CN107292470A - Visualize power network diagnosis of the status quo analysis system - Google Patents

Visualize power network diagnosis of the status quo analysis system Download PDF

Info

Publication number
CN107292470A
CN107292470A CN201610218311.4A CN201610218311A CN107292470A CN 107292470 A CN107292470 A CN 107292470A CN 201610218311 A CN201610218311 A CN 201610218311A CN 107292470 A CN107292470 A CN 107292470A
Authority
CN
China
Prior art keywords
power supply
distribution
circuit
index
ratio
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610218311.4A
Other languages
Chinese (zh)
Inventor
吴健
杨波
吴奎华
杨慎全
冯亮
李凯
邓少治
庞怡君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Zhiyuan Electric Power Design And Consulting Co Ltd
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
Shandong Zhiyuan Electric Power Design And Consulting Co Ltd
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Zhiyuan Electric Power Design And Consulting Co Ltd, State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical Shandong Zhiyuan Electric Power Design And Consulting Co Ltd
Priority to CN201610218311.4A priority Critical patent/CN107292470A/en
Publication of CN107292470A publication Critical patent/CN107292470A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S50/00Market activities related to the operation of systems integrating technologies related to power network operation or related to communication or information technologies
    • Y04S50/16Energy services, e.g. dispersed generation or demand or load or energy savings aggregation

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to Electric Power Network Planning technical field, and in particular to one kind visualization power network diagnosis of the status quo analysis system, sets four layers of evaluation index:First layer is operation level and power supply capacity comprehensive score;The second layer is respectively operation level and power supply capacity;Third layer is respectively integrated operation, circuit, distribution transforming, switch, distribution power supply point and distribution network, and wherein integrated operation, circuit, distribution transforming and switch is under the jurisdiction of the assessment of operation level, and distribution power supply point and distribution network are under the jurisdiction of the assessment of power supply capacity;4th layer is the specific evaluation index of each several part;Every layer of index comprehensive score is summed after its lower floor's score weighting and obtained, all indexs are carried out after successively weighted sum, finally give assessment area operation level and power supply capacity comprehensive score, the calculation formula of each layer evaluation index is pre-set in processor, automatic result of calculation after data needed for obtaining.The present invention carries out visualizing clear division to all kinds of indexs, shortens calculating cycle, improves and calculates accuracy.

Description

Visualize power network diagnosis of the status quo analysis system
Technical field
The present invention relates to Electric Power Network Planning technical field, and in particular to one kind visualization power network diagnosis of the status quo analysis system.
Background technology
Current power network diagnostic analysis index multi-source is in other systems, and analysis personnel take to be needed to be advised according to power network after data Draw business characteristic and carry out calculating analysis, overall merit electric network state can be just obtained, so as to diagnose electrical network weak link in time.Power network Diagnostic analysis index includes including some indexs in comprehensive diagnos, power transmission network diagnosis, power distribution network three classes of diagnosis, each class content, Each index divides different types to show again, so the index classification to be shown is more, substantial amounts.
Due to without ripe analysis calculating instrument, generally requiring manual calculations key index, and calculation formula compares Complexity, each index can correspond to different weights, cause calculating cycle longer and the probability of result of calculation error is larger.
The content of the invention
In order to solve the above technical problems, it is an object of the invention to:A kind of visualization power network diagnosis of the status quo analysis system is provided All kinds of indexs are carried out visualizing clear division, shorten calculating cycle, improve and calculate accuracy by system.
The technical scheme that the present invention is used by solution its technical problem for:
The visualization power network diagnosis of the status quo analysis system, sets four layers of evaluation index:
First layer is operation level and power supply capacity comprehensive score;
The second layer is respectively operation level and power supply capacity;
Third layer is respectively integrated operation, circuit, distribution transforming, switch, 6 parts of distribution power supply point and distribution network, wherein Integrated operation, circuit, 4 parts of distribution transforming and switch are under the jurisdiction of the assessment of operation level, distribution power supply point and distribution network two Part is under the jurisdiction of the assessment of power supply capacity;
4th layer is the specific evaluation index of each several part;
Every layer of index comprehensive score is summed after its lower floor's score weighting and obtained, and all indexs are carried out into successively weighted sum Afterwards, finally give and each layer assessment is pre-set in assessment area operation level and power supply capacity comprehensive score, core services module The calculation formula of index, calculates and is shown automatically after data needed for obtaining, each evaluation index also by form, block diagram or Line chart is shown.
After each block supply company obtains operation level and power supply capacity comprehensive score, net provincial company is public to affiliated districts and cities Department collects the assessment score for obtaining net provincial company after being weighted, weighting weight is that regional distribution evaluation year electricity sales amount is accounted for entirely Save the ratio that year total electricity sales amount is evaluated in distribution.
Assessment by the system to distribution operation level and power supply capacity, most obtains different levels and assesses content at last Point value of evaluation;After assessment terminates, should be existed not according to assessment result, analysis and evaluation region distribution operation level and power supply capacity Foot, and in distribution planning and designing from now on, build, gradual perfection in the work such as operation, technological transformation realizes closed-loop dynamic pipe Reason, rolling are improved.
It is qualified that the specific evaluation index of integrated operation includes power supply reliability RS1, power supply reliability RS3, integrated voltage Rate and 10kV line losses per unit;The specific evaluation index of circuit includes overhead transmission line fault rate, cable line fault rate, circuit underloading ratio Circuit ratio, line insulation rate that the heavily loaded ratio of example, circuit, operation surpass 30 years;The specific evaluation index of distribution transforming includes matching somebody with somebody accident The circuit ratio heavily loaded with control with changed scale, the circuit ratio of distribution transforming underloading, distribution transforming that barrier rate, height loss surpass 30 years with control with changed scale, operation Example, distribution transforming information gathering rate;Switch switch ratio, switch nothing that specific evaluation index surpasses 20 years including switch fault rate, operation Oiling rate, switch " two is distant " rate;The specific evaluation index of distribution power supply point includes capacity-load ratio, main transformer and meets N-1 ratios, power supply capacity With transmittability matching rate;The specific evaluation index of distribution network meets N-1 ratios, circuit contact rate including circuit, become from different There are the circuit ratio of contact, the circuit ratio of distribution transforming overload, averagely overload circuit ratio, the exceeded overhead line of segmentation capacity in power station Road ratio, dress are shown in the exceeded circuit ratio of capacity.
Each index weights are allocated as follows shown in table:
Each index interpretation such as following table:
Each index scoring formula and it is described as follows, the x in scoring formula is each desired value, and y is the score of the index, index Retain two after score decimal point, the numbering of each index is identical with index number in upper table.
1.1 power supply reliability RS1 (%)
Note:Leap year is 8784h
Index score calculation formula:
1.2 power supply reliability RS3 (%)
Index score calculation formula:
1.3 integrated voltage qualification rates (%)
Index score calculation formula:
1.4 10kV line losses per unit (%)
Index score calculation formula:
The 2.1 overhead transmission line number of stoppages (secondary/hundred kilometers of years)
Index score calculation formula:
2.2 cable line fault rates (secondary/hundred kilometers of years)
Index score calculation formula:
2.3 circuit underloading ratios (%)
Index score calculation formula:
2.4 circuits heavy duty ratio (%)
Index score calculation formula:
The circuit ratio (%) that 2.5 operations surpass 30 years
Index score calculation formula:
2.6 line insulation rates (%)
Index score calculation formula:
3.1 distribution transforming fault rates (secondary/100 year)
Index score calculation formula:
Control with changed scale (%) is matched somebody with somebody in 3.2 high losses
Index score calculation formula:
3.3 operation surpass 30 years match somebody with somebody control with changed scale (%)
Index score calculation formula:
The circuit ratio (%) of 3.4 distribution transforming underloadings
Index score calculation formula:
The circuit ratio (%) of 3.5 distribution transformings heavy duty
Index score calculation formula:
3.6 distribution transforming information gathering rates
Index score calculation formula:
4.1 switch fault rates (secondary/100 year)
Index score calculation formula:
The switch proportion (%) that 4.2 operations surpass 20 years
Index score calculation formula:
4.3 oil-free rates (%)
Index score calculation formula:
4.4 " two the is distant " rate (%) of switch
Index score calculation formula:
5.1 capacity-load ratio
Index score calculation formula:
5.2 main transformers meet N-1 ratios (%)
Index score calculation formula:
5.3 power supply capacities and transmittability matching rate
Index score calculation formula:
6.1 circuits meet N-1 ratios (%)
Index score calculation formula:
6.2 circuit contact rates (%)
Index score calculation formula:
6.3 different substations have the circuit ratio (%) of contact
Index score calculation formula:
The circuit ratio (%) of 6.4 distribution transforming load factors overload
Index score calculation formula:
6.5 overload circuit ratios (%)
Index score calculation formula:
6.6 are averagely segmented the exceeded overhead transmission line ratio (%) of capacity
Index score calculation formula:
6.7 dresses are shown in the exceeded circuit ratio (%) of capacity
Index score calculation formula:
Data source needed for the specific evaluation index is calculated can pass through PMS systems, work bill system, operation ticket system, electricity Energy quality system, marketing support system, Demand-side monitoring system and dispatch automated system are obtained automatically, are obtained and are calculated after data Machine calculates assessment area operation level and power supply capacity comprehensive score, nothing according to each index calculation formula and the distribution of each index weights Manual calculations are needed, mitigate worker workload, operating efficiency is improved and assesses accuracy.
The core services module includes system database and application server, and both pass through LAN or internet and visitor Family end carries out information exchange, application server be used for information exchange between processing system database and each application system of power network, Client service application is responded, and database is used for data source and diagnostic analysis knot needed for the unified specific evaluation index of storage is calculated Really.
Compared with prior art, the invention has the advantages that:
The present invention carries out visualizing clear division to all kinds of indexs, shortens calculating cycle, improves and calculates accuracy.In each area Domain electric company is obtained after operation level and power supply capacity comprehensive score, and affiliated prefecture-level company is weighted net provincial company Collect the assessment score for obtaining net provincial company afterwards, it is total that weighting weight accounts for the whole province's distribution evaluation year for regional distribution evaluation year electricity sales amount The ratio of electricity sales amount.Assessment by the system to distribution operation level and power supply capacity, most obtains different levels assessment at last The point value of evaluation of content;After assessment terminates, it should be deposited according to assessment result, analysis and evaluation region distribution operation level and power supply capacity Deficiency, and in distribution planning and designing from now on, build, gradual perfection in the work such as operation, technological transformation, realize that closed loop is dynamic State management, rolling are improved.
Embodiment
The embodiment of the present invention is described further below:
Embodiment 1:
The visualization power network diagnosis of the status quo analysis system of the present invention, sets four layers of evaluation index:
First layer is operation level and power supply capacity comprehensive score;
The second layer is respectively operation level and power supply capacity;
Third layer is respectively integrated operation, circuit, distribution transforming, switch, 6 parts of distribution power supply point and distribution network, wherein Integrated operation, circuit, 4 parts of distribution transforming and switch are under the jurisdiction of the assessment of operation level, distribution power supply point and distribution network two Part is under the jurisdiction of the assessment of power supply capacity;
4th layer is the specific evaluation index of each several part;
Every layer of index comprehensive score is summed after its lower floor's score weighting and obtained, and all indexs are carried out into successively weighted sum Afterwards, finally give and each layer assessment is pre-set in assessment area operation level and power supply capacity comprehensive score, core services module Automatic calculate ties and shown that each evaluation index is also by form, block diagram after the calculation formula of index, data needed for obtaining Or line chart displaying.
It is qualified that the specific evaluation index of integrated operation includes power supply reliability RS1, power supply reliability RS3, integrated voltage Rate and 10kV line losses per unit;The specific evaluation index of circuit includes overhead transmission line fault rate, cable line fault rate, circuit underloading ratio Circuit ratio, line insulation rate that the heavily loaded ratio of example, circuit, operation surpass 30 years;The specific evaluation index of distribution transforming includes matching somebody with somebody accident The circuit ratio heavily loaded with control with changed scale, the circuit ratio of distribution transforming underloading, distribution transforming that barrier rate, height loss surpass 30 years with control with changed scale, operation Example, distribution transforming information gathering rate;Switch switch ratio, switch nothing that specific evaluation index surpasses 20 years including switch fault rate, operation Oiling rate, switch " two is distant " rate;The specific evaluation index of distribution power supply point includes capacity-load ratio, main transformer and meets N-1 ratios, power supply capacity With transmittability matching rate;The specific evaluation index of distribution network meets N-1 ratios, circuit contact rate including circuit, become from different There are the circuit ratio of contact, the circuit ratio of distribution transforming overload, averagely overload circuit ratio, exceeded built on stilts of segmentation capacity in power station Circuit ratio, dress are shown in the exceeded circuit ratio of capacity.
Each index weights are allocated as follows shown in table:
Each index interpretation such as following table:
Each index scoring formula and it is described as follows, the x in scoring formula is each desired value, and y is the score of the index, index Retain two after score decimal point, the numbering of each index is identical with index number in upper table.
1.1 power supply reliability RS1 (%)
Note:Leap year is 8784h
Index score calculation formula:
1.2 power supply reliability RS3 (%)
Index score calculation formula:
1.3 integrated voltage qualification rates (%)
Index score calculation formula:
1.4 10kV line losses per unit (%)
Index score calculation formula:
The 2.1 overhead transmission line number of stoppages (secondary/hundred kilometers of years)
Index score calculation formula:
2.2 cable line fault rates (secondary/hundred kilometers of years)
Index score calculation formula:
2.3 circuit underloading ratios (%)
Index score calculation formula:
2.4 circuits heavy duty ratio (%)
Index score calculation formula:
The circuit ratio (%) that 2.5 operations surpass 30 years
Index score calculation formula:
2.6 line insulation rates (%)
Index score calculation formula:
3.1 distribution transforming fault rates (secondary/100 year)
Index score calculation formula:
Control with changed scale (%) is matched somebody with somebody in 3.2 high losses
Index score calculation formula:
3.3 operation surpass 30 years match somebody with somebody control with changed scale (%)
Index score calculation formula:
The circuit ratio (%) of 3.4 distribution transforming underloadings
Index score calculation formula:
The circuit ratio (%) of 3.5 distribution transformings heavy duty
Index score calculation formula:
3.6 distribution transforming information gathering rates
Index score calculation formula:
4.1 switch fault rates (secondary/100 year)
Index score calculation formula:
The switch proportion (%) that 4.2 operations surpass 20 years
Index score calculation formula:
4.3 oil-free rates (%)
Index score calculation formula:
4.4 switch " two is distant " rates (%)
Index score calculation formula:
5.1 capacity-load ratio
Index score calculation formula:
5.2 main transformers meet N-1 ratios (%)
Index score calculation formula:
5.3 power supply capacities and transmittability matching rate
Index score calculation formula:
6.1 circuits meet N-1 ratios (%)
Index score calculation formula:
6.2 circuit contact rates (%)
Index score calculation formula:
6.3 different substations have the circuit ratio (%) of contact
Index score calculation formula:
The circuit ratio (%) of 6.4 distribution transforming load factors overload
Index score calculation formula:
6.5 overload circuit ratios (%)
Index score calculation formula:
6.6 are averagely segmented the exceeded overhead transmission line ratio (%) of capacity
Index score calculation formula:
6.7 dresses are shown in the exceeded circuit ratio (%) of capacity
Index score calculation formula:
Data source needed for the specific evaluation index is calculated can pass through PMS systems, work bill system, operation ticket system, electricity Energy quality system, marketing support system, Demand-side monitoring system and dispatch automated system are obtained automatically, are obtained and are calculated after data Machine calculates assessment area operation level and power supply capacity comprehensive score, nothing according to each index calculation formula and the distribution of each index weights Manual calculations are needed, mitigate worker workload, operating efficiency is improved and assesses accuracy.
After each block supply company obtains operation level and power supply capacity comprehensive score, net provincial company is public to affiliated districts and cities Department collects the assessment score for obtaining net provincial company after being weighted, weighting weight is that regional distribution evaluation year electricity sales amount is accounted for entirely Save the ratio that year total electricity sales amount is evaluated in distribution.
Assessment by the system to distribution operation level and power supply capacity, most obtains different levels and assesses content at last Point value of evaluation;After assessment terminates, should be existed not according to assessment result, analysis and evaluation region distribution operation level and power supply capacity Foot, and in distribution planning and designing from now on, build, gradual perfection in the work such as operation, technological transformation realizes closed-loop dynamic pipe Reason, rolling are improved.
The core services module includes system database and application server, and both pass through LAN or internet and visitor Family end carries out information exchange, application server be used for information exchange between processing system database and each application system of power network, Client service application is responded, and database is used for data source and diagnostic analysis knot needed for the unified specific evaluation index of storage is calculated Really.

Claims (6)

1. one kind visualization power network diagnosis of the status quo analysis system, it is characterised in that four layers of evaluation index are set:
First layer is operation level and power supply capacity comprehensive score;
The second layer is respectively operation level and power supply capacity;
Third layer is respectively integrated operation, circuit, distribution transforming, switch, 6 parts of distribution power supply point and distribution network, wherein comprehensive Operation, circuit, 4 parts of distribution transforming and switch are under the jurisdiction of the assessment of operation level, two parts of distribution power supply point and distribution network It is under the jurisdiction of the assessment of power supply capacity;
4th layer is the specific evaluation index of each several part;
Every layer of index comprehensive score is summed after its lower floor's score weighting and obtained, and all indexs are carried out after successively weighted sum, Finally give and each layer evaluation index is pre-set in assessment area operation level and power supply capacity comprehensive score, core services module Calculation formula, calculate and shown automatically after data needed for obtaining, each evaluation index is also by form, block diagram or broken line Figure displaying.
2. visualization power network diagnosis of the status quo analysis system according to claim 1, it is characterised in that each block supply company Obtain after operation level and power supply capacity comprehensive score, net provincial company collects after affiliated prefecture-level company is weighted to be obtained The assessment score of net provincial company, weighting weight is that regional distribution evaluation year electricity sales amount accounts for the ratio that year total electricity sales amount is evaluated in the whole province's distribution Example.
3. visualization power network diagnosis of the status quo analysis system according to claim 1, it is characterised in that the integrated operation tool Body evaluation index includes power supply reliability RS1, power supply reliability RS3, integrated voltage qualification rate and 10kV line losses per unit;Circuit is specific Evaluation index includes the heavily loaded ratio of overhead transmission line fault rate, cable line fault rate, circuit underloading ratio, circuit, operation and surpasses 30 Circuit ratio, the line insulation rate in year;The specific evaluation index of distribution transforming includes distribution transforming fault rate, high loss with control with changed scale, operation The circuit ratio heavily loaded with control with changed scale, the circuit ratio of distribution transforming underloading, distribution transforming, the distribution transforming information gathering rate for surpassing 30 years;Switch tool Body evaluation index includes switch fault rate, the switch ratio that operation surpasses 20 years, switch oil-free rate, switch " two is distant " rate;Distribution The specific evaluation index of power supply point includes capacity-load ratio, main transformer and meets N-1 ratios, power supply capacity and transmittability matching rate;Power distribution network The specific evaluation index of network meets N-1 ratios, circuit contact rate including circuit, has the circuit ratio of contact with different substation, matches somebody with somebody The circuit ratio, overload circuit ratio, the averagely exceeded overhead transmission line ratio of segmentation capacity, dress for becoming overload are shown in the exceeded circuit of capacity Ratio.
4. visualization power network diagnosis of the status quo analysis system according to claim 3, it is characterised in that each index weights It is allocated as follows shown in table:
5. visualization power network diagnosis of the status quo analysis system according to claim 1, it is characterised in that the specific assessment refers to Data source needed for mark is calculated can support system by PMS systems, work bill system, operation ticket system, power quality system, marketing System, Demand-side monitoring system and dispatch automated system are obtained automatically, and obtaining after data can be according to each index calculation formula and each Index weights distribution calculates assessment area operation level and power supply capacity comprehensive score.
6. visualization power network diagnosis of the status quo analysis system according to claim 5, it is characterised in that the kernel service mould Block includes system database and application server, and both carry out information exchange, application by LAN or internet with client Server is for the information exchange between processing system database and each application system of power network, client service application response, number It is used for data source and diagnostic analysis result needed for the unified specific evaluation index of storage is calculated according to storehouse.
CN201610218311.4A 2016-04-10 2016-04-10 Visualize power network diagnosis of the status quo analysis system Pending CN107292470A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610218311.4A CN107292470A (en) 2016-04-10 2016-04-10 Visualize power network diagnosis of the status quo analysis system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610218311.4A CN107292470A (en) 2016-04-10 2016-04-10 Visualize power network diagnosis of the status quo analysis system

Publications (1)

Publication Number Publication Date
CN107292470A true CN107292470A (en) 2017-10-24

Family

ID=60093441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610218311.4A Pending CN107292470A (en) 2016-04-10 2016-04-10 Visualize power network diagnosis of the status quo analysis system

Country Status (1)

Country Link
CN (1) CN107292470A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109409653A (en) * 2018-09-14 2019-03-01 国电南瑞科技股份有限公司 A kind of operation of power networks failure disposition data visualization analysis method of Process-Oriented
CN114049036A (en) * 2021-11-24 2022-02-15 广东电网有限责任公司 Data computing platform, method, device and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102063657A (en) * 2010-12-23 2011-05-18 中国电力科学研究院 Operating level and power supplying capability evaluation method for urban electric distribution network
CN102081756A (en) * 2009-11-30 2011-06-01 吉林省电力有限公司长春供电公司 Electrical network real-time three-dimensional visualization system
CN102169412A (en) * 2011-03-31 2011-08-31 北京清大高科系统控制有限公司 Real-time three-dimensional visual system of power grid
CN102968668A (en) * 2012-12-03 2013-03-13 黑龙江省电力科学研究院 Urban power distribution network evaluation system and method
CN104408549A (en) * 2014-10-31 2015-03-11 国家电网公司 Running state evaluation method of urban distribution network

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102081756A (en) * 2009-11-30 2011-06-01 吉林省电力有限公司长春供电公司 Electrical network real-time three-dimensional visualization system
CN102063657A (en) * 2010-12-23 2011-05-18 中国电力科学研究院 Operating level and power supplying capability evaluation method for urban electric distribution network
CN102169412A (en) * 2011-03-31 2011-08-31 北京清大高科系统控制有限公司 Real-time three-dimensional visual system of power grid
CN102968668A (en) * 2012-12-03 2013-03-13 黑龙江省电力科学研究院 Urban power distribution network evaluation system and method
CN104408549A (en) * 2014-10-31 2015-03-11 国家电网公司 Running state evaluation method of urban distribution network

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109409653A (en) * 2018-09-14 2019-03-01 国电南瑞科技股份有限公司 A kind of operation of power networks failure disposition data visualization analysis method of Process-Oriented
CN114049036A (en) * 2021-11-24 2022-02-15 广东电网有限责任公司 Data computing platform, method, device and storage medium

Similar Documents

Publication Publication Date Title
CN107038530A (en) A kind of power distribution network overall planning method and system
CN108573350A (en) A kind of matching net wire loss synchronization calculates and multidimensional analysis method
CN101309009A (en) Urban electric grid overall evaluation system established based on layer analysis and Delphi
CN109447284B (en) Distribution network fault information sending method and system for power supply service command platform
CN103618383A (en) Power distribution network monitoring and management system
CN102208807A (en) Medium and low voltage distribution network energy efficiency evaluation method based on accurate load measurement data
CN103236023B (en) A kind of acquisition methods of the AC-HVDC scope of application
CN108631295A (en) The online accurate calculation system of theory wire loss of measured data
CN108764501A (en) A kind of analysis of line loss problem and defect elimination processing method
CN104992382A (en) Data fusion method facing current situation assessment of power distribution network
CN104538957B (en) Power grid model self-adaptive processing method for counting low-frequency low-voltage load shedding capacity
CN103839187A (en) Comprehensive assessment index system for power-supplying capacity and operation level of regional power grid
CN105893516A (en) Power distribution network operation-maintenance cockpit based on operation and distribution data and application thereof
Arritt et al. Investigation load estimation methods with the use of AMI metering for distribution system analysis
CN113469486A (en) Line negative loss and high loss analysis method
CN108305019A (en) A kind of 10KV based on basic account and power distribution network investment decision methods below
CN110826228B (en) Regional power grid operation quality limit evaluation method
CN105048456B (en) Wastage reducing and energy saving management method and system applied to intelligent metering platform
CN103020761A (en) Method for overhauling distribution network based on automatic unit division and evaluation
CN110309945A (en) Power distribution station project optimizing evaluation method based on G1- entropy assessment
CN109166051A (en) A kind of dispatching of power netwoks data programming count and multidimensional visualize application method
CN107798477A (en) A kind of distribution network planning project implementation operating method
CN104123588A (en) Comprehensive evaluation system and method of smart distribution grid
CN107292470A (en) Visualize power network diagnosis of the status quo analysis system
Arnold et al. An approach to smart grid metrics

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171024