CN107181445B - A kind of installation method of photovoltaic power plant bracket waterborne - Google Patents

A kind of installation method of photovoltaic power plant bracket waterborne Download PDF

Info

Publication number
CN107181445B
CN107181445B CN201710412628.6A CN201710412628A CN107181445B CN 107181445 B CN107181445 B CN 107181445B CN 201710412628 A CN201710412628 A CN 201710412628A CN 107181445 B CN107181445 B CN 107181445B
Authority
CN
China
Prior art keywords
cant beam
cant
installation
stake
beams
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710412628.6A
Other languages
Chinese (zh)
Other versions
CN107181445A (en
Inventor
曹永明
高建岳
孙胜君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Solar Energy Technology Co Ltd
Original Assignee
Suzhou Solar Energy Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Solar Energy Technology Co Ltd filed Critical Suzhou Solar Energy Technology Co Ltd
Priority to CN201710412628.6A priority Critical patent/CN107181445B/en
Publication of CN107181445A publication Critical patent/CN107181445A/en
Application granted granted Critical
Publication of CN107181445B publication Critical patent/CN107181445B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02SGENERATION OF ELECTRIC POWER BY CONVERSION OF INFRARED RADIATION, VISIBLE LIGHT OR ULTRAVIOLET LIGHT, e.g. USING PHOTOVOLTAIC [PV] MODULES
    • H02S20/00Supporting structures for PV modules
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Abstract

The present invention relates to a kind of installation methods of photovoltaic power plant bracket waterborne, comprising: more than first a cant beams are installed in stake a more than first;The cant beam hookup wire set up between multiple cant beams;According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or more than second a cant beams are installed in more than second a stakes between stake a more than first;And the mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams.

Description

A kind of installation method of photovoltaic power plant bracket waterborne
Technical field
The present invention relates to photovoltaic technology field waterborne, a kind of particularly installation method of photovoltaic power plant bracket waterborne.
Background technique
Photovoltaic waterborne refers to using the idle water surface photovoltaic power generation application for building photovoltaic plant.Photovoltaic plant tool waterborne Many advantages, such as being not take up land land resource, reducing Water Evaporation, avoid algal grown, there is vast potential for future development. However, at present photovoltaic plant waterborne there is the construction period many problems such as long, at high cost, affect pushing away for photovoltaic plant waterborne Extensively.
Summary of the invention
For the technical problems in the prior art, the invention proposes a kind of installation sides of photovoltaic power plant bracket waterborne Method, comprising: more than first a cant beams are installed in stake a more than first;The cant beam hookup wire set up between multiple cant beams;According to oblique Second installation second cant beam of the beam hookup wire between stake a more than first;Or more than second a stakes between stake a more than first More than second a cant beams of upper installation;And a cant beam and more than second a cant beams more than more than the first a cant beams and the second cant beam or first Upper mounting purlines.
Method as described above, wherein the top, center, and/or bottom end of a cant beam more than first is arranged in cant beam hookup wire.
Method as described above, wherein without using measuring device or Angle Measuring Equipment installation the second cant beam or more is used only A second cant beam.
Method as described above further comprises the component mounting line for laying photovoltaic module.
Method as described above further comprises the cable that installation is used for photovoltaic module.
Method as described above further comprises installation skewed horizontal load.
Method as described above, wherein following any two step can carry out simultaneously: installing in stake a more than first A cant beam more than one;The cant beam hookup wire set up between multiple cant beams;According to cant beam hookup wire between stake a more than first Two the second cant beams of installation;Or more than second a cant beams are installed in more than second a stakes between stake a more than first;And Mounting purlines on a cant beam more than a cant beam more than one and the second cant beam or first and more than second a cant beams.
Method as described above, wherein following any two step can carry out simultaneously: installing in stake a more than first A cant beam more than one;The cant beam hookup wire set up between multiple cant beams;According to cant beam hookup wire between stake a more than first Two the second cant beams of installation;Or more than second a cant beams are installed in more than second a stakes between stake a more than first;More than first Mounting purlines on a cant beam more than a cant beam and the second cant beam or first and more than second a cant beams;Lay the component peace of photovoltaic module Wiring;Installation is used for the cable of photovoltaic module;And installation skewed horizontal load.
Method as described above, wherein further comprising installation photovoltaic component;And the step of installation photovoltaic component, can be with Any one or more steps can carry out simultaneously below: more than first a cant beams are installed in stake a more than first;In multiple cant beams Between the cant beam hookup wire that sets up;According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or More than second a cant beams are installed in more than second a stakes between stake a more than first;In more than first a cant beams and the second cant beam or Mounting purlines on a cant beam more than one and more than second a cant beams;Lay the component mounting line of photovoltaic module;Installation is used for photovoltaic module Cable;And installation photovoltaic component.
Method as described above, wherein further comprise independently prepare for following any one or more steps, distribute, Or transported material: more than first a cant beams are installed in stake a more than first;The cant beam hookup wire set up between multiple cant beams;According to Second installation second cant beam of the cant beam hookup wire between stake a more than first;Or more than second between stake a more than first More than second a cant beams are installed in stake;More than cant beam a more than first and the second cant beam or first on a cant beam and more than second a cant beams Mounting purlines;Lay the component mounting line of photovoltaic module;Installation is used for the cable of photovoltaic module;Skewed horizontal load is installed;And peace Fill photovoltaic module.
According to another aspect of the present invention, a kind of construction method of photovoltaic plant is proposed, comprising: as above any waterborne The installation method of photovoltaic power plant bracket.
Detailed description of the invention
In the following, the preferred embodiment of the present invention will be described in more detail in conjunction with attached drawing, in which:
Fig. 1 is the installation method flow chart of photovoltaic power plant bracket waterborne according to one embodiment of present invention;
Fig. 2 be according to one embodiment of present invention bracket installation before schematic diagram;
Fig. 3 is to install the schematic diagram after cant beam in selected stake according to one embodiment of present invention;
Fig. 4 is the schematic diagram after cant beam hookup wire erection according to one embodiment of present invention;
Fig. 5 is the schematic diagram after cant beam installation according to one embodiment of present invention;
Fig. 6 is the schematic diagram after purlin installation according to one embodiment of present invention;
Fig. 7 is the schematic diagram after component mounting line installation according to one embodiment of present invention;
Fig. 8 is the schematic diagram after bridging installation according to one embodiment of present invention;And
Fig. 9 is the schematic diagram after optical module installation according to one embodiment of present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
In the following detailed description, the specific embodiment for being used to illustrate the application as the application a part may refer to Each Figure of description.In the accompanying drawings, similar appended drawing reference describes substantially similar component in different drawings.This Shen Each specific embodiment please has carried out description detailed enough following, so that having the general of ability domain-dependent knowledge and technology Logical technical staff can implement the technical solution of the application.It should be appreciated that can also be using other embodiments or to the application Embodiment carry out structure, logic or electrical property change.
Photovoltaic module or solar panel are the capital equipments of photovoltaic plant.Special installation environment on the water Under, an important factor for being mounted for influencing photovoltaic plant construction period waterborne of photovoltaic module.With one 200 megawatts of light waterborne For overhead utility, construction personnel needs to install about 30,000 pieces of photovoltaic modulies, and construction period is usually 3 months.
Photovoltaic module needs rack-mount.The invention proposes a kind of new bracket installation methods.According to the present invention Some embodiments, the construction period of 200 megawatts of photovoltaic plant waterborne can shorten to about 4 weeks.Improving construction as a result, While efficiency, construction period is substantially reduced, reduces the construction cost of photovoltaic plant waterborne.
Fig. 1 is the installation method flow chart of photovoltaic power plant bracket waterborne according to an embodiment of the invention.Such as Fig. 1 institute Show, the installation method 100 of photovoltaic power plant bracket waterborne includes the following steps:
In step 110, cant beam is installed in selected multiple stakes.Fig. 2 is the schematic diagram before bracket is installed.Such as Fig. 2 institute Show, multiple stakes have been arranged on the water surface.Multiple stakes are arranged in rows and columns.Although it will be appreciated by those skilled in the art that in Fig. 2 Three row stake 101-103 are illustrated only, for the solution of the present invention, the quantity for the stake that row and column is respectively included is not limited System.
Fig. 3 is that the schematic diagram after cant beam is installed in selected stake.As shown in figure 3, selecting some stakes in every a line stake As staking, such as stake 201-203.Staking is generally spaced apart from each other, such as the 3-6 stake in interval, is preferably spaced 4 or 5 Stake.In step 110, cant beam is installed on selected multiple stakings.According to one embodiment of present invention, optionally, sharp Cant beam is installed on staking with measuring device, with ensure the cant beam on staking relative to the height on the water surface or ground, phase The tilt angle in direction and cant beam for multiple row or column meets the requirement of design.A reality according to the present invention Example is applied, step 110 further comprises that anchor ear and cant beam bracket are installed on selected staking, and cant beam is then installed to cant beam On bracket.Using measuring device, anchor ear, cant beam bracket and/or cant beam are adjusted, to guarantee oblique depth of beam and angle all in just True position.
In step 120, the cant beam hookup wire that is erected between mounted cant beam.Fig. 4 shows the erection of cant beam hookup wire Schematic diagram afterwards.As shown in figure 4, cant beam hookup wire 301 is erected between the mounted cant beam top of staking of every a line.It can Selection of land, it is accurate with the position for guaranteeing each cant beam defined in cant beam hookup wire using measuring device adjustment cant beam hookup wire.Root According to one embodiment of the present of invention, a plurality of cant beam hookup wire can be set up in every a line stake, to facilitate cant beam in subsequent step Installation.According to one embodiment of present invention, cant beam hookup wire may be mounted at the mounted cant beam of staking top, in The heart, and/or bottom end.
In step 130, it is based on cant beam hookup wire, cant beam is installed in each stake.Fig. 5 shows the signal after cant beam installation Figure.Specifically, the position determined in the case where a cant beam hookup wire using cant beam hookup wire and hand-held angle are surveyed Cant beam can be installed to desired position by amount equipment.And in the case where two cant beam hookup wires, it is not necessary to use any survey Amount equipment can complete the correct installation of cant beam.Therefore, it when installing cant beam in each stake, does not need as in step 110 Measuring device is relied on to determine whether the cant beam after installation is in correct position.This can greatly improve the efficiency of construction.Root According to one embodiment of the present of invention, the scheme using a cant beam hookup wire is more efficient.
Step 140, mounting purlines.Fig. 6 shows the schematic diagram after purlin installation.As shown in fig. 6, on cant beam, installation There is purlin 601-604.It will be appreciated by those skilled in the art that the installation of purlin can use the usual method of this field.In Fig. 6 Shown in except embodiment, still have other purlin plans of establishment, the plan of establishment of these purlins all the scope of the present invention it It is interior.
Step 150, the component mounting line of photovoltaic module is laid.Component mounting line is used for the position of positioning component, after convenient The installation of continuous component.
Step 160, installation is used for the cable of photovoltaic module.Fig. 7 shows the schematic diagram after cable installation.As shown in fig. 7, Cable 701 is laid by the direction of row.It will be appreciated by those skilled in the art that cable 701 can also otherwise be laid, these Mode is also within the scope of the present invention.It will be appreciated by those skilled in the art that the installation of cable can be above-mentioned any one Before or after a step.
Step 170, optionally, the skewed horizontal load between stake is installed.In order to enable whole system is more stable, in stake and stake Between skewed horizontal load can be installed.So-called " skewed horizontal load " includes a variety of reinforcement by connection such as bridging, scaffold, cant beam, inclined plate Mode.Fig. 8 shows the schematic diagram after bridging installation.As shown in figure 8, bridging 800 has been mounted between two column stakes.Ability Field technique personnel should be appreciated that skewed horizontal load may be mounted between other positions, such as two row stakes;Or not in same a line or Between two stakes of person's same row;Or skewed horizontal load only is installed between the stake of part.It will be appreciated by those skilled in the art that tiltedly Installation to support can be before or after any of the above steps.Preferably, it is installed before installation photovoltaic component oblique It is inconvenient to be reduced to construction bring to support.
It, can also further installation photovoltaic component after being mounted with bracket.Fig. 9 shows the signal after photovoltaic module installation Figure.As shown in figure 9, forming the photovoltaic group by being arranged in rows and columns according to component mounting line installation photovoltaic component 900 on purlin The photovoltaic array of part composition.
Further, for the construction method of photovoltaic plant, following steps be can further include:
Photovoltaic module is electrically connected with cable;And it connects the cable to header box and inverter is connected to by header box. Output direct current or alternating current can be further configured from inverter, to realize the power generation of photovoltaic plant.
According to one embodiment of present invention, step 110 and step 120 can carry out simultaneously.Due in a row or column It may include more piles, after installing cant beam on the staking of part, so that it may while cant beam is installed on other stakings Cant beam hookup wire is installed between the staking for having installed cant beam.
According to one embodiment of present invention, step 120 and step 130 can carry out simultaneously.Due in a row or column It may include more piles, after the cant beam hookup wire between installation good part staking, so that it may continue staking after mounting Between cant beam hookup wire while cant beam is installed in the stake for having installed cant beam hookup wire.
According to one embodiment of present invention, step 130 and step 140 can carry out simultaneously.Due in a row or column It may include more piles, after the cant beam for installing good part stake according to cant beam hookup wire, so that it may continue the oblique of stake after mounting While beam after having installed mounting purlines in the stake of cant beam.
According to one embodiment of present invention, step 140 and step 150 can carry out simultaneously.Due in a row or column It may include more piles, after the purlin of part stake installs, so that it may while continuing the purlin of stake after mounting Mounting assembly hookup wire between the stake of purlin after installation.
According to one embodiment of present invention, step 160 can carry out simultaneously with other steps.The step of installing cable is straight It connects and is operated between stake, can be carried out simultaneously with all of above step or step 170.
According to one embodiment of present invention, step 170 can carry out simultaneously with other steps.The step of oblique line support is installed Suddenly it directly operates, can be carried out simultaneously with all of above step between stake.
According to one embodiment of present invention, the mounting assembly in the stake for laid cable the step of can with it is above-mentioned Other steps carry out simultaneously.
According to one embodiment of present invention, above-mentioned steps 110- step 170 and the step of mounting assembly in any two Or multiple steps can carry out simultaneously.For the construction of photovoltaic plant, need the quantity of mounting bracket very much, while Above-mentioned steps are carried out in different stakes can be improved construction efficiency.
According to one embodiment of present invention, above-mentioned steps 110- step 170 and the step of mounting assembly, carry out simultaneously, with Construction efficiency is improved to the maximum extent.
One problem of over-water construction is that the transport of material on the water is time-consuming and laborious.It is applied to further increase Work efficiency rate avoids multiple or all steps in the step of repeating transport and ineffective traffic, being step 110-170 and mounting assembly Suddenly independently prepare and distribute material, it is ensured that the maximization of construction efficiency.
The construction speed of photovoltaic plant waterborne can be significantly increased in optical module installation method of the invention, and shortening is applied The work duration reduces construction cost, will play an important role for improving the promotion and application of photovoltaic plant waterborne.
Above-described embodiment is used for illustrative purposes only, and is not limitation of the present invention, in relation to the general of technical field Logical technical staff can also make a variety of changes and modification without departing from the present invention, therefore, all equivalent Technical solution also should belong to scope disclosed by the invention.

Claims (11)

1. a kind of installation method of photovoltaic power plant bracket waterborne, comprising:
Anchor ear and cant beam bracket are installed in stake a more than first;
More than first a cant beams are installed on cant beam bracket;
Cant beam hookup wire is set up between cant beam a more than first;
According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or according to cant beam hookup wire More than second a cant beams are installed in more than second a stakes more than one between a stake;And
The mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams;
Wherein, using measuring device, anchor ear, cant beam bracket and/or more than first a cant beams are adjusted, to guarantee more than first a cant beams Height and angle are all in correct position.
2. according to the method described in claim 1, wherein cant beam hookup wire be arranged in a cant beam more than first top, center and/ Or bottom end.
3. according to the method described in claim 2, without using measuring device or Angle Measuring Equipment installation second wherein is used only Cant beam or more than second a cant beams.
4. according to the method described in claim 1, further comprising the component mounting line for laying photovoltaic module.
5. according to the method described in claim 1, further comprising the cable that installation is used for photovoltaic module.
6. according to the method described in claim 1, further comprising installation skewed horizontal load.
7. according to the method described in claim 1, wherein following any two step can carry out simultaneously:
Anchor ear and cant beam bracket are installed in stake a more than first;
More than first a cant beams are installed on cant beam bracket;
Cant beam hookup wire is set up between cant beam a more than first;
According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or according to cant beam hookup wire More than second a cant beams are installed in more than second a stakes more than one between a stake;And
The mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams.
8. according to the method described in claim 6, wherein following any two step can carry out simultaneously:
Anchor ear and cant beam bracket are installed in stake a more than first;
More than first a cant beams are installed on cant beam bracket;
Cant beam hookup wire is set up between cant beam a more than first;
According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or according to cant beam hookup wire More than second a cant beams are installed in more than second a stakes more than one between a stake;
The mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams;
Lay the component mounting line of photovoltaic module;
Installation is used for the cable of photovoltaic module;And
Skewed horizontal load is installed.
9. according to the method described in claim 8, wherein further comprising installation photovoltaic component;And the step of installation photovoltaic component It can be carried out simultaneously with following any one or more steps:
Anchor ear and cant beam bracket are installed in stake a more than first;
More than first a cant beams are installed on cant beam bracket;
The cant beam hookup wire set up between cant beam a more than first;
According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or according to cant beam hookup wire More than second a cant beams are installed in more than second a stakes more than one between a stake;
The mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams;
Lay the component mounting line of photovoltaic module;
Installation is used for the cable of photovoltaic module;And
Skewed horizontal load is installed.
10. according to the method described in claim 9, wherein further comprise for following any one or more steps it is independently quasi- Standby, distribution or transported material:
Anchor ear and cant beam bracket are installed in stake a more than first;
More than first a cant beams are installed on cant beam bracket;
The cant beam hookup wire set up between cant beam a more than first;
According to second installation second cant beam of the cant beam hookup wire between stake a more than first;Or according to cant beam hookup wire More than second a cant beams are installed in more than second a stakes more than one between a stake;
The mounting purlines on a cant beam more than cant beam a more than first and the second cant beam or first and more than second a cant beams;
Lay the component mounting line of photovoltaic module;
Installation is used for the cable of photovoltaic module;
Skewed horizontal load is installed;And
Installation photovoltaic component.
11. a kind of construction method of photovoltaic plant, comprising: such as the installation of claim 1-10 any photovoltaic power plant bracket waterborne Method.
CN201710412628.6A 2017-06-05 2017-06-05 A kind of installation method of photovoltaic power plant bracket waterborne Active CN107181445B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710412628.6A CN107181445B (en) 2017-06-05 2017-06-05 A kind of installation method of photovoltaic power plant bracket waterborne

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710412628.6A CN107181445B (en) 2017-06-05 2017-06-05 A kind of installation method of photovoltaic power plant bracket waterborne

Publications (2)

Publication Number Publication Date
CN107181445A CN107181445A (en) 2017-09-19
CN107181445B true CN107181445B (en) 2019-07-30

Family

ID=59836661

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710412628.6A Active CN107181445B (en) 2017-06-05 2017-06-05 A kind of installation method of photovoltaic power plant bracket waterborne

Country Status (1)

Country Link
CN (1) CN107181445B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1933389A2 (en) * 2006-12-15 2008-06-18 Sunrise Facility for production of solar energy and roofing, application to the roofing of vehicle parking areas
US8592738B1 (en) * 2010-07-01 2013-11-26 Suncore Photovoltaics, Inc. Alignment device for use with a solar tracking photovoltaic array
CN204729854U (en) * 2015-04-22 2015-10-28 江东金具设备有限公司 Fishing light complimentary bracket
CN105553397A (en) * 2015-12-04 2016-05-04 蚌埠凯盛工程技术有限公司 Fishing light complementation photovoltaic fixing support
CN205430138U (en) * 2015-12-04 2016-08-03 蚌埠凯盛工程技术有限公司 Complementary photovoltaic fixed bolster of fishing light

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1933389A2 (en) * 2006-12-15 2008-06-18 Sunrise Facility for production of solar energy and roofing, application to the roofing of vehicle parking areas
US8592738B1 (en) * 2010-07-01 2013-11-26 Suncore Photovoltaics, Inc. Alignment device for use with a solar tracking photovoltaic array
CN204729854U (en) * 2015-04-22 2015-10-28 江东金具设备有限公司 Fishing light complimentary bracket
CN105553397A (en) * 2015-12-04 2016-05-04 蚌埠凯盛工程技术有限公司 Fishing light complementation photovoltaic fixing support
CN205430138U (en) * 2015-12-04 2016-08-03 蚌埠凯盛工程技术有限公司 Complementary photovoltaic fixed bolster of fishing light

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
光伏电站施工方案;wangxinhtysbd;《百度文库 https://wenku.baidu.com/view/356e37e487c24028905fc3cf.html》;20160622;第1-19页

Also Published As

Publication number Publication date
CN107181445A (en) 2017-09-19

Similar Documents

Publication Publication Date Title
US10094596B2 (en) Racking assemblies for solar panel installations
CN205647362U (en) Large -span prestressing force cable photovoltaic support
CN105760590A (en) Roof type photovoltaic array pitch optimizing method based on shadow radiation analysis
KR101781064B1 (en) Joint assembly connecting with pole and concrete base for Photovoltaic Power Generation
CN107181445B (en) A kind of installation method of photovoltaic power plant bracket waterborne
CN109088580B (en) Slope photovoltaic power station transformation design method
US10615738B2 (en) Photovoltaic solar array support structure
CN202651150U (en) Hanging rope fixing device of photovoltaic module
US11456695B2 (en) Leading edge units device and methods
CN112878354A (en) Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator
CN105162392A (en) Diamond-shaped photovoltaic support applicable for being installed on mountain
CN107370449A (en) Without steel construction overhead type photovoltaic module support system and electrical power transmission system
CN206878748U (en) Without steel construction overhead type photovoltaic module support system and electrical power transmission system
JP2015086654A (en) Truss beam frame for solar panel and assembling method using the same
CN203423204U (en) Deadweight-type photovoltaic support frame
CN210175091U (en) Floating type photovoltaic power generation installation system
CN209692284U (en) Photovoltaic cable gantry and photovoltaic system
CN209562474U (en) A kind of photovoltaic bracket for terraced fields landform
CN207184397U (en) A kind of attachment structure of photovoltaic column
KR101359438B1 (en) A roof fixing type solar generator
CN103835512B (en) Regularization assemble type protection canopy mounting method
CN219247746U (en) Flexible photovoltaic support connection structure
CN105583773A (en) Flexible photovoltaic support
CN210007256U (en) kinds of supports
US20230039623A1 (en) Edge units device and methods

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20170919

Assignee: Northman Energy Technology (Beijing) Co.,Ltd.

Assignor: SUZHOU NUOYA JIANZHOU PHOTOVOLTAIC TECHNOLOGY CO.,LTD.

Contract record no.: X2022980009065

Denomination of invention: An installation method of bracket for photovoltaic power station on water

Granted publication date: 20190730

License type: Common License

Record date: 20220704