CN107130627A - A kind of construction method of the observation pier based on GNSS system for monitoring displacement - Google Patents

A kind of construction method of the observation pier based on GNSS system for monitoring displacement Download PDF

Info

Publication number
CN107130627A
CN107130627A CN201710410819.9A CN201710410819A CN107130627A CN 107130627 A CN107130627 A CN 107130627A CN 201710410819 A CN201710410819 A CN 201710410819A CN 107130627 A CN107130627 A CN 107130627A
Authority
CN
China
Prior art keywords
concrete
observation pier
poling
construction method
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710410819.9A
Other languages
Chinese (zh)
Inventor
葛锐
汪国靖
赵伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Space And Space Mdt Infotech Ltd
Original Assignee
Anhui Space And Space Mdt Infotech Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Space And Space Mdt Infotech Ltd filed Critical Anhui Space And Space Mdt Infotech Ltd
Priority to CN201710410819.9A priority Critical patent/CN107130627A/en
Publication of CN107130627A publication Critical patent/CN107130627A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes

Abstract

The present invention discloses a kind of construction method of the observation pier based on GNSS system for monitoring displacement, comprises the following steps:Excavation pit, matrix treatment, reinforcing bar colligation, poling is installed, concreting, top cage bar is fixed, remove middle part template, concrete curing, pit is backfilled, top stirrup colligation, top PVC sleeve pipes, which are installed, to be fixed, concrete is mixed and stirred, pour, vibrate, eliminate unnecessary poling, aperture residual concrete is poured to vibrate by hand, levelness is adjusted, model sheetinstallat, mortar or concrete are mixed and stirred, floor leveling layer mortar is filled or platform concreting, form removal, observation pier is integrally sprinkled water maintenance.Compared with prior art, beneficial effects of the present invention are:The position of adjacent observation pier is consolidated, it is ensured that the stability of observation result, can be prevented effectively from GNSS signal and be absorbed or blocked.

Description

A kind of construction method of the observation pier based on GNSS system for monitoring displacement
Technical field
The present invention relates to a kind of construction method of observation pier, and in particular to a kind of observation based on GNSS system for monitoring displacement The construction method of pier.
Background technology
Prevent and reduce natural disasters field, be in very for the surface displacement variation monitoring of Potential hazards body in engineering and geological disaster How consequence, obtain the displacement information of measured point and how to realize that quick, effective early warning is current in real time Great difficult problem urgently to be resolved hurrily.
Being presently used for automating the equipment of ground displacement mainly has:Stay-supported ground displacement instrument, laser type Table displacement monitor, time domain reflectometry, GPS monitoring systems etc..Bracing wire or laser type ground displacement instrument belong to relative displacement Monitoring method, in real time measurement distance between two points change has the advantages that precision is high, is protected from weather influences, low-power consumption, but can only measure Change in displacement in one-dimensional square;Time domain reflectometry falls within one-dimensional measurement, it is measurable go out along any point deformation, it is this Excessively complexity is realized on method and technology, technological layer is not still very ripe, it should seldom;GNSS (the whole world based on satellite fix Navigational satellite system) it is the new technology developed rapidly in recent years, more and more starting in geology, engineering field should With using GNSS carrier phase relative positioning technologies, carrier phase and pseudo range data by the use of two receiver collections are used as master Want observation to carry out difference resolving, and estimate the integer ambiguity of carrier phase, high-precision relative position can be obtained in real time Confidence ceases, and greatly improves operating efficiency, reduces operating cost, and the setting of the observation pier position of GNSS system for monitoring displacement Precision for monitoring result plays vital effect.
The content of the invention
It is an object of the invention to provide a kind of construction method of the observation pier based on GNSS system for monitoring displacement, to ensure Monitoring result is accurate.
To achieve these goals, the technical scheme that provides of the present invention is:A kind of sight based on GNSS system for monitoring displacement The construction method of pier is surveyed, is comprised the following steps:
Step one:Excavation pit, excavates the foundation ditch for carrying concrete observation pier according to the position selected on construction drawing, opens After digging terminates, pit periphery is tamped, by crater wall soil pressure reality and little water is sprayed;
Step 2:Matrix treatment, is arranged and is rinsed to surface of bedrock;
Step 3:Reinforcing bar colligation, carries out bottom reinforcement bars, some or all of stirrup colligation of middle part cage bar, and concrete and mixes With;
Step 4:Poling is installed, and carries out the installation and fixation of installing fixed and middle part template of poling;
Step 5:Concreting, concrete carries out placement layer by layer according to 30cm thickness after mixing and stirring, vibrated;
Step 6:Top cage bar is fixed, and top cage bar is inserted into fixed after the concrete 20cm of middle part;
Step 7:Middle part template is removed, by middle part form removable after concrete strength is more than 30%;
Step 8:Concrete curing, watering maintenance is carried out to middle part and lower concrete;
Step 9:Pit is backfilled, and concrete periphery pastes the thick cystosepiments of 2cm or carries out isolation back-filling in layers with the thick coarse sands of 4cm;
Step 10:Top stirrup colligation;
Step 11:Top PVC sleeve pipes are installed, fixed;
Step 12:Concrete is mixed and stirred, 30cm thickness placement layer by layer, vibrated, until below the mouth of pipe at 20cm;
Step 13:Unnecessary poling is eliminated, the redundance of poling is reamed and makes mouth of pipe level, sealed again with adhesive tape;
Step 14:Pour aperture residual concrete vibrate by hand, and the forced centering of fixed pin bolt will be installed in time The pin bolt insertion concrete on chassis, adjustment chassis is so that its placed in the middle and surface level, poling is aligned with threading hole;
Step 15:Levelness is adjusted, every water for detecting and adjusting forced centering plate for 5 minutes with horizon rule during concrete initial set Pingdu;
Step 10 six:Model sheetinstallat, observation pier surrounding ground is smooth and tamps, and 0.8 × 0.8m side mould is installed and fixed, and keeps Template center and observation pier center are concentric, and make template direction and attachment body parallel or vertical;
Step 10 seven:Mortar or concrete are mixed and stirred;
Step 10 eight:Floor leveling layer mortar is filled or platform concreting;
Step 10 nine:Form removal, leveling mortar or platform concrete strength more than 30% after form removal;
Step 2 ten:Observation pier is integrally sprinkled water maintenance.
Preferably, when the poling described in step 4 installs fixed, poling two need to be sealed.
Preferably, step 6 is carried out in 20 minutes after the completion of the concreting of middle part.
Preferably, described in step 9 backfill material is using excavated material outside cystosepiment or coarse sand and tamps.
Preferably, the mouth of pipe described in step 13 is highly less than mould pipe height 4mm.
Preferably, described in step 10 eight floor leveling layer mortar fill or platform concreting during with cystosepiment, Cardboard, plank or pitch coarse sand mud etc. carry out isolation seam isolation.
Compared with prior art, beneficial effects of the present invention are:The position of adjacent observation pier is consolidated, it is ensured that observation result Stability, can be prevented effectively from GNSS signal and be absorbed or blocked.
Embodiment
A kind of construction method of the observation pier based on GNSS system for monitoring displacement, comprises the following steps:
Step one:Excavation pit, excavates the foundation ditch for carrying concrete observation pier according to the position selected on construction drawing, opens After digging terminates, pit periphery is tamped, by crater wall soil pressure reality and little water is sprayed;Sprinkling little water is used to consolidate side slope, there is pre- Discharge lightning protection should pole install after carry out;
Step 2:Matrix treatment, is arranged and is rinsed to surface of bedrock;
Step 3:Reinforcing bar colligation, carries out bottom reinforcement bars, some or all of stirrup colligation of middle part cage bar, and concrete and mixes With;There is pre-arcing to be grounded and go electrostatic grounding, its built-in fitting and company should synchronously complete;
Step 4:Poling is installed, and carries out the installation and fixation of installing fixed and middle part template of poling;
Step 5:Concreting, concrete carries out placement layer by layer according to 30cm thickness after mixing and stirring, vibrated;
Step 6:Top cage bar is fixed, and top cage bar is inserted into fixed after the concrete 20cm of middle part;
Step 7:Middle part template is removed, by middle part form removable after concrete strength is more than 30%;
Step 8:Concrete curing, watering maintenance is carried out to middle part and lower concrete;
Step 9:Pit is backfilled, and concrete periphery pastes the thick cystosepiments of 2cm or carries out isolation back-filling in layers with the thick coarse sands of 4cm;
Step 10:Top stirrup colligation;
Step 11:Top PVC sleeve pipes are installed, fixed;
Step 12:Concrete is mixed and stirred, 30cm thickness placement layer by layer, vibrated, until below the mouth of pipe at 20cm;
Step 13:Unnecessary poling is eliminated, the redundance of poling is reamed and makes mouth of pipe level, sealed again with adhesive tape;
Step 14:Pour aperture residual concrete vibrate by hand, and the forced centering of fixed pin bolt will be installed in time The pin bolt insertion concrete on chassis, adjustment chassis is so that its placed in the middle and surface level, poling is aligned with threading hole;
Step 15:Levelness is adjusted, every water for detecting and adjusting forced centering plate for 5 minutes with horizon rule during concrete initial set Pingdu;
Step 10 six:Model sheetinstallat, observation pier surrounding ground is smooth and tamps, and 0.8 × 0.8m side mould is installed and fixed, and keeps Template center and observation pier center are concentric, and make template direction and attachment body parallel or vertical;
Step 10 seven:Mortar or concrete are mixed and stirred;
Step 10 eight:Floor leveling layer mortar is filled or platform concreting;
Step 10 nine:Form removal, leveling mortar or platform concrete strength more than 30% after form removal;
Step 2 ten:Observation pier is integrally sprinkled water maintenance.
The optimal technical scheme of the present embodiment is that when the poling described in step 4 installs fixed, need to seal poling two.
The optimal technical scheme of the present embodiment is that step 6 is carried out in 20 minutes after the completion of the concreting of middle part.
The optimal technical scheme of the present embodiment is that backfill material uses excavated material outside the cystosepiment or coarse sand described in step 9 And tamp.
The optimal technical scheme of the present embodiment is that the mouth of pipe described in step 13 is highly less than mould pipe height 4mm.
The optimal technical scheme of the present embodiment is that floor leveling layer mortar is filled described in step 10 eight or platform concrete is poured Isolation seam isolation is carried out during building with cystosepiment, cardboard, plank or pitch coarse sand mud etc..Isolation seam construction is carried out with template, Need first to construct to the mortar or concrete in 0.5 × 0.5m, 0.5 × 0.5m internal models, treat mortar or concrete in internal model After initial set, isolated material is installed and carries out mortar or concrete construction in external mold again.
The present invention observation pier concreting step be:
1st, concrete raw material is selected:
A. it is not less than 325 using cement grade, makes the concrete pillar not influenceed by freeze thawing, it is preferential to use slag and volcanic ash Matter cement, makes the concrete pillar influenceed by freeze thawing, uses Portland cement.Making by saline and alkaline, seawater or industry When sewage corrodes the markstone in area, sulfate-resistant cement must be used, the markstone in the dry environments such as desert, gobi must not make With volcano grey matter cement;
B. stone matches somebody with somebody qualified 5-40mm natural pebble or hard rubble using level, should not use the stone of same size;
C. sand uses the middle sand of 0.15-3mm particle diameters, and clay content is no more than 3%;
D. water must be no more than 1% using the fresh water cleaned, sulphates content;
E. additive can be selected according to construction environment, such as early strength agent, water reducer, air entraining agent, and its quality should meet respective specified, The additive containing villaumite must not be used.
2nd, Concrete:
The configuration of its aggregate and cement, water, the consumption of sand and mixing ratio are with reference to following table during Concrete.
3rd, concrete construction:
A. concrete is modulated, must be first net by sand, granite-wash, when burning filling markstone, successively must fully it make firm by ramming;
B. when temperature is below 0 DEG C, it is necessary to add antifreezing agent, striking time is no less than 24 hours;
C. striking time can be determined according to temperature and additive performance, under general condition, when temperature on average is more than 0 DEG C, form removal Time is no less than 12 hours.

Claims (6)

1. a kind of construction method of the observation pier based on GNSS system for monitoring displacement, it is characterised in that comprise the following steps:
Step one:Excavation pit, excavates the foundation ditch for carrying concrete observation pier according to the position selected on construction drawing, opens After digging terminates, pit periphery is tamped, by crater wall soil pressure reality and little water is sprayed;
Step 2:Matrix treatment, is arranged and is rinsed to surface of bedrock;
Step 3:Reinforcing bar colligation, carries out bottom reinforcement bars, some or all of stirrup colligation of middle part cage bar, and concrete and mixes With;
Step 4:Poling is installed, and carries out the installation and fixation of installing fixed and middle part template of poling;
Step 5:Concreting, concrete carries out placement layer by layer according to 30cm thickness after mixing and stirring, vibrated;
Step 6:Top cage bar is fixed, and top cage bar is inserted into fixed after the concrete 20cm of middle part;
Step 7:Middle part template is removed, by middle part form removable after concrete strength is more than 30%;
Step 8:Concrete curing, watering maintenance is carried out to middle part and lower concrete;
Step 9:Pit is backfilled, and concrete periphery pastes the thick cystosepiments of 2cm or carries out isolation back-filling in layers with the thick coarse sands of 4cm;
Step 10:Top stirrup colligation;
Step 11:Top PVC sleeve pipes are installed, fixed;
Step 12:Concrete is mixed and stirred, 30cm thickness placement layer by layer, vibrated, until below the mouth of pipe at 20cm;
Step 13:Unnecessary poling is eliminated, the redundance of poling is reamed and makes mouth of pipe level, sealed again with adhesive tape;
Step 14:Pour aperture residual concrete vibrate by hand, and the forced centering of fixed pin bolt will be installed in time The pin bolt insertion concrete on chassis, adjustment chassis is so that its placed in the middle and surface level, poling is aligned with threading hole;
Step 15:Levelness is adjusted, every water for detecting and adjusting forced centering plate for 5 minutes with horizon rule during concrete initial set Pingdu;
Step 10 six:Model sheetinstallat, observation pier surrounding ground is smooth and tamps, and 0.8 × 0.8m side mould is installed and fixed, and keeps Template center and observation pier center are concentric, and make template direction and attachment body parallel or vertical;
Step 10 seven:Mortar or concrete are mixed and stirred;
Step 10 eight:Floor leveling layer mortar is filled or platform concreting;
Step 10 nine:Form removal, leveling mortar or platform concrete strength more than 30% after form removal;
Step 2 ten:Observation pier is integrally sprinkled water maintenance.
2. the construction method of the observation pier according to claim 1 based on GNSS system for monitoring displacement, it is characterised in that step When poling described in rapid four installs fixed, poling two need to be sealed.
3. the construction method of the observation pier according to claim 1 based on GNSS system for monitoring displacement, it is characterised in that step Rapid six are carried out in 20 minutes after the completion of the concreting of middle part.
4. the construction method of the observation pier according to claim 1 based on GNSS system for monitoring displacement, it is characterised in that step Backfill material is using excavated material outside cystosepiment or coarse sand described in rapid nine and tamps.
5. the construction method of the observation pier according to claim 1 based on GNSS system for monitoring displacement, it is characterised in that step The mouth of pipe described in rapid 13 is highly less than mould pipe height 4mm.
6. the construction method of the observation pier according to claim 1 based on GNSS system for monitoring displacement, it is characterised in that step Described in rapid 18 floor leveling layer mortar fill or platform concreting during use cystosepiment, cardboard, plank or pitch coarse sand Mud etc. carries out isolation seam isolation.
CN201710410819.9A 2017-06-04 2017-06-04 A kind of construction method of the observation pier based on GNSS system for monitoring displacement Pending CN107130627A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710410819.9A CN107130627A (en) 2017-06-04 2017-06-04 A kind of construction method of the observation pier based on GNSS system for monitoring displacement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710410819.9A CN107130627A (en) 2017-06-04 2017-06-04 A kind of construction method of the observation pier based on GNSS system for monitoring displacement

Publications (1)

Publication Number Publication Date
CN107130627A true CN107130627A (en) 2017-09-05

Family

ID=59734215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710410819.9A Pending CN107130627A (en) 2017-06-04 2017-06-04 A kind of construction method of the observation pier based on GNSS system for monitoring displacement

Country Status (1)

Country Link
CN (1) CN107130627A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108007442A (en) * 2017-12-13 2018-05-08 山西四建集团有限公司 Hole construction method is surveyed in experimental plot with automatic monitored control system
CN113513995A (en) * 2021-06-03 2021-10-19 马龙 Ground displacement monitoring device for geological monitoring

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101229129B1 (en) * 2010-11-15 2013-02-01 현대건설주식회사 Method for measuring verticality of structure using GNSS and system thereof
CN103076010A (en) * 2013-01-25 2013-05-01 天津二十冶建设有限公司 Fabrication method of forced centering observation pillar for precision engineering measurement and observation pillar
CN203310412U (en) * 2013-06-20 2013-11-27 中国地震局地震研究所 GNSS (global navigation satellite system) observation pillar for reducing multipath effect
CN203364831U (en) * 2013-07-02 2013-12-25 中国地震局地震研究所 Global navigational satellite system observation pillar for reducing temperature difference effect

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101229129B1 (en) * 2010-11-15 2013-02-01 현대건설주식회사 Method for measuring verticality of structure using GNSS and system thereof
CN103076010A (en) * 2013-01-25 2013-05-01 天津二十冶建设有限公司 Fabrication method of forced centering observation pillar for precision engineering measurement and observation pillar
CN203310412U (en) * 2013-06-20 2013-11-27 中国地震局地震研究所 GNSS (global navigation satellite system) observation pillar for reducing multipath effect
CN203364831U (en) * 2013-07-02 2013-12-25 中国地震局地震研究所 Global navigational satellite system observation pillar for reducing temperature difference effect

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108007442A (en) * 2017-12-13 2018-05-08 山西四建集团有限公司 Hole construction method is surveyed in experimental plot with automatic monitored control system
CN113513995A (en) * 2021-06-03 2021-10-19 马龙 Ground displacement monitoring device for geological monitoring

Similar Documents

Publication Publication Date Title
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN109630137A (en) An a kind of tunnel high position passes through the backfill processing construction method of huge molten chamber
CN106242422A (en) Self-compaction cement grout is used in fertile groove backfill
CN110106868B (en) Karst geology large-diameter pile foundation pore-forming process method
CN113186924A (en) Subway foundation pit deep-buried karst cave treatment method
CN113774917B (en) Safe construction method for earth and rockfill excavation and side slope supporting engineering
CN101597888B (en) Construction method of municipal drainage culvert sinking trough
CN110397079A (en) Marine facies rich water karst strata open-cut station construction technology
CN109706952A (en) Large-scale well-sinking construction method
CN110528578A (en) Under wear existing railway double track tunnel cover and cut construction method
CN109914161A (en) A kind of construction method of soft clay area high-speed railway filled-up ground
CN113636809A (en) Collapsible loess aggregate filling material
CN107130627A (en) A kind of construction method of the observation pier based on GNSS system for monitoring displacement
CN109914445A (en) A kind of level of ground water alternately changes the construction method of location expensive soil cutting
CN109457705A (en) A kind of Open Cut Method construction method
CN208293588U (en) A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN110512594A (en) The simple and easy method of churning driven opportunity cavity pore-forming
CN109811771A (en) Make the simple and easy method not bent when anchor bar steel waist rail tensioning
CN113373867A (en) Coastline soft foundation solidified soil structure and process
CN112627245B (en) Abandoned dreg site surveying and ecological restoration method based on in-situ recognition
CN114232636A (en) Simple method for backfilling fertilizer grooves of building foundation pit based on solid waste utilization
CN107700478A (en) Work transmission line bored concrete pile single-pile foundation one-shot forming construction method
CN209669857U (en) A kind of variable diameters steel reinforcement cage enlarged footing anchor pole anti-floating or pressure bearing pile
CN113322967A (en) Coastline soft foundation in-situ curing method and curing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170905

RJ01 Rejection of invention patent application after publication