficiency of project design, construction and management, and brings great added value to building enterprises adopting the technology.
At present, BIM platform is applied to improve design, rework is avoided, BIM is used for simulation, and the technology of optimizing construction scheme and the like is relatively mature. But the potential of how to use BIM on site to guide construction correctly has not been explored.
At present, site construction is carried out by site constructors according to a construction scheme compiled in advance, combined with national standard standards and the like, and then supervision is carried out and acceptance is carried out according to the national acceptance standards. A large amount of data such as drawings and standards need to be brought to the site so as to be referred at any time. The traditional construction drawing of the field project can not bring the sense of being personally on the scene for construction management personnel, and the experience sense is poor.
Therefore, how to provide a problem handling/supervision method/system, a storage medium, and a terminal for a field project to solve the defects that the traditional construction drawing of the field project cannot bring a sense of being personally on the scene to construction managers, and the experience sense is poor in the prior art, and thus, the technical problem to be solved by the technical personnel in the field is really needed.
Disclosure of Invention
In view of the above-mentioned shortcomings of the prior art, an object of the present invention is to provide a method/system, a storage medium, and a terminal for problem handling/supervision of a field project, which are used to solve the problem in the prior art that a construction manager cannot feel personally on the scene due to a traditional construction drawing of the field project, and experience is poor.
To achieve the above and other related objects, an aspect of the present invention provides a problem handling system for a field project, the problem handling system for the field project comprising: the problem creating module is used for marking project problems on a building model, starting a problem event input interface by intercepting the building model pictures marked with the project problems, and using the problem event input interface to input information data about the project problems to create the problem events.
In an embodiment of the present invention, the information data of the field project includes a project problem name, a project problem number, a project problem type, a project problem solving status, a project problem emergency level, and/or a project problem specialty; the problem types comprise safety problems, quality problems or/and third type problems; the urgency level includes general project issues, important project issues, or/and urgent project issues; the project problem solving state comprises a to-be-solved state, a solving state or/and a solved state; the project problem specialties comprise a building project problem, a structural project problem, an electrical project problem, a water supply and drainage project problem, a heating and ventilation project problem, a fire-fighting project problem, a site project problem or/and a ninth professional project problem.
In an embodiment of the present invention, after the question event input interface is started, the project question marked on the building model is saved in the building model picture and is not saved on the building model; the building model picture is automatically added to the problem event input interface when the problem event input interface is started.
In an embodiment of the present invention, the problem submitting module is configured to submit the problem event generated by the problem creating module, and submit the problem event in the form of an email after the information processing system of the field project enters a communication link state; or binding the problem event with the two-dimension code and submitting the two-dimension code.
Another aspect of the present invention provides a method for processing a problem of a field project, where the method for processing a problem of a field project includes: marking project problems on a building model, and starting a problem event input interface by intercepting the building model pictures marked with the project problems; and inputting information data about project problems by using the problem event input interface and creating problem events.
In another aspect, the present invention provides a monitoring system for a field project, including: the storage module is used for storing the building model of the field project; the screening module is used for screening the problem events according to the screening conditions so as to obtain the screening result of the problem events; the problem event is derived from a problem handling system of the field project of any one of claims 1 to 4; the processing module is used for receiving a problem checking instruction, searching the content of the problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event through the display module; the content of the question event comprises a project question number, an initiator, a project question specialty, the type of the project question, a question name and/or project question details; the screening condition comprises any combination of project problem types, emergency levels, solution states or project problem specialties.
In an embodiment of the present invention, the content of the problem event further includes a scene picture, a positioning icon, a two-dimensional code, and/or a message board of the project problem; the message board comprises a selection icon and a calling icon; the processing module comprises: the positioning unit corresponds to the positioning icon and is used for linking the building model with the problem event, and searching a model position corresponding to the positioning instruction on the building model after the positioning icon is sensed to be triggered; the binding unit is used for binding the content of the problem event with the two-dimensional code; when a scanning request for scanning the two-dimensional code is received, pushing the content of the problem event and/or the position of the problem event on the building model; the selective photographing unit corresponds to the selective icon and is used for selectively photographing the content of the problem event according to the selection requirement of the user and inputting the content to the message board; and the calling unit corresponds to the calling icon and is used for calling the picture from the acquired field picture according to the calling requirement of the user and inputting the picture to the message board.
In another aspect, the present invention provides a method for supervising a field project, including: storing a building model of the site project; screening the problem events according to the screening conditions to obtain screening results of the problem events; receiving a problem checking instruction, searching the content of a problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event; the content of the issue event includes an item issue number, an originator, an item issue specialty, a type of item issue, an issue name, and/or item issue details.
Yet another aspect of the present invention provides a storage medium having stored thereon a computer program that, when executed by a processor, implements a problem handling method for the field item or implements a supervision method for the field item.
A final aspect of the present invention provides a terminal, including: a processor and a memory; the memory is used for storing a computer program, and the processor is used for executing the computer program stored by the memory so as to enable the terminal to execute a problem processing method of the field project or realize a supervision method of the field project
As described above, the problem processing/supervision method/system, storage medium, and terminal of the field project of the present invention have the following beneficial effects:
the information processing/monitoring method, the system and the electronic equipment for the field project can bring the construction management personnel with a feeling of being personally on the scene, the experience feeling is better, the management efficiency of the construction personnel is improved, and paperless project management is realized.
Drawings
FIG. 1 is a schematic block diagram of a problem handling system for a field project according to an embodiment of the present invention.
FIG. 2 is a flow chart illustrating a problem handling method for a field project according to an embodiment of the present invention.
Fig. 3 is a schematic structural diagram of a supervision system for a field project according to an embodiment of the present invention.
Fig. 4 is a schematic plan view of a second display interface according to an embodiment of the invention.
Fig. 5 is a flowchart illustrating a method for supervising a field project according to an embodiment of the present invention.
Description of the element reference numerals
1 problem handling System for a field project
11 first memory module
12 question creation Module
13 question submission module
3 monitoring system for field projects
31 second memory module
32 lightweight module
33 screening module
34 processing module
35 display module
341 positioning unit
342 supply unit
343 selection photographing unit
344 calling unit
345 feedback unit
S21-S23
S51-S55
Detailed Description
The embodiments of the present invention are described below with reference to specific embodiments, and other advantages and effects of the present invention will be easily understood by those skilled in the art from the disclosure of the present specification. The invention is capable of other and different embodiments and of being practiced or of being carried out in various ways, and its several details are capable of modification in various respects, all without departing from the spirit and scope of the present invention. It is to be noted that the features in the following embodiments and examples may be combined with each other without conflict.
It should be noted that the drawings provided in the following embodiments are only for illustrating the basic idea of the present invention, and the components related to the present invention are only shown in the drawings rather than drawn according to the number, shape and size of the components in actual implementation, and the type, quantity and proportion of the components in actual implementation may be changed freely, and the layout of the components may be more complicated.
Example one
The present embodiment provides a problem processing system for a field project, where the information processing system for the field project includes:
the problem creating module is used for marking project problems on a building model, starting a problem event input interface by intercepting the building model pictures marked with the project problems, and using the problem event input interface to input information data about the project problems to create the problem events.
The problem processing system for the field project provided by the present embodiment will be described in detail below with reference to the drawings. The system for processing the problems of the field projects is applied to an electronic device with a touch display screen, wherein the touch display screen provides an output interface and an input interface between the electronic device and a user at the same time. The electronic device includes an electronic device capable of automatically performing numerical calculation and information processing according to a preset or stored instruction and having a multimedia audio/video function, and includes, but is not limited to, an electronic device with a touch screen, such as a smart phone, a tablet computer, and a notebook computer. The touch display controller receives/sends electrical signals from/to the touch display. The touch screen display then displays visual output to the user. This visual output may include text, graphics, video, and any combination thereof. Some or all of the visual output may correspond to user interface objects, more details of which are described below.
Touch displays also accept user input based on tactile and/or tactile contact. The touch screen display forms a touch sensitive surface that accepts user input. The touch display screen and touch display screen controller (along with any associated modules and/or sets of instructions in memory) detect contact (and any movement or breaking of the touch) on the touch display screen and transform the detected contact into interaction with user interface objects, such as one or more soft keys, displayed on the touch display screen. In one exemplary embodiment, the point of contact between the touch display screen and the user corresponds to one or more fingers of the user. The touch display screen may use LCD (liquid crystal display) technology or LPD (light emitting polymer display) technology, but in other embodiments other display technologies may be used. Touch displays and touch display controllers can detect contact and movement or breaking thereof using any of a number of touch sensitive technologies, including but not limited to capacitive, resistive, infrared, and surface acoustic wave technologies, as well as other proximity sensor arrays, or other technologies for determining one or more points of contact with a touch display. The user may contact the touch screen display using any suitable object or accessory, such as a stylus, finger, or the like.
The contact/motion module, in conjunction with the touch display controller, detects contact with the touch display. The contact/motion module includes various software components for performing various operations associated with detection of contact with a touch display screen, such as determining whether contact has occurred, determining whether the contact has moved, and tracking movement on the touch display screen, and determining whether the contact has been broken (i.e., whether contact has ceased). Determining movement of the point of contact may include determining a velocity (magnitude), a velocity (magnitude and direction), and/or an acceleration (including magnitude and/or direction) of the point of contact. In some embodiments, the contact/motion module and touch display controller also detect contact on the touch panel.
In the present embodiment, the field items include a construction site, a finishing site, and the like.
Specifically, please refer to fig. 1, which is a schematic structural diagram of a problem handling system for a field project according to an embodiment. As shown in fig. 1, the problem processing system 1 of the field project includes a first storage module 11, a problem creation module 12, and a problem submission module 13.
The first storage module 11 is used for storing the building model of the field project. The building model is a 3D model obtained based on simulation of model files including various relevant vector building drawings for simulating the on-site building project, building information of components, component names, geometric dimensions, materials, weights, colors, three-dimensional positioning information in the building, progress information, shipping places and even construction cost information, and the like.
The question creating module 12 connected to the first storage module 11 is configured to mark a project question on the building model, start a question event input interface by intercepting a picture of the building model with the marked project question, and input information data about the project question by using the question event input interface to create a question event. . The information data of the project problems comprise project problem names, project problem numbers, project problem types, project problem emergency levels and project problem specialties.
Specifically, the question creation module 11 is configured to mark the project question on the building model by touching a question submission icon suspended on a preset area of the building model. In this embodiment, when a click action occurs on the question submitting icon to be sensed, a drop-down box appears, and the drop-down box includes multiple question labeling icons and a question adding icon. The problem label icon comprises a character label icon, a marking line label with different colors and an icon for canceling the previous operation. Specifically, the problem creation module 11 divides the project problem according to a problem type, an emergency level, a solution status, or/and a project problem specialty. The question types include security questions, quality questions, or/and a third type of question (other types of questions); the urgency level includes general project issues, important project issues, or/and urgent project issues; the solution state comprises a to-be-solved state, a solution state or/and a solved state; the project problem specials comprise building project problems, structural project problems, electrical project problems, water supply and drainage project problems, heating and ventilation project problems, fire fighting project problems, site project problems or/and ninth professional project problems (other professional project problems).
For example, the problem information is the construction area of No. 6 building No. 2, the floor-dragging line is too long and is always idle on the ground, which seriously affects the safety of the small cart operator. This problem may cause the operator to trip, fall, and even be injured, and should be rectified immediately. And configuring pictures of the building model of the No. 6 floor 2 construction area on the problem creation interface for the No. 6 floor 2 construction area. And the scene picture of the project problem comes from an album of the electronic equipment or is shot in the scene and uploaded.
Specifically, the question creating module 11 marks a line according to the text label icon and different colors, and cancels the labeling function provided by the previous operation icon, so as to assist the operator to add a label for the question event. The various labeling functions provided in this embodiment can be used to label on the building model.
In this embodiment, after the question event input interface is started, the project question marked on the building model is saved in the building model picture and is not saved on the building model; the building model picture is automatically added to the problem event input interface when the problem event input interface is started. The problem submitting module 13 connected to the problem creating module 12 is configured to submit the problem event generated by the problem creating module 12, and submit the problem event in the form of an email after the information processing system of the field project enters a communication link state; or binding the problem event with the two-dimension code and submitting the two-dimension code. In this embodiment, when submitting the problem event, the problem submitting module 12 may also transmit the problem event to a terminal bound to the electronic device, and bind a two-dimensional code to the problem event, so that an operator can download the problem event. In this embodiment, the electronic device is connected to a printing device for printing a two-dimensional code.
In this embodiment, the question creation interface further includes a cancel icon for canceling the creation of the question event, and a print icon for printing the created question event.
Example two
The embodiment provides a problem processing method for a field project, which specifically comprises the following steps:
marking project problems on a building model, and starting a problem event input interface by intercepting the building model pictures marked with the project problems;
and inputting information data about project problems by using the problem event input interface and creating problem events. The information processing method of the field item described in the present embodiment will be described in detail below with reference to the drawings. Please refer to fig. 2, which is a flowchart illustrating a problem handling method for a field project according to an embodiment. As shown in fig. 2, the problem processing method for the field project specifically includes the following steps:
and S21, storing the building model of the field project.
S22, marking project problems on a building model, and starting a problem event input interface by intercepting the building model pictures marked with the project problems; and inputting information data about project problems by using the problem event input interface and creating problem events. The problem event is associated with a project problem occurring in the field project. The information data of the project problems comprise project problem names, project problem numbers, project problem types, project problem emergency levels and project problem specialties. In this embodiment, the process of creating the problem event includes:
dividing the project problem according to the problem type, the emergency level, the solution state or/and the project problem specialty;
a project problem is marked on a building model, and a problem event input interface is started by intercepting a building model picture with the marked project problem. In this embodiment, marking out and marking in different colors are performed according to the text marking icon, and various marking functions provided by the operation icon in the previous step are cancelled, so as to assist the operator in marking project problems on the building model.
And inputting information data about project problems by using the problem event input interface to generate problem events.
S23, submitting the problem event generated by the problem creation module, and submitting the problem event to a terminal bound with the electronic equipment in an email form after the information processing system of the field project enters a communication link state; or binding the problem event with the two-dimensional code, and submitting the two-dimensional code so that an operator can download the problem event.
EXAMPLE III
The embodiment provides a supervision system of a field project, which is characterized by comprising:
the storage module is used for storing the building model of the field project;
the screening module is used for screening the problem events according to the screening conditions so as to obtain the screening result of the problem events; the problem event is derived from the problem processing system of the field project described in the first embodiment.
The processing module is used for receiving a problem checking instruction, searching the content of the problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event through the display module; the content of the issue event includes an item issue number, an originator, an item issue specialty, a type of item issue, an issue name, and/or item issue details.
The monitoring system for the field project provided by the present embodiment will be described in detail below with reference to the drawings. The supervision system for the field item is also applied to an electronic device with a touch display screen, wherein the touch display screen provides an output interface and an input interface simultaneously between the electronic device and a user. Please refer to fig. 3, which is a schematic structural diagram of a monitoring system for a field project in an embodiment. As shown in fig. 3, the supervision system 3 of the field project includes a second storage module 31, a lightweight module 32, a screening module 33, a processing module 34, and a display module 35.
The second storage module 31 is used for storing the building model of the field project. The building model is a 3D model obtained based on simulation of model files including various relevant vector building drawings for simulating the on-site building project, building information of components, component names, geometric dimensions, materials, weights, colors, three-dimensional positioning information in the building, progress information, shipping places and even construction cost information, and the like.
The weight reducing module 32 connected to the second storage module 31 is configured to perform weight reducing processing on the stored building model of the field project to extract key points of the building model, so as to form a simplified building model. At present, the lightweight technology is various, and representative two technologies are JT and 3 DXML. 3DXML is a lightweight technology proposed by Dassault, Microsoft, etc., and JT is a lightweight technology proposed by JT open architecture.
And the screening module 33 connected with the light weight module 32 is used for screening the problem events according to the screening conditions so as to obtain the screening result of the problem events. In this embodiment, the screening condition includes any combination of problem type, urgency level, resolution status, or/and project problem specialty. The problem types comprise safety problems, quality problems or/and third type problems; the urgency level includes general project issues, important project issues, or/and urgent project issues; the solution state comprises a to-be-solved state, a solution state or/and a solved state; the project problem specialties comprise a building project problem, a structural project problem, an electrical project problem, a water supply and drainage project problem, a heating and ventilation project problem, a fire-fighting project problem, a site project problem or/and a ninth professional project problem.
For example, the problem type in the screening condition is a safety problem, the emergency level is an important project problem, the solution state is an unsolved state, and the project problem is professional as a field. And screening out a problem event A, a problem event B, a problem event C and a problem event D according to the screening conditions. In this embodiment, problem event a, problem event B, problem event C, and problem event D are respectively displayed as a list in problem icon a1, problem icon B1, problem icon C1, and problem icon D1, and problem icon a1, problem icon B1, problem icon C1, and problem icon D1 provide event entry interface a2, event entry interface B2, event entry interface C2, and event entry interface D2 for entering and viewing problem information on the first display interface. Event entry interface A2, event entry interface B2, event entry interface C2, event entry interface D2 are linked with the created problem event A, problem event B, problem event C, and problem event D.
For example, the specialty in the screening condition is a site, the approach state is an unsolved state, and the problem type is that the special equipment in the security problem is not managed in place. And screening out important problem events E1 and emergency problem events F1, wherein the important problem events E1 and the emergency problem events are not managed by special equipment according to the screening conditions. Significant problem event E1 and emergency problem event F1 are displayed as a list of problem icon E2 and problem icon F2, respectively, and problem icon E2 and problem icon F2 provide event entry interfaces E3 and F3 for entering to view problem information, and event entry interfaces E3 and F3 are linked with created significant problem event E1 and emergency problem event F1.
The processing module 34 connected to the screening module 33 is configured to receive a question checking instruction, search for content of a question event corresponding to the question checking instruction according to the question checking instruction, and display the content of the question event through the display module; the content of the issue event includes an item issue number, an originator, an item issue specialty, a type of item issue, an issue name, and/or item issue details. For example, the question icon F2 is triggered, and the content of the emergency question event corresponding to the triggered question icon F1 is searched through the event entry interface F3.
And the display module 35 connected with the processing module 34 is used for displaying the contents of the searched problem events. The content of the problem event comprises a project problem number, an initiator, project problem specialties, the type of the project problem, a problem name, problem information of the project problem, a field picture of the project problem, a positioning icon, a two-dimensional code and/or a message board; the message board comprises a selection icon and a calling icon. In this embodiment, the contents of the found problem event are displayed through the display interface.
For example, the found emergency event F1 is displayed on the display interface. The problem number of the emergency problem event F1 is 210011, a certain person is initiated, the specialty is a field, the problem type is a safety problem, the problem name is a potential safety hazard, the problem information of the project problem is a No. 6 building No. 2 construction area, the floor dragging line is too long and is idle on the ground all the time, the safety of a small handcart operator is seriously influenced, the problem can cause the operator to trip, fall and even be injured, the site pictures of 4 project problems need to be immediately corrected, the positioning icon positioned in the No. 6 building No. 2 construction area, the two-dimensional code bound with the emergency problem event F1 and the message board are positioned. The two-dimensional code is bound with the problem display interface or the position of the project problem in the building model. Referring to fig. 4, a schematic plan view of a display interface according to an embodiment is shown.
In this embodiment, when the positioning icon is sensed to be clicked on the display interface, the positioning unit 341 in the processing module 34 corresponds to the positioning icon, and is configured to link the building model with the problem event, and after the positioning icon is sensed to be triggered, a model position corresponding to the positioning instruction is searched for on the building model.
When a scanning instruction for scanning the two-dimensional code is sensed, the binding unit 342 in the processing module 34 is configured to bind the two-dimensional code of the content of the problem event, and when a scanning request for scanning the two-dimensional code is received, push the content of the problem event and/or the position of the problem event on the building model.
When the selection icon is sensed to be clicked on the display interface, the selection photographing unit 343 corresponding to the selection icon in the processing module 35 selects the content of the problem event selected to be photographed on the display interface according to the selection requirement of the user, and inputs the content to the message board.
When the calling icon is sensed to be clicked on the display interface, the calling unit 344 corresponding to the calling icon in the processing module 34 calls a picture from the collected on-site pictures according to the calling requirement of the user, and inputs the picture to the message board.
When receiving the feedback of the operator on the message board on the display interface, the feedback module 345 in the processing module 34 displays the feedback on the message board. In this embodiment, the feedback module 345 uses a virtual keyboard on the display interface to input the opinion in the feedback opinion input box.
Example four
The embodiment provides a method for supervising a field project, which comprises the following steps:
storing a building model of the site project;
screening the problem events according to the screening conditions to obtain screening results of the problem events;
receiving a problem checking instruction, searching the content of a problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event; the content of the issue event includes an item issue number, an originator, an item issue specialty, a type of item issue, an issue name, and/or item issue details.
The method for supervising the field project provided by the present embodiment will be described in detail with reference to the drawings. Please refer to fig. 5, which is a flowchart illustrating a monitoring method for a field project according to an embodiment. As shown in fig. 5, the method for supervising the field project specifically includes the following steps:
and S51, storing the building model of the field project. The building model is a 3D model obtained based on simulation of model files including various relevant vector building drawings for simulating the on-site building project, building information of components, component names, geometric dimensions, materials, weights, colors, three-dimensional positioning information in the building, progress information, shipping places and even construction cost information, and the like.
And S52, carrying out weight reduction processing on the stored building model of the field project to extract key points of the building model and form a simplified building model.
And S53, screening the problem events according to the screening conditions to obtain the screening result of the problem events. In this embodiment, the screening condition includes any combination of problem type, urgency level, resolution status, or/and project problem specialty. The problem types comprise safety problems, quality problems or/and third type problems; the urgency level includes general project issues, important project issues, or/and urgent project issues; the solution state comprises a to-be-solved state, a solution state or/and a solved state; the project problem specialties comprise a building project problem, a structural project problem, an electrical project problem, a water supply and drainage project problem, a heating and ventilation project problem, a fire-fighting project problem, a site project problem or/and a ninth professional project problem.
And S54, receiving the question checking instruction, and searching the content of the question event corresponding to the question checking instruction according to the question checking instruction. The content of the issue event includes an item issue number, an originator, an item issue specialty, a type of item issue, an issue name, and/or item issue details.
The step S54 specifically includes linking the building model with the problem event when the click of the positioning icon is sensed on the display interface, and searching for a model position corresponding to the positioning instruction on the building model when the click of the positioning icon is sensed to trigger the positioning icon.
And when a scanning instruction for scanning the two-dimensional code is sensed, binding the two-dimensional code of the content of the problem event, and when a scanning request for scanning the two-dimensional code is received, pushing the content of the problem event and/or the position of the problem event on the building model.
And when the selection icon is sensed to be clicked on the display interface, selecting the content of the problem event selected to be photographed on the display interface according to the selection requirement of the user, and inputting the content to the message board.
And when the calling icon is sensed to be clicked on the display interface, calling the picture from the acquired on-site pictures according to the calling requirement of the user, and inputting the picture to the message board.
And when receiving feedback opinions of an operator on a message board on the display interface, displaying the feedback opinions on the message board. In this embodiment, the virtual keyboard on the display interface is used to input the opinions in the feedback opinion input box.
And S55, displaying the content of the searched problem event. The content of the problem event comprises a project problem number, an initiator, project problem specialties, the type of the project problem, a problem name, problem information of the project problem, a field picture of the project problem, a positioning icon, a two-dimensional code and/or a message board; the message board comprises a selection icon and a calling icon. In this embodiment, the contents of the found problem event are displayed through the display interface.
EXAMPLE five
The present embodiment provides a storage medium (computer-readable storage medium) having stored thereon a computer program characterized in that the program, when executed by a processor, implements a problem handling method for the field project or implements a supervision method for the field project. Those of ordinary skill in the art will understand that: all or part of the steps for implementing the above method embodiments may be performed by hardware associated with a computer program. The aforementioned computer program may be stored in a computer readable storage medium. When executed, the program performs steps comprising the method embodiments described above; and the aforementioned storage medium includes: various media that can store program codes, such as ROM, RAM, magnetic or optical disks.
EXAMPLE six
The present embodiment provides a terminal, including: a processor, a memory, a transceiver, a communication interface, and a system bus; the memory is used for storing the computer program, the communication interface is used for communicating with other devices, the processor and the transceiver are used for running the computer program, and the terminal executes each step of the problem processing method of the field project or executes each step of the supervision method of the field project.
The above-mentioned system bus may be a Peripheral Component Interconnect (PCI) bus, an Extended Industry Standard Architecture (EISA) bus, or the like. The system bus may be divided into an address bus, a data bus, a control bus, and the like. For ease of illustration, only one thick line is shown, but this does not mean that there is only one bus or one type of bus. The communication interface is used for realizing communication between the database access device and other equipment (such as a client, a read-write library and a read-only library). The memory may include a Random Access Memory (RAM), and may further include a non-volatile memory (non-volatile memory), such as at least one disk memory.
The processor may be a general-purpose processor, and includes a Central Processing Unit (CPU), a Network Processor (NP), and the like; the integrated circuit may also be a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), a Field Programmable Gate Array (FPGA) or other programmable logic device, discrete gate or transistor logic device, or discrete hardware components.
In summary, the problem processing/supervision method/system for the field project, the storage medium and the terminal can bring the construction manager with a feeling of being personally on the scene, experience is better, the management efficiency of the construction manager is improved, and paperless project management is realized. Therefore, the invention effectively overcomes various defects in the prior art and has high industrial utilization value.
The foregoing embodiments are merely illustrative of the principles and utilities of the present invention and are not intended to limit the invention. Any person skilled in the art can modify or change the above-mentioned embodiments without departing from the spirit and scope of the present invention. Accordingly, it is intended that all equivalent modifications or changes which can be made by those skilled in the art without departing from the spirit and technical spirit of the present invention be covered by the claims of the present invention.

Claims (8)

1. A problem handling system for a field project, the problem handling system for a field project comprising:
the problem creating module is used for marking project problems on a building model, starting a problem event input interface by intercepting the building model pictures marked with the project problems, inputting information data about the project problems by using the problem event input interface and creating problem events; the problem event is associated with a project problem occurring in the field project; the information data comprises project problem names, project problem numbers, project problem types, project problem solving states, project problem emergency levels or/and project problem specialties; the problem types comprise safety problems, quality problems or/and third type problems; the project problem emergency level comprises general project problems, important project problems or/and emergency project problems; the project problem solving state comprises a to-be-solved state, a solving state or/and a solved state; the project problem major comprises a building project problem, a structural project problem, an electrical project problem, a water supply and drainage project problem, a heating and ventilation project problem, a fire-fighting project problem, a site project problem or/and a ninth major project problem;
the problem creating module marks project problems on the building model by touching a problem submitting icon suspended on a preset area of the building model;
and the problem submitting module is used for submitting the problem event generated by the problem creating module, submitting the problem event in an email form after the problem processing system of the field project enters a communication link state, or binding the problem event with the two-dimension code and submitting the two-dimension code.
2. The problem handling system for a field project of claim 1, wherein: after the problem event input interface is started, storing the project problem marked on the building model in the building model picture; the building model picture is automatically added to the problem event input interface when the problem event input interface is started.
3. A problem processing method of a field project is characterized in that the method is applied to a problem processing system of the field project; the problem processing method of the field project comprises the following steps:
marking project problems on a building model, and starting a problem event input interface by intercepting the building model pictures marked with the project problems; the method comprises the following steps that a problem submitting icon which is suspended on a preset area of the building model is touched, and project problems are marked on the building model; the problem event is associated with a project problem occurring in the field project;
inputting information data about project problems by using the problem event input interface, and creating problem events; the information data comprises project problem names, project problem numbers, project problem types, project problem solving states, project problem emergency levels or/and project problem specialties; the problem types comprise safety problems, quality problems or/and third type problems; the project problem emergency level comprises general project problems, important project problems or/and emergency project problems; the project problem solving state comprises a to-be-solved state, a solving state or/and a solved state; the project problem major comprises a building project problem, a structural project problem, an electrical project problem, a water supply and drainage project problem, a heating and ventilation project problem, a fire-fighting project problem, a site project problem or/and a ninth major project problem;
submitting the generated problem event, and submitting the problem event to a terminal bound with the electronic equipment in an email form after a problem processing system of the field project enters a communication link state; or binding the problem event with the two-dimensional code, and submitting the two-dimensional code so that an operator can download the problem event.
4. A supervisory system for a field item, the supervisory system for the field item comprising:
the storage module is used for storing the building model of the field project;
the screening module is used for screening the problem events according to the screening conditions so as to obtain the screening result of the problem events; the problem event is derived from a problem handling system of a field project; the screening module screens the problem events according to the screening conditions, displays the problem events in a problem icon form, provides an event entry interface for entering and checking problem information, and links the event entry interface with the created problem events; the content of the problem event also comprises a scene picture, a positioning icon, a two-dimensional code and/or a message board of the project problem; the message board comprises a selection icon and a calling icon;
the processing module is used for receiving a problem checking instruction, searching the content of the problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event through the display module; the content of the question event comprises a project question number, an initiator, a project question specialty, a project question type, a project question name and/or project question details; the screening conditions comprise any combination of project problem types, project problem emergency levels, project problem solving states and project problem specialties; the processing module links the building model and the problem event through a positioning unit corresponding to the positioning icon, and searches a model position corresponding to the positioning icon on the building model after the positioning icon is sensed to be triggered.
5. The system of monitoring a field project of claim 4, wherein:
the processing module comprises:
the binding unit is used for binding the content of the problem event with the two-dimensional code; when a scanning request for scanning the two-dimensional code is received, pushing the content of the problem event and/or the position of the problem event on the building model;
the selective photographing unit corresponds to the selective icon and is used for selectively photographing the content of the problem event according to the selection requirement of the user and inputting the content to the message board;
and the calling unit corresponds to the calling icon and is used for calling the picture from the acquired field picture according to the calling requirement of the user and inputting the picture to the message board.
6. A method of supervising a field item, the method comprising:
storing a building model of the site project;
screening the problem events according to the screening conditions to obtain screening results of the problem events; the problem events are screened out according to the screening conditions, the problem events are displayed in a problem icon form, the problem icons provide event entry interfaces for entering to view problem information, and the event entry interfaces are linked with the created problem events; the content of the problem event also comprises a scene picture, a positioning icon, a two-dimensional code and/or a message board of the project problem; the message board comprises a selection icon and a calling icon;
receiving a problem checking instruction, searching the content of a problem event corresponding to the problem checking instruction according to the problem checking instruction, and displaying the content of the problem event; the content of the question event comprises a project question number, an initiator, a project question specialty, a project question type, a project question name and/or project question details; when clicking of the positioning icon is sensed on a display interface, the building model is linked with the problem event, and after the positioning icon is sensed to be triggered, a model position corresponding to the positioning icon is searched on the building model.
7. A storage medium having stored thereon a computer program, characterized in that the program, when being executed by a processor, implements a problem handling method of a field item as claimed in claim 3, or implements a supervision method of a field item as claimed in claim 6.
8. A terminal, comprising: a processor and a memory;
the memory is configured to store a computer program, and the processor is configured to execute the computer program stored by the memory to cause the terminal to perform the problem handling method of the field project of claim 3 or to implement the supervision method of the field project of claim 6.
CN201710432781.5A 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal Active CN107368996B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710432781.5A CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710432781.5A CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Publications (2)

Publication Number Publication Date
CN107368996A CN107368996A (en) 2017-11-21
CN107368996B true CN107368996B (en) 2021-03-26

Family

ID=60304797

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710432781.5A Active CN107368996B (en) 2017-06-09 2017-06-09 Method/system for problem handling/supervision of field project, storage medium, terminal

Country Status (1)

Country Link
CN (1) CN107368996B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108595865A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108595864A (en) * 2018-04-28 2018-09-28 四川隧唐科技股份有限公司 Disease preparation method and device
CN108629427A (en) * 2018-04-28 2018-10-09 四川隧唐科技股份有限公司 Disease preparation method and device
CN108647901A (en) * 2018-05-18 2018-10-12 四川隧唐科技股份有限公司 Disease preparation method and device
CN111832255A (en) * 2020-06-29 2020-10-27 万翼科技有限公司 Label processing method, electronic equipment and related product
CN112101904A (en) * 2020-09-15 2020-12-18 江南造船(集团)有限责任公司 Ship manufacturing site problem management method, system and device of three-dimensional model

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103886139A (en) * 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
CN104680588A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based event marking method and system
CN104766154A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 System and method for applying snapshot image to intellectualized engineering management on basis of BIM
CN105580048A (en) * 2014-03-18 2016-05-11 深圳市希图数创科技有限公司 Process management system for digital media production and method therefor

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014510330A (en) * 2011-01-25 2014-04-24 ティファニー・ホージー・ブラウン Construction information management, software, and methods for the construction industry

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103886139A (en) * 2014-02-27 2014-06-25 上海蓝色星球科技有限公司 Event interaction method based on building information model (BIM)
CN105580048A (en) * 2014-03-18 2016-05-11 深圳市希图数创科技有限公司 Process management system for digital media production and method therefor
CN104680588A (en) * 2015-02-13 2015-06-03 上海同筑信息科技有限公司 BIM-based event marking method and system
CN104766154A (en) * 2015-02-13 2015-07-08 上海同筑信息科技有限公司 System and method for applying snapshot image to intellectualized engineering management on basis of BIM

Also Published As

Publication number Publication date
CN107368996A (en) 2017-11-21

Similar Documents

Publication Publication Date Title
CN107368996B (en) Method/system for problem handling/supervision of field project, storage medium, terminal
CN107358401B (en) Intelligent management system/method for building project, readable storage medium and terminal
CN102197377B (en) Multi-touch object inertia simulation
EP2252926B1 (en) Interpreting ambiguous inputs on a touch-screen
US20160342779A1 (en) System and method for universal user interface configurations
US10592211B2 (en) Generation of application behaviors
CN102598012A (en) Password processing method and apparatus
CN104680588B (en) Event marker method and system based on BIM
US11205220B2 (en) System and method for visual traceability of requirements for products
CN103955339A (en) Terminal operation method and terminal equipment
CN104024983B (en) Interaction models for indirect interaction equipment
US20100271398A1 (en) System and method for manipulating digital images on a computer display
CN104995618A (en) Electronic book inscription system
CN107592929A (en) Annotation creates system and method
CN103135911A (en) Information processing method and electronic terminal
WO2012154628A2 (en) Interaction-based interface to a logical client
CN107357957A (en) Intelligent supervision method/system, readable storage medium storing program for executing and the terminal of live project
CN108885556A (en) Control numeral input
CN114629800B (en) Visual generation method, device, terminal and storage medium for industrial control network target range
CN115688112A (en) Industrial control risk assessment method, device, equipment and storage medium
CN107885452A (en) 3D Touch analogy methods and device, computer installation and computer-readable recording medium
CN106648280B (en) Task management interaction method and device
CN112596725A (en) Grading method and grading device for programming works, terminal equipment and storage medium
US20190324589A1 (en) Input device with touch sensitive surface
KR102211864B1 (en) Application user interface making tool

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant