CN107288039A - Railway Through Steel concrete combination bridge floor steel truss girder construction method - Google Patents

Railway Through Steel concrete combination bridge floor steel truss girder construction method Download PDF

Info

Publication number
CN107288039A
CN107288039A CN201710433966.8A CN201710433966A CN107288039A CN 107288039 A CN107288039 A CN 107288039A CN 201710433966 A CN201710433966 A CN 201710433966A CN 107288039 A CN107288039 A CN 107288039A
Authority
CN
China
Prior art keywords
steel
construction
steel truss
girder
truss girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710433966.8A
Other languages
Chinese (zh)
Inventor
苏春生
张庆
何十美
梁朋刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201710433966.8A priority Critical patent/CN107288039A/en
Publication of CN107288039A publication Critical patent/CN107288039A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses railway Through Steel concrete combination bridge floor steel truss girder construction method, construction technology process includes steel truss girder assembling construction, temporary rest pier construction, steel truss girder hauling construction, steel truss beam support are installed, bridge deck concrete is constructed, building site application, using launching method organizing construction, hand fit's loop wheel machine assembly girder steel, vertex top girder steel is played by particular design after the completion of assembly, up and down slideway facility is installed, in the dilatory advance of elevator machine travel lower girder steel, fall beam facility temporarily using pier top, top lifting girder steel, up and down slideway is removed, falls beam in place.The present invention, which is applied to railway Through Steel concrete combination bridge floor steel truss girder design and construction technique, to be had strong adaptability, can reduce rail top to beam bottom height, bridge down train headroom problem is effectively solved, structure integral rigidity is big, noise is smaller, overall economic efficiency is notable.

Description

Railway Through Steel concrete combination bridge floor steel truss girder construction method
Technical field
It is a kind of railway Through Steel concrete combination bridge floor steel truss specifically the present invention relates to conveying equipment field Beam construction method.
Background technology
The bridge deck form that China railways steel truss girder is continued to use always is open bridge floors, and not only noise is big, pollution environment, Er Qie Lateral amplitude of vibration overrun issues are occurred in that in railway speed increase.Although taking some reinforcement measures, effect is not very obvious.
Steel truss joist steel concrete combination floorings are the combining structures of steel truss and concrete, and concrete slab is indulged with steel truss The integral common stress of crossbeam shape.Structural steel amount is relatively low, and the rigidity of structure is remarkably reinforced, compared with other forms, is built Building height can accordingly be reduced, and improve stress performance, while construction costs is reduced, late maintaining maintenance load less, is used During dilatory method erection construction so that construction is more convenient, can reduce the influence to ground reason traffic.
With the development of railway construction in China, railroad bridge design standard is improved, and original steel truss girder uses open bridge floors form It is difficult to the requirement for meeting lateral stiffness and comfort level, so use has quarrel bridge floor more now.Freely-supported steel truss girder design in recent years, system Make and erection technique achieves significant achievement, but the bridge floor form combined entirely is using less.
The content of the invention
It is an object of the invention to provide a kind of railway Through Steel concrete combination bridge floor steel truss girder construction method, have Strong adaptability, rail top to beam bottom height can be reduced, effectively solve bridge down train headroom problem, structure integral rigidity is big, noise compared with Small, overall economic efficiency is notable.
The present invention is achieved through the following technical solutions:A kind of railway Through Steel concrete combination bridge floor steel truss girder construction party Method, construction technology process is steel truss girder assembling construction, temporary rest pier construction, the installation of steel truss girder hauling construction, steel truss beam support, bridge Surface concrete construction, building site application.Construction technology of the present invention uses launching method organizing construction, that is, utilizes roadbed after abutment platform And abutment is that temporary rest pier carries out girder steel consolidation service, hand fit's loop wheel machine assembly girder steel;Pass through particular design after the completion of assembly Rise vertex top girder steel, install up and down slideway facility, using two 10t hoist engine by two three walk five pulley Group, in the way of flat slope is dilatory, the vertical shift of longitudinal pull girder steel is by girder steel design attitude, using the adjustment facility of pier top, Girder steel is adjusted to design attitude, falls beam facility temporarily using pier top, top lifting girder steel removes up and down slideway, falls beam in place, then Construction bridge deck and road are arranged in each lower-chord panel point of steel truss girder, and glide path elongated arrangement on buttress and related roadbed is removed Temporary rest pier.
Above-mentioned steel truss girder assembling construction according to from bottom to up, after first lower plane the inside installation principle, form triangle as early as possible Shape rock-steady structure, then installs plane, and the beam in length and breadth for often installing two sections is the brace for installing a section, often installs two sections Brace is to install one to save top bracing, the like assembled complete.
Above-mentioned steel truss girder assembling construction is spelled according to the order of main truss longeron, primary and secondary crossbeam, brace, top bracing, horizontal-associate Dress.
The basic technology of above-mentioned steel truss girder assembling construction is hung including bundle, device to hole, drift bolt bolt and tight bolt.
Above-mentioned temporary rest pier construction is using overall buttress basic engineering.
Above-mentioned steel truss girder hauling construction uses dilatory without nose girder, and the dilatory mode of traction is dilatory to promote, that is, will slide Car group is placed on girder steel rear end, and fixed pulley group is placed under the appropriate place in front, volume field machine travel, and girder steel will be pushed advance, we Formula does not set the instruments such as coaster, volume field machine in girder steel front end, to reduce amount of deflection under front end, it is ensured that pier on smoothly.
Above-mentioned steel truss girder hauling construction uses double end extension pulley group, coordinates volume field machine to start simultaneously, tackle pulley is used Roller bearing slideway system, intermittently-arranged each in steel truss girder of sliding way shows contact up and down, and glide path is on buttress and part roadbed Elongated arrangement.
Above-mentioned steel truss beam support installation kit includes hold-down support and installed and movable bearing support installation.
Above-mentioned bridge deck concrete construction includes concrete and matches, stirs, transports and pour, the side being molded using a placing Method is poured.
Above-mentioned building site application is mainly repairing and the full-bridge of breakage in the painting benefit of each intersegmental attachment weld, construction Last one of finish paint spraying.
The present invention compared with prior art, with advantages below and beneficial effect:
(1)The present invention is only highly 2.212m using bridge floor steel truss girder rail top to beam bottom is combined, and efficiently solves bridge down train net Sky is required, without raising of track absolute altitude, reduces whole Cost of Bridge;
(2)Concrete slab of the present invention and the common stress of steel truss girder, not only with beam in length and breadth, and are combined with lower boom, in state It is interior it is fewer see, increase structure integral rigidity, reduce noise;
(3)Concrete slab of the present invention is combined entirely with beam in length and breadth and lower boom, is eliminated lower flat vertical connection, braking connection, is saved steel, This bridge steel are about 12.5t/m.
Brief description of the drawings
Fig. 1 is construction technology process block diagram of the invention.
Fig. 2 is steel truss girder hauling construction technological process.
Embodiment
A kind of technological process railway Through Steel concrete combination bridge floor steel truss girder construction method as shown in Figure 1, is used Launching method organizing construction, i.e., be that temporary rest pier carries out girder steel consolidation service using roadbed after abutment platform and abutment, manually match somebody with somebody Close the assembled girder steel of loop wheel machine;Vertex top girder steel is played by particular design after the completion of assembly, up and down slideway facility is installed, two are utilized Platform 10t hoist engine by two three walk five assembly pulley, in the way of flat slope is dilatory, longitudinal pull girder steel vertical shift passes through To girder steel design attitude, using the adjustment facility of pier top, adjustment girder steel to design attitude falls beam facility temporarily using pier top, Top lifting girder steel, removes up and down slideway, falls beam in place, then construction bridge deck and road are arranged in each lower-chord panel point of steel truss girder, Glide path elongated arrangement on buttress and related roadbed removes temporary rest pier.
Wherein, steel truss girder assembling construction according to from bottom to up, after first lower plane the inside installation principle, form triangle as early as possible Shape rock-steady structure, then installs plane, and the beam in length and breadth for often installing two sections is the brace for installing a section, often installs two sections Brace is to install one to save top bracing, the like assembled complete.Steel truss girder assembling construction according to main truss longeron, primary and secondary crossbeam, tiltedly Bar, top bracing, the order of horizontal-associate carry out assembly, with 50t automobiles loop wheel machine that rod member is assembled one by one, first by node metal plate, spelling before assembly Dress metal plate, fill out metal plate, high-strength bolt and be fitted on each near nodal.
Wherein, temporary rest pier construction is using overall buttress basic engineering, and Temporary Piers squeeze into steel-pipe pile progress using Φ's 630 Set up, stake is long to be more than two rows of 20.1m steel-pipe piles longitudinal direction, and horizontal spacing 2.3m, longitudinal pitch 2.2m set distribute in length and breadth thereon Beam, the longeron of distribution beam uses 2I40 I-steel, and crossbeam uses 3I55 I-steel, and glide path beam is formed using the weldering of steel box-girder group, So basis of temporary rest pier and support is all the steel-pipe piles of identical Φ 630, forms overall buttress, increases the steady of temporary rest pier It is qualitative.
Wherein, the technological process of steel truss girder hauling construction is as shown in Fig. 2 using dilatory without nose girder, draw dilatory mode to push away Enter dilatory, that is, slide trucks group is placed on girder steel rear end, fixed pulley group is placed under the appropriate place in front, volume field machine travel, steel Beam will be pushed advance, and the manner does not set the instruments such as coaster, volume field machine in girder steel front end, to reduce amount of deflection under front end, it is ensured that suitable Pier in profit;Using double end extension pulley group, coordinate volume field machine to start simultaneously, the speed for carrying out adjustable pulley group can also be opened Degree, levelling traction deviation, hauling speed is controlled in 60~80m/h;Tackle pulley uses roller bearing slideway system, and sliding way is intermittently-arranged Each in steel truss girder shows contact, glide path elongated arrangement, the Controlling principle of overall stability on buttress and part roadbed up and down For maximum hanging no more than 3 panel lengths of steel truss girder, i.e. 30m.
Anti-skidding emergent precautionary measures arrange that platform on roadbed platform, borrows fairlead, using 2 using anti-slippery hoist engine Times steel wire rope is fixed on after steel truss girder on end floor beam, and holding steel truss girder prevents slippery, and anti-skidding steel wire rope is guarded in tensing all the time State, shoe is moved forward in time according to pull-offs direction.
The each ultimate range of slide trucks displacement is 45cm, after in-position, and running block caudad displacement continues to drag Draw, when being displaced to most back rest tail;Because hoist engine position and fixed block group position are spacing, it is impossible to when reaching final position, or Person is dilatory, and skew is larger, it is impossible to pull-offs direction will be aligned when aligning, using dilatory method, hoist engine is fixed on into pier scaffold Front, movable pulley, which is fixed on steel truss girder, to carry out being dragged to position.
Steel truss girder falls beam and positioned to carry out moving beam and Luo Liang, each pier top placement 2 using jack, sliding beam, rolling bar etc. Platform 500t jack, jack is operated under unified command, and jack must be made synchronous, first together push up beam with bearing Rise, sliding beam is laid under bearing, rolling bar is then placed between sliding beam and bearing again, is vertically and horizontally moved with jack and reversible chain block Beam, must accomplish when moving beam at the uniform velocity, it is synchronous, go slowly, operated in strict accordance with jack operational procedure.
Wherein, steel truss beam support material and the accuracy of manufacture should meet design requirement, the finished product quality certification that should have manufactory, and It is required that casting detection record and rewelding record with supply unit's management visa, while visual examination should be made and to assembling Overall size afterwards is checked.One layer of thin fine sand should be spread before the formal bearing installation of steel truss girder in the range of base-plate floating, Make uniform force, bearing crab-bolt must carefully be verified by crab-bolt installation diagram when installing, must not hunted leak.It is put into lower bolt Afterwards, should be stifled tight by anchor hole foam or cotton yarn, prevent foreign matter from falling into anchor hole, influence last bearing formally in place.
Wherein, bridge deck concrete construction includes concrete and matches, stirs, transports and pour, using placing shaping Method is poured;Concrete will disperse slowly to drop, and prevent a large amount of concrete from concentrating impact steel bar reinforced and WELDING STUDS, make coagulation firm by ramming Vibrating head is avoided to be contacted with WELDING STUDS when native, concrete enters to be noted protecting WELDING STUDS in mold process, prevents WELDING STUDS collision change Shape;After the completion of concrete placing, surface will carry out secondary receive and starch, and then be covered with geotextiles, and maintenance of sprinkling water, and treat real curing When its compression strength of the concrete sample of shield reaches the 90% of canal portion concrete design strength, geotextiles are opened, watering continues to support Shield, remains that concrete surface is moist, and maintenance number of days is no less than 7 days, while carrying out the health of bottom surface and side.
Wherein, building site application be mainly each intersegmental attachment weld painting mend, the repairing of breakage and complete in construction The spraying of last one of finish paint of bridge.
It is described above, be only presently preferred embodiments of the present invention, any formal limitation not done to the present invention, it is every according to According to the present invention technical spirit above example is made any simple modification, equivalent variations, each fall within the present invention protection Within the scope of.

Claims (10)

1. railway Through Steel concrete combination bridge floor steel truss girder construction method, construction technology process be steel truss girder assembling construction, Temporary rest pier construction, steel truss girder hauling construction, steel truss beam support are installed, bridge deck concrete is constructed, building site application, and its feature exists In:Using launching method organizing construction, i.e., it is that temporary rest pier carries out girder steel consolidation service using roadbed after abutment platform and abutment, Hand fit's loop wheel machine assembly girder steel;Vertex top girder steel is played by particular design after the completion of assembly, up and down slideway facility is installed, Using two 10t volume field machine by two three walk five assembly pulley, in the way of flat slope is dilatory, longitudinal pull girder steel is indulged Mobile Communication is crossed to girder steel design attitude, and using the adjustment facility of pier top, adjustment girder steel to design attitude falls beam temporarily using pier top Facility, top lifting girder steel removes up and down slideway, falls beam in place, then construction bridge deck and road are arranged in each lower edge of steel truss girder Node, glide path elongated arrangement on buttress and related roadbed removes temporary rest pier.
2. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The step steel truss girder assembling construction according to from bottom to up, after first lower plane the inside installation principle, form triangle as early as possible stable Structure, then installs plane, and the beam in length and breadth for often installing two sections is the brace for installing a section, and the brace for often installing two sections is Install one and save top bracing, the like assembled complete.
3. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The steel truss girder assembling construction carries out assembled according to the order of main truss longeron, primary and secondary crossbeam, brace, top bracing, horizontal-associate.
4. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The basic technology of the steel truss girder assembling construction is hung including bundle, device to hole, drift bolt bolt and tight bolt.
5. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The temporary rest pier construction is using overall buttress basic engineering.
6. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The steel truss girder hauling construction uses dilatory without nose girder, and the dilatory mode of traction is dilatory to promote.
7. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The steel truss girder hauling construction uses double end extension pulley group, coordinates volume field machine to start simultaneously, tackle pulley uses roller bearing slideway System, intermittently-arranged each in steel truss girder of sliding way shows contact, glide path elongated arrangement on buttress and part roadbed up and down.
8. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The steel truss beam support installation kit includes hold-down support and installed and movable bearing support installation.
9. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, it is characterised in that: The bridge deck concrete construction includes concrete and matches, stirs, transports and pour, and the method being molded using a placing is poured Build.
10. railway Through Steel concrete combination bridge floor steel truss girder construction method according to claim 1, its feature exists In:The building site application be mainly each intersegmental attachment weld painting mend, construction in breakage repairing and full-bridge most The spraying of one of finish paint afterwards.
CN201710433966.8A 2017-06-09 2017-06-09 Railway Through Steel concrete combination bridge floor steel truss girder construction method Pending CN107288039A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710433966.8A CN107288039A (en) 2017-06-09 2017-06-09 Railway Through Steel concrete combination bridge floor steel truss girder construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710433966.8A CN107288039A (en) 2017-06-09 2017-06-09 Railway Through Steel concrete combination bridge floor steel truss girder construction method

Publications (1)

Publication Number Publication Date
CN107288039A true CN107288039A (en) 2017-10-24

Family

ID=60097491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710433966.8A Pending CN107288039A (en) 2017-06-09 2017-06-09 Railway Through Steel concrete combination bridge floor steel truss girder construction method

Country Status (1)

Country Link
CN (1) CN107288039A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176867A (en) * 2020-08-28 2021-01-05 中铁九局集团第七工程有限公司 Single-track single-span railway steel truss girder dragging, installing and constructing method and single-track single-span railway
CN114134811A (en) * 2021-10-19 2022-03-04 中铁二十五局集团第二工程有限公司 Steel truss girder dragging frame and bridge steel truss girder erecting method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220580A (en) * 2007-12-04 2008-07-16 中铁大桥局股份有限公司 Portrait multi-point continuously dragging construction method for trussed steel beam
CN202064293U (en) * 2011-05-12 2011-12-07 中铁二十局集团第一工程有限公司 Traction system used for steel trussed beam cantilever hauling construction
CN202809492U (en) * 2012-09-05 2013-03-20 中铁十六局集团第五工程有限公司 Dragging system of steel truss girder obliquely crossing existing line through continuous jack in guide rail-free way

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101220580A (en) * 2007-12-04 2008-07-16 中铁大桥局股份有限公司 Portrait multi-point continuously dragging construction method for trussed steel beam
CN202064293U (en) * 2011-05-12 2011-12-07 中铁二十局集团第一工程有限公司 Traction system used for steel trussed beam cantilever hauling construction
CN202809492U (en) * 2012-09-05 2013-03-20 中铁十六局集团第五工程有限公司 Dragging system of steel truss girder obliquely crossing existing line through continuous jack in guide rail-free way

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
唐继昌: ""无导梁拖拉法架设钢桁梁关键技术"", 《城市建设理论研究(电子版)》 *
武广客运专线有限责任公司编著: "《武广铁路客运专线工程总结》", 31 December 2012, 中国铁道出版社 *
铁道部工程设计鉴定中心、铁道第三勘察设计院集团有限公司: "《2008中国高速铁路桥梁技术国际交流会论文集(上册)》", 31 July 2008, 中国铁道出版社 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112176867A (en) * 2020-08-28 2021-01-05 中铁九局集团第七工程有限公司 Single-track single-span railway steel truss girder dragging, installing and constructing method and single-track single-span railway
CN114134811A (en) * 2021-10-19 2022-03-04 中铁二十五局集团第二工程有限公司 Steel truss girder dragging frame and bridge steel truss girder erecting method
CN114134811B (en) * 2021-10-19 2024-03-08 中铁二十五局集团第二工程有限公司 Steel truss girder traction frame and erection method of steel truss girder for bridge

Similar Documents

Publication Publication Date Title
CN106702910B (en) A kind of main girder construction technique of the double rope face low-pylon cable-stayed bridges of double tower
CN108004928B (en) A kind of asymmetric rigid frame-continuous girder construction technology
CN101914897B (en) Construction method of single main cable inclined suspender ground anchor type suspension bridge
CN100587165C (en) Cast-in-situ beam-making construction method of assembled support
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN107905114B (en) A kind of construction method of large span Successive interference cancellation
CN103939114B (en) A kind of outstanding rail chassis lining construction method
CN108004927B (en) Double-limb triangular hanging basket and construction method for cantilever beam section of large-span continuous rigid frame bridge
CN103924525B (en) Urban interchange industrialization short-term precast assembly construction method
CN110453613B (en) Full-section one-step suspension casting construction method for large-span beam bridge box girder
CN101787678A (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN103030070B (en) A kind of can the transfer crane of traveling and operation on ramp
CN106522112A (en) Cable-stayed bridge side span beam section erecting system and method thereof
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN107974942B (en) A kind of abrupt slope side rigid frame-continuous girder end bay construction method
CN102587282B (en) Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude
CN105568870A (en) Triangle hanging basket suspended casting device used for overpass bridge construction and construction method thereof
CN110700119A (en) Upper traveling system of assembled Bailey beam hanging basket and design method thereof
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN105603879B (en) The construction technology in large-scale pipeline crossing construction cat road
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
CN205242278U (en) A triangle string basket method is hanged and is watered device for deck bridge construction
CN107288039A (en) Railway Through Steel concrete combination bridge floor steel truss girder construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20171024

RJ01 Rejection of invention patent application after publication