CN107059940A - Close on the guard method of deep basal pit existing building shallow foundation - Google Patents

Close on the guard method of deep basal pit existing building shallow foundation Download PDF

Info

Publication number
CN107059940A
CN107059940A CN201710056238.XA CN201710056238A CN107059940A CN 107059940 A CN107059940 A CN 107059940A CN 201710056238 A CN201710056238 A CN 201710056238A CN 107059940 A CN107059940 A CN 107059940A
Authority
CN
China
Prior art keywords
existing building
foundation
deep
building
guard method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710056238.XA
Other languages
Chinese (zh)
Inventor
刘海云
宋文智
谭辉
陈东全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201710056238.XA priority Critical patent/CN107059940A/en
Publication of CN107059940A publication Critical patent/CN107059940A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/08Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil

Abstract

The present invention relates to building enclosure field, specifically a kind of guard method for closing on deep basal pit existing building shallow foundation;It is characterized in that:Including deep foundation pit support;Partition wall is set between deep foundation pit supporting structure and existing building shallow foundation;Two fluid grouting is carried out between partition wall and existing building;Building inclination is monitored.The protection to existing building shallow foundation so can be achieved by setting partition wall between deep basal pit and the shallow foundation of existing building and carrying out two fluid grouting in the present invention;Partition wall in this guard method can avoid influence of the land movement with sedimentation to building, and two fluid grouting can improve building shallow soil strength nearby, and then building basis is protected.

Description

Close on the guard method of deep basal pit existing building shallow foundation
Technical field
The present invention relates to building enclosure field, specifically a kind of protection side for closing on deep basal pit existing building shallow foundation Method.
Background technology
With the exploitation and a large amount of construction of skyscraper of urban underground space, deep-foundation pit engineering is emerged in multitude, its Scale and cutting depth are being continuously increased.Due to the limitation of a variety of conditions, many deep-foundation pit engineerings are located in intensive groups of building, its Middle part foundation ditch is close to the basis of existing building.The excavation of foundation ditch is not only related to the safety of foundation ditch in itself, and is related to The safety of its existing building being close to and normally use.If not protected to the basis of existing building, excavation of foundation pit Caused deformation has the differential settlement for causing in hole and closing on existing building basis very much, and then causes to close on existing building Tilt, ftracture, or even collapse, the safety of life and property to the people causes loss difficult to the appraisal.
The content of the invention
Deep basal pit existing building shallow foundation is closed on it is an object of the invention to overcome the deficiencies of the prior art and provide one kind Guard method, it can effectively protect the safety of surrounding deep foundation pit existing building.
In order to achieve the above object, the present invention is realized in:
A kind of guard method for closing on deep basal pit existing building shallow foundation, including
Step 1, deep foundation pit support:By design drawing requirement, deep foundation pit supporting structure is constructed;
Step 2, between deep foundation pit supporting structure and existing building shallow foundation partition wall is set:Using solid matter cast-in-situ bored pile As partition wall, the depth of cast-in-situ bored pile must be more than depth at least more than the 2m of deep foundation pit supporting structure;
Step 3, two fluid grouting is carried out between partition wall and existing building:Cement mortar is made using portland cement and water, Cement mortar and waterglass are admixed, the presetting period for controlling admixture is 0.5min ~ 1.5min;The mass ratio of admixture is:Silicon Acid salt cement:Water:Waterglass is 1:0.5:0.05;
Step 4, building inclination monitoring:In Excavation Process, sedimentation and inclination to closing on deep basal pit existing building It is monitored, if building inclination is excessive or Ramp rates increase, must stops excavating immediately.
The described guard method for closing on deep basal pit existing building shallow foundation, the strength grade of portland cement is 42.5。
The described guard method for closing on deep basal pit existing building shallow foundation, enters between partition wall and existing building The row of row one, two row or multi-row two fluid grouting.
The described guard method for closing on deep basal pit existing building shallow foundation, it is characterized in that:Cement mortar is mixed with waterglass With the one or more in middle addition flyash, slag, volcanic ash, its gross mass is no more than the 10% of cement quality.
The present invention between deep basal pit and the shallow foundation of existing building by setting partition wall and carrying out two fluid grouting, such as This can realize the protection to existing building shallow foundation;Partition wall in this guard method can avoid land movement with sedimentation to building The influence of thing is built, two fluid grouting can improve building shallow soil strength nearby, and then building basis is protected.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
A kind of guard method for closing on deep basal pit existing building shallow foundation, including
Step 1, deep foundation pit support:By design drawing requirement, deep foundation pit supporting structure is constructed;
Step 2, between deep foundation pit supporting structure and existing building shallow foundation partition wall is set:Using solid matter cast-in-situ bored pile As partition wall, the depth of cast-in-situ bored pile must be more than depth at least more than the 2m of deep foundation pit supporting structure;
Step 3, two fluid grouting is carried out between partition wall and existing building:Cement mortar is made using portland cement and water, Cement mortar and waterglass are admixed, the presetting period for controlling admixture is 0.5min ~ 1.5min;The mass ratio of admixture is:Silicon Acid salt cement:Water:Waterglass is 1:0.5:0.05;
Step 4, building inclination monitoring:In Excavation Process, sedimentation and inclination to closing on deep basal pit existing building It is monitored, if building inclination is excessive or Ramp rates increase, must stops excavating immediately.
The described guard method for closing on deep basal pit existing building shallow foundation, the strength grade of portland cement is 42.5。
The described guard method for closing on deep basal pit existing building shallow foundation, enters between partition wall and existing building The row of row one, two row or multi-row two fluid grouting.
The described guard method for closing on deep basal pit existing building shallow foundation, it is characterized in that:Cement mortar is mixed with waterglass With the one or more in middle addition flyash, slag, volcanic ash, its gross mass is no more than the 10% of cement quality.
The present invention between deep basal pit and the shallow foundation of existing building by setting partition wall and carrying out two fluid grouting, such as This can realize the protection to existing building shallow foundation;Partition wall in this guard method can avoid land movement with sedimentation to building The influence of thing is built, two fluid grouting can improve building shallow soil strength nearby, and then building basis is protected.

Claims (4)

1. a kind of guard method for closing on deep basal pit existing building shallow foundation, it is characterized in that:Including
Step 1, deep foundation pit support:By design drawing requirement, deep foundation pit supporting structure is constructed;
Step 2, between deep foundation pit supporting structure and existing building shallow foundation partition wall is set:Using solid matter cast-in-situ bored pile As partition wall, the depth of cast-in-situ bored pile must be more than depth at least more than the 2m of deep foundation pit supporting structure;
Step 3, two fluid grouting is carried out between partition wall and existing building:Cement mortar is made using portland cement and water, Cement mortar and waterglass are admixed, the presetting period for controlling admixture is 0.5min ~ 1.5min;The mass ratio of admixture is:Silicon Acid salt cement:Water:Waterglass is 1:0.5:0.05;
Step 4, building inclination monitoring:In Excavation Process, sedimentation and inclination to closing on deep basal pit existing building It is monitored, if building inclination is excessive or Ramp rates increase, must stops excavating immediately.
2. the guard method according to claim 1 for closing on deep basal pit existing building shallow foundation, it is characterized in that:Silicate The strength grade of cement is 42.5.
3. the guard method according to claim 1 for closing on deep basal pit existing building shallow foundation, it is characterized in that:In cut-off A row, two row or multi-row two fluid grouting are carried out between wall and existing building.
4. the guard method according to claim 1 for closing on deep basal pit existing building shallow foundation, it is characterized in that:Cement mortar The one or more added in being admixed with waterglass in flyash, slag, volcanic ash, its gross mass is no more than cement quality 10%。
CN201710056238.XA 2017-01-25 2017-01-25 Close on the guard method of deep basal pit existing building shallow foundation Pending CN107059940A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710056238.XA CN107059940A (en) 2017-01-25 2017-01-25 Close on the guard method of deep basal pit existing building shallow foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710056238.XA CN107059940A (en) 2017-01-25 2017-01-25 Close on the guard method of deep basal pit existing building shallow foundation

Publications (1)

Publication Number Publication Date
CN107059940A true CN107059940A (en) 2017-08-18

Family

ID=59598712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710056238.XA Pending CN107059940A (en) 2017-01-25 2017-01-25 Close on the guard method of deep basal pit existing building shallow foundation

Country Status (1)

Country Link
CN (1) CN107059940A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109837911A (en) * 2019-03-18 2019-06-04 辽宁工程技术大学 A method of Foundation Pit Support Design is carried out using two fluid grouting
CN111058454A (en) * 2019-11-29 2020-04-24 天津建岩岩土工程有限公司 Construction protection method on one side of existing building

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061697A (en) * 2010-11-25 2011-05-18 中铁六局集团有限公司广州分公司 Method for treating uneven settlement of building
CN102296631A (en) * 2011-05-31 2011-12-28 天津二十冶建设有限公司 Top-down construction method of cyclone well
CN103195069A (en) * 2013-04-01 2013-07-10 北京工业大学 Method for shoring prestressed double-row-pile strong-constraint deep foundation pit
CN104612160A (en) * 2014-11-18 2015-05-13 中大建设有限公司 Maintenance structure for foundation pit next to existing building and construction method
JP2015152348A (en) * 2014-02-12 2015-08-24 アズビル株式会社 Capacitance type pressure sensor
CN105649089A (en) * 2016-01-13 2016-06-08 江西博慧工程技术服务有限公司 Construction method for excavating foundation pit close to existing shallow foundation protection structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061697A (en) * 2010-11-25 2011-05-18 中铁六局集团有限公司广州分公司 Method for treating uneven settlement of building
CN102296631A (en) * 2011-05-31 2011-12-28 天津二十冶建设有限公司 Top-down construction method of cyclone well
CN103195069A (en) * 2013-04-01 2013-07-10 北京工业大学 Method for shoring prestressed double-row-pile strong-constraint deep foundation pit
JP2015152348A (en) * 2014-02-12 2015-08-24 アズビル株式会社 Capacitance type pressure sensor
CN104612160A (en) * 2014-11-18 2015-05-13 中大建设有限公司 Maintenance structure for foundation pit next to existing building and construction method
CN105649089A (en) * 2016-01-13 2016-06-08 江西博慧工程技术服务有限公司 Construction method for excavating foundation pit close to existing shallow foundation protection structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109837911A (en) * 2019-03-18 2019-06-04 辽宁工程技术大学 A method of Foundation Pit Support Design is carried out using two fluid grouting
CN109837911B (en) * 2019-03-18 2020-11-03 辽宁工程技术大学 Method for carrying out foundation pit supporting design by using double-liquid grouting
CN111058454A (en) * 2019-11-29 2020-04-24 天津建岩岩土工程有限公司 Construction protection method on one side of existing building

Similar Documents

Publication Publication Date Title
CN203256729U (en) Larson steel sheet pile containment device for open caisson construction
CN104027911A (en) Fire prevention method for coal gangue mountain
CN107059940A (en) Close on the guard method of deep basal pit existing building shallow foundation
CN110106883A (en) A kind of Real-time Feedback grouting method for correcting subway tunnel horizontal distortion
CN105862659B (en) High-frequency debris flow shore protection and diversion method
CN203463016U (en) Three-axle agitator drill suitable for piercing gravel layer soil
CN207047796U (en) A kind of light-duty mud-rock flow arch blocking dam
CN204825923U (en) Relay formula underground structure
CN204626474U (en) Strong stirring loosens soil stress release wall
CN107700434B (en) Arch-shaped grid type reinforced concrete debris flow blocking dam and construction method thereof
CN103790170A (en) Prefabricated concrete hollow framework slope protection structure
CN104631467B (en) The erection method of the L-type support replacement plate of deep excavation project
CN103866779B (en) A kind of construction method of sealing space enclosing structure of soft foundation building foundation pit
CN204940314U (en) A kind of bellend pressure reduction well and deep foundation ditch structure thereof
CN205688448U (en) A kind of foundation pit support device utilizing karst fragmented rock body to reinforce bearing
CN203755326U (en) Water stopping building envelope of soft soil foundation building foundation pit
CN203144914U (en) Urban canal-bridge-and-culvert structure
CN204881603U (en) Multi -functional deformation monitoring devices
CN102677671A (en) Construction method of precast pile in thick-slag-stone-layer field
CN112832307A (en) Dam foundation altered rock mass reinforcement treatment structure and construction method thereof
CN209194522U (en) A kind of anchor cable construction structure in easy collapse hole stratum
CN206512722U (en) A kind of enhanced Larsen steel plate pile supporting system
CN203174628U (en) Overhanging underground diaphragm wall
Ho et al. Jet grouting for the mitigation of excavation wall movements in glacial silts
CN104895099B (en) Water-stop curtain device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170818