CN107134761A - A kind of power distribution network distributed intelligence control method based on regional agency pattern - Google Patents

A kind of power distribution network distributed intelligence control method based on regional agency pattern Download PDF

Info

Publication number
CN107134761A
CN107134761A CN201710352299.0A CN201710352299A CN107134761A CN 107134761 A CN107134761 A CN 107134761A CN 201710352299 A CN201710352299 A CN 201710352299A CN 107134761 A CN107134761 A CN 107134761A
Authority
CN
China
Prior art keywords
switch
regional agency
signal power
power monitoring
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710352299.0A
Other languages
Chinese (zh)
Inventor
嵇文路
王敬华
朱红勤
张海台
沈培锋
张明
吴辉
王勇
周航
孙昕杰
马洲俊
毛小武
周科锋
陈建坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nanjing Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nanjing Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Nanjing Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201710352299.0A priority Critical patent/CN107134761A/en
Publication of CN107134761A publication Critical patent/CN107134761A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • H02H7/261Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured involving signal transmission between at least two stations
    • H02J13/0079
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/20Systems supporting electrical power generation, transmission or distribution using protection elements, arrangements or systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/124Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wired telecommunication networks or data transmission busses

Abstract

The invention provides a kind of power distribution network distributed intelligence control method based on regional agency pattern, step includes:Password Management(KDC), STU detects failure, startup separator positioning, the isolation and fault recovery of failure.The power distribution network distributed intelligence control method completes distributed FA using regional agency mode, realizes the management in LAN, and can realize the service restoration strategy of complexity.

Description

A kind of power distribution network distributed intelligence control method based on regional agency pattern
Technical field
The present invention relates to a kind of power distribution network distributed intelligence control method, especially a kind of matching somebody with somebody based on regional agency pattern Power network distributed intelligence control method.
Background technology
Distribution network failure distributed AC servo system, which has, controls fireballing advantage, while distributed AC servo system also has certain peace Full hidden danger, because distribution terminal STU operational capability is limited, it is impossible to do the equipment in the encryption certification work of complexity, LAN Protective capacities is weaker.The present invention is using the distributed FA under agentbased control mode, in order to ensure the security of whole system, uses Wide area network is to master station communication, the double web frames communicated between LAN device, and wide area network is using complicated cipher mode, it is considered to local It is comparatively safe in net, relatively simple digital signature measure is used between STU and SRC, it is ensured that the security of communication.
The content of the invention
The technical problem to be solved in the present invention is
In order to solve the above-mentioned technical problem, the invention provides a kind of power distribution network distributed intelligence control based on regional agency pattern Method processed, comprises the following steps:
Step 1, a station terminal is specified in power distribution network as regional agency server S RC, by regional agency server S RC timings Each signal power monitoring cell S TU into system sends key, and key includes public key and private key;
Step 2, signal power monitoring cell S TU upon failure detection, is entered using the current private key that receives to fault detection information Row signature, then the failure indication information after signature is sent to regional agency server S RC;
Step 3, regional agency server S RC is receiving the switch changed position information that failure indication information and outlet switch are reported Afterwards, the fault detection information after signature is verified using public key, and is verifying qualified rear progress fault location;
Step 4, regional agency server S RC inquires failure boundary switch after the completion of fault location, then is opened to failure boundary Signal power monitoring cell S TU at pass, which is issued, utilizes the switch separating brake order after private key signature;
Step 5, signal power monitoring cell S TU is after the switch separating brake order of regional agency server S RC transmissions is received, profit The switch separating brake order after signature is verified with public key, and accordingly opened according to switch separating brake order execution after checking is qualified The sub-switching operation of pass, then will be sent after sub-switching operation completion Information Pull private key signature to regional agency server S RC;
Step 6, regional agency server S RC receives sub-switching operation and completed after information, using public key to the switching manipulation after signature Complete information to be verified, and outlet sent to the corresponding signal power monitoring cell S TU of outlet switch after checking is qualified to open Switching signal is closed, then loads of the fault down stream signal power monitoring cell S TU before failure is obtained by regional agency server S RC Daily record, calculates the borderline region that can recover according to load daily record according to removal of load algorithm, then to the letter at borderline region position Number power supply supervision unit STU is sent to be closed a floodgate order progress fault recovery control using public key to the switch after signature.
Key is sent using each STU of SRC timings into system, encryption handling in region, enhancing signal transmission is realized Safety and reliability;Fault down stream signal power monitoring cell S TU is obtained before failure using regional agency server S RC Load daily record, the borderline region that can recover is calculated according to removal of load algorithm according to load daily record, so that real to greatest extent Existing service restoration, reduces loss of outage.
As the further limits scheme of the present invention, in step 3, regional agency server S RC carries out fault location Concretely comprise the following steps:
Step 3.1, it is determined that receiving switch changed position information that outlet switch reports and signal power monitoring cell S TU indicating fault Information;
Step 3.2, it is downstream topological from outlet switch according to topological structure, find reporting fault configured information in topological downstream Signal power monitoring cell S TU, failure is just between this signal power monitoring cell S TU and outlet switch.
The switch changed position information and signal power monitoring cell S TU failure indication information reported using outlet switch is come really It is fixed to break down, it is ensured that the reliability broken down, if having only received fault indication signal, outlet switch tripping operation letter is not received Number, then it is transient fault to illustrate failure, is handled without Fault Isolation and recovery.
As the further limits scheme of the present invention, signal power monitoring cell S TU timings preserve information on load to daily record File.Checked using preserving when information on load can be easy to restore electricity after failure to journal file, so as to greatest extent Realize service restoration.
As the further limits scheme of the present invention, regional agency server S RC generated a key every 30 minutes, and Signal power monitoring cell S TU is sent to by UDP multicasts, signal power monitoring cell S TU is received and preserved after key, logical Cross signed when GooseOverUDP or IEC104 stipulations communicate with regional agency server S RC using the key of preservation or Checking.
As the further limits scheme of the present invention, in step 6, energy is calculated according to removal of load algorithm according to load daily record The borderline region of recovery is concretely comprised the following steps:
Step 6.1, the load value preserved by fault down stream signal power monitoring cell S TU, calculates outlet switch and believes with downstream Region load value between number power supply supervision unit STU;
Step 6.2, the information on load of standby electricity source point, and rated capacity and present load value by standby electricity source point are obtained The capacity restored electricity can be possessed by calculating;
Step 6.3, if the capacity that can restore electricity is more than the sum of all load values of fault down stream, completely restored electricity, no With removal of load, if can not completely recover, at the interconnection switch Adding Area load value, until can not behind Adding Area again Meet and stop after power demands, preserve boundary switch now.
The borderline region that can be restored electricity is calculated according to removal of load algorithm, so as to realize the reasonable of capacity that can restore electricity Distribution, realizes that can possess the capacity restored electricity makes full use of.
The beneficial effects of the present invention are:Key is sent using each STU of SRC timings into system, realized in region Encryption handling, the safety and reliability of enhancing signal transmission;Fault down stream signal electricity is obtained using regional agency server S RC Load daily records of the source monitoring unit STU before failure, the border that can recover is calculated according to load daily record according to removal of load algorithm Region, so as to realize service restoration to greatest extent, reduces loss of outage.
Brief description of the drawings
Fig. 1 is distributed system overall framework figure of the invention;
Fig. 2 is wide area network system structure chart of the invention;
Fig. 3 is distributed AC servo system sub-network structures figure of the invention;
Key distributions and reception flow chart of the Fig. 4 for the present invention;
Fig. 5 distributes for the key of the present invention and uses flow chart;
Detections and positioning flow figure of the Fig. 6 for the failure of the present invention;
Fig. 7 is process of fault isolation flow chart of the invention;
Fig. 8 is fault recovery flow chart of the invention.
Embodiment
As shown in figures 1-8, the power distribution network distributed intelligence control method disclosed by the invention based on regional agency pattern, bag Include following steps:
Step 1, a station terminal is specified in power distribution network as regional agency server S RC, by regional agency server S RC timings Each signal power monitoring cell S TU into system sends key, and key includes public key and private key;
Step 2, signal power monitoring cell S TU upon failure detection, is entered using the current private key that receives to fault detection information Row signature, then the failure indication information after signature is sent to regional agency server S RC;
Step 3, regional agency server S RC is receiving the switch changed position information that failure indication information and outlet switch are reported Afterwards, the fault detection information after signature is verified using public key, and is verifying qualified rear progress fault location;
Step 4, regional agency server S RC inquires failure boundary switch after the completion of fault location, then is opened to failure boundary Signal power monitoring cell S TU at pass, which is issued, utilizes the switch separating brake order after private key signature;
Step 5, signal power monitoring cell S TU is after the switch separating brake order of regional agency server S RC transmissions is received, profit The switch separating brake order after signature is verified with public key, and accordingly opened according to switch separating brake order execution after checking is qualified The sub-switching operation of pass, then will be sent after sub-switching operation completion Information Pull private key signature to regional agency server S RC;
Step 6, regional agency server S RC receives sub-switching operation and completed after information, using public key to the switching manipulation after signature Complete information to be verified, and outlet sent to the corresponding signal power monitoring cell S TU of outlet switch after checking is qualified to open Switching signal is closed, then loads of the fault down stream signal power monitoring cell S TU before failure is obtained by regional agency server S RC Daily record, calculates the borderline region that can recover according to load daily record according to removal of load algorithm, then to the letter at borderline region position Number power supply supervision unit STU is sent to be closed a floodgate order progress fault recovery control using public key to the switch after signature.
Wherein, in step 3, regional agency server S RC carries out concretely comprising the following steps for fault location:
Step 3.1, it is determined that receiving switch changed position information that outlet switch reports and signal power monitoring cell S TU indicating fault Information;
Step 3.2, it is downstream topological from outlet switch according to topological structure, find reporting fault configured information in topological downstream Signal power monitoring cell S TU, failure is just between this signal power monitoring cell S TU and outlet switch.
Signal power monitoring cell S TU timings preserve information on load to journal file;RC is every 30 for regional agency server S Key of minute generation, and signal power monitoring cell S TU is sent to by UDP multicasts, signal power monitoring cell S TU connects Receive and preserved after key, utilized when being communicated by GooseOverUDP or IEC104 stipulations with regional agency server S RC The key of preservation is signed or verified.
In step 6, concretely comprising the following steps for the borderline region that can recover is calculated according to removal of load algorithm according to load daily record:
Step 6.1, the load value preserved by fault down stream signal power monitoring cell S TU, calculates outlet switch and believes with downstream Region load value between number power supply supervision unit STU;
Step 6.2, the information on load of standby electricity source point, and rated capacity and present load value by standby electricity source point are obtained The capacity restored electricity can be possessed by calculating;
Step 6.3, if the capacity that can restore electricity is more than the sum of all load values of fault down stream, completely restored electricity, no With removal of load, if can not completely recover, at the interconnection switch Adding Area load value, until can not behind Adding Area again Meet and stop after power demands, preserve boundary switch now.
As shown in Figures 2 and 3, the present invention is in order to meet communication security requirements, and using wide area network+LAN scheme, distribution is whole End STU and higher level's master station communication use wide area network, and distributed AC servo system uses local subnet, double network datas isolation, both ensure that and are The opening of system, has taken into account security again.
As shown in Figures 4 and 5, SRC sends key by multicast, sends once within every 30 minutes, complete by the flow shown in Fig. 4 Into the distribution and reception of key, SRC is used as key Distribution Center(KDC), generate a key within every 30 minutes, pass through UDP multicasts STU is sent to, STU is received and preserved after key, then is all passed through when being communicated by GooseOverUDP, IEC104 stipulations with SRC This key is signed.Key distribution detailed process be:
(1)SRC is used as key Distribution Center(KDC), produce a key within every 30 minutes.
(2)STU monitors the udp port specified(Such as 500), for receiving key.
(3)SRC sends key by UDP multicasts.
(4)STU receives key and preserved.
As shown in fig. 6, STU is detected after failure, send fault indication signal and pass through topological structure and failure to SRC, SRC Configured information, fault location is carried out by location algorithm.
As shown in fig. 7, after SRC fault location, produce isolation scheme, remote control sub-gate signal is sent to the STU specified, STU is received and remote control is performed after remote control separating brake, and sequence of events recording SOE is sent into SRC.
As shown in figure 8, SRC is carried out after Fault Isolation success, fault recovery is carried out, first remote control trouble circuit outlet switch is closed Lock, restores electricity to failure upstream region, then obtains the information on load in fault down stream region and the load letter of standby electricity source point Breath, fault recovery is carried out by removal of load algorithm.
SRC fault location processes are:
(1)Receive the trip signal of outlet switch.
(2)Receive circuit STU fault indication signal.
(3)It is downstream topological from outlet switch according to topological structure, the switch of the reporting fault of most downstream in topology is found, Failure is just herein between switch and downstream switches.
Explanation:If having only received fault indication signal, outlet switch trip signal is not received, then it is instantaneous to illustrate failure Failure, is handled without Fault Isolation and recovery.
Fault Isolation:SRC finds out the switch that need to isolate after abort situation is calculated, and SRC is given by GooseOverUDP The switch of isolation is needed to send remote control separating brake information, STU is received and performed straighforward operation after guidance command, will displacement after switch changed position SOE is sent to SRC by GooseOverUDP, and SRC is being received after all switches that need to isolate are carried out successfully, judges isolation Success, can perform recovery operation.
Process of fault isolation is specific as follows:
(1)SRC generates the switch list that need to isolate according to positioning result.
(2)SRC sends remote control separating brake order to STU.
(3)STU, which is received, performs remote control after guidance command.
(4)Switch changed position SOE signals are sent to SRC by STU.
(5)Whether SRC succeeds according to the displacement signal detection and isolation received.
Fault recovery:After SRC successfully carries out Fault Isolation, failure recovery operation, first SRC remote controls outlet can be carried out Switch is closed a floodgate, and recovery is powered to failure upstream region;Then SRC obtains fault down stream STU information on load, negative according to getting rid of Lotus algorithm calculates the borderline region that can recover;Last SRC remote controls interconnection switch closes a floodgate and boundary switch separating brake progress failure is extensive It is multiple.
Removal of load algorithm is as follows:
(1)The load value switched by fault down stream, calculates the region load value between switch and downstream switches.
(2)The capacity restored electricity can be possessed by being calculated by the rated capacity and present load value of standby electricity source point.
(3)If the capacity that can restore electricity is more than the sum of all load values of fault down stream, expression can completely restore electricity, Without removal of load.
(4)If can not completely recover, since interconnection switch, Adding Area load value, until nothing behind Adding Area again Method is met to be stopped after power demands, preserves boundary switch now.
(5)The recovery that many power supply points are powered:The maximum power supply point of residual capacity is taken as removal of load power supply point, if still not Meet, consider further that the removal of load of other capacity.
The above described is only a preferred embodiment of the present invention, being not the limitation for making other forms to the present invention, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. Imitate embodiment.But it is every without departing from technical solution of the present invention content, the technical spirit according to the present invention is to above example institute Any simple modification, equivalent variations and the remodeling made, still fall within the protection domain of technical solution of the present invention.

Claims (5)

1. a kind of power distribution network distributed intelligence control method based on regional agency pattern, it is characterised in that comprise the following steps:
Step 1, a station terminal is specified in power distribution network as regional agency server S RC, by regional agency server S RC timings Each signal power monitoring cell S TU into system sends key, and key includes public key and private key;
Step 2, signal power monitoring cell S TU upon failure detection, is entered using the current private key that receives to fault detection information Row signature, then the failure indication information after signature is sent to regional agency server S RC;
Step 3, regional agency server S RC is receiving the switch changed position information that failure indication information and outlet switch are reported Afterwards, the fault detection information after signature is verified using public key, and is verifying qualified rear progress fault location;
Step 4, regional agency server S RC inquires failure boundary switch after the completion of fault location, then is opened to failure boundary Signal power monitoring cell S TU at pass, which is issued, utilizes the switch separating brake order after private key signature;
Step 5, signal power monitoring cell S TU is after the switch separating brake order of regional agency server S RC transmissions is received, profit The switch separating brake order after signature is verified with public key, and accordingly opened according to switch separating brake order execution after checking is qualified The sub-switching operation of pass, then will be sent after sub-switching operation completion Information Pull private key signature to regional agency server S RC;
Step 6, regional agency server S RC receives sub-switching operation and completed after information, using public key to the switching manipulation after signature Complete information to be verified, and outlet sent to the corresponding signal power monitoring cell S TU of outlet switch after checking is qualified to open Switching signal is closed, then loads of the fault down stream signal power monitoring cell S TU before failure is obtained by regional agency server S RC Daily record, calculates the borderline region that can recover according to load daily record according to removal of load algorithm, then to the letter at borderline region position Number power supply supervision unit STU is sent to be closed a floodgate order progress fault recovery control using public key to the switch after signature.
2. the power distribution network distributed intelligence control method according to claim 1 based on regional agency pattern, its feature exists In in step 3, regional agency server S RC carries out concretely comprising the following steps for fault location:
Step 3.1, it is determined that receiving switch changed position information that outlet switch reports and signal power monitoring cell S TU indicating fault Information;
Step 3.2, it is downstream topological from outlet switch according to topological structure, find reporting fault configured information in topological downstream Signal power monitoring cell S TU, failure is just between this signal power monitoring cell S TU and outlet switch.
3. the power distribution network distributed intelligence control method according to claim 1 based on regional agency pattern, its feature exists In signal power monitoring cell S TU timings preserve information on load to journal file.
4. the power distribution network distributed intelligence control method according to claim 1 based on regional agency pattern, its feature exists In regional agency server S RC generated a key every 30 minutes, and was sent to signal power monitoring list by UDP multicasts First STU, signal power monitoring cell S TU are received and preserved after key, are passing through GooseOverUDP or IEC104 stipulations and area Domain proxy server SRC is signed or verified using the key of preservation when communicating.
5. the power distribution network distributed intelligence control method according to claim 1 based on regional agency pattern, its feature exists In in step 6, concretely comprising the following steps for the borderline region that can recover is calculated according to removal of load algorithm according to load daily record:
Step 6.1, the load value preserved by fault down stream signal power monitoring cell S TU, calculates outlet switch and believes with downstream Region load value between number power supply supervision unit STU;
Step 6.2, the information on load of standby electricity source point, and rated capacity and present load value by standby electricity source point are obtained The capacity restored electricity can be possessed by calculating;
Step 6.3, if the capacity that can restore electricity is more than the sum of all load values of fault down stream, completely restored electricity, no With removal of load, if can not completely recover, at the interconnection switch Adding Area load value, until can not behind Adding Area again Meet and stop after power demands, preserve boundary switch now.
CN201710352299.0A 2017-05-18 2017-05-18 A kind of power distribution network distributed intelligence control method based on regional agency pattern Pending CN107134761A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710352299.0A CN107134761A (en) 2017-05-18 2017-05-18 A kind of power distribution network distributed intelligence control method based on regional agency pattern

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710352299.0A CN107134761A (en) 2017-05-18 2017-05-18 A kind of power distribution network distributed intelligence control method based on regional agency pattern

Publications (1)

Publication Number Publication Date
CN107134761A true CN107134761A (en) 2017-09-05

Family

ID=59731999

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710352299.0A Pending CN107134761A (en) 2017-05-18 2017-05-18 A kind of power distribution network distributed intelligence control method based on regional agency pattern

Country Status (1)

Country Link
CN (1) CN107134761A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107465177A (en) * 2017-10-11 2017-12-12 山东理工大学 A kind of power distribution network low current grounding partition method based on regional agency
CN107732883A (en) * 2017-11-24 2018-02-23 山东理工大学 Distributed feeder fault processing information interacts method of controlling security
CN109067566A (en) * 2018-07-09 2018-12-21 北京奇安信科技有限公司 A kind of method, terminal and the monitoring equipment of the screenshot under silent mode
CN110661231A (en) * 2019-10-15 2020-01-07 贵州电网有限责任公司 Data processing method during fault recovery based on master station SOE information processing
CN112531900A (en) * 2020-12-08 2021-03-19 珠海欧力配网自动化股份有限公司 Distributed feeder automation method based on message agent

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102497021A (en) * 2011-12-14 2012-06-13 广东电网公司佛山供电局 Real-time monitoring and analysis system for distribution circuit
CN202856452U (en) * 2012-04-28 2013-04-03 成都智达电力自动控制有限公司 Power distribution network system
CN104868594A (en) * 2015-05-20 2015-08-26 南京国电南自电网自动化有限公司 Intelligent distributed feed line automation global data exchange method
CN106254157A (en) * 2016-09-21 2016-12-21 山东大学 The distributed management and control of a kind of power distribution network topology and recognition methods
CN106532684A (en) * 2016-10-20 2017-03-22 燕山大学 Active distribution network multi-fault repair method based on multi-agent system
CN206149022U (en) * 2016-10-27 2017-05-03 烟台科大正信电气有限公司 Net feeder automation terminal is joined in marriage to distributing type

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102497021A (en) * 2011-12-14 2012-06-13 广东电网公司佛山供电局 Real-time monitoring and analysis system for distribution circuit
CN202856452U (en) * 2012-04-28 2013-04-03 成都智达电力自动控制有限公司 Power distribution network system
CN104868594A (en) * 2015-05-20 2015-08-26 南京国电南自电网自动化有限公司 Intelligent distributed feed line automation global data exchange method
CN106254157A (en) * 2016-09-21 2016-12-21 山东大学 The distributed management and control of a kind of power distribution network topology and recognition methods
CN106532684A (en) * 2016-10-20 2017-03-22 燕山大学 Active distribution network multi-fault repair method based on multi-agent system
CN206149022U (en) * 2016-10-27 2017-05-03 烟台科大正信电气有限公司 Net feeder automation terminal is joined in marriage to distributing type

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姚强: "基于数字签名的智能配电网通信安全方法", 《信息安全》 *
范开俊: "配电网智能分布式控制技术及其应用", 《中国博士学位论文全文数据库》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107465177A (en) * 2017-10-11 2017-12-12 山东理工大学 A kind of power distribution network low current grounding partition method based on regional agency
CN107465177B (en) * 2017-10-11 2019-08-27 山东理工大学 A kind of power distribution network small current grounding fault partition method based on regional agency
CN107732883A (en) * 2017-11-24 2018-02-23 山东理工大学 Distributed feeder fault processing information interacts method of controlling security
CN109067566A (en) * 2018-07-09 2018-12-21 北京奇安信科技有限公司 A kind of method, terminal and the monitoring equipment of the screenshot under silent mode
CN109067566B (en) * 2018-07-09 2021-08-17 奇安信科技集团股份有限公司 Method, terminal and monitoring equipment for screenshot in silent mode
CN110661231A (en) * 2019-10-15 2020-01-07 贵州电网有限责任公司 Data processing method during fault recovery based on master station SOE information processing
CN110661231B (en) * 2019-10-15 2021-07-16 贵州电网有限责任公司 Data processing method during fault recovery based on master station SOE information processing
CN112531900A (en) * 2020-12-08 2021-03-19 珠海欧力配网自动化股份有限公司 Distributed feeder automation method based on message agent
CN112531900B (en) * 2020-12-08 2023-07-04 珠海欧力配网自动化股份有限公司 Distributed feeder automation method based on message proxy

Similar Documents

Publication Publication Date Title
CN107134761A (en) A kind of power distribution network distributed intelligence control method based on regional agency pattern
Habib et al. Multi-agent-based technique for fault location, isolation, and service restoration
Dai et al. Risk assessment for cyberattack in active distribution systems considering the role of feeder automation
Hong et al. Detection of cyber intrusions using network-based multicast messages for substation automation
KR102030837B1 (en) Apparatus and method for intrusion detection
Roberson et al. Improving grid resilience using high-voltage dc: Strengthening the security of power system stability
CN101917064B (en) Back-up protection processing method of digital substation transformer based on GOOSE mode
CN106300285A (en) It is independent of the self adaptation type feeder automation fault handling method on the spot of network topology
CN104580061B (en) The polymerization and system of fault-tolerant and resisting differential attack are supported in a kind of intelligent grid
Hong et al. Cyber-physical security testbed for substations in a power grid
Mavridou et al. A situational awareness architecture for the smart grid
CN112421614A (en) Power distribution station self-healing control system and method based on local communication and topology identification
CN106300436A (en) A kind of hydroelectric power plant's simultaneous interconnecting control method and device
CN105896490A (en) Fault processing method and device of power distribution network
Chawla et al. Denial-of-service resilient frameworks for synchrophasor-based wide area monitoring systems
CN105337314A (en) Multisource coordination control fault treatment method based on distributed power supply black start technology
O’Brien et al. Synchrophasor spoofing detection and remediation for wide-area damping control
Drayer et al. Resilient distribution grids—cyber threat scenarios and test environment
Tuinema et al. Cyber-physical system modeling for assessment and enhancement of power grid cyber security, resilience, and reliability
CN105162091A (en) Cascading fault risk estimation method for electrical power system of considering information system risk
CN109639466B (en) Power engineering control system network safety detection system based on' source network load
Lo et al. A multi-agent based service restoration in distribution network with distributed generations
Amare et al. Dependability analysis of smart distribution grid architectures considering various failure modes
EP3840326A1 (en) Systems and methods for mitigating electrical installation security threats
Kim et al. Robust Cyber Infrastructure for Cyber Attack Enabling Resilient Distribution System

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170905

RJ01 Rejection of invention patent application after publication