CN107090802A - A kind of construction method of batardeau on the sea closure - Google Patents

A kind of construction method of batardeau on the sea closure Download PDF

Info

Publication number
CN107090802A
CN107090802A CN201710302032.0A CN201710302032A CN107090802A CN 107090802 A CN107090802 A CN 107090802A CN 201710302032 A CN201710302032 A CN 201710302032A CN 107090802 A CN107090802 A CN 107090802A
Authority
CN
China
Prior art keywords
closure
embankment
length
port door
carried out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710302032.0A
Other languages
Chinese (zh)
Inventor
刘勇
吴光辉
伊左林
林猛
陈仁昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
In Sanhang (xiamen) Engineering Co Ltd
China Construction Third Engineering Bureau Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by In Sanhang (xiamen) Engineering Co Ltd, China Construction Third Engineering Bureau Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical In Sanhang (xiamen) Engineering Co Ltd
Priority to CN201710302032.0A priority Critical patent/CN107090802A/en
Publication of CN107090802A publication Critical patent/CN107090802A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a kind of construction method of batardeau on the sea closure, comprise the following steps:Longkou addressing, the determination for block stone specification of jettisoninging, closure gap, once increase mouth door ground sill, Longkou compression, compression section embankment reinforce, it is secondary increase mouth door ground sill, Longkou closure and Longkou embankment reinforce.When once being increased mouth door ground sill method is blocked up using flat;When carrying out Longkou compression method is blocked up using vertical;It is compressed when section embankment is reinforced and uses explosive replacement;Carry out it is secondary when increasing mouth door ground sill again using flat stifled method;Method is blocked up when carrying out Longkou closure using vertical again;Carry out also using explosive replacement when Longkou embankment is reinforced.The construction method of the batardeau on the sea closure of the present invention, has effectively ensured engineering level, and easy construction, effect are good, easy to operate, effectively reduce Longkou bedding and wash away, the control soil body is lost in.

Description

Construction method for sea dyke closure
Technical Field
The invention relates to a construction method for closing an offshore dike.
Background
The closure construction of the dike is the most important, the most difficult and the most risky stage in the construction of the seawall of the sea reclamation engineering. In the embankment project, closure of the closure opening is a construction link directly related to the quality of the whole project. Uncertain factors are numerous in closure construction, and hydrological weather is variable, so that the closure construction has huge risks; the hydraulic conditions faced during closure are the worst in the whole seawall construction, the water level drop at the opening door is large, the flow velocity is large, and the water flow condition is very complex. The closure plugging construction needs to finish a large amount of material throwing work in a short time, the field operation surface is very narrow, the working surface is few, and the requirements on the specification of throwing fillers, the capacity of construction machines and tools, the construction organization management and the like are high.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a construction method of an offshore dike closure, which effectively guarantees the engineering level, has convenient construction, good effect and easy operation, effectively reduces the scouring of a closure bed and controls the loss of soil.
The purpose of the invention is realized as follows: a construction method of an offshore dyke closure comprises the following steps: the method comprises the following steps of (1) positioning a closure gap, determining specification of a cast stone, protecting a closure gap bottom, adding a door sill with a high opening at one time, compressing the closure gap, reinforcing a compression section embankment, adding a door sill with a high opening at the second time, closing the closure gap and reinforcing the closure gap embankment; wherein,
when the step of carrying out the dragon mouth site selection is carried out, a road section with the length of a mouth door being L, the bottom being a mud surface layer and the elevation being 0 to +0.5m is selected as the dragon mouth, the thickness of the mud surface layer is 10m, and a pebble layer is arranged below the mud surface layer;
when the specification of the thrown block stone is determined, the diameter of a single spherical block stone is calculated to be 0.659m according to the impact-resistant stable critical flow rate of the single thrown block stone on the rockfill body of the cut-off dike, and the weight of the single spherical block stone is not less than 400 kg;
when the bottom protection step of the closure opening is carried out, the length of the opening door is kept to be L, and sea throwing is adopted, namely, a 2000-3000 t iron barge is used for throwing and filling 200-500 kg of block stones, so that the protection bottom is heightened to be +3m, the width of the bottom of the protection bottom is 10m, and the width of the top of the protection bottom is 6 m;
when the step of heightening the bottom threshold of the port door is carried out for the first time, the leveling plug is thrown on land in a low tide period, the length of the port door is kept to be L, the barge is docked at two ends of the port door in a high tide, a loader is used for propelling a riprap leveling plug from two ends of the port door to the middle of the port door to be heightened by taking a low tide, the specification of riprap materials is larger than 400kg, the height of the bottom threshold of the port door is increased to +4m, and the width of the top of the bottom threshold of the port door is kept at 6 m;
when the step of dragon mouth compression is carried out, a ferry barge is parked at two ends of a port door with the length of L by a high tide, a loader is utilized to push the unloading vertical plug from the two ends to the middle, the length of the port door is compressed to 1/2L from L, embankments with the length of 1/4L at the two ends of the port door are heightened to +7.5m, and the width of the two sections of embankments is 6 m; the dykes at the two ends are protected by block stones of more than 500 kg;
when the compression section embankment reinforcing step is carried out, firstly, a barge is adopted for loading, the embankment is transported to the side of an embankment by sea, the compression section embankment with the length of 1/4L at the two ends of a port door is heightened to +9.5m, the two compression section embankments are widened to the top width of 10m, and then blasting compaction is adopted to enable the two compression section embankments to fall to the bottom of a pebble layer;
when the step of heightening the entrance sill for the second time is carried out, the length of the entrance is maintained to be 1/2L, the barge is parked at two ends of the entrance with the length of 1/2L, riprap is pushed from two ends to the middle by a loader to be leveled and heightened, the entrance sill is heightened to be +5m, and the width of the top of the entrance sill is kept at 6 m;
when the step of closing the opening is carried out, the iron barge is parked at two ends of a port door with the length of 1/2L by taking the climax, the loading machine is used for pushing the unloading vertical plug from the two ends to the middle, the length of the port door is compressed from 1/2L to close the opening, the elevation of a port door embankment with the length of 1/2L is increased to +7.5m, and the width of the port door embankment is 6 m;
when the step of reinforcing the closure embankment is carried out, ship-transported stone land throwing is immediately adopted after closure of the closure, the portal embankment is heightened to +9.5m, the portal embankment is widened to 10m of top width, and first blasting and silt squeezing of the section of the embankment are timely completed, so that the embankment falls to the bottom of the pebble layer.
Before the step of protecting the bottom of the closure opening, the embankment with the length of 1/3L at the two ends of the closure opening is subjected to blasting and silt squeezing at least once, and the embankment heads at the two sides of the closure opening are subjected to anti-scour protection by adopting a method of throwing more than 500kg of block stones by a ship.
According to the construction method of the sea dyke closure, when the step of heightening the threshold is carried out for one time, construction is carried out at each low-tide-level time, and the construction time is 5-6 hours.
According to the construction method of the offshore dyke closure, the closure step is carried out at the full tide time.
The construction method of the sea dyke closure of the invention adopts the method of combining flat plug and vertical plug and adopts the method of closing after necking, so that the closure is firstly reduced by half, which is beneficial to preventing the scouring of the downstream foundation, thereby ensuring the stability of the dyke head, and then closing, simplifying the preparation work of closure, thereby winning time, saving investment and ensuring the stability of the dyke head. The construction method of the invention effectively guarantees the engineering level, has convenient construction, good effect and easy operation, effectively reduces the erosion of the closure bed and controls the loss of soil.
Drawings
FIG. 1 is a flow chart of the construction method of the sea dyke closure of the invention;
FIG. 2 is a cross-sectional view of the bottom protection after the step of protecting the closure bottom according to the construction method of the present invention;
FIG. 3 is a longitudinal sectional view of the closure after the closure bottom protecting step in the construction method of the present invention;
FIG. 4 is a cross-sectional view of the back doorsill after a step of heightening the doorsill at one time in the construction method of the present invention;
FIG. 5 is a longitudinal sectional view of the closure after the step of heightening the sill of the doorway is performed for one time in the construction method of the present invention;
FIG. 6 is a cross-sectional view of the dike body after a closure compression step is performed in the construction method of the present invention;
FIG. 7 is a longitudinal sectional view of the closure after the closure compression step in the construction method of the present invention;
fig. 8 is a cross-sectional view of the embankment body after the embankment reinforcing step of the compression section is performed in the construction method of the present invention;
FIG. 9 is a longitudinal sectional view of the closure after the step of consolidating the embankment at the compression section in the construction method of the present invention;
FIG. 10 is a cross-sectional view of the back doorsill after the step of heightening the doorsill twice in the construction method of the present invention;
FIG. 11 is a longitudinal sectional view of the closure after the step of heightening the sill of the doorway twice in the construction method of the present invention;
FIG. 12 is a cross-sectional view of the closure after the closure closing step in the construction method of the present invention;
FIG. 13 is a longitudinal sectional view of the closure after the closure closing step in the construction method of the present invention;
fig. 14 is a cross-sectional view of the closure after the step of reinforcing the closure embankment in the construction method of the present invention.
Detailed Description
The invention will be further explained with reference to the drawings.
Referring to fig. 1 to 14, the method for constructing an offshore dyke closure according to the present invention includes the following steps: the method comprises the following steps of positioning a closure gap, determining the specification of a cast stone, protecting the closure gap, adding a sill at a primary heightening port, compressing the closure gap, reinforcing a compression section embankment, adding the sill at a secondary heightening port, closing the closure gap and reinforcing the closure gap embankment.
When the step of the location of the closure opening is carried out, a road section with the length L of 300m, the bottom of a mud surface layer and the elevation of 0 to +0.5m is selected as the closure opening, the thickness of the mud surface layer is 10m, and a pebble layer is arranged below the mud surface layer.
When the specification of the thrown block stone is determined, calculating the diameter D of a single spherical block stone to be 0.659m and the weight to be not less than 400kg according to the impact-resistant stable critical flow rate of the single thrown block stone on the rockfill body of the cut-off dike; the specific calculation formula is as follows:
in the formula: kCFor stability factor, the diameter of the cushion layer block stone is preferably 0.7-1.0 when smaller than that of the block stone thrown on the cushion layer block stone, the diameter of the cushion layer block stone is preferably 1.0-1.2 when larger than or equal to that of the thrown block stone, and the strip bodies such as a reinforcement cage are preferably 1.0;
g is gravity acceleration (m/s)2) Should be 9.8m/s2
γsIs the weight of the projectile (kN/m)3) For granite block stone, 26kN/m can be taken3
γ0Is the seawater severity (kN/m)3) It may take 10kN/m3~10.3kN/m3
D is the equivalent diameter (m) of the lump stone converted according to the spherical body;
-the rockfill repose angle (°) is taken according to engineering experience;
α -the angle of inclination (degree) of the bed course of the riprap body can be taken to be less than the angle of repose of the riprap body according to engineering experience, i.e. the angle of inclination (degree)
The maximum flow velocity value in the process of the engineering plugging is 4.437m/s, and the corresponding weight of the rock block is calculated as follows:
d0.659 m, radius R D/2 0.3295m
Weight of spherical lump stone 0.1498m3×2.6t/m3=0.3895t≈400kg
Therefore, the weight of the closed-line cast stone is required to be not less than 400 kg.
When the longkou bottom protection step is carried out, keeping the length L of a port door to be 300m, adopting sea throwing, namely adopting a 2000-3000 t iron barge to throw and fill 200-500 kg of block stones, enabling the iron barge to enter the throwing and filling positions of embankments at two ends of the port door by virtue of high tide, positioning a ship vertical to the axis of the embankment, throwing stones to a preset position by utilizing a loader, enabling the bottom protection to be lifted horizontally and uniformly, enabling the bottom protection to be raised to +3m, enabling the cross section of the bottom protection to be trapezoidal, enabling the width of the bottom protection to be 10m, and enabling the width of the top of the bottom protection to be 6 m; before the closure bottom protection, the embankment with the length of 1/3L (100 m) at both ends of the closure is blasted and silted at least once, and the embankment at both sides of the closure is protected against scouring by a method of throwing more than 500kg of block stones by a ship.
When the step of heightening the sill at the entrance is carried out for one time, construction is carried out at each low-tide level time, the construction time is 5-6 hours, and flat blocking is thrown on land at the low-tide level time; the length of the portal is maintained to be 300m, the barge is docked at two ends of the portal when in high tide, riprap leveling and blocking are pushed from two ends of the portal to the middle by a loader to be heightened when in low tide, the specification of riprap is more than 400kg, the portal sill is heightened to be +4m, and the width of the top of the portal sill is kept to be 6 m.
When the dragon mouth compression step is carried out, a ferry ship is parked at the two ends of a gate with the length L being 300m by a high tide, a loader is used for pushing the discharging vertical plug from the two ends to the middle, the gate length is compressed from L being 300m to 1/2L being 150m, embankments with the length of 1/4L being 75m at the two ends of the gate are heightened to +7.5m, and the width of the two sections of embankments is 6 m; the dykes at the two ends are protected by block stones of more than 500 kg.
When the step of reinforcing the compression section embankment is carried out, a barge is adopted for loading materials, the materials are transported to the side of the embankment by sea, the compression section embankment with the length of 1/4L (75 m) at the two ends of the port door is heightened to +9.5m, the two compression section embankments are widened to the top width of 10m, and then blasting and silt squeezing are adopted to enable the two compression section embankments to fall to the bottom of the pebble layer.
When the step of heightening the entrance sill for the second time is carried out, the length of the entrance is maintained to be 1/2L-150 m, the refuge ship is parked at the two ends of the entrance with the length of 1/2L-150 m by the high tide, riprap is pushed from the two ends to the middle by a loader to be leveled and heightened, the entrance sill is heightened to be +5m, and the width of the top of the entrance sill is maintained to be 6 m.
When the closure step is carried out, construction is carried out at the full tide section, a railway barge is parked at two ends of a port door with the length of 1/2L-150 m by a high tide, a loader is utilized to push the discharging vertical plug from the two ends to the middle, the length of the port door is compressed from 1/2L-150 m to the closure, the closure of the closure is completed, the height of the port door embankment with the length of 1/2L-150 m is increased to +7.5m, and the width of the port door embankment is 6 m.
When the step of reinforcing the closure embankment is carried out, ship-transported stone land throwing is immediately adopted after closure of the closure, the portal embankment is heightened to +9.5m, the portal embankment is widened to 10m of top width, and first blasting and silt squeezing of the section of the embankment are timely completed, so that the embankment falls to the bottom of the pebble layer.
The construction method of the invention effectively guarantees the engineering level, has convenient construction, good effect and easy operation, effectively reduces the erosion of the closure bed and controls the loss of soil.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and therefore all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (4)

1. A construction method of an offshore dyke closure is characterized by comprising the following steps: the method comprises the following steps of (1) positioning a closure gap, determining specification of a cast stone, protecting a closure gap bottom, adding a door sill with a high opening at one time, compressing the closure gap, reinforcing a compression section embankment, adding a door sill with a high opening at the second time, closing the closure gap and reinforcing the closure gap embankment;
when the step of carrying out the dragon mouth site selection is carried out, a road section with the length of a mouth door being L, the bottom being a mud surface layer and the elevation being 0 to +0.5m is selected as the dragon mouth, the thickness of the mud surface layer is 10m, and a pebble layer is arranged below the mud surface layer;
when the specification of the thrown block stone is determined, the diameter of a single spherical block stone is calculated to be 0.659m according to the impact-resistant stable critical flow rate of the single thrown block stone on the rockfill body of the cut-off dike, and the weight of the single spherical block stone is not less than 400 kg;
when the bottom protection step of the closure opening is carried out, the length of the opening door is kept to be L, and sea throwing is adopted, namely, a 2000-3000 t iron barge is used for throwing and filling 200-500 kg of block stones, so that the protection bottom is heightened to be +3m, the width of the bottom of the protection bottom is 10m, and the width of the top of the protection bottom is 6 m;
when the step of heightening the bottom threshold of the port door is carried out for the first time, the leveling plug is thrown on land in a low tide period, the length of the port door is kept to be L, the barge is docked at two ends of the port door in a high tide, a loader is used for propelling a riprap leveling plug from two ends of the port door to the middle of the port door to be heightened by taking a low tide, the specification of riprap materials is larger than 400kg, the height of the bottom threshold of the port door is increased to +4m, and the width of the top of the bottom threshold of the port door is kept at 6 m;
when the step of dragon mouth compression is carried out, a ferry barge is parked at two ends of a port door with the length of L by a high tide, a loader is utilized to push the unloading vertical plug from the two ends to the middle, the length of the port door is compressed to 1/2L from L, embankments with the length of 1/4L at the two ends of the port door are heightened to +7.5m, and the width of the two sections of embankments is 6 m; the dykes at the two ends are protected by block stones of more than 500 kg;
when the compression section embankment reinforcing step is carried out, firstly, a barge is adopted for loading, the embankment is transported to the side of an embankment by sea, the compression section embankment with the length of 1/4L at the two ends of a port door is heightened to +9.5m, the two compression section embankments are widened to the top width of 10m, and then blasting compaction is adopted to enable the two compression section embankments to fall to the bottom of a pebble layer;
when the step of heightening the entrance sill for the second time is carried out, the length of the entrance is maintained to be 1/2L, the barge is parked at two ends of the entrance with the length of 1/2L, riprap is pushed from two ends to the middle by a loader to be leveled and heightened, the entrance sill is heightened to be +5m, and the width of the top of the entrance sill is kept at 6 m;
when the step of closing the opening is carried out, the iron barge is parked at two ends of a port door with the length of 1/2L by taking the climax, the loading machine is used for pushing the unloading vertical plug from the two ends to the middle, the length of the port door is compressed from 1/2L to close the opening, the elevation of a port door embankment with the length of 1/2L is increased to +7.5m, and the width of the port door embankment is 6 m;
when the step of reinforcing the closure embankment is carried out, ship-transported stone land throwing is immediately adopted after closure of the closure, the portal embankment is heightened to +9.5m, the portal embankment is widened to 10m of top width, and first blasting and silt squeezing of the section of the embankment are timely completed, so that the embankment falls to the bottom of the pebble layer.
2. The construction method of the sea dyke closing according to claim 1, characterized in that before the step of protecting the bottom of the closure opening, the embankment with the length of 1/3L at both ends of the closure opening is blasted and silted at least once, and the embankment heads at both sides of the closure opening are protected against scour by a method of throwing more than 500kg of rock blocks by a ship.
3. The construction method of the offshore dyke closure according to claim 1, wherein the step of heightening the sill at the entrance is performed at every low tide level for 5-6 hours.
4. The method for constructing sea dyke closure according to claim 1, wherein the closure step is carried out at full tide.
CN201710302032.0A 2017-05-02 2017-05-02 A kind of construction method of batardeau on the sea closure Pending CN107090802A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710302032.0A CN107090802A (en) 2017-05-02 2017-05-02 A kind of construction method of batardeau on the sea closure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710302032.0A CN107090802A (en) 2017-05-02 2017-05-02 A kind of construction method of batardeau on the sea closure

Publications (1)

Publication Number Publication Date
CN107090802A true CN107090802A (en) 2017-08-25

Family

ID=59637493

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710302032.0A Pending CN107090802A (en) 2017-05-02 2017-05-02 A kind of construction method of batardeau on the sea closure

Country Status (1)

Country Link
CN (1) CN107090802A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517835A (en) * 2018-06-08 2018-09-11 长江南京航道工程局 A kind of the protection structure and its closure method of unconventional storage capacity corral sea wall list Longkou
CN109975523A (en) * 2019-04-29 2019-07-05 华侨大学 A kind of compacting mud by explosion mudstone mixed layer engineering properties prediction technique
CN112900353A (en) * 2021-01-22 2021-06-04 长江勘测规划设计研究有限责任公司 River channel intercepting method and arrangement structure thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619194A (en) * 2012-04-17 2012-08-01 上海市水利工程设计研究院 Method for closure of high-flow-rate closure gap by riprapping and frames used in method
CN104711952A (en) * 2013-12-13 2015-06-17 上海勘测设计研究院 Closure gap protection structure applied to deep beach enclosure and closure method for closure gap protection structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619194A (en) * 2012-04-17 2012-08-01 上海市水利工程设计研究院 Method for closure of high-flow-rate closure gap by riprapping and frames used in method
CN104711952A (en) * 2013-12-13 2015-06-17 上海勘测设计研究院 Closure gap protection structure applied to deep beach enclosure and closure method for closure gap protection structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
王民寿: "《水利水电工程施工过程中的水流控制》", 31 December 1983, 成都科学技术大学,四川省水利发电工程学会施工专业委员会 *
陈德春等: "围海工程堵口合龙技术研究", 《河海大学学报(自然科学版)》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517835A (en) * 2018-06-08 2018-09-11 长江南京航道工程局 A kind of the protection structure and its closure method of unconventional storage capacity corral sea wall list Longkou
CN109975523A (en) * 2019-04-29 2019-07-05 华侨大学 A kind of compacting mud by explosion mudstone mixed layer engineering properties prediction technique
CN109975523B (en) * 2019-04-29 2021-06-29 华侨大学 Method for predicting engineering property of explosive silt-squeezing mixed layer
CN112900353A (en) * 2021-01-22 2021-06-04 长江勘测规划设计研究有限责任公司 River channel intercepting method and arrangement structure thereof
CN112900353B (en) * 2021-01-22 2021-10-15 长江勘测规划设计研究有限责任公司 River channel intercepting method and arrangement structure thereof

Similar Documents

Publication Publication Date Title
CN104653191B (en) A kind of method of earth pressure shield tunneling machine high efficient driving in rich water round gravel stratum
CN107090802A (en) A kind of construction method of batardeau on the sea closure
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN113094799B (en) Comprehensive control method for deformation of ultra-high core wall rock-fill dam
CN106939587A (en) A kind of power station major river bed river closure construction method
CN207919486U (en) A kind of deep water soft soil foundation quay wall structure
CN100516367C (en) Geotechnical soil-ballasted sack cofferdam for water piers of river-crossing bridge and its production method
CN108316236B (en) Dykes and dams suitable for large tidal range in reclamation engineering and multi-closure method thereof
CN111636450A (en) Construction method of high-pressure rotary-spraying impervious wall on gravel layer
CN112922616A (en) Method for controlling shield crossing construction
CN103806409A (en) Milling forming system of gravity wharf foundation bed and construction method for gravity wharf structure
CN114718585A (en) Shield construction method suitable for passing tidal lake downwards
CN110172970B (en) Jet grouting pile slurry supply pipeline capable of avoiding slurry backflow and slurry spraying method thereof
CN106192910A (en) A kind of earth and rockfill dam layer of sand earthquake liquefaction ballast ruggedized construction and method under water
CN206090478U (en) Embankment dam sand bed earthquake under water liquefaction ballast reinforced structure
CN214089677U (en) Upgrading and transforming structure of caisson wharf
CN111197300B (en) Earth-rock cofferdam back slope type seepage-proofing dam and reverse construction method
CN215165202U (en) High-efficient interim pier that combines gabion net and protect concrete certainly under water
CN212427144U (en) Prevent inclined wall geomembrane cofferdam surface protection structure of rockfall destruction
CN210315404U (en) Concrete block and U-shaped gabion apron filled with concrete block
Steele et al. Rockfill Dams: Salt Springs and Lower Bear River Concrete Face Dams
CN106400785A (en) Construction method for grouting by adopting highly spraying, drilling and grouting integrated machine
CN112854116A (en) Upgrading and transforming method for caisson wharf
KING et al. MAINTENANCE OF SOME RUBBLE BREAKWATERS. a/SCAPA FLOW CAUSEWAYS, 1945-50. b/ALDERNEY BREAKWATER. MARITIME & WATERWAYS ENGINEERING DIVISION.
CN116971791A (en) Under-pressure bin opening method suitable for deep-buried water-rich weak stratum by bin filling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170825

RJ01 Rejection of invention patent application after publication