CN107218620A - Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels - Google Patents

Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels Download PDF

Info

Publication number
CN107218620A
CN107218620A CN201710510480.XA CN201710510480A CN107218620A CN 107218620 A CN107218620 A CN 107218620A CN 201710510480 A CN201710510480 A CN 201710510480A CN 107218620 A CN107218620 A CN 107218620A
Authority
CN
China
Prior art keywords
plate
pulverized coal
housing
fixed
phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201710510480.XA
Other languages
Chinese (zh)
Inventor
丁为平
徐明厚
陈太文
陈克祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU ZHONGNENG POWER EQUIPMENT CO Ltd
Original Assignee
JIANGSU ZHONGNENG POWER EQUIPMENT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU ZHONGNENG POWER EQUIPMENT CO Ltd filed Critical JIANGSU ZHONGNENG POWER EQUIPMENT CO Ltd
Priority to CN201710510480.XA priority Critical patent/CN107218620A/en
Publication of CN107218620A publication Critical patent/CN107218620A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23KFEEDING FUEL TO COMBUSTION APPARATUS
    • F23K3/00Feeding or distributing of lump or pulverulent fuel to combustion apparatus
    • F23K3/02Pneumatic feeding arrangements, i.e. by air blast
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23NREGULATING OR CONTROLLING COMBUSTION
    • F23N1/00Regulating fuel supply
    • F23N1/02Regulating fuel supply conjointly with air supply
    • F23N1/027Regulating fuel supply conjointly with air supply using mechanical means
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23KFEEDING FUEL TO COMBUSTION APPARATUS
    • F23K2203/00Feeding arrangements
    • F23K2203/006Fuel distribution and transport systems for pulverulent fuel
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F23COMBUSTION APPARATUS; COMBUSTION PROCESSES
    • F23NREGULATING OR CONTROLLING COMBUSTION
    • F23N2239/00Fuels
    • F23N2239/02Solid fuels

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)

Abstract

The invention provides the adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels, the achievable coal dust of the present invention and air are evenly distributed, and the pulverized coal flow and air mass flow of each branch pipe can be adjusted respectively, not interfere with each other substantially.The present invention has abandoned traditional principle that breeze airflow is directly split to distribution, cancels resistance elements unnecessary in traditional restricting orifice structure, reduction system;It is adjustable in operation, by the way that the concentrated phase governor motion and dilute phase governor motion on distributor are adjusted into appropriate position with regard to that can reach the effect evenly distributed;Realize and control the deviation of instead matching somebody with somebody of coal dust and air below ± 10%;By taking Precautionary Measure, wear-resistant ceramic is laid with position easy to wear, service life extension, maintenance workload is small.

Description

Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels
Technical field
The present invention relates to pulverized coal distributor field, and in particular to the adjustable moulded coal for 1000MW boiler controller system pulverized coal channels Powder distributor.
Background technology
The commonly used unit pulverized-coal system of a large amount of capacity coal-burning boilers, blows each burner First air of formula pulverized coal preparation system now Whether evenly distributed powder is to determine one of key factor of Combustion Operation of Boilers.The primary air velocity and coal of each burner of reasonable disposition Powder concentration is to ensure boiler controller system safety, the essential condition of economical operation, is also the premise bar that low Nox combustion technologies are smoothly implemented Part.Wind powder distribution between each burner is uneven, will directly affect catching fire and surely firing for burner outlet breeze airflow, causes flame Deflection, wash away furnace wall, furnace load and temperature deviation, Nox discharge capacitys increase, it is also possible to cause coal in First air horizontal pipe Powder is precipitated, and is caused plugging, is caused corresponding burner to burn out, or even is caused local reduction atmosphere strong and produced the local height of heating surface The problems such as temperature corrosion or coking, booster, have a strong impact on the security and economy of unit operation.Because of primary wind and powder distribution inequality The example for causing boiler to be not normally functioning is too numerous to enumerate.Peak regulation task is undertaken in unit and environmental requirement increasingly stricter feelings Under condition, the evenly distributed sex chromosome mosaicism of wind powder shows important especially.Power industry standard《Thermal power plant coal dust preparation system design standard and Computational methods》(DL/T5154-2002) expressly provide in the 8.1st article, it is each with layer burner to medium-speed pulverizer unit pulverized-coal system Coal dust and air between primary air piping should be evenly distributed, and its air quantity difference is not more than ± 8%, and coal powder distribation deviation is not more than ± 10%.Pulverized coal distributor is the device that breeze airflow is uniformly distributed to some branch pipes, is just had early in the fifties abroad Using what the country was applied earliest is the diffused coal dust that the 120MW unit E70 coal pulverizers that Huainan power plant the seventies are introduced are used Distributor;The eighties, Dou He power plant, Yaomeng power plant and Chaoyang power plant introduce employed in unit or transformation process diffused, The pulverized coal distributor of grid type and Germany BABCOCK.The nineties, the grid moulded coal developed by domestic relevant R&D institution Powder distributor is applied successfully on the 200-300MW units of the power plant such as first Yangshan, Longkou, Fengcheng successively.It is existing Grid pulverized coal distributor is that performance is best in all types distributor, and grid pulverized coal distributor is by grid by breeze airflow point Some narrow slit flows are segmented into, two branch pipes are re-introduced into.Its intrinsic distribution deviation is ± 10%- ± 15%, adds drag characteristic and causes Additional deviation, total distribution deviation can be bigger, it is impossible to the need for meeting large sized unit safety and economic operation, solves wind powder point Key with offset issue be in distributor so that enter each branch pipe air quantity and powder measure it is uniform.
The content of the invention
In order to solve problems of the prior art, the invention provides for 1000MW boiler controller system pulverized coal channels Adjustable type pulverized coal distributor, substantially improves unit pulverized-coal system primary wind and powder partition characteristic, substantially eliminates Large Copacity coal-fired The boiler various problems relevant with primary wind and powder partition characteristic.
Technical proposal that the invention solves the above-mentioned problems is:Adjustable type coal dust for 1000MW boiler controller system pulverized coal channels Distributor, including housing, dilute phase governor motion, concentrated phase governor motion, maintenance door;
Concentrated phase governor motion includes concentrated phase regulation handle, concentrated phase baffle plate, first axle, and concentrated phase regulation handle includes first Frame, the first retainer ring, first support two ends are respectively equipped with the first mounting hole, the first circular hole, and the first retainer ring is circular arc, first Some apertures are provided with along circular arc in retainer ring, the first retainer ring is fixed on housing;First support is located in the first retainer ring, the One support is mutually fixed by the first circular hole with the first retainer ring;First axle one end is fixed on the first mounting hole, the other end with it is dense Phase baffle plate is connected;Concentrated phase baffle plate is circular arc;
Dilute phase governor motion includes dilute phase regulation handle, dilute phase baffle plate, the second axle, and dilute phase regulation handle includes second Frame, the second retainer ring, second support two ends are respectively equipped with the second mounting hole, the second circular hole;Second retainer ring is circular arc, second Some apertures are provided with along circular arc in retainer ring, the second retainer ring is fixed on housing;Second support is located in the second retainer ring, the Two supports are mutually fixed by the second circular hole with the second retainer ring;Second axle one end is fixed on the second mounting hole, the other end with it is dilute Phase baffle plate is connected;Dilute phase baffle plate is circular arc;
Maintenance door includes window, housing, and housing is rectangle, and window is fixed in housing by nut;
Housing includes the first plate, the second plate, the 3rd plate, the 4th plate, and the first plate and the second plate be symmetrical, the 3rd plate and the Symmetrical before and after four plates, housing is hollow structure, and enclosure interior is provided with shunting zone, workspace, and shunting zone is located at lower housing portion, work Area is located at housing upper, and workspace is longitudinally divided into concentrated phase workspace, dilute phase workspace by the first dividing plate, and second partition is by dilute phase work The first dilute phase workspace, the second dilute phase workspace are divided into, two pieces of dilute phase baffle plates are located at the first dilute phase workspace, second respectively Dilute phase workspace, respectively by second supporting, the 3rd supporting position, second supporting, the 3rd supporting respectively by the second fixed seat, 3rd fixed seat is fixed on the first dividing plate, and concentrated phase baffle plate is located at concentrated phase workspace, is positioned by the first supporting, and the first supporting is logical The first fixed seat is crossed to be fixed on housing;
Housing bottom shunting zone is sequentially provided with the first flase floor group, the second flase floor group, guide plate, the first lattice from top to bottom Screen group includes two piece of first flase floor, and two piece of first flase floor is tilted respectively is fixed on the first plate, on the second plate, two piece first Flase floor mirror image is positioned to outer "eight" shape, and the first flase floor is 45 ° with horizontal plane angle;Second flase floor group includes two pieces the Two flase floors, two piece of second flase floor is tilted respectively is fixed on the first plate, on the second plate, and two piece of second flase floor mirror image is positioned to Interior "eight" shape, the first flase floor is 45 with horizontal plane angle;Guide plate section is triangular in shape, and guide plate is located at enclosure interior, Guide plate is fixed on the 3rd plate;First flase floor and the second grating board structure, size all same, using the integrated knot of differential Structure;
3rd plate outer wall is sequentially provided with concentrated phase installing zone, dilute phase installing zone from top to bottom, and concentrated phase governor motion is located at dense Phase installing zone, concentrated phase regulation handle is fixed on the 3rd plate, and 2 dilute phase governor motions are symmetrically distributed in dilute phase installing zone, and 2 dilute Phase regulation handle is fixed on the 3rd plate;Maintenance door is located at dilute phase installing zone bottom, and maintenance door is fixed on the 3rd plate, and first Plate, the second plate, the 3rd plate, the 4th plate top are respectively equipped with a hoisting ring.
The housing, the first flase floor, the second flase floor use 16Mn material manufactures.
The inner walls, the first flase floor, the second grid plate surface are lined with ceramic layer.
The thickness of shell is not less than 10mm.
The inner walls ceramic layer thickness is not less than 12mm.
The sealing of the maintenance door and housing uses a diameter of 10mm asbestos cord.
The sealing of the concentrated phase governor motion and housing is sealed using immersion oil asbestos cord.
The sealing of the dilute phase governor motion and housing is sealed using immersion oil asbestos cord.
The present invention has beneficial effect:The achievable coal dust of the present invention and air are evenly distributed, the pulverized coal flow of each branch pipe It can respectively adjust, do not interfere with each other substantially with air mass flow.The present invention, which has been abandoned, traditional directly splits breeze airflow distribution Principle, cancel resistance elements unnecessary in traditional restricting orifice structure, reduction system;It is adjustable in operation, by inciting somebody to action Concentrated phase governor motion and dilute phase governor motion on distributor are adjusted to appropriate position with regard to that can reach the effect evenly distributed;Realize The deviation of instead matching somebody with somebody of coal dust and air is controlled below ± 10%;By taking Precautionary Measure, it is laid with position easy to wear Wear-resistant ceramic, service life extension, maintenance workload is small.
Brief description of the drawings
Fig. 1 is front view of the present invention.
Fig. 2 is right view of the present invention;
Sectional views of the Fig. 3 for the present invention along A-A directions.
Sectional views of the Fig. 4 for the present invention along B-B directions.
Fig. 5 is the first grating board structure schematic diagram of the invention.
Fig. 6 is stripe grating plate structure schematic diagram of the present invention.
Fig. 7 is grid grating board structure schematic diagram of the present invention.
Fig. 8 is triangle grating board structure schematic diagram of the present invention.
In figure:1- housings, 2- concentrated phase governor motions, 3- dilute phase governor motions, 4- hoisting rings, 5- maintenance doors, 6- concentrated phases are adjusted Handle is saved, 7- concentrated phase baffle plates, 8- first axles, 10- first supports, the retainer rings of 11- first, the mounting holes of 12- first, 13- first justifies Hole, 14- dilute phase regulation handles, 15- dilute phase baffle plates, the axles of 16- second, 18- second supports, the retainer rings of 19- second, 20- second pacifies Dress hole, the circular holes of 21- second, 23- housings, 24- windows, the flase floors of 25- first, the flase floors of 26- second, 27- stripe grating plates, 28- grid flase floors, 29- triangle flase floors, 30- rectangular frames, 31- demarcation strips, the transverse slats of 32- first, 33- starting staves, The transverse slats of 34- second, the risers of 35- second, 36- dividing plates, the plates of 37- first, the plates of 38- second, the plates of 39- the 3rd, the plates of 40- the 4th, 41- points Stream area, 42- workspaces, 43- concentrated phases workspace, the first dilute phases of 44- workspace, the second dilute phases of 45- workspace, the dividing plates of 46- first, 47- second partitions, 48- first is supported, the fixed seats of 49- first, 50- the first flase floor groups, 51- the second flase floor groups, and 52- is oriented to Plate, 53- concentrated phase installing zones, 54- dilute phase installing zones, 55- second is supported, the fixed seats of 56- second.
Embodiment
Below in conjunction with the accompanying drawings and embodiment the present invention is further illustrated.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, merely to Be easy to the description present invention and simplify description, rather than indicate or imply signified device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that indicating or implying relative importance.
As illustrated, the adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels, for 1000MW boilers The adjustable type pulverized coal distributor of unit pulverized coal channel, including housing, dilute phase governor motion, concentrated phase governor motion, maintenance door;
Concentrated phase governor motion includes concentrated phase regulation handle, concentrated phase baffle plate, first axle, and concentrated phase regulation handle includes first Frame, the first retainer ring, first support two ends are respectively equipped with the first mounting hole, the first circular hole, and the first retainer ring is circular arc, first Some apertures are provided with along circular arc in retainer ring, the first retainer ring is fixed on housing;First support is located in the first retainer ring, the One support is mutually fixed by the first circular hole with the first retainer ring;First axle one end is fixed on the first mounting hole, the other end with it is dense Phase baffle plate is connected;Concentrated phase baffle plate is circular arc;
Dilute phase governor motion includes dilute phase regulation handle, dilute phase baffle plate, the second axle, and dilute phase regulation handle includes second Frame, the second retainer ring, second support two ends are respectively equipped with the second mounting hole, the second circular hole, and the second retainer ring is circular arc, second Some apertures are provided with along circular arc in retainer ring, the second retainer ring is fixed on housing;Second support is located in the second retainer ring, the Two supports are mutually fixed by the second circular hole with the second retainer ring;Second axle one end is fixed on the second mounting hole, the other end with it is dilute Phase baffle plate is connected;Dilute phase baffle plate is circular arc;
Maintenance door includes window, housing, and housing is rectangle, and window is fixed in housing by nut;
First flase floor and the second grating board structure, size all same, the first flase floor include stripe grating plate, grid lattice Screen, triangle flase floor, stripe grating plate include rectangular frame, demarcation strip, and demarcation strip is located in rectangular frame, 6 pieces points Longitudinal direction of the dividing plate along length direction framework is uniformly distributed;Grid flase floor is erected including rectangular frame, the first transverse slat, first Plate, the first transverse slat is located in rectangular frame, and longitudinal direction of 6 piece of first transverse slat along length direction framework is uniformly distributed;First Riser is located in rectangular frame, and horizontal direction of 9 pieces of starting staves along length direction framework is uniformly distributed;6 piece of first transverse slat With the interlaced multiple square lattices of formation of 9 pieces of starting staves;Triangle flase floor includes rectangular frame, the second transverse slat, the Two risers, dividing plate, the second transverse slat are located in rectangular frame, and longitudinal direction of 6 piece of second transverse slat along length direction framework is uniform Distribution;Second riser is located in rectangular frame, and horizontal direction of 9 piece of second riser along length direction framework is uniformly distributed;6 pieces First transverse slat and 9 pieces of starting staves it is interlaced formed be equipped with multiple square lattices, each square lattice one every Plate, dividing plate is located on the diagonal of square lattice;Triangle flase floor is fixed on grid flase floor, and grid flase floor is fixed on On stripe grating plate;
Housing includes the first plate, the second plate, the 3rd plate, the 4th plate, and the first plate and the second plate be symmetrical, the 3rd plate and the Symmetrical before and after four plates, housing is hollow structure, and enclosure interior is provided with shunting zone, workspace, and shunting zone is located at lower housing portion, work Area is located at housing upper, and workspace is longitudinally divided into concentrated phase workspace, dilute phase workspace by the first dividing plate;Second partition is by dilute phase work The first dilute phase workspace, the second dilute phase workspace are divided into, two pieces of dilute phase baffle plates are located at the first dilute phase workspace, second respectively Dilute phase workspace, respectively by second supporting, the 3rd supporting position, second supporting, the 3rd supporting respectively by the second fixed seat, 3rd fixed seat is fixed on the first dividing plate, and concentrated phase baffle plate is located at concentrated phase workspace, is positioned by the first supporting, and the first supporting is logical The first fixed seat is crossed to be fixed on housing;Dilute phase baffle plate is located at the first phase workspace, is positioned by the first supporting, and the first supporting is logical The first fixed seat is crossed to be fixed on housing;
Housing bottom shunting zone is sequentially provided with the first flase floor group, the second flase floor group, guide plate, the first lattice from top to bottom Screen group includes two piece of first flase floor, and two piece of first flase floor is tilted respectively is fixed on the first plate, on the second plate, two piece first Flase floor mirror image is positioned to outer "eight" shape, and the first flase floor is 45 ° with horizontal plane angle;Second flase floor group includes two pieces the Two flase floors, two piece of second flase floor is tilted respectively is fixed on the first plate, on the second plate, and two piece of second flase floor mirror image is positioned to Interior "eight" shape, the first flase floor is 45 with horizontal plane angle;Guide plate section is triangular in shape, and guide plate is located at enclosure interior, Guide plate is fixed on the 3rd plate;First flase floor and the second grating board structure, size all same, using differential integrated structure
3rd plate outer wall is sequentially provided with concentrated phase installing zone, dilute phase installing zone from top to bottom, and concentrated phase governor motion is located at dense Phase installing zone, concentrated phase regulation handle is fixed on the 3rd plate, and 2 dilute phase governor motions are located in dilute phase installing zone, dilute phase regulation Handle is fixed on the 3rd plate;Maintenance door is located at dilute phase installing zone bottom, and maintenance door is fixed on the 3rd plate, the first plate, second Plate, the 3rd plate, the 4th plate top are respectively equipped with a hoisting ring.
The housing, the first flase floor, the second flase floor use 16Mn material manufactures.
The inner walls, the first flase floor, the second grid plate surface are lined with ceramic layer.
The thickness of shell is not less than 10mm.
The inner walls ceramic layer thickness is not less than 12mm.
The sealing of the maintenance door and housing uses a diameter of 10mm asbestos cord.
The sealing of the concentrated phase governor motion and housing is sealed using immersion oil asbestos cord.
The sealing of the dilute phase governor motion and housing is sealed using immersion oil asbestos cord.
In use, the wind coal mixture come out from coal pulverizer is blown into by pressure wind below housing, after housing is entered, After wind coal mixture is by guide plate, the first flase floor, the second flase floor, pulverized coal particle tries hard to protect in the presence of inertia force Its original flow direction is held, so as to directly get on guide plate, is ejected to original opposite direction, result is that wind coal is mixed Zoarium is decomposed into thick coal culm stream and dilute pulverized coal flow, and thick coal culm stream is the air-flow of high concentration low discharge, and dilute pulverized coal flow is big stream The air-flow of volume low-concentration, then this two strands of air-flows are allocated respectively, concentrated phase workspace and dilute phase workspace are respectively disposed with not Same governor motion so that assigning process is adjustable, and dense, light two strands of air-flows after distribution mutually converge in export distributor, by phase The pulverized coal channel answered is sent in stove.So achieve that to every coal dust and air mass flow point towards the pulverized coal feed pipe of burner It is not adjusted and controls.When the pulverized coal flow of a certain pipeline will be tuned up, regulation concentrated phase governor motion makes concentrated phase flow become big, Then concentrated phase regulation handle is fixed in retainer ring with bolt and nut, it is ensured that do not moved in debugging front hand grip position next time It is dynamic, dilute phase flow is diminished while adjusting dilute phase governor motion, dilute phase regulation handle is then fixed on fixation with bolt and nut On ring;When the pulverized coal flow of a certain pipeline will be turned down, regulation concentrated phase governor motion makes concentrated phase flow diminish, and then uses bolt spiral shell Concentrated phase regulation handle is fixed in retainer ring by mother, it is ensured that be not moved in debugging front hand grip position next time, while regulation is dilute Phase governor motion makes dilute phase flow become big, and then dilute phase regulation handle is fixed in retainer ring with bolt and nut;
By the regulation to the pulverized coal distributor, evenly distributing for coal dust and air, the pulverized coal flow of each branch pipe can be achieved It can respectively adjust, do not interfere with each other substantially with air mass flow.That is, while being tuned up to the pulverized coal flow of a certain pipeline, Air mass flow to the pipeline can be turned down;While being turned down to the pulverized coal flow of a certain pipeline, the air mass flow to the pipeline can Tune up.
Many other changes and remodeling can be made by not departing from the spirit and scope of the present invention.It should be appreciated that the present invention is not It is limited to specific embodiment, the scope of the present invention is defined by the following claims.

Claims (8)

1. the adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels, it is characterised in that adjusted including housing, dilute phase Save mechanism, concentrated phase governor motion, maintenance door;
Concentrated phase governor motion includes concentrated phase regulation handle, concentrated phase baffle plate, first axle;Concentrated phase regulation handle includes first support, the One retainer ring, first support two ends are respectively equipped with the first mounting hole, the first circular hole, and the first retainer ring is circular arc, and first fixes Some apertures are provided with along circular arc on ring, the first retainer ring is fixed on housing;First support is located in the first retainer ring, first Frame is mutually fixed by the first circular hole with the first retainer ring;First axle one end is fixed on the first mounting hole, and the other end is kept off with concentrated phase Plate is connected;Concentrated phase baffle plate is circular arc;
Dilute phase governor motion includes dilute phase regulation handle, dilute phase baffle plate, the second axle, and dilute phase regulation handle includes second support, the Two retainer rings, second support two ends are respectively equipped with the second mounting hole, the second circular hole, and the second retainer ring is circular arc, and second fixes Some apertures are provided with along circular arc on ring, the second retainer ring is fixed on housing;Second support is located in the second retainer ring, second Frame is mutually fixed by the second circular hole with the second retainer ring;Second axle one end is fixed on the second mounting hole, and the other end is kept off with dilute phase Plate is connected;Dilute phase baffle plate is circular arc;
Maintenance door includes window, housing, and housing is rectangle, and window is fixed in housing by nut;
Housing includes the first plate, the second plate, the 3rd plate, the 4th plate, and the first plate and the second plate are symmetrical, the 3rd plate and the 4th plate Front and rear symmetrical, housing is hollow structure, and enclosure interior is provided with shunting zone, workspace, and shunting zone is located at lower housing portion, and work position In housing upper, workspace is longitudinally divided into concentrated phase workspace, dilute phase workspace by the first dividing plate, and second partition is by dilute phase workspace It is divided into the first dilute phase workspace, the second dilute phase workspace, two pieces of dilute phase baffle plates are located at the first dilute phase workspace, the second dilute phase respectively Workspace, is positioned by the second supporting, the 3rd supporting respectively, and the second supporting, the 3rd supporting pass through the second fixed seat, the 3rd respectively Fixed seat is fixed on the first dividing plate, and concentrated phase baffle plate is located at concentrated phase workspace, is positioned by the first supporting, and the first supporting passes through the One fixed seat is fixed on housing;
Housing bottom shunting zone is sequentially provided with the first flase floor group, the second flase floor group, guide plate, the first flase floor from top to bottom Group includes two piece of first flase floor, and two piece of first flase floor is tilted respectively is fixed on the first plate, on the second plate, two piece of first grid Plate mirror image is positioned to outer "eight" shape, and the first flase floor is 45 ° with horizontal plane angle;Second flase floor group includes two piece of second lattice Screen, two piece of second flase floor is tilted respectively is fixed on the first plate, on the second plate, in two piece of second flase floor mirror image is positioned to "eight" shape, the first flase floor is 45 with horizontal plane angle;Guide plate section is triangular in shape, and guide plate is located at enclosure interior, leads It is fixed on to plate on the 3rd plate;First flase floor and the second grating board structure, size all same, using differential integrated structure;
3rd plate outer wall is sequentially provided with concentrated phase installing zone, dilute phase installing zone from top to bottom, and concentrated phase governor motion is located in concentrated phase peace Area is filled, concentrated phase regulation handle is fixed on the 3rd plate, 2 dilute phase governor motions are symmetrically distributed in dilute phase installing zone, 2 dilute phases are adjusted Section handle is fixed on the 3rd plate;Maintenance door is located at dilute phase installing zone bottom, and maintenance door is fixed on the 3rd plate, the first plate, the Two plates, the 3rd plate, the 4th plate top are respectively equipped with a hoisting ring.
2. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the housing, the first flase floor, the second flase floor use 16Mn material manufactures.
3. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the inner walls, the first flase floor, the second grid plate surface are lined with ceramic layer.
4. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the thickness of shell is not less than 10mm.
5. inner walls as claimed in claim 3 are lined with ceramic layer, it is characterised in that the inner walls ceramic layer thickness is not Less than 12mm.
6. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the sealing of the maintenance door and housing uses a diameter of 10mm asbestos cord.
7. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the sealing of the concentrated phase governor motion and housing is sealed using immersion oil asbestos cord.
8. being used for the adjustable type pulverized coal distributor of 1000MW boiler controller system pulverized coal channels as claimed in claim 1, its feature exists In the sealing of the dilute phase governor motion and housing is sealed using immersion oil asbestos cord.
CN201710510480.XA 2017-06-28 2017-06-28 Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels Withdrawn CN107218620A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710510480.XA CN107218620A (en) 2017-06-28 2017-06-28 Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710510480.XA CN107218620A (en) 2017-06-28 2017-06-28 Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels

Publications (1)

Publication Number Publication Date
CN107218620A true CN107218620A (en) 2017-09-29

Family

ID=59950573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710510480.XA Withdrawn CN107218620A (en) 2017-06-28 2017-06-28 Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels

Country Status (1)

Country Link
CN (1) CN107218620A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108204601A (en) * 2017-12-21 2018-06-26 北京博奇电力科技有限公司 Two-stage adjusts gas-particle two-phase fluidic distributor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108204601A (en) * 2017-12-21 2018-06-26 北京博奇电力科技有限公司 Two-stage adjusts gas-particle two-phase fluidic distributor

Similar Documents

Publication Publication Date Title
TWI402468B (en) Low nox nozzle tip for a pulverized solid fuel furnace
AU762789B2 (en) Method of operating a tangential firing system
WO2017206430A1 (en) Circulating fluidized bed combustion system with uniform air distribution device
CN107131518B (en) Intermediate storage bin type medium-speed mill positive pressure direct-fired pulverizing system
CN101513635B (en) High-efficiency low-resistance coal powder light-dark separation device used for W-shaped flame boiler
KR20050112094A (en) Balancing damper
CN202082915U (en) W-shape flame boiler with grading secondary air layout structure
CN104654292B (en) Space shade type straight-through pulverized coal burner
CN107218620A (en) Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels
TW440668B (en) Coal firing furnace and method of operating a coal-fired furnace
CN107023824A (en) Vertical pulverized-coal fired boiler
CN207112855U (en) Adjustable type pulverized coal distributor for 1000MW boiler controller system pulverized coal channels
CN107084387A (en) The low NOx Horizontal CFB Boilers of multipaths that a kind of flue gas strile-backs
CN206861513U (en) The low NOx Horizontal CFB Boilers of multipaths that a kind of flue gas strile-backs
CN202182463U (en) Combustion system of W-shaped flame furnace
CN103697463A (en) Up-and-down thick-and-thin primary air concentrated distribution type combustion device
CN206831550U (en) A kind of compact pulverized coal distributor
CN103234203A (en) Combustor for ignition furnace of sintering machine
CN210964678U (en) Smoke air mixing box with multiple built-in distributors
CN107191960A (en) A kind of compact pulverized coal distributor
CN209246065U (en) A kind of Novel DC coal burner
JPS63315805A (en) Method of feeding air for combustion
CN205782889U (en) It is beneficial to discharge air-distribution device and the multipath circulating fluidized bed boiler of bulky grain thing
CN201858639U (en) Spraying blow pipe material returner for circulating fluidized bed boiler
JP2731794B2 (en) High performance overfire air system for NOx control

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20170929