CN107318121A CN201710527076.3A CN201710527076A CN107318121A CN 107318121 A CN107318121 A CN 107318121A CN 201710527076 A CN201710527076 A CN 201710527076A CN 107318121 A CN107318121 A CN 107318121A
Authority
CN
China
Prior art keywords
modules
epc
data
standby
epc system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710527076.3A
Other languages
Chinese (zh)
Other versions
CN107318121B (en
Inventor
晏建军
颜志凌
陶琴
邵鹄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Hongxin Technology Development Co Ltd
Original Assignee
Wuhan Hongxin Telecommunication Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Hongxin Telecommunication Technologies Co Ltd filed Critical Wuhan Hongxin Telecommunication Technologies Co Ltd
Priority to CN201710527076.3A priority Critical patent/CN107318121B/en
Publication of CN107318121A publication Critical patent/CN107318121A/en
Application granted granted Critical
Publication of CN107318121B publication Critical patent/CN107318121B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W24/00Supervisory, monitoring or testing arrangements
    • H04W24/04Arrangements for maintaining operational condition
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0654Management of faults, events, alarms or notifications using network fault recovery
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L41/00Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
    • H04L41/06Management of faults, events, alarms or notifications
    • H04L41/0654Management of faults, events, alarms or notifications using network fault recovery
    • H04L41/0668Management of faults, events, alarms or notifications using network fault recovery by dynamic selection of recovery network elements, e.g. replacement by the most appropriate element after failure

Abstract

The present invention provides a kind of data back up method for LTE EPC systems, two EPC systems, main EPC system and standby EPC system is set, wherein having EPC modules and OpenSAF modules, the network equipment;Main EPC system starts during all processes of EPC, when there is terminal to have business operation, then each process is in the corresponding each pieces number of data Cun Chudao for needing to back up, Backup Data is sent to OpenSAF, standby EPC system starts after EPC, the data of main EPC system backup are then received, each process, which is received, will take out data and reduce according to piece number after message;If standby EPC system does not start EPC processes, OpenSAF preserves the data of each process backup;To each block number according to the unique piece number of correspondence, when certain a piece of number backup n times, final reduction is once;Backup number of times is reduced, hot standby and cold standby is supported, backs up in realtime, incremental backup and monolithic backup function are realized to data structure, backup storage efficiency is improved.

Description

A kind of data back up method for LTE EPC systems
Technical field
The invention belongs to the communications field, it is related to a kind of data back up method for LTE EPC systems.
Background technology
With the fast development of the communication technology, enterprise uses the core data of computer disposal oneself, due to LTE (Long Term Evolution, Long Term Evolution) there is the spies such as high-speed, wide covering, low time delay, concurrent many, high stable, quick movement Property, it is very high to business continuance, real-time and stability requirement, to improve operating efficiency, reducing data disaster risk, reduction dimension Cost, enhanced quality-of-service are protected, continues not interrupt for guarantee business, and invents the data back up method of LTE EPC systems.
The content of the invention
The present invention provides one kind in EPC (Evolved Packet Core:Evolution block core net) data backup in system Method, there are abnormal conditions to solve EPC system, cause the scene communication systems such as track traffic, civil aviaton, colliery interrupt ask Topic.
To achieve the above object, the technical solution adopted by the present invention is:
A kind of data back up method for LTE EPC systems, including main EPC system, standby FPC systems, three interchangers, The main EPC system and standby EPC system install EPC softwares;, EPC softwares include MME modules, XGW modules, main modules, Trans modules and OpenSAf modules, MME modules, XGW modules, main modules, trans modules connect with OpenSAf modules respectively Connect;Main EPC system and standby EPC system are provided with three network interfaces, are connected respectively by three network interfaces with three interchangers, three One in interchanger is connected with base station, and one is connected with server;
When the data of backup find change, the data of main EPC system are backed up to OpenSAF modules, OpenSAF modules will Data storage and by OpenSAF modules on network backup to standby EPC system, which process is OpenSAF modules be by judging Data, data are dealt into corresponding module, each module receives message solution packet, and restoring data.
Data backup is divided into two kinds of situations, and one kind is cold standby, after starting when standby EPC system needs, main EPC system handle The data of all backups backup to standby EPC system, and standby EPC system is switched to when required;One kind is Hot Spare, main EPC systems After system starts, standby EPC system also starts, and standby EPC system keeps synchronous with main EPC system.When main frame failure, it can open at any time Replaced with hot-standby server.
When the main EPC system, standby EPC system startup go into operation, XGW modules need to receive after mian module messages, XGW moulds Block sends out the message that goes into operation to trans modules, while XGW modules normally go into operation;
Backup Data is needed in MME modules or XGW modules, MME modules or XGW modules can be triggered by the data of backup Main EPC system OpenSAF modules are issued in packing, and the OpenSAF modules of main EPC system issue standby EPC system by network OpenSAF modules, the OpenSAF modules of standby EPC system receive data by processing, relay to corresponding module, corresponding Scheduler module receives restoring data after data.
If the main EPC system of monitoring goes wrong or restarts or the abnormal conditions such as power off, OpenSAF is switched to for EPC System, the service switching such as ATTACH DETACH TAU SR X2S1HO to standby EPC system, standby EPC system becomes as main EPC system.
Moreover, after the main EPC system starts, having after the access of base station, triggering MME modules back up eNodeB and SCTP respectively Business datum, and back up data to the MME modules of standby EPC system.
Moreover, after the main EPC system starts, have after terminal access, triggering MME modules and XGW modules back-up terminals and The business datum in tunnel, and back up data to standby EPC system MME modules and XGW modules.
Moreover, described set up dedicated bearing according to configuration, after UE accesses, triggering MME modules and XGW modules back-up terminals, The relevant information of dedicated bearing, tunnel, and back up data to standby EPC system MME modules and XGW modules.
Moreover, described by calling HaBackupSctpData () and HaBackupSzData () function backup eNodeB Information, then the former information using szOspMsgProc () reduction backups eNodeB.
Moreover, it is described by call HaBackupUeData (), HaBackupCCEnbData () and HaBackupBrData () function backup UE information, then the former information using CcOspMsgPreProc () reduction backups UE.
Moreover, the information by calling HaBackupXgwData () function backup tunnel, then original are used GtpuHaRevertData () reduces the information of backup tunnel.
The main of technical solution of the present invention is improved to:
1. using the present invention program, increase data can be with incremental backup.
2. data convert has increase, deleted and modification operation, first judge whether there are data when addition is operated, if Then when renewal is handled;Otherwise when addition is handled.It is to update operation first to judge whether there are data, is first added if without if Processing;Otherwise renewal is handled.
3. system can recover all business in 400ms.
4. upon handover, first remove main EPC system SGW and PGW IP, in the IP with the EPC system SGW and PGW that purchase.
The technical scheme is relative to the advantage of other Integrated Solutions:
For relative thermal is for integrated scheme, the present invention using burst backup, per it is a piece of can be complete to a certain data structure Office's backup can have very big flexibility with incremental backup again;Each module has up to ten million pieces, and each piece has a volume Number, data storage is placed in fixed numbering, when a certain data variation is very frequent, it is possible to achieve OpenSAF modules last time Standby EPC system is backuped to, backup number of times is reduced.
For relative thermal is for integrated scheme, the present invention can back up the data of up to ten million pieces, and each module has thousands of Ten thousand pieces.
Therefore, the present invention realizes that conveniently, backup data quantity is big, high efficiency, high stability, with important market value, It is that guarantee business continues not interrupt most practical plan.
Brief description of the drawings
Fig. 1 is the theory diagram of the present invention.
110-UE, 120-LTE base station, the 130-the first interchanger, 131-second switch, 132-3rd switch, 140-main EPC system, 141-OpenSAf modules, 142-MME modules, 143-XGW modules, 144-main modules, 145- Trans modules, the network interface 3 of network interface 2,148-main EPC system of network interface 1,147-main EPC system of 146-main EPC system, 150-standby EPC system, 156-from the network interface 1,157 of EPC system-from the network interface 2,158 of EPC system-from the net of EPC system Mouth 3,160-server.
Embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, it is right below in conjunction with drawings and Examples The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only to explain the present invention, not For limiting the present invention.
As shown in figure 1, being that there is provided a kind of method in EPC system data backup for one embodiment of the present of invention.
The platform of technical solution of the present invention operation supports the linux operating systems of OpenSAF modules for kernel.Embodiment In, main EPC system 140 and standby EPC system 150 are arranged on the linux main frames of centos6.5 systems, and have successfully loaded OpenSAF kernel modules.In the present invention program, advocate peace standby EPC system MME modules, XGW modules, main modules, trans moulds Block and OpenSAf modules will be run simultaneously.Main EPC system 140 is to do business, and standby EPC system 150 does not do business, only receives master The data that EPC system 140 is backed up;Main EPC system 140 uses netting twine 4 by network interface 1 (146), passes through interchanger 131 and standby EPC The network interface 1 (156) of system 150 is communicated, and realizes data backup.
ENodeB (120) is LTE base station, is that ue (110) provides wireless coverage and information transmission, this reality within the specific limits Apply in example, main EPC system 140 and standby EPC system 150 are connected with eNodeB (120) using same IP address position 172.16.137.56, the ip of main EPC system 140 is set to 172.16.137.56, what the IP of standby EPC system 150 was to turn off, does not have There is ip.
Main EPC system 140 and standby EPC system 150 are connected with server (160) and are using same IP address 172.16.114.200, the IP of main EPC system 140 is set to 172.16.114.200, what the IP of standby EPC system 150 was to turn off, There is no IP.
ENodeB (120) is that LTE base station is first connected with the foundation of main EPC system 140, walks regular traffic flow;Standby EPC system Operation flow is not walked after 145 initialization, when main EPC system 140 is switched to standby EPC system 150, main EPC system 140 is first closed Network interface 2 (147) and network interface 3 (148), are reconfigured at the main network interface 2 (157) of EPC system 150 and network interface 3 (158), receive main modules After 154 message, XGW modules 153 start the request that goes into operation, while notifying trans modules 155 to start working.
EPC software function codes are installed on main EPC system 140 and standby EPC system 150 to be needed at " XGW go into operation request " " MME go into operation request " two parts make modification processing.
Modification " XGW the go into operation request " part, refers to that on active/standby server EPC programs go into operation when asking, is revised as Receive and gone into operation after the message of main modules, while sending the message that goes into operation to trans modules.
Modification " MME the go into operation request " part, S1 processes receive the correlation whether reading parameter after message initializes S1 Information.
EPC softwares are installed, function code needs at " XGW module datas backup and reduction " and " backup of MME module datas is also Original " two parts make modification processing.
Described modification " MME module datas backup and reduction " part, the MME module datas of main EPC system backup to standby EPC systems System, standby EPC system MME modules are by data convert.
When eNodeB is accessed.Concrete operations are:At the end of a certain flow, the MME modules of main EPC system call backup After group of functions bag, data are sent out after sending data, main EPC system OpenSAF resume modules to main EPC system OpenSAF modules To standby EPC system OpenSAF modules, message is then sent out to standby EPC system when standby EPC system OpenSAF modules there are data to update MME modules, MME modules unpack and preserve data.
The backup function group bag, backup function will be called by referring to the MME module interfaces of main EPC system, fill in task number, Piece number, data length, data type, Data Identification, sync id and synchrodata.
Described unpacking simultaneously preserves data, is the data that standby EPC system receives main EPC system, according to task number, a certain Receive the data of backup under task, line obtains piece number, according to piece number corresponding data convert into corresponding data structure.
Embodiment is specifically comprised the following steps:
Pass through HaBackupUeData (CC_UE_STRUCT_TYPE, ueNum, ueIndex, (&gp_CcCb-> UeCbList [ueIndex], sizeof (CcUeCb)) backup ueIndex data,
Osp_send_ha_data_msg (OspHaMsg) is called after completion group bag;Function sends out OspHaMsg data structures Give OpenSAF modules.
Standby EPC system OpenSAF modules are received after message, send message to corresponding dtaskid, MME modules, which are received, to disappear Piece number, data length, data type, Data Identification, sync id, in memcpy () data to corresponding data are first solved after breath In structure, data backup is completed
Described modification " XGW module datas backup and reduction " part, the XGW module datas of main EPC system backup to standby EPC systems System, standby EPC system XGW modules are by data convert.
When eNodeB is accessed.Concrete operations are:It is cunicular to set up, operation, the XGW of main EPC system is deleted or modified Module is called after backup function group bag, is sent to main EPC system OpenSAF modules at data, main EPC system OpenSAF modules Data are issued into standby EPC system OpenSAF modules after reason, when standby EPC system OpenSAF modules have data update then hair message to The XGW modules of standby EPC system, XGW modules unpack and preserve data, while needing the operation to three RBTrees.
The backup function group bag, backup function will be called by referring to the XGW module interfaces of main EPC system, fill in task number, Piece number, data length, data type, Data Identification, sync id and synchrodata.
Described unpacking simultaneously preserves data, is the data that standby EPC system receives main EPC system, according to task number, a certain Receive the data of backup under task, line obtains piece number, according to piece number corresponding data convert into corresponding data structure.
Embodiment is specifically comprised the following steps:
Pass through HaBackupXgwData (GTPU_INFO_STRUCT_TYPE, EPC_MSG_UPDATE, * pPos, (u8*) PTunnelInfo, sizeof (TGtpuTunnelInfo)) backup TGtpuTunnelInfo data,
Osp_send_ha_data_msg (OspHaMsg) is called after completion group bag;Function sends out OspHaMsg data structures Give OpenSAF modules.
Standby EPC system OpenSAF modules are received after message, send message to corresponding dtaskid, XGW modules, which are received, to disappear Piece number, data length, data type, Data Identification, sync id, in memcpy () data to corresponding data are first solved after breath In structure, data backup is completed, while the operation according to type parameters to three RBTrees.
The operation of three RBTrees, refers to be added RBTree, changes and deletion action.
Finally, when main EPC system occurs abnormal, main EPC system is switched to standby EPC system by OpenSAF modules, standby EPC system becomes as main EPC system, and main EPC system is changed into standby EPC system.
When it is implemented, those skilled in the art can realize above technical scheme using software mode, you can realize main EPC The data automatic synchronization of the data of system and standby EPC system, it is ensured that main EPC system occur abnormal conditions can seamlessly switch to it is standby EPC system.The present invention can reduce data disaster risk, reduction maintenance cost, enhanced quality-of-service, during guarantee business continues not It is disconnected.
Main EPC system 140 and standby EPC system 150 are same set of software, and hardware can be unified to configure, the realization of embodiment It is as follows:
When main EPC system starts initialization, main EPC system starts according to normal flow;Standby EPC system starts initialization, Partial parameters are without initialization in MME, and XGW modules will send message to trans;
The MME modules of main EPC system are called after backup function group bag, standby EPC system is dealt into by OpenSAF modules MME modules, call reduction group of functions to unpack, realize data backup;
The XGW modules of main EPC system are called after backup function group bag, standby EPC system is dealt into by OpenSAF modules XGW modules, call reduction group of functions to unpack, data backup are realized, while being operated accordingly to three RBTrees.
Implement it is consistent with software realization mode, the present invention it will not go into details.
Related symbol implication see the table below 1:
Table 1 is ordered and character lexical or textual analysis
The foregoing is only one of embodiments of the invention, be not intended to limit the invention, it is all the present invention principle it Interior made any modifications, equivalent substitutions and improvements etc., should be included in the scope of the protection.

Claims (9)

1. a kind of data back up method for LTE EPC systems, it is characterised in that:Including main EPC system, standby EPC system;When When the data of backup change, the data of main EPC system are backed up in realtime to standby EPC system by OpenSAF modules Data are dealt into corresponding module and solve packet restoring data by OpenSAF modules, OpenSAF modules.
2. a kind of data back up method for LTE EPC systems according to claim 1, it is characterised in that:The master EPC system, standby EPC system include MME modules, XGW modules, main modules, trans modules and OpenSAf modules.
3. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:MME moulds When needing Backup Data in block or XGW modules, MME modules or XGW modules can be triggered by the data group bag of backup to main EPC System OpenSAF modules, the OpenSAF modules of main EPC system issue the OpenSAF modules of standby EPC system by network, standby The OpenSAF modules of EPC system receive data by processing, are transmitted to corresponding module, and respective modules are received and reduced after data Data.
4. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:The master EPC system module goes wrong or restarted or powering-off state, and OpenSAF is switched to standby EPC system, ATTACH DETACH TAU SR X2 S1HO service switchings are to standby EPC system, and standby EPC system change is main EPC system.
5. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:The master After EPC system starts, have after the access of base station, triggering MME modules back up eNodeB and UE business datum respectively, and data are standby Part arrives the MME modules of standby EPC system.
6. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:The master After EPC system starts, have after terminal access, triggering MME modules and XGW module back-up terminals business datums, and by data backup To standby EPC system MME modules and XGW modules;After terminal access, triggering MME modules and XGW modules back-up terminals, dedicated bearing Relevant information, and back up data to standby EPC system MME modules and XGW modules.
7. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:The number Include two kinds of situations according to backup, one kind is cold standby, after starting when standby EPC system needs, main EPC system is all backups Data backup to standby EPC system, and standby EPC system is switched to when required;One kind is Hot Spare, standby after main EPC system starts EPC system also starts, and standby EPC system keeps synchronous with main EPC system.
8. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:It is each whole Data one unique memory space of correspondence at end, when multiple data variation occurs for some UE data, reverts to standby EPC system Last time last time, improves backup efficiency.
9. a kind of data back up method for LTE EPC systems according to claim 2, it is characterised in that:
By calling HaBackupSctpData()And HaBackupSzData()Function backup eNodeB information, then original are used szOspMsgProc()Reduce backup eNodeB information;
By calling HaBackupUeData()、HaBackupCCEnbData()And HaBackupBrData()Function backup UE Information, then original uses CcOspMsgPreProc()Reduce backup UE information;
By calling HaBackupXgwData()The information of function backup tunnel, then original use GtpuHaRevertData()Also The information of former backup tunnel.
CN201710527076.3A 2017-06-30 2017-06-30 Data backup method for LTE EPC system Active CN107318121B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710527076.3A CN107318121B (en) 2017-06-30 2017-06-30 Data backup method for LTE EPC system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710527076.3A CN107318121B (en) 2017-06-30 2017-06-30 Data backup method for LTE EPC system

Publications (2)

Publication Number Publication Date
CN107318121A true CN107318121A (en) 2017-11-03
CN107318121B CN107318121B (en) 2020-11-20

Family

ID=60181283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710527076.3A Active CN107318121B (en) 2017-06-30 2017-06-30 Data backup method for LTE EPC system

Country Status (1)

Country Link
CN (1) CN107318121B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106470117A (en) * 2015-08-21 2017-03-01 成都鼎桥通信技术有限公司 The transmission changing method of LTE broadband cluster system, equipment and system
CN114007238A (en) * 2020-07-28 2022-02-01 海能达通信股份有限公司 Method and device for service recovery after local point failure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101127588A (en) * 2007-10-11 2008-02-20 华为技术有限公司 A failure processing method, system and device for wireless network controller
CN103684839A (en) * 2012-09-26 2014-03-26 中国移动通信集团四川有限公司 Data transmission method for hot standby, system and server
US8804494B1 (en) * 2012-04-04 2014-08-12 Wichorus, Inc. Methods and apparatus for improving network performance using virtual instances for system redundancy
CN104284359A (en) * 2014-06-17 2015-01-14 南京邮电大学 Trans-regional disaster tolerant system under EPC network and control method
CN105897486A (en) * 2016-06-07 2016-08-24 武汉邮电科学研究院 Hot backup method of SCTP

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101127588A (en) * 2007-10-11 2008-02-20 华为技术有限公司 A failure processing method, system and device for wireless network controller
US8804494B1 (en) * 2012-04-04 2014-08-12 Wichorus, Inc. Methods and apparatus for improving network performance using virtual instances for system redundancy
CN103684839A (en) * 2012-09-26 2014-03-26 中国移动通信集团四川有限公司 Data transmission method for hot standby, system and server
CN104284359A (en) * 2014-06-17 2015-01-14 南京邮电大学 Trans-regional disaster tolerant system under EPC network and control method
CN105897486A (en) * 2016-06-07 2016-08-24 武汉邮电科学研究院 Hot backup method of SCTP

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106470117A (en) * 2015-08-21 2017-03-01 成都鼎桥通信技术有限公司 The transmission changing method of LTE broadband cluster system, equipment and system
CN106470117B (en) * 2015-08-21 2019-10-11 成都鼎桥通信技术有限公司 Transmission switching method, equipment and the system of LTE broadband cluster system
CN114007238A (en) * 2020-07-28 2022-02-01 海能达通信股份有限公司 Method and device for service recovery after local point failure

Also Published As

Publication number Publication date
CN107318121B (en) 2020-11-20

Similar Documents

Publication Publication Date Title
US6920320B2 (en) Method and apparatus for stable call preservation
CN1327728C (en) Method for realizing mobile switching center double ownerships
CN104284359B (en) Trans-regional disaster tolerance system and control method under a kind of EPC networks
CN101729426B (en) Method and system for quickly switching between master device and standby device of virtual router redundancy protocol (VRRP)
CN111193637B (en) Core network switching method, device, communication system, equipment and storage medium
US20220361056A1 (en) Communication Path Switching Method and Device
CN105376768A (en) Pool disaster recovery method and system for mobility management entity
CN106888475B (en) Wireless system processing method, device and base station
CN102957623A (en) Maintenance method and equipment of neighborhood of border gate protocol
CN107318121A (en) A kind of data back up method for LTE EPC systems
CN101166309B (en) A method for realizing user data synchronization in dual home system
CN102045187A (en) Method and equipment for realizing HA (high-availability) system with checkpoints
CN108419258B (en) Processing method for network communication function abnormity, modem and mobile terminal
CN103812697A (en) Remote disaster recovery method and remote disaster recovery system of distributed communication network
WO2000051366A2 (en) Time management using common channel signalling in a cellular telecommunication network
CN101188787B (en) Disaster tolerance method and system for home register
CN101217405B (en) SGSN backup method and communication system, communication device
CN108307522B (en) Method and device for processing radio bearer, terminal and base station
CN108282804B (en) Processing method for network communication function abnormity, application processor and mobile terminal
US8666404B2 (en) Method and apparatus for unloading terminal quickly
CN101325738B (en) Method and apparatus for repairing fault of mobile communication core network register
CN104582002B (en) The method and device that resource discharges in satellite mobile communication system
CN111314272B (en) Task processing method and device
CN108668307B (en) Called service recovery processing method, mobility management entity and service gateway
CN100571154C (en) The method of a kind of global data dynamic synchronization between multimode

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TA01 Transfer of patent application right

Effective date of registration: 20201106

Address after: 430205 No.1 tanhu 2nd Road, Canglong Island, Jiangxia Economic Development Zone, Wuhan City, Hubei Province

Applicant after: Wuhan Hongxin Technology Development Co.,Ltd.

Address before: 430073 Hubei province Wuhan Dongxin East Lake high tech Development Zone, Road No. 5

Applicant before: Wuhan Hongxin Telecommunication Technologies Co.,Ltd.

TA01 Transfer of patent application right