CN107300647A - A kind of intelligent substation relay protection distributed test method - Google Patents

A kind of intelligent substation relay protection distributed test method Download PDF

Info

Publication number
CN107300647A
CN107300647A CN201710423165.3A CN201710423165A CN107300647A CN 107300647 A CN107300647 A CN 107300647A CN 201710423165 A CN201710423165 A CN 201710423165A CN 107300647 A CN107300647 A CN 107300647A
Authority
CN
China
Prior art keywords
test
distributed
test terminal
signal generator
protective relaying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710423165.3A
Other languages
Chinese (zh)
Inventor
周震宇
盛海华
杨建华
周宗庚
奚洪磊
江涌
杨振
潘武略
周芳
王黎敏
林群
梅宏
刘曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Zhejiang Electric Power Co Ltd
Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Zhejiang Electric Power Co Ltd, Wenzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710423165.3A priority Critical patent/CN107300647A/en
Publication of CN107300647A publication Critical patent/CN107300647A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The present invention relates to a kind of intelligent substation relay protection distributed test method, the irrational deficiency of protective relaying device method of testing in the prior art is solved.A kind of intelligent substation relay protection distributed test method that the present invention is provided; multiple distributed signal generators are connected with test terminal using spare fibre; to be tested protective relaying device by testing terminal test; test process is directly perceived, continuous, is conducive to improving the certainty of protective relaying device check test;When testing protective relaying device, test terminal can be tested multiple relay protectors simultaneously, reduce the labor intensity of technical staff;One-touch check test is realized in intelligent substation scene relay protection, improves testing efficiency, and scene is adaptable.

Description

A kind of intelligent substation relay protection distributed test method
Technical field
The present invention relates to the method for testing of electric network protection device, more particularly to a kind of intelligent substation relay protection are distributed Method of testing.
Background technology
The major function of power network is that by power end electric energy is delivered into load side, with for users to use.To ensure power network Stable operation, access has a variety of protection devices in power network, to cut off the failure in power network in power network local fault, keeps away Exempt from electric grid large area failure.Protection device answers routine test, it is to avoid protection device tripping causes electric network fault.
When testing in the prior art protection device, method of testing is unreasonable, causes protection device testing efficiency low, and And, easily occur the problems such as test leakage, wrong survey in actual test.
The content of the invention
A kind of intelligent substation relay protection distributed test method that the present invention is provided, it is intended to overcome prior art to relay The irrational deficiency of electrical protective device method of testing.
In order to solve the above-mentioned technical problem, the present invention is adopted the following technical scheme that:A kind of intelligent substation relay protection point Cloth method of testing, comprises the following steps:
A, using live spare fibre by least two distributed signal generators with test terminal be connected, test terminal and At least two distributed signal generators are communicated by spare fibre;
All distributed signal generators being connected with test terminal of b, test terminal inquiry, and according to the mark of spare fibre Label detect whether there is wiring error, there is wiring error, and next step is entered after modification, is directly entered during in the absence of wiring error Enter next step;
C, in test terminal the test parameter list of protective relaying device to be measured is set, makes distributed signal generator Numbering is corresponded with the numbering in protective relaying device test parameter list to be measured, and is passed test parameter using spare fibre Transport to distributed signal generator;
E, regulation test terminal clock, the clock of distributed signal generator, make the clock and distribution of test terminal The clock of signal generator is synchronous;
F, test terminal clock it is synchronous with the clock of distributed signal generator in the state of, start test;
G, test terminal are when receiving protective relaying device GOOSE message to be measured and confirming protection act, synchronous averaging point Cloth signal generator state switches;
H, distributed signal generator export next shape according to the status switching instruction of test parameter list and test terminal State signal records live action feedback information to terminal, distributed signal generator is tested;
Test ending message is fed back to test terminal by i, distributed signal generator after END instruction is received;
J, distributed signal generator transmit test signal output data and live action feedback data to test terminal;
K, test terminal are dynamic according to live action information, each distributed signal generator test signal output data, scene Make feedback data formation test result;
L, test terminal preserve test result, and test terminates.
A kind of optional scheme, the inserting step d between step c and step e, the step d:Need to check relay to be measured During the definite value of protection device, test terminal reads the definite value of protective relaying device to be measured, and by the definite value of the reading with it is to be measured after The standard value of electrical protective device is compared, when definite value is consistent with standard value, into step e, when definite value and inconsistent standard value Stop the test of the protective relaying device.The step mainly for detection of protective relaying device definite value and standard value whether one Cause, so as to be effectively prevented from protection device mistake survey, improve the degree of accuracy of protective relaying device test.
A kind of END instruction in optional scheme, the step i is sent by test terminal.The program is easy to operate, skill Art personnel can easily control to test whether to terminate, and optimize the performance of test terminal.
A kind of END instruction in optional scheme, the step i is terminated by test parameter list information in signal output Test ending message is sent to distributed signal generator afterwards.Program test parameter list information carries END instruction, letter Change operation during relay protection test, reduce the labor intensity of technical staff.
Tested in a kind of optional scheme, the step l after terminal preserves test result and pass through test result on network Reach Cloud Server.Test result is uploaded to Cloud Server, related technical staff can easily consult, analyze, favorably In the maintenance of power network.
Compared with prior art, a kind of intelligent substation relay protection distributed test method that the present invention is provided, has Following advantage:Multiple distributed signal generators are connected by the method for testing using spare fibre with test terminal, with by surveying Try terminal test and be tested protective relaying device, test process is directly perceived, continuous, is conducive to improving protective relaying device check test Certainty;When testing protective relaying device, test terminal can be tested multiple relay protectors simultaneously, reduced The labor intensity of technical staff;One-touch check test is realized in intelligent substation scene relay protection, improves testing efficiency, scene It is adaptable.
Embodiment
A kind of intelligent substation relay protection distributed test method of the present invention is described further below.Following reality Apply example to be only used for helping skilled in the art to understand the present invention, be not limitation of the present invention.
Relay protection test refers to test protective relaying device using test equipment, to verify protective relaying device Whether can be operating normally, it is to avoid in grid collapses, protective relaying device tripping causes electric grid large area failure.Relay Protect test should easy to operate, test it is accurate.
A kind of intelligent substation relay protection distributed test method, comprises the following steps:
A, using live spare fibre by least two distributed signal generators with test terminal be connected, test terminal and At least two distributed signal generators are communicated by spare fibre;Signal generator, test terminal are of the prior art Conventional equipment, distributed signal generator is connected with protective relaying device;
All distributed signal generators being connected with test terminal of b, test terminal inquiry, and according to the mark of spare fibre Label detect whether there is wiring error, there is wiring error, next step are entered after modification, it is wrong that reclosing wiring can exclude wiring By mistake, it is directly entered next step during in the absence of wiring error;
C, in test terminal the test parameter list of protective relaying device to be measured is set, makes distributed signal generator Numbering is corresponded with the numbering in protective relaying device test parameter list to be measured, and is passed test parameter using spare fibre Transport to distributed signal generator;
Step d is optional step, the step d:When needing to check the definite value of protective relaying device to be measured, test terminal is read The definite value of protective relaying device to be measured is taken, and the definite value of the reading and the standard value of protective relaying device to be measured are compared, When definite value is consistent with standard value, into step e, definite value stops the test of the protective relaying device with standard value when inconsistent, stop Only the test of the protective relaying device refers to stop definite value and the test of the inconsistent protective relaying device of standard value, has no effect on The test of other protective relaying devices, it is to be tested finish after, the protective relaying device inconsistent to definite value and standard value is individually surveyed Examination;
E, regulation test terminal clock, the clock of distributed signal generator, make the clock and distribution of test terminal The clock of signal generator is synchronous;
F, test terminal clock it is synchronous with the clock of distributed signal generator in the state of, start test;
G, test terminal are when receiving protective relaying device GOOSE message to be measured and confirming protection act, synchronous averaging point Cloth signal generator state switches;
H, distributed signal generator export next shape according to the status switching instruction of test parameter list and test terminal State signal records live action feedback information to terminal, distributed signal generator is tested;
Test ending message is fed back to test terminal by i, distributed signal generator after END instruction is received;
END instruction in the step i is sent by test terminal;
Or, the END instruction in the step i is tied test after signal output terminates by test parameter list information Beam information is sent includes END instruction to distributed signal generator, i.e. parameter list information;
J, distributed signal generator transmit test signal output data and live action feedback data to test terminal;
K, test terminal are dynamic according to live action information, each distributed signal generator test signal output data, scene Make feedback data formation test result;
L, test terminal preserve test result, and test terminates.Test terminal passes through test result after preserving test result Network is uploaded to Cloud Server, so that related personnel consults.
Such scheme is relative to prior art, and relay protection test is simple to operate, and testing efficiency is high, reduces technical staff Labor intensity.
The section Example of the present invention is described in detail above.Those skilled in the art are read after this specification, Based on technical scheme, above-described embodiment can be modified, these modifications still fall within protection scope of the present invention.

Claims (5)

1. a kind of intelligent substation relay protection distributed test method, it is characterised in that comprise the following steps:
A, using live spare fibre at least two distributed signal generators be connecteds with test terminal, test terminal and at least Two distributed signal generators are communicated by spare fibre;
All distributed signal generators being connected with test terminal of b, test terminal inquiry, and examined according to the label of spare fibre Survey and whether there is wiring error, there is wiring error, next step is entered after modification, is directly entered down during in the absence of wiring error One step;
C, in test terminal the test parameter list of protective relaying device to be measured is set, makes the numbering of distributed signal generator With in protective relaying device test parameter list to be measured numbering correspond, and using spare fibre by test parameter transmit to Distributed signal generator;
E, regulation test terminal clock, the clock of distributed signal generator, make the clock and distributed signal of test terminal The clock of generator is synchronous;
F, test terminal clock it is synchronous with the clock of distributed signal generator in the state of, start test;
G, test terminal are when receiving protective relaying device GOOSE message to be measured and confirming protection act, and synchronous averaging is distributed Signal generator state switches;
H, distributed signal generator are according to test parameter list and the status switching instruction output NextState letter of test terminal Number to test terminal, distributed signal generator record live action feedback information;
Test ending message is fed back to test terminal by i, distributed signal generator after END instruction is received;
J, distributed signal generator transmit test signal output data and live action feedback data to test terminal;
K, test terminal are anti-according to live action information, each distributed signal generator test signal output data, live action Present data formation test result;
L, test terminal preserve test result, and test terminates.
2. a kind of intelligent substation relay protection distributed test method according to claim 1, it is characterised in that:In step Rapid inserting step d between c and step e, the step d:When needing to check the definite value of protective relaying device to be measured, test terminal is read The definite value of protective relaying device to be measured is taken, and the definite value of the reading and the standard value of protective relaying device to be measured are compared, When definite value is consistent with standard value, into step e, definite value stops the test of the protective relaying device with standard value when inconsistent.
3. a kind of intelligent substation relay protection distributed test method according to claim 1, it is characterised in that:It is described END instruction in step i is sent by test terminal.
4. a kind of intelligent substation relay protection distributed test method according to claim 1, it is characterised in that:It is described END instruction in step i is sent test ending message to distribution after signal output terminates by test parameter list information Signal generator.
5. a kind of intelligent substation relay protection distributed test method according to claim 1, it is characterised in that:It is described Test result is uploaded to Cloud Server by network after test terminal preservation test result in step l.
CN201710423165.3A 2017-06-07 2017-06-07 A kind of intelligent substation relay protection distributed test method Pending CN107300647A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710423165.3A CN107300647A (en) 2017-06-07 2017-06-07 A kind of intelligent substation relay protection distributed test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710423165.3A CN107300647A (en) 2017-06-07 2017-06-07 A kind of intelligent substation relay protection distributed test method

Publications (1)

Publication Number Publication Date
CN107300647A true CN107300647A (en) 2017-10-27

Family

ID=60134801

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710423165.3A Pending CN107300647A (en) 2017-06-07 2017-06-07 A kind of intelligent substation relay protection distributed test method

Country Status (1)

Country Link
CN (1) CN107300647A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108802547A (en) * 2018-06-12 2018-11-13 国网江苏省电力有限公司电力科学研究院 A kind of relay protection device of intelligent substation Auto-Test System and method based on cloud storage
CN109687411A (en) * 2018-12-28 2019-04-26 国网浙江省电力有限公司电力科学研究院 A kind of definite value simultaneously operating method and apparatus for distributed element protection
CN109787186A (en) * 2017-11-15 2019-05-21 中国电力科学研究院有限公司 A kind of multistage power grid wide area definite value check method and system based on cloud platform
CN110470933A (en) * 2019-08-27 2019-11-19 小波科技有限公司 A kind of distributed intelligence substation relay protection test device
CN110471354A (en) * 2019-08-27 2019-11-19 小波科技有限公司 A kind of controlling terminal structure
CN110519000A (en) * 2019-08-27 2019-11-29 小波科技有限公司 A kind of distributed signal generator
CN111487492A (en) * 2020-04-20 2020-08-04 国网河南省电力公司新乡供电公司 Digital input power amplifier and test system of distributed relay protection system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799501A (en) * 2010-03-26 2010-08-11 河南电力试验研究院 One-key type test method for optical digital relay protection devices
CN102608464A (en) * 2012-03-21 2012-07-25 山东电力集团公司济南供电公司 Modularized automatic test assembly system of rely protection device and test method of modularized automatic test assembly system
CN103245855A (en) * 2013-04-23 2013-08-14 国家电网公司 Digital simulation based method and system for testing relay protection function of intelligent substation
CN104459385A (en) * 2014-11-25 2015-03-25 国家电网公司 Relay protection automatic testing method
CN105116248A (en) * 2015-08-05 2015-12-02 国家电网公司 Automatic closed-loop test method for intelligent transformer station relay protection equipment
CN105301419A (en) * 2015-12-03 2016-02-03 中国电力科学研究院 Cloud-technology-based automatic test system for protective relaying device
CN105467233A (en) * 2015-11-16 2016-04-06 国家电网公司 Intelligent substation local relay protection test system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101799501A (en) * 2010-03-26 2010-08-11 河南电力试验研究院 One-key type test method for optical digital relay protection devices
CN102608464A (en) * 2012-03-21 2012-07-25 山东电力集团公司济南供电公司 Modularized automatic test assembly system of rely protection device and test method of modularized automatic test assembly system
CN103245855A (en) * 2013-04-23 2013-08-14 国家电网公司 Digital simulation based method and system for testing relay protection function of intelligent substation
CN104459385A (en) * 2014-11-25 2015-03-25 国家电网公司 Relay protection automatic testing method
CN105116248A (en) * 2015-08-05 2015-12-02 国家电网公司 Automatic closed-loop test method for intelligent transformer station relay protection equipment
CN105467233A (en) * 2015-11-16 2016-04-06 国家电网公司 Intelligent substation local relay protection test system
CN105301419A (en) * 2015-12-03 2016-02-03 中国电力科学研究院 Cloud-technology-based automatic test system for protective relaying device

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109787186A (en) * 2017-11-15 2019-05-21 中国电力科学研究院有限公司 A kind of multistage power grid wide area definite value check method and system based on cloud platform
CN109787186B (en) * 2017-11-15 2022-08-09 中国电力科学研究院有限公司 Cloud platform based multi-stage power grid wide area fixed value checking method and system
CN108802547A (en) * 2018-06-12 2018-11-13 国网江苏省电力有限公司电力科学研究院 A kind of relay protection device of intelligent substation Auto-Test System and method based on cloud storage
CN109687411A (en) * 2018-12-28 2019-04-26 国网浙江省电力有限公司电力科学研究院 A kind of definite value simultaneously operating method and apparatus for distributed element protection
CN110470933A (en) * 2019-08-27 2019-11-19 小波科技有限公司 A kind of distributed intelligence substation relay protection test device
CN110471354A (en) * 2019-08-27 2019-11-19 小波科技有限公司 A kind of controlling terminal structure
CN110519000A (en) * 2019-08-27 2019-11-29 小波科技有限公司 A kind of distributed signal generator
CN111487492A (en) * 2020-04-20 2020-08-04 国网河南省电力公司新乡供电公司 Digital input power amplifier and test system of distributed relay protection system

Similar Documents

Publication Publication Date Title
CN107300647A (en) A kind of intelligent substation relay protection distributed test method
CN105373655B (en) A kind of method of one electrical secondary system connection figure of organic association Intelligent transformer station
CN106124935A (en) Middle and low voltage network Fault Locating Method
CN102361346A (en) Master station full-digital scene testing method of power distribution automation system
CN104539473A (en) Whole-group verification method and system for network virtual secondary loop of intelligent substation
CN101871988A (en) System and method for positioning medium voltage distribution network using power line carrier communication
CN103066700B (en) Power grid fault information processing method and system
CN104062543B (en) High-power transformer homodyne protects polarity verification method and homodyne protective calibration method
CN101551442B (en) A generator rotor insulation on-line monitoring grounding locating method and device
KR102262653B1 (en) System for circuit breaker simulation and analysis
Cheng et al. Protection and Control Challenges of Low-Voltage Networks with High Distributed Energy Resources Penetration-Part 1: Utility Workshop and Low-Voltage Network Modeling
CN109581098A (en) The intelligent O&M test method of site protective device
CN104795804A (en) Auxiliary relay protection monitoring processing system and processing method thereof
CN104299172A (en) Power grid weak link comprehensive recognition method
CN108008236A (en) A kind of method for detecting electrical equipment fault
Lifan et al. The Experiences of Decentralized Self-Healing Grid
CN106533739A (en) Process layer network port fault positioning method and device
CN102520303A (en) Detector and detection method for alternating-current loops of wind generation set
CN109599828A (en) Trouble analysis system and method based on high-speed railway tractive power supply system
Kamps et al. Reliability of decentralized network automation systems and impacts on distribution network reliability
CN102508052A (en) Test method for field band channel operation of automatic bus transfer system of area network
CN206292365U (en) Relay protection operation case actuating of relay characteristic tester and its automatic wire-changing device
Tlusty et al. The monitoring of power system events on transmission and distribution level by the use of phasor measurements units (PMU)
CN111342554B (en) Automatic identification system and method for topology of transformer area
CN106600451A (en) Power grid fault diagnosis graphic element graphical display interface system based on plug-in architecture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171027