CN107142935A - Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection - Google Patents

Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection Download PDF

Info

Publication number
CN107142935A
CN107142935A CN201710571398.8A CN201710571398A CN107142935A CN 107142935 A CN107142935 A CN 107142935A CN 201710571398 A CN201710571398 A CN 201710571398A CN 107142935 A CN107142935 A CN 107142935A
Authority
CN
China
Prior art keywords
steel pipe
retaining wall
pipe section
reinforced
bank protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710571398.8A
Other languages
Chinese (zh)
Inventor
陈国民
王丰
肖荣锋
王强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201710571398.8A priority Critical patent/CN107142935A/en
Publication of CN107142935A publication Critical patent/CN107142935A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of reinforced steel pipe grouted anchor bar construction method suitable for retaining wall bank protection, some slurry outlets are opened up on the circumference of steel pipe section, make by some Pipe with Steel Ribbed Ring and the combined reinforced bar skeleton of stiffener, in tandem, the position that stiffener is in contact with the outer circumference surface of Pipe with Steel Ribbed Ring respectively is connected length direction of the Pipe with Steel Ribbed Ring along stiffener;Some cushion blocks are set on stiffener lateral surface;After depth of pore forming reaches design requirement, steel pipe section is pushed into, combined reinforced bar skeleton is pushed into steel pipe section, adjustment position, reinforced steel pipe grouted anchor bar structure is formed, it is disposable continuously fill after slurry, then form reinforced steel pipe grouted anchor bar.The preparation method of the present invention, can shorten the duration of retaining wall bank protection, it is ensured that the disposable quick formation of the retaining wall bank protection under complex geological condition, beneficial to the special carrying design requirement for needing to reach after the retaining wall protection slope forming reached under complex geological condition.

Description

Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection
Technical field
It is applicable the present invention relates to a kind of steel pipe grouted anchor bar construction method suitable for retaining wall bank protection, more particularly to one kind In the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection.
Background technology
Traditional retaining wall slope protection construction, typically carries out retaining wall bank protection, in construction using reinforced anchor bolt or anchor cable formula Middle reinforced anchor bolt formula barricade adaptability is poor, anchor cable formula barricade tedious process and procedures cycle are longer, is unfavorable for intricately Retaining wall bank protection under the conditions of matter is quickly formed, and retaining wall bank protection quality is difficult to ensure that.Secondly, the earth-retaining under complex geological condition The probability that collapse hole occurs in wall bank protection pore-forming is larger, and the operation for being unfavorable for retaining wall bank protection forms construction, it is difficult to meet construction quality And construction period;The construction technology of this pore-forming for being mainly retaining wall bank protection and anchor pole form needs to improve.
The content of the invention
The present invention is for above shortcomings in the prior art, and the invention provides the reinforcement suitable for retaining wall bank protection Shape steel tube grouted anchor bar construction method, it is easy to the design and construction of retaining wall bank protection.
Technical scheme:A kind of reinforced steel pipe grouted anchor bar construction method suitable for retaining wall bank protection, its It is characterised by comprising the following steps:
(1)According to production engineering specifications, selection steel pipe section, and some slurry outlets, slurry outlet are opened up on the circumference of steel pipe section Connected with the inner chamber of steel pipe section;
(2)According to production engineering specifications, combined reinforced bar skeleton is made;Described combined reinforced bar skeleton include some Pipe with Steel Ribbed Ring and Stiffener, in tandem, excircle of the stiffener along Pipe with Steel Ribbed Ring is annular for length direction of the Pipe with Steel Ribbed Ring along stiffener Arrange, and the position being in contact respectively with the outer circumference surface of Pipe with Steel Ribbed Ring is connected;On stiffener lateral surface, along length side To some cushion blocks of setting;The external diameter for being provided with the combined reinforced bar skeleton of cushion block is less than the internal diameter of steel pipe section;
(3)Anchor position planning according to the retaining wall bank protection of technological design carries out the pore-forming operation of bank protection, is set when depth of pore forming reaches After meter is required, steel pipe section is pushed into, and combined reinforced bar skeleton is pushed into steel pipe section, the frame position for occurring reversing is carried out Adjustment, forms reinforced steel pipe grouted anchor bar structure;
(4)It is disposable continuously fill after slurry according to production engineering specifications, then form reinforced steel pipe grouted anchor bar.
Further feature is:In a termination of every section of steel pipe section or two ends, external screw thread is set, then by being provided with Two sections of steel pipe sections are threadedly coupled by the interior mantle fiber connection sleeve pipe of internal thread, extending length.
In step(3)Pore-forming operation in, occur pore-forming cave in phenomenon when, using steel pipe section follow up pore-forming, treat as Hole depth is reached after design requirement, and combined reinforced bar skeleton is pushed into steel pipe section, adjusts the position of combined reinforced bar, is formed and strengthened Shape steel tube grouted anchor bar structure.
The reinforced steel pipe grouted anchor bar construction method suitable for retaining wall bank protection of the present invention, can shorten retaining wall bank protection Duration, it is ensured that the disposable quick formation of the retaining wall bank protection under complex geological condition, beneficial to reaching under complex geological condition Retaining wall protection slope forming after need the special carrying design requirement that reaches, and required technical quality effect.
Brief description of the drawings
Fig. 1 is the anchor structure figure of anchor rod construction method of the present invention;
Fig. 2 is Fig. 1 along A direction views;
Fig. 3 is steel pipe section and slurry outlet position view;
Fig. 4 is the interior mantle fiber connection sleeve pipe of adapted of the present invention(Part 6)Figure.
In accompanying drawing:1-steel pipe section, 2-slurry outlet, 3-stiffener, 4-Pipe with Steel Ribbed Ring, 5-cushion block, 6-inner sleeve Silk connection sleeve pipe.
Embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
As shown in Figure 1,2,3, 4, reinforced steel pipe grouted anchor bar construction once suitable for retaining wall bank protection of the invention Method, shortens the duration of retaining wall bank protection, it is ensured that the disposable quick formation of the retaining wall bank protection under complex geological condition, including Following steps:
(1)According to production engineering specifications, selection steel pipe section, and some slurry outlets, slurry outlet are opened up on the circumference of steel pipe section Connected with the inner chamber of steel pipe section;
(2)According to production engineering specifications, combined reinforced bar skeleton is made;Described combined reinforced bar skeleton include some Pipe with Steel Ribbed Ring and Stiffener, in tandem, excircle of the stiffener along Pipe with Steel Ribbed Ring is annular for length direction of the Pipe with Steel Ribbed Ring along stiffener Arrange, and the position being in contact respectively with the outer circumference surface of Pipe with Steel Ribbed Ring is connected(Generally connected by welding);Strengthening On reinforcing bar lateral surface, set along its length(Colligation)Some cushion blocks;Set(Colligation)Have cushion block combined reinforced bar skeleton it is outer Footpath is less than the internal diameter of steel pipe section, and the diameter d and steel pipe section internal diameter D of Pipe with Steel Ribbed Ring proportionate relationship are true according to technological requirement It is fixed;The cushion block selects prefabricated concrete small cushion block, generally by tied silk colligation on stiffener lateral surface;Concrete seat pad ring is pressed Certain spacing colligation is on the stiffener of combined reinforced bar skeleton, between the steel pipe walls of stiffener and steel pipe section, rises Framework of steel reinforcement is positioned and concrete slurry protection reinforcing bar effect;
(3)Anchor position planning according to the retaining wall bank protection of technological design carries out the pore-forming operation of bank protection, is set when depth of pore forming reaches After meter is required, steel pipe section is pushed into, and combined reinforced bar skeleton is pushed into steel pipe section, the position of combined reinforced bar is adjusted, it is such as right The frame position for occurring reversing carries out adjustment, combined reinforced bar in axially and radially position of steel pipe section inner chamber etc., is formed and strengthened Shape steel tube grouted anchor bar structure;
If in conventional pore-forming operation, it is possible to pore-forming occur and cave in phenomenon, occur pore-forming cave in phenomenon when, using steel pipe Follow up pore-forming for section, i.e., companion drilling equipment in steel pipe section together enters in pore-forming, after depth of pore forming reaches design requirement, will In combined reinforced bar skeleton push-in steel pipe section, adjust the position of combined reinforced bar, such as to occur reversing frame position progress adjustment, Combined reinforced bar forms reinforced steel pipe grouted anchor bar structure in axially and radially position of steel pipe section inner chamber etc.;
(4)It is disposable continuously fill after slurry according to production engineering specifications, then form reinforced steel pipe grouted anchor bar.
If the length of steel pipe section is less than hole depth, it is necessary to when inserting two sections or more of steel pipe section, then at every section One termination of steel pipe section or two ends set external screw thread, then by setting female interior mantle fiber connection sleeve pipe by two sections of steel Tube segment is threadedly coupled, extending length, forms longer steel pipe joint;
Carry out bank protection pore-forming operation, if there is pore-forming cave in phenomenon when, using steel pipe section follow up pore-forming;Into hole depth Degree is reached after design requirement, and combined reinforced bar skeleton is pushed into steel pipe section, and adjustment, shape are carried out to the frame position for occurring reversing Into reinforced steel pipe grouted anchor bar structure.
The interior mantle fiber connection sleeve pipe of the present invention, is provided with internal thread, and the external screw thread set with steel pipe section termination is engaged, The termination of steel pipe section is screwed in interior mantle fiber connection sleeve pipe, two sections or more of steel pipe section is threadedly coupled, extending length.
The present invention, carries out the processing and fabricating of slurry outlet 2 on steel pipe section 1, and shaping steel tube during primary concreting concrete can be achieved Grouted anchor bar is combined closely with protection slope forming duct;Pipe with Steel Ribbed Ring 4 is made, spot welding is combined between Pipe with Steel Ribbed Ring 4 and reinforcing bar 3 Type, the steel pipe grouted anchor bar of formation is monolithic construction, and bank protection anchoring effect is easy to ensure;On the lateral surface of stiffener 3, edge Some cushion blocks 5 of length direction colligation;The external diameter for being banded with the combined reinforced bar skeleton of cushion block 5 is less than the internal diameter D of steel pipe section 1;Also Have, the termination mantle fiber of steel pipe section 1 is processed, process in the external screw thread pair of certain length, interior mantle fiber connection sleeve pipe 6 in mantle fiber processing Screw thread, can be with duct depth the need for, steel pipe section 1 is threadedly coupled using interior mantle fiber connection sleeve pipe 6, steel pipe slip casting anchor can be lengthened The length of bar, the succinct construction technology of the retaining wall bank protection special carrying design requirement applied under complex geological condition.
Finally it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention rather than restriction technologies side Case, although the present invention is described in detail with reference to preferred embodiment by applicant, one of ordinary skill in the art should manage Solution, those modify or equivalent substitution to technical scheme, without departing from the objective and scope of the technical program, It all should cover among scope of the presently claimed invention.

Claims (3)

1. a kind of reinforced steel pipe grouted anchor bar construction method suitable for retaining wall bank protection, it is characterised in that including following step Suddenly:
(1)According to production engineering specifications, selection steel pipe section, and some slurry outlets, slurry outlet are opened up on the circumference of steel pipe section Connected with the inner chamber of steel pipe section;
(2)According to production engineering specifications, combined reinforced bar skeleton is made;Described combined reinforced bar skeleton include some Pipe with Steel Ribbed Ring and Stiffener, in tandem, excircle of the stiffener along Pipe with Steel Ribbed Ring is annular for length direction of the Pipe with Steel Ribbed Ring along stiffener Arrange, and the position being in contact respectively with the outer circumference surface of Pipe with Steel Ribbed Ring is connected;On stiffener lateral surface, along length side To some cushion blocks of colligation;The external diameter for being banded with the combined reinforced bar skeleton of cushion block is less than the internal diameter of steel pipe section;
(3)Anchor position planning according to the retaining wall bank protection of technological design carries out the pore-forming operation of bank protection, is set when depth of pore forming reaches After meter is required, steel pipe section is pushed into, and combined reinforced bar skeleton is pushed into steel pipe section, the position of combined reinforced bar is adjusted, is formed Reinforced steel pipe grouted anchor bar structure;
(4)It is disposable continuously fill after slurry according to production engineering specifications, then form reinforced steel pipe grouted anchor bar.
2. being applied to the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection according to claim 1, its feature exists In:In a termination of every section of steel pipe section or two ends, external screw thread is set, then by setting female interior mantle fiber adapter sleeve Two sections of steel pipe sections are threadedly coupled by pipe, extending length.
3. being applied to the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection according to claim 1, its feature exists In:In step(3)Pore-forming operation in, occur pore-forming cave in phenomenon when, using steel pipe section follow up pore-forming, work as depth of pore forming Reach after design requirement, combined reinforced bar skeleton is pushed into steel pipe section, adjust the position of combined reinforced bar, form reinforced steel pipe Grouted anchor bar structure.
CN201710571398.8A 2017-07-13 2017-07-13 Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection Pending CN107142935A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710571398.8A CN107142935A (en) 2017-07-13 2017-07-13 Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710571398.8A CN107142935A (en) 2017-07-13 2017-07-13 Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection

Publications (1)

Publication Number Publication Date
CN107142935A true CN107142935A (en) 2017-09-08

Family

ID=59776651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710571398.8A Pending CN107142935A (en) 2017-07-13 2017-07-13 Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection

Country Status (1)

Country Link
CN (1) CN107142935A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5998932A (en) * 1982-11-29 1984-06-07 Giken Kogyo Kk Setting method of latticed slope frame with anchor
CN2568815Y (en) * 2002-05-31 2003-08-27 刘维杰 Strengthening slip casting anchor stock
CN104762978A (en) * 2014-12-26 2015-07-08 浙江省电力设计院 Anchor rod gravity retaining wall for high slope support and manufacturing method
CN105821771A (en) * 2016-04-03 2016-08-03 郑州市市政工程总公司 Jacking construction technology of super-long box-girder bridge below high-filled urban expressway and construction structure adopted in technology

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5998932A (en) * 1982-11-29 1984-06-07 Giken Kogyo Kk Setting method of latticed slope frame with anchor
CN2568815Y (en) * 2002-05-31 2003-08-27 刘维杰 Strengthening slip casting anchor stock
CN104762978A (en) * 2014-12-26 2015-07-08 浙江省电力设计院 Anchor rod gravity retaining wall for high slope support and manufacturing method
CN105821771A (en) * 2016-04-03 2016-08-03 郑州市市政工程总公司 Jacking construction technology of super-long box-girder bridge below high-filled urban expressway and construction structure adopted in technology

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高军: "《高速铁路岩溶地质路基设计与整治技术》", 31 October 2014, 中国地质大学出版社 *

Similar Documents

Publication Publication Date Title
CN109854255B (en) Method for processing tunnel unconverged collapse
CN108457372A (en) A kind of steel core concrete column-steel plate concrete ring beam joint and its construction method
CN104711987B (en) A kind of deep covering layer sleeving valve tube method controllable grouting method
CN205975626U (en) Strut integrated configuration with stagnant water unification in soft soil layer foundation ditch
CN204326248U (en) A kind of steel reinforcement abutting joints with the concavo-convex rib of spirality connects grout sleeve
CN203684211U (en) Pile head processing device of bored pile
CN102605773B (en) Construction method of slip-casting expanded-base cast-in-situ bored pile and extruding-extending device thereof
CN105863683B (en) Large cross-section tunnel indulges ring beam and pays protection structure in advance
CN212714913U (en) Super-large-diameter cast-in-place pile double-layer reinforcement cage with embedded pipe
CN108301570A (en) Half grout sleeve processing method of antidetonation self-locking, concrete member processing method
CN107355010A (en) Precast concrete shear wall shaped steel node connection structure
CN112502152A (en) Construction method of ultra-deep vibroflotation pile
CN104295112A (en) Reinforced concrete column upper-connected concrete filled steel tube column connecting structure and construction method thereof
CN104832085B (en) A kind of deep covering layer pipe-following drilling method
CN210341897U (en) Novel prefabricated tubular pile structure
CN105275013B (en) Core tube inverse superimposed underground diaphragm wall and construction method thereof
CN111005361A (en) High-pressure grouting device for deep water karst fracture development geology and construction method
CN207392252U (en) A kind of connection structure of pile body and cushion cap
CN206987200U (en) A kind of short grout sleeve of bar connecting
CN107268620A (en) Suitable for the reinforced steel pipe grouted anchor bar preparation method of retaining wall bank protection
CN107142935A (en) Suitable for the reinforced steel pipe grouted anchor bar construction method of retaining wall bank protection
CN106151695B (en) The molding seamless steel pipe of cold rolling and its manufacturing method
CN104695441B (en) A kind of deep covering layer two-shot grouting method
CN206458923U (en) The seamless steel pipe and FRP muscle or the grouting branch sleeve of Ribbed Bar of cold rolling shaping
CN104908150B (en) A kind of piping shaft making template and the method based on factorial praluction piping shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170908