CN107143296A - A kind of horizontal gas well negative pressure drags for sand method, horizontal gas well negative pressure and drags for sand system - Google Patents

A kind of horizontal gas well negative pressure drags for sand method, horizontal gas well negative pressure and drags for sand system Download PDF

Info

Publication number
CN107143296A
CN107143296A CN201710323144.4A CN201710323144A CN107143296A CN 107143296 A CN107143296 A CN 107143296A CN 201710323144 A CN201710323144 A CN 201710323144A CN 107143296 A CN107143296 A CN 107143296A
Authority
CN
China
Prior art keywords
sand
coiled tubing
gas
negative pressure
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710323144.4A
Other languages
Chinese (zh)
Other versions
CN107143296B (en
Inventor
刘岳龙
黄祥峰
唐万举
周舰
梅洁
谭苗
张立强
毕辰星
吕军爱
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
Petroleum Engineering Technology Research Institute of Sinopec North China oil and Gas Co
Original Assignee
China Petroleum and Chemical Corp
Petroleum Engineering Technology Research Institute of Sinopec North China oil and Gas Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Chemical Corp, Petroleum Engineering Technology Research Institute of Sinopec North China oil and Gas Co filed Critical China Petroleum and Chemical Corp
Priority to CN201710323144.4A priority Critical patent/CN107143296B/en
Publication of CN107143296A publication Critical patent/CN107143296A/en
Application granted granted Critical
Publication of CN107143296B publication Critical patent/CN107143296B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B27/00Containers for collecting or depositing substances in boreholes or wells, e.g. bailers, baskets or buckets for collecting mud or sand; Drill bits with means for collecting substances, e.g. valve drill bits

Abstract

Sand method, horizontal gas well negative pressure are dragged for the present invention relates to a kind of horizontal gas well negative pressure and drags for sand system, belong to petroleum gas workover treatment field.The horizontal gas well negative pressure of the present invention drags for sand method, comprises the following steps:1) ball-and-seat is set in one end of coiled tubing, coiled tubing is provided with to one end of ball-and-seat as in the horizontal segment of front end tripping in Wellbore of Gas Wells, by producing or sand is caught in emptying progress;2) catch after sand terminates, coiled tubing is gone out from Wellbore of Gas Wells, sand setting is discharged.The horizontal gas well negative pressure of the present invention drags for sand method, coiled tubing is transferred into the horizontal fragment position of pit shaft by sand washing ball-and-seat, only relying on gas flow can bring sand grains in coiled tubing into, can be by abrasive band outlet well shaft by playing lower tubular column.Compared with conventional sand washing process, entirely drag for during sand, can be achieved to remain that wellbore pressure is less than strata pressure, and required operational discharge capacity is small, efficiency of construction is high, and stratum will not be damaged.

Description

A kind of horizontal gas well negative pressure drags for sand method, horizontal gas well negative pressure and drags for sand system
Technical field
Sand method, horizontal gas well negative pressure are dragged for the present invention relates to a kind of horizontal gas well negative pressure and drags for sand system, belong to oil natural Gas workover treatment field.
Background technology
In low pressure horizontal gas well production process, after gas well shakes out, because reservoir pressure is relatively low, sand in well can not be by Air-flow is taken out of in time, and the phenomenon that sand is deposited in pit shaft horizontal segment just occurs so that flow resistance increase, causes gas well to produce Amount declines, or even stops production;Meanwhile, during gas well test jobs, pit shaft product sand easily causes testing tool and is hampered, meets card, damage Bad tester, directly results in test jobs failure.
Conventional gas well sand washing process is, by tripping in oil pipe, to set up circulation canal, and direct circulation or reacting cycle are passed through with liquid Mode the abrasive band in pit shaft is gone out to ground, there is problems with to the gas well of pressure in the sand washing process:One is that sand washing is liquid-tight Degree is big, causes wellbore pressure to be more than strata pressure, and hydraulic slip amount is big, and returning fluid's upward velocity causes sand washing effect poor slowly, applies The work cycle is long;Two be due to sand cleaning fluid leakage, causes reservoir damage, and gas well deliverability declines;Three be due to that wastage is big, later stage row The liquid cycle is long, and the long period can just return to normal production.
The content of the invention
Sand method is dragged for it is an object of the invention to provide a kind of high horizontal gas well negative pressure of simple, efficiency of construction.
Sand system is dragged for present invention also offers a kind of horizontal gas well negative pressure.
In order to realize the above object the horizontal gas well negative pressure of the present invention drags for the technical scheme that sand method used is:
A kind of horizontal gas well negative pressure drags for sand method, comprises the following steps:
1) in the horizontal segment of the front end tripping in Wellbore of Gas Wells of coiled tubing, it will be produced or be vented by coiled tubing and caught Sand;The front end of the coiled tubing is provided with ball-and-seat;
2) catch after sand terminates, coiled tubing is gone out from Wellbore of Gas Wells, sand setting is discharged.
Ball-and-seat can control the sand flow body of taking in Wellbore of Gas Wells horizontal segment to enter coiled tubing from front end and can prevent sand Grain flows back to pit shaft out of coiled tubing.The sand flow body of taking is the gas and liquid for carrying the gas of sand body or carrying sand grains Mixture.
The horizontal gas well negative pressure of the present invention drags for sand method, and coiled tubing is transferred into the horizontal section of pit shaft by sand washing ball-and-seat Put, only relying on gas flow can both bring sand grains in coiled tubing into, can be by abrasive band outlet well shaft by playing lower tubular column. It compared with conventional sand washing process, during entirely dragging for sand, can be achieved to remain that wellbore pressure is less than strata pressure, and required apply Work discharge capacity is small, and efficiency of construction is high, and stratum will not be damaged.
It is preferred that, step 1) in, coiled tubing is moved on Wellbore of Gas Wells horizontal segment bearing of trend during catching sand Front end.The front end that the side extended in Wellbore of Gas Wells horizontal segment moves up coiled tubing is produced or is vented, you can the company of completion Continuous sand washing process.It is further preferred that from close to the one of well head on Wellbore of Gas Wells horizontal segment bearing of trend during sand washing Hold and the front end of coiled tubing is moved to one end away from well head.It can ensure that the sand in pit shaft is gone out completely.
It is preferred that, step 1) it is additionally included in catch before sand or catch and high-pressure natural gas is injected into Wellbore of Gas Wells during sand.Note When entering high-pressure natural gas, the pressure in control Wellbore of Gas Wells is less than strata pressure.Pressure in pit shaft is less than strata pressure, can Prevent outside fluid from entering reservoir, prevent from polluting reservoir.For the small horizontal gas well of gas production, only pass through the day in Wellbore of Gas Wells Right gas carries out catching sand, and effect is not good, by injecting high-pressure natural gas into Wellbore of Gas Wells, when being produced or being vented, can be with Increase rate of flow of fluid, the sand grains in pit shaft is carried along into coiled tubing.Catch before sand or catch and inject high-pressure natural gas during sand When, the process of injection natural gas can be continued until that dragging for sand terminates, and can also only continue for some time.It is further preferred that Production or emptying catch the process of sand and inject high-pressure natural gas into Wellbore of Gas Wells carrying out simultaneously.Catch sand process with to gas well Injection high-pressure natural gas is carried out simultaneously in pit shaft, can improve the efficiency for dragging for sand.
It is further preferred that high pressure day is injected into Wellbore of Gas Wells by the annular space between corresponding production casing and oil pipe Right gas.Coiled tubing has a set of sealing device in well head, for sealing the annular space between Russia's coiled tubing and well head.Pass through annular space High-pressure natural gas is injected into Wellbore of Gas Wells, the efficiency of sand washing can be improved, and it is more preferable to drag for sand effect.
It is preferred that, in the horizontal segment by the front end of coiled tubing by oil pipe tripping in Wellbore of Gas Wells.
The horizontal gas well negative pressure of the present invention drag for technical scheme that sand system used for:
A kind of horizontal gas well negative pressure drags for sand system, including for the preventer being connected with oil pipe, the company being connected with preventer Continuous tubing injector head, it can carry out catching sand through preventer and coiled tubing injection head tripping in Wellbore of Gas Wells horizontal segment and can be from Rise to carry out the coiled tubing of sediment outflow in Wellbore of Gas Wells;The coiled tubing is included for tripping in Wellbore of Gas Wells horizontal segment front end With the end for being arranged on ground, the front end is provided with the single current that sand flow body enters coiled tubing of taking being used in controlled level section Valve, the end is provided with control valve.
It is described to take sand flow body for the gas for carrying sand grains or the mixture of the gas and liquid that carry sand body.The control valve For controlling the end of coiled tubing to open or closed, the end of coiled tubing can be produced or be vented when opening.
Coiled tubing injection head can play sealed effect, moreover it is possible to apply downward power to coiled tubing, it is ensured that continuous It is capable of the horizontal segment of tripping in pit shaft in the front end of oil pipe.
The horizontal gas well negative pressure of the present invention drags for sand system, simple in construction, using flexible, and coiled tubing sequentially passes through continuous oil Tube injection head, preventer and oil pipe tripping in sand flushing tool with pressure can be removed continuously, be not required to shackle, and working procedure is simple, applies The work cycle is short.
It is preferred that, above-mentioned horizontal gas well negative pressure drags for the oil pipe that sand system also includes passing through for coiled tubing, is set in oil pipe Outer production casing, forms annular space between the production casing and oil pipe, production casing is provided with least one and the annular space The natural gas filling entrance of connection.Natural gas filling entrance is set on production casing, is easy to the injection high pressure into Wellbore of Gas Wells natural Gas.Oil pipe in Wellbore of Gas Wells namely for gas production flow string, it is general under to horizontal well horizontal segment starting point with Upper 50m, during sand washing coiled tubing typically will during sand washing under starting point to the end of horizontal segment, it is ensured that the sand of horizontal segment Into continuously having in oil pipe.
Also include being used for natural gas filling entrance and natural gas it is further preferred that above-mentioned horizontal gas well negative pressure drags for sand system Compressor is provided between the connected discharge in source, the entrance of the discharge and natural gas.Compressor be able to can only be carried in station During for low pressure natural gas, it is easy to be pressurized low pressure natural gas.
Brief description of the drawings
Fig. 1 is that horizontal gas well negative pressure drags for sand system embodiment one and horizontal gas well negative pressure drags for the signal of sand embodiment of the method one Figure;
Fig. 2 is that horizontal gas well negative pressure drags for sand system embodiment two and horizontal gas well negative pressure drags for the signal of sand embodiment of the method two Figure;
Fig. 3 is that horizontal gas well negative pressure drags for sand system embodiment three and horizontal gas well negative pressure drags for the signal of sand embodiment of the method three Figure;
Gas production wellhead tubular column structure when Fig. 4 normally produces for the gas recovery well that horizontal gas well negative pressure drags for sand system embodiment one Schematic diagram.
Embodiment
Technical scheme is described further below in conjunction with embodiment.
The horizontal gas well negative pressure of the present invention drags for the embodiment one of sand system as shown in figure 1, including being located in Wellbore of Gas Wells Production casing 12, the oil pipe 13 being located in production casing 12 and the coiled tubing 17 through oil pipe 13;Oil pipe 13 is located at ground One end is connected with preventer 19 and coiled tubing injection head 20 in turn, and coiled tubing 17 includes being used for tripping in Wellbore of Gas Wells horizontal segment Front end and set end on the ground, front end is provided with the ball-and-seat that sand flow body enters coiled tubing 17 of taking in controlled level section 18, end is provided with control valve 22, and control valve 22 is used for the unlatching or closed for controlling the end of coiled tubing 17, the end of coiled tubing 17 End can be produced or be vented when opening;The front end of coiled tubing 17 sequentially passes through coiled tubing injection head 20, the and of preventer 19 In the horizontal segment of the tripping in Wellbore of Gas Wells of oil pipe 13;Production casing 12 includes being arranged on the sleeve pipe latter end of gas well vertical section and is arranged on The sleeve pipe leading portion of gas well horizontal segment, forms annular space between sleeve pipe latter end and oil pipe 13, and sleeve pipe latter end is provided with what is connected with annular space String is provided with string on sleeve valve 2 and sleeve valve 5, branch pipe b and is provided with sleeve valve 3 and casing valve on branch pipe a and branch pipe b, branch pipe a Door 6, branch pipe b is connected as natural gas filling entrance with low pressure natural gas discharge in station, and set compressor on branch pipe b 23.Coiled tubing 17 is on coiled tubing reel 21.
The horizontal gas well negative pressure of the present invention drags for the embodiment two of sand system, as shown in Fig. 2 dragging for sand system with horizontal gas well negative pressure Branch pipe b is directly connected by differing only in for the embodiment one of system with station inner high voltage natural gas collecting pipe, is not provided with compressor.
The horizontal gas well negative pressure of the present invention drags for the embodiment three of sand system, as shown in figure 3, dragging for sand system with horizontal gas well negative pressure Differing only in for the embodiment one of system is not provided with natural gas filling entrance on production casing 12.
In the prior art, when gas recovery well is normally produced, gas recovery well wellhead column structural representation is shown in Fig. 4, gas recovery well well head Tubing string includes oil pipe 13, along oil pipe 13 to bearing of trend inside gas well on the test valve 7, the gas production wellhead main gate-board that set gradually Valve 4, gas production wellhead main switch plate valve 1;Oil pipe 13 has two branch being arranged between test valve 7 and gas production wellhead main switch plate valve 4 String is provided with string on tubing valve 8 and tubing valve 10, another branch pipe and is provided with tubing valve 9 and tubing valve on pipe, a branch pipe Door 11;Oil pipe 13, which is located at outside the oil pipe of part of the gas production wellhead main switch plate valve below 1, is arranged with production casing 12, production casing 12 Close to the position of gas production wellhead provided with annular space is connected between oil pipe 12 and production casing 13 branch pipe a and branch pipe b, branch pipe a Upper string is provided with string on sleeve valve 2 and sleeve valve 5, branch pipe b and is provided with sleeve valve 3 and sleeve valve 6.There is target on Wellbore of Gas Wells Point A15 and target spot B16, is reservoir 14 between target spot A and target spot B.
The horizontal gas well negative pressure of the present invention drags for the embodiment one of sand method, as shown in figure 1, with the small horizontal gas well of gas production For objective for implementation, comprise the following steps:
1) ground flow is first connected, the control valve of the end of coiled tubing 17 is closed, tubing valve 8, tubing valve is closed 9th, tubing valve 10, tubing valve 11, branch pipe valve 2, branch pipe valve 5, branch pipe valve 3 and branch pipe valve 6;Lift coiled tubing Injection head 20, preventer 19 are connected with test valve;Coiled tubing 17 is pulled out from coiled tubing reel 21, makes coiled tubing 17 Front end sequentially passes through coiled tubing injection head 20, preventer 19 and oil pipe 13;Coiled tubing injection head 20 seals coiled tubing 17, Test valve, gas production wellhead main switch plate valve and gas production wellhead main switch plate valve are opened, it is by coiled tubing 17 that ball-and-seat 18 is with pressure Under to the horizontal fragment position of Wellbore of Gas Wells;Compressor 23 is set on branch pipe b, then by branch pipe b and low pressure natural gas gas collection in station Pipe is connected;
After in the horizontal segment of the front end tripping in Wellbore of Gas Wells of coiled tubing;Branch pipe valve 3 and branch pipe valve 6 are opened, is beaten The low pressure natural gas supercharging in 23 pairs of stations of compressor is opened, then by the natural gas after supercharging through between production casing 12 and oil pipe 13 Annular space be injected into Wellbore of Gas Wells, control Wellbore of Gas Wells in pressure be less than strata pressure;Coiled tubing end is opened simultaneously Control valve 22 be vented, and by the front end of coiled tubing from target spot A15 be moved to target spot B16 carry out catch sand;
2) catch after sand terminates, stop injection natural gas, the control valve 22 for closing coiled tubing end stops emptying, from gas well With pressure goes out coiled tubing 17 in pit shaft, and the sand grains in pit shaft is taken out of, sand setting is then discharged out.
It is whole to drag for gas production wellhead main gate valve and main gate valve, test valve during sand and be in normally open, only play passage Effect.
The horizontal gas well negative pressure of the present invention drags for the embodiment two of sand method, as shown in Fig. 2 with the small horizontal gas well of gas production For objective for implementation, the difference for dragging for the embodiment one of sand method with horizontal gas well negative pressure is that the high pressure used in station is natural Gas, without compression, inner high voltage natural gas will be stood through the ring between production casing 12 and oil pipe 13 by directly opening valve 3 and valve 6 Sky is injected into Wellbore of Gas Wells, and the pressure in control Wellbore of Gas Wells is less than strata pressure.
The horizontal gas well negative pressure of the present invention drags for the embodiment three of sand method, as shown in figure 3, with the larger horizontal gas of gas production Well is objective for implementation, and the difference of the embodiment one of sand method is dragged for without injecting day into Wellbore of Gas Wells with horizontal gas well negative pressure Right gas and it is whole drag for branch pipe valve 3 and branch pipe valve 6 during sand and be closed, by the front end tripping in gas of coiled tubing 17 The horizontal segment of well shaft, directly opens coiled tubing and is vented, while the front end of coiled tubing is moved into target spot from target spot A B carries out catching sand.
The horizontal gas well negative pressure of the present invention drags for the example IV of sand method, as shown in Fig. 2 dragging for sand side with horizontal gas well negative pressure The difference of the embodiment two of method is to close valve 3 and valve 6, high-pressure natural gas is not injected by casing annulus, by oil pipe 13 The branch pipe for being provided with tubing valve 9 and tubing valve 11 is connected with the high-pressure natural gas in station, opens tubing valve 9 and tubing valve Door 11, high-pressure natural gas is injected into Wellbore of Gas Wells.
The horizontal gas well negative pressure of the present invention is dragged in the other embodiment of sand method, and the front end of coiled tubing is lowered into gas well After pit shaft horizontal segment, the front end that can not also move coiled tubing carries out catching sand, but do not move the progress of coiled tubing front end Efficiency comparison is low.

Claims (7)

1. a kind of horizontal gas well negative pressure drags for sand method, it is characterised in that:Comprise the following steps:
1) progress in the horizontal segment of the front end tripping in Wellbore of Gas Wells of coiled tubing, will be produced or be vented by coiled tubing catch sand; The front end of the coiled tubing is provided with ball-and-seat;
2) catch after sand terminates, coiled tubing is gone out from Wellbore of Gas Wells, sand setting is discharged.
2. horizontal gas well negative pressure according to claim 1 drags for sand method, it is characterised in that:Step 1) in, catch the process of sand In on Wellbore of Gas Wells horizontal segment bearing of trend mobile coiled tubing front end.
3. horizontal gas well negative pressure according to claim 1 drags for sand method, it is characterised in that:Step 1) it is additionally included in and catches before sand Or catch high-pressure natural gas is injected into Wellbore of Gas Wells during sand.
4. horizontal gas well negative pressure according to claim 3 drags for sand method, it is characterised in that:By corresponding production casing and Annular space between oil pipe injects high-pressure natural gas into Wellbore of Gas Wells.
5. a kind of horizontal gas well negative pressure drags for sand system, it is characterised in that:Including the preventer and preventer for being connected with oil pipe Connected coiled tubing injection head, it can carry out catching sand through preventer and coiled tubing injection head tripping in Wellbore of Gas Wells horizontal segment And the coiled tubing of carry out sediment outflow can be gone out from Wellbore of Gas Wells;The coiled tubing includes being used for tripping in Wellbore of Gas Wells horizontal segment Front end and end for being arranged on ground, the front end is provided with the sand flow body of taking being used in controlled level section and enters continuous oil The ball-and-seat of pipe, the end is provided with control valve.
6. horizontal gas well negative pressure according to claim 5 drags for sand system, it is characterised in that:Also include passing through for coiled tubing Oil pipe, the production casing that is set in outside oil pipe, annular space is formed between the production casing and oil pipe, production casing is provided with extremely Lack a natural gas filling entrance connected with the annular space.
7. horizontal gas well negative pressure according to claim 6 drags for sand system, it is characterised in that:Also include being used for natural gas filling Compressor is provided between the discharge that entrance is connected with gas source, discharge and the natural gas filling entrance.
CN201710323144.4A 2017-05-09 2017-05-09 A kind of horizontal gas well negative pressure fishing sand method, horizontal gas well negative pressure fish out sand system Active CN107143296B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710323144.4A CN107143296B (en) 2017-05-09 2017-05-09 A kind of horizontal gas well negative pressure fishing sand method, horizontal gas well negative pressure fish out sand system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710323144.4A CN107143296B (en) 2017-05-09 2017-05-09 A kind of horizontal gas well negative pressure fishing sand method, horizontal gas well negative pressure fish out sand system

Publications (2)

Publication Number Publication Date
CN107143296A true CN107143296A (en) 2017-09-08
CN107143296B CN107143296B (en) 2019-11-22

Family

ID=59777381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710323144.4A Active CN107143296B (en) 2017-05-09 2017-05-09 A kind of horizontal gas well negative pressure fishing sand method, horizontal gas well negative pressure fish out sand system

Country Status (1)

Country Link
CN (1) CN107143296B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083621A (en) * 2018-07-28 2018-12-25 中国石油天然气股份有限公司 A kind of horizontal well coiled tubing composite blockage relieving method
CN112377148A (en) * 2020-11-12 2021-02-19 中联煤层气有限责任公司 Speed pipe communication device and method
CN113175311A (en) * 2020-04-08 2021-07-27 中国石油天然气股份有限公司 Throttle device and method for replacing throttle core

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2007110871A (en) * 2007-03-23 2008-09-27 Государственное образовательное учреждение высшего профессионального образовани "Тюменский государственный нефтегазовый университет" (RU) METHOD FOR WASHING A SAND BLOCK AND PREVENTING A SAND FORMATION IN A WATERFILL
CN102720453A (en) * 2012-06-04 2012-10-10 遂宁市华旭科技有限公司 Method and device for mechanically removing sand and draining liquid from pit shaft of oil/gas well in underbalanced state
CN102817594A (en) * 2012-09-06 2012-12-12 中国石油化工股份有限公司 Drainage gas recovery method and device of horizontal well
CN104141463A (en) * 2013-05-07 2014-11-12 中国石油化工股份有限公司 Device and method for negative-pressure sand draining of horizontal well by utilizing concentric double-layer coiled tubing to drag injection pump
CN105840127A (en) * 2016-05-30 2016-08-10 泸州长江石油工程机械有限公司 Double-layer coiled tube sand pumping device and double-layer coiled tube sand pumping technology
CN205778654U (en) * 2016-05-30 2016-12-07 泸州长江石油工程机械有限公司 Double layer continuous oil pipe sand pumping device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2007110871A (en) * 2007-03-23 2008-09-27 Государственное образовательное учреждение высшего профессионального образовани "Тюменский государственный нефтегазовый университет" (RU) METHOD FOR WASHING A SAND BLOCK AND PREVENTING A SAND FORMATION IN A WATERFILL
CN102720453A (en) * 2012-06-04 2012-10-10 遂宁市华旭科技有限公司 Method and device for mechanically removing sand and draining liquid from pit shaft of oil/gas well in underbalanced state
CN102817594A (en) * 2012-09-06 2012-12-12 中国石油化工股份有限公司 Drainage gas recovery method and device of horizontal well
CN104141463A (en) * 2013-05-07 2014-11-12 中国石油化工股份有限公司 Device and method for negative-pressure sand draining of horizontal well by utilizing concentric double-layer coiled tubing to drag injection pump
CN105840127A (en) * 2016-05-30 2016-08-10 泸州长江石油工程机械有限公司 Double-layer coiled tube sand pumping device and double-layer coiled tube sand pumping technology
CN205778654U (en) * 2016-05-30 2016-12-07 泸州长江石油工程机械有限公司 Double layer continuous oil pipe sand pumping device

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
冀东石油勘探开发公司井下作业公司编: "《井下作业与试油技术实用手册》", 30 June 2003, 北京:石油工业出版社 *
李宗田编著: "《连续油管技术手册》", 30 September 2003, 石油工业出版社 *
王金雨: "负压抽排清砂项目技术经济评价研究-以塔里木东河油田为例", 《中国优秀硕士学位论文全文数据库工程技术Ⅰ辑》 *
石油院校教材编写组编: "《采油工程 第3分册》", 28 February 1962, 北京:中国工业出版社 *
西南油气田公司编著: "《采气工安全操作读本》", 31 December 2013, 中国工人出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083621A (en) * 2018-07-28 2018-12-25 中国石油天然气股份有限公司 A kind of horizontal well coiled tubing composite blockage relieving method
CN113175311A (en) * 2020-04-08 2021-07-27 中国石油天然气股份有限公司 Throttle device and method for replacing throttle core
CN113175311B (en) * 2020-04-08 2022-08-05 中国石油天然气股份有限公司 Throttle device and method for replacing throttle core
CN112377148A (en) * 2020-11-12 2021-02-19 中联煤层气有限责任公司 Speed pipe communication device and method

Also Published As

Publication number Publication date
CN107143296B (en) 2019-11-22

Similar Documents

Publication Publication Date Title
CN101864921B (en) Well completion and oil production string of horizontal well and well completion and oil production processes thereof
CN202108493U (en) Water jetting multi-cluster subsection fracturing strings of horizontal well
CN108266173B (en) Method for segmented reconstruction of well completion
CN106194112B (en) A kind of oil well pipe cleaning sand washing integrated apparatus and pipe cleaning sand washing method
CN107143296B (en) A kind of horizontal gas well negative pressure fishing sand method, horizontal gas well negative pressure fish out sand system
CN104533356B (en) The method and oil production by layer method of a kind of two-layer automatic control oil production by layer
CN106522918B (en) Test operation tubular column capable of realizing direct-push kill well and stratum test method thereof
CN101775977B (en) Dual-tube injection well safety production string
CN105937393A (en) Horizontal well dragging type liquid producing section testing tubular column and testing method thereof
CN110344809B (en) Horizontal well intersegment multi-slit temporary plugging acidification method
CN110424912A (en) Method, the row's of returning service unit and the completion structure of tubing string replacement filling layer are not changed
CN111577257B (en) Horizontal well subsection setting type flow metering water exploration pipe column and water exploration method thereof
CN207568570U (en) Water drainage gas production device
CN102230377A (en) Multifunctional gas lifting strata testing string
CN103452531B (en) Oil pipe under underbalance, no killing well gaslift, turn the method for taking out, examining pump and maintenance oil pipe
CN105952431A (en) Immovable string plug removal method
CN107780879A (en) A kind of reverse inlet well well formation device and method
CN101122218A (en) Drift sand well harnessing process
CN110439510A (en) A kind of method of layer-by-layer acidification seperated layer water injection
CN202081890U (en) All-service gas lifting stratum testing tubular column
CN203626820U (en) Gas-lift flow-aiding horizontal well water exploration tubular column
CN203939477U (en) A kind of formation testing and completion practice integrated pipe column
CN108868729A (en) A kind of pressure break process method for well completion
CN109403861A (en) A kind of oil field welldrilling does not stop to infuse boring method
CN113027392B (en) A throw and drag for survey and regulate integrative sand control water injection tubular column for pit shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant