CN107059902A - A kind of reusable steel boxed cofferdam structure and its construction method - Google Patents

A kind of reusable steel boxed cofferdam structure and its construction method Download PDF

Info

Publication number
CN107059902A
CN107059902A CN201710464376.1A CN201710464376A CN107059902A CN 107059902 A CN107059902 A CN 107059902A CN 201710464376 A CN201710464376 A CN 201710464376A CN 107059902 A CN107059902 A CN 107059902A
Authority
CN
China
Prior art keywords
section
steel
cofferdam
coxopodite
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710464376.1A
Other languages
Chinese (zh)
Other versions
CN107059902B (en
Inventor
向敏
张亚磊
李甜
杨从娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Tiedao University
Original Assignee
Shijiazhuang Tiedao University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Tiedao University filed Critical Shijiazhuang Tiedao University
Priority to CN201710464376.1A priority Critical patent/CN107059902B/en
Publication of CN107059902A publication Critical patent/CN107059902A/en
Application granted granted Critical
Publication of CN107059902B publication Critical patent/CN107059902B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere

Abstract

The invention discloses a kind of reusable steel boxed cofferdam structure and construction method, belong to technical field of bridge construction.The precast-boxed cofferdam is that inside and outside wallboard connects to form body structure by horizontal ring flat-plate and horizontal support, it is made up of coxopodite section and at least one epimerite section, the multiple locking nubs in each section point, vertical shifting board is set between per locking nub, be connected setting horizonal base plate in section bottom with coxopodite section, horizonal base plate perforate and conduit is set in each separation, pass through conduit and carry out coxopodite section nacelle filling concrete;First assembly coxopodite section during construction, under discharge water, symmetrical assembled next block successively, then successively other assembled sections to sinking to completing;Construction is completed, and wallboard inside and outside the section of cutting horizontal bottom plate bottom, upper several sections are floated, and segmented successively and locking nub is removed and floats up to completion.Simple in construction, reasonable in design, easy construction of the invention, can be used to different size piers and different water depth constructions by increasing and decreasing section number and symmetrical locking nub of removing, saves material, reduce construction cost.

Description

A kind of reusable steel boxed cofferdam structure and its construction method
Technical field
The present invention relates to technical field of bridge construction.
Background technology
Due to the superiority in terms of steel construction processing, transport, sinking conveniently, steel boxed cofferdam is applied more and more widely In the foundation construction of large-sized deep water bridge.Double-Wall Steel Boxed Cofferdam is a kind of cofferdam form of Bridges in Our Country technical staff invention, it The Jiujiang Bridge over Yangtse River seventies in last century is come across first, it is therefore intended that solve flood period construction problem and cofferdam is crossed big vast safety and asked Topic.For the cofferdam of other forms, Double-Wall Steel Boxed Cofferdam has the following advantages that:1. larger hydraulic pressure can be born so that flood The construction of water phase is possibly realized;2. Double-Wall Steel Boxed Cofferdam is rigidly big, can bear to pressure from inside to outside, security is higher;3. double-walled Steel cofferdam process is simple, and groundwork is exactly cofferdam spelling, inhales the clear base of mud convenient.It is fixed against and sets in field of engineering technology construction Meter, design always as much as possible meets economical under the premise of security applicability durability is met.
Difference pier cap size need to design different steel cofferdams at present, and steel cofferdam is mostly disposable, waste of materials, is led Cost increase is caused, it is therefore necessary to design a kind of new steel boxed cofferdam structure that can be reused.
The content of the invention
The technical problem to be solved in the present invention is that there is provided a kind of reusable steel for above-mentioned the deficiencies in the prior art Precast-boxed cofferdam structure and its construction method, this is simple in construction, reasonable in design, and stability is good, easy construction, by being divided into section Section, the method for locking nub, increase and decrease section number and the locking nub number symmetrically gone are to be applicable to various sizes of pier and different water Deep construction, it is not necessary to redesign a variety of steel boxed cofferdams, can reuse steel cofferdam locking nub in various sizes of pier, save material Material, reduces construction cost.
Common steel cofferdam of the prior art need to design sizes according to different pier caps, and be disposably to make mostly With, locking nub recycling is difficult, waste of materials and cause cost to increase.
In order to solve the above technical problems, the technical solution used in the present invention is:A kind of reusable steel jacket box encloses Weir structure, including outer wall panel and inwall panel, steel boxed cofferdam are that outer wall panel and inwall panel pass through horizontal support and water Flat ring plate connects to form body structure, and it includes stacking gradually the coxopodite section of connection and at least one epimerite from bottom to top Section, each section is divided into some locking nubs, and the locking nub of same section is highly equal, and vertical shifting board is provided between every locking nub, with The bottom of the connected section of coxopodite section is provided with the horizonal base plate of closing, each separation horizonal base plate perforate and sets concrete to lead Pipe, tremie enters coxopodite Duan Bi cabins through horizonal base plate.
Preferably, being provided with several vertical wallboard ribbed stiffeners on the inside of the outer wall panel and inwall panel.
It is further preferred that the steel boxed cofferdam internal water level land is provided with several inner support steel pipes.
Still more preferably, the agent structure of the steel boxed cofferdam is Q235B steel members;The outer wall panel and interior Wall board is 6 millimeters of steel plates, and horizontal support is 8 millimeters of angle steel, and horizontal ring flat-plate is 10 millimeters of steel plates, shifting board and horizonal base plate It is 10 millimeters of steel plates;Use and be welded to connect between per section and per locking nub.
It is a kind of to reuse the construction method of steel boxed cofferdam structure, comprise the following steps:
1)Steel boxed cofferdam is divided into some sections, is divided into some locking nubs per section, vertical shifting board is provided between every locking nub, Be connected with the coxopodite section bottom of section is provided with the horizonal base plate of closing, each separation horizonal base plate perforate and sets concrete Conduit, tremie enters coxopodite Duan Bi cabins through horizonal base plate, and coxopodite section nacelle concrete is carried out by tremie Perfusion;
2)First assembly coxopodite section during construction, under discharge water, coxopodite section fill concrete is poured to away from horizonal base plate and reserve coxopodite Section cofferdam cutting position, and water filling makes first layer epimerite sink in backward wall cabin;According to symmetrical assembled locking nub, connect high cofferdam, by The method of section sinking section, makes the epimerite positioned at first layer epimerite upper strata sink section by section, makes sinking of cofferdam to designed elevation;
3)After the completion of construction, the water filling into steel bushing tank wall cabin, in reserved cutting position cutting horizontal bottom plate bottom section inside and outside wall Plate, under water divider base section and first layer epimerite;Using the horizonal base plate of watertight, the water in a certain amount of wall cabin is extracted out by several times, control Water level in nacelle processed, making cofferdam, section floats section by section, splits locking nub along assembled weld seam, by assembled opposite sequence, is used for after trimming The construction of next pier.
Preferably, step 1)The described mode that steel boxed cofferdam is divided into some sections is that steel boxed cofferdam edge is high Degree direction is divided into some sections;Several locking nubs height divided per section is equal.
It is further preferred that step 2)Specific implementation method comprise the following steps:
1)Factory processes locking nub according to design requirement, is assemblied into section in pre-splicing place and is ready for construction after the assay was approved;
2)High steel cofferdam is followed by completing bored pile construction, and bracket is set on the water surface, building bracket on the outside of steel pile casting Platform is used for assembled coxopodite section cofferdam, and measurement rectification work is carried out simultaneously, it is ensured that every locking nub accurate positioning, make every locking nub level with Vertically;
3)In cofferdam construction, steel pile casting is slotted and interim hangar system is installed, after the completion of coxopodite section cofferdam is assembled, ox is cut off Leg platform, in being discharged water using hoist engine under coxopodite section, is carried out coxopodite section nacelle filling concrete by tremie, makes bottom Section sinking certain altitude, symmetrical assembly first layer epimerite, gradation casting concrete or into wall cabin water filling make first layer epimerite Sink, in the same way again successively other assembled sections to sinking to completing;The fill concrete of wherein coxopodite section is at most poured Stop to cutting position is reserved away from first layer epimerite horizonal base plate, water filling can then make into wall cabin under the continuation of first layer epimerite It is heavy.
Still more preferably, the scope of the reserved cutting position is 0.2~1 meter.
Still more preferably, the construction method is by increasing and decreasing the locking nub number of section number and symmetrical region, with suitable The construction of different size piers and the depth of water is answered, realizes that locking nub is reused;According to the cushion cap absolute altitude and cushion cap of each pier footing The actual (real) thickness adjustment coxopodite and the height of first layer epimerite of bottom sludge layer, assembled good steel boxed cofferdam have watertightness.
Still more preferably, the concrete is C30 grades of concrete.
It is using the beneficial effect produced by above-mentioned technical proposal:The present invention provides a kind of reusable steel jacket box Cofferdam structure and its construction method, this is simple in construction, reasonable in design, and stability is good, easy construction, by being divided into section, section The method of block, increase and decrease section number and the locking nub number symmetrically gone are to be applicable to applying for various sizes of pier and different water depth Work, it is not necessary to redesign a variety of steel boxed cofferdams, can reuse steel cofferdam locking nub in various sizes of pier, utilize second section The horizonal base plate of cofferdam watertight, by the buoyancy of water, makes the method that coxopodite top cofferdam is floated obtain coxopodite top cofferdam section With recycling, this steel boxed cofferdam structure and its construction method can save material, easy construction and reduction construction cost.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of another angle of the invention
In figure:1st, outer wall panel;2nd, inwall panel;3rd, wallboard ribbed stiffener;4th, horizontal support;5th, horizontal ring flat-plate;6th, shifting board;7、 Horizonal base plate;8th, tremie;9th, inner support steel pipe;10th, pier shaft;11st, cushion cap;12nd, drilled pile.
Embodiment
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description, it is clear that disclosed below Embodiment be only the present invention a part of embodiment, rather than whole embodiment.Based on embodiments of the invention, ability Domain those of ordinary skill is all to be made on the basis of technical scheme on the premise of creative work is not made Any modification, equivalent substitution and improvements etc., should be included within the scope of the present invention, belong to the scope of protection of the invention.
Embodiment 1
A kind of reusable steel boxed cofferdam structure, including outer wall panel and inwall panel, steel boxed cofferdam is by outside wall surface Box-like structure is formed by horizontal support 4 and the connection of horizontal ring flat-plate 5 between plate 1 and inwall panel 2;Steel boxed cofferdam is along height side To four sections are divided into, coxopodite section J1, second section J2, the 3rd section J3, fourth segment J4 are followed successively by from bottom to top, Ten locking nubs are divided into per section, symmetrically assembled by ten contour locking nubs, ten locking nubs are respectively A and A' areas, B and B' Area, C and C' areas, D and D' areas, E and E' areas, wherein, A areas are identical with A' plot structure blocks, and other blocks are also identical by that analogy; Per vertical shifting board 6 is provided between locking nub, the inner side of outer wall panel 1 and inwall panel 2 is provided with several vertical walls Plate ribbed stiffener 3, second section J2 bottom is provided with the horizonal base plate 7 of closing, each separation the perforate of horizonal base plate 7 and set Tremie 8, tremie 8 enters coxopodite J1 walls cabin through horizonal base plate 7, and steel boxed cofferdam is internally provided with several The inner support steel pipe 9 of level.
Herein it should be noted that the agent structure of the steel boxed cofferdam of the present invention uses steel matter, and steel matter It is Q235B;MAT'L specification meets《Carbon structural steels》(GB1700-2006)Requirement, it is used in this construction method The grade of concrete be C30;Outer wall panel 1 and inwall panel 2 are using 6 millimeters of steel plates, and wallboard ribbed stiffener 3 is ∠ 75x50x8mm angle steel, horizontal support 4 uses ∠ 75x75x8mm angle steel, and horizontal ring flat-plate 5 uses 250mm(It is wide)x10mm(It is thick)Steel Plate, shifting board 6 and second section J2 horizonal base plates 7 use 10mm steel plates, and set three layers of well word support altogether, and three layers of well word support use φ 630*10mm steel pipes, the power transmission of steel pipe is completed using force transmission rack, wherein, per section, connected mode uses weldering between every locking nub Connect in succession.
The construction method of above-mentioned reusable steel boxed cofferdam structure, specifically includes following steps:
In design, comprehensive various situations, first investigation obtain pier job location geological hydrology and construction drawing, according to investigation As a result section quantity and size are reasonably divided, cofferdam is designed and produced according to different pier sizes and the depth of water, by cofferdam along highly Direction classifying rationally is four sections, and ten contour locking nubs are divided into per section, per locking nub between shifting board 6 is set, the Two section J2 cofferdam bottoms set the horizonal base plate 7 of closing, and horizonal base plate 7 reserves the passage of tremie 8, assembled good steel cofferdam Should integrally have watertightness;Design requirement machining cell block is pressed by factory, and in pre-splicing place, assembly is constructed after the assay was approved;Adopt The inwall panel 2 of each locking nub, outer wall panel 1 are connected to form casing by horizontal ring flat-plate 5 and horizontal support 4 with welding manner Structure;Vertical wallboard ribbed stiffener 3 and shifting board 6 is welded on the wallboard of each locking nub, and requires watertight.
During cofferdam construction, complete after drilled pile construction, connect high steel pile casting, bracket is set on the outside of steel pile casting on the water surface, Coxopodite platform for lining is built, first in the assembled coxopodite section J1 cofferdam of platform, measurement rectification work is carried out simultaneously, it is ensured that locking nub is positioned Accurately, locking nub abswolute level is made and vertical;Steel pile casting is slotted and interim hangar system is installed, interim corbels support is cut off and puts down Platform, in being discharged water using hoist engine under coxopodite section J1, is carried out coxopodite section J1 nacelle filling concretes by tremie 8, made Coxopodite section J1 sinking certain altitudes, symmetrical assembly second section J2, calculate the amount of pouring of coxopodite section J1 concrete, at most make coxopodite Section J1 fill concretes are poured to when reserving 0.5 meter of coxopodite section J1 cofferdam cutting position away from second section J2 cofferdam horizonal base plate 7 Stop, then water filling second section J2 cofferdam can be made to continue to sink into wall cabin;According to symmetrical assembled locking nub, connect high cofferdam, by The method of section sinking section, makes the 3rd section J3, fourth segment J4 sink section by section, makes sinking of cofferdam to designed elevation;Inhaled Mud sinks, blocked, sand bedding course is filled, pour bottom concrete, installation inner support of drawing water steel pipe 9, clear base, steel pile casting are cut off, stake The construction for process that head is cut, pier is poured etc..
After the completion of construction, to prevent the floating for cutting off cofferdam after coxopodite J1 highly excessive, the water filling into steel bushing tank wall cabin, Wallboard inside and outside coxopodite section J1 under reserved cutting position imderwater cutting horizonal base plate;Divider base section J1 and second section under water J2;Using the horizonal base plate 7 of the second section J2 bottoms of watertight, extract out by several times in the water in a certain amount of wall cabin, control cabinet body Water level, makes fourth segment J4 cofferdam float, and splits locking nub along assembled weld seam, by assembled opposite sequence, in the same way, makes to enclose Section floats section by section on weir, splits locking nub along assembled weld seam, by assembled opposite sequence, the construction of next pier is used for after trimming
Wherein it should be noted that in design, comprehensive various situations, first investigation obtain pier job location geological hydrology with And construction drawing, section quantity and size are reasonably divided according to investigation result, is drawn according to the different Sizes of 10 cushion cap of bridge pier 11 Merogenesis block length and height, symmetrically divide locking nub according to section size reasonable, make the change of the increase and decrease corresponding depth of section, make The change of the various pier sizes of increase and decrease correspondence of locking nub.
Herein it should be noted that the steel bushing box structure of the present invention is applied to the construction of underwater support table 11, according to each The height of the absolute altitude of cushion cap 11 of pier footing and the actual (real) thickness adjustment coxopodite section J1 and second section J2 of the bottom sludge of cushion cap 11 layer Spend to adapt to the constructions of different size piers and the depth of water, can also by increase and decrease the steel boxed cofferdam locking nub number water in B and B' areas with The construction of different size piers and the depth of water is adapted to, realizes that locking nub is reused.
It should be noted that wall cabin planted agent keeps certain water level in work progress, its height is according to bottom concrete top Depending on absolute altitude and water level elevation, in principle in both intermediate ranges;The water filling into cofferdam and in nacelle if necessary, keeps reasonable Inside and outside head difference;Shifting board alignment above and below being required in assembly, the alignment of adjacent level ring flat-plate, vertical ribs 3 allows not up and down Alignment, but must be welded with horizontal ring flat-plate 5, welding quality all should meet requirement, and wallboard, separation plate welding seams must be oozed by kerosene Saturating experimental check, inside and outside wall steel plate edge joint position pastes weldering using 0.3x0.15m@0.5m pasting boards, and pasting board and wallboard require full weld, and protect Demonstrate,prove watertightness.
It can further be stated that all whole steel, welding rods used etc. in the steel bushing box structure and construction method of the present invention Main material all should meet the requirement of design document and current standard and have product certificate, otherwise should carry out mechanics, chemistry And weldability test;Steel surface used answers smooth bright and clean, finds the defect of influence intensity and deformation, should abrogate and use;Steel bushing Before case is started from, workmen should be familiar with and check whole drawings, draw craft exploded view etc., using appropriate welding procedure And welding parameter;Making required precision all should be met by making the workbench in place, flatness;Steel jacket box piecemeal is made after one, Answer measuring unit product overall dimension, it is errorless on inspection after, then make second, two blocks through examination it is assembled it is qualified after, can criticize Amount production;Steel jacket box builds connection using welding, and when welding processing component is manufactured, process unit should formulate severe action, excellent Change construction technology, reduce component machining deformation, reduce weld residual stress, deformation occur should correct in time;Weld seam intersection, must The processing that must adopt an effective measure prevents stress concentration;During Member Welding spreading, process unit must in strict accordance with construction drawing and Corresponding evaluation of engineering quality standard and manufacture of steel structure quality control standards (QCS) strict implement;Wallboard requires watertight with shifting board, Weld seam should carry out watertightness inspection.Each unit(Segmentation)Manufactured on moulding bed, each several part foozle ± 5mm, it is ensured that structure Assembled size and welding quality;Postwelding should be corrected, according to《Structural steelwork and acceptance specification》Inspected for acceptance, and carried For welding procedure quality examination report;Steel jacket box completes be delivered for use before, manufacturer should provide detailed self-inspection data, Quality inspection personnel, workmen and designer's reply casing endure strict scrutiny examinations, can be come into operation after signing in many ways;It is flat Face size:Steel cofferdam inner side wall plate is cushion cap template, should strictly control inner side wall plate size, its size should be with design requirement phase Symbol.The length allowable error of length and width both direction is respectively ± 20mm, and inner side wall plate surface irregularity should be less than 0.5mm;Steel plate Blanking should use plate shearing machine or surface trimming, and jigsaw weld root catching groove welding, butt weld will ensure through welding;Steel cofferdam plus Work manufacture will select the producer for meeting regulation qualification of technology and experience;Weld bead height should weld enough by design size, ribbed stiffener It is bilateral intermittent weld 75 between wallboard(150)Mm, i.e. fusion length 150mm, disconnect 75mm, and both sides interlock welding, weld seam height Spend 6mm;It is bilateral sequential welding, weld bead height 8mm between the ring flat-plate of horizontal support, the backing plate of shifting board and wallboard;Horizontal support Angle steel uses three face weld all arounds with ring flat-plate, and Size of welds takes 8mm, and limb backweld length is no less than 130mm, and acropodium weld seam length is no less than 60mm, the welding of remaining each component uses sequential welding, and weld bead height is 1.2 times of thickness of slab, and butt weld requires through welding;It is each to spell Fill unit(Segmentation)Hanger, by manufactory according to each lifting unit weight designed, designed process;Steel jacket box is fabricated: Carry out, transported after the completion of manufacture to scene in factory, transportation ensures that casing block part is indeformable and does not sustain damage, constructed Due to other factors local damage and breakage occur for Cheng Zhong, steel jacket box, answer timely remediation.
In a word, the present invention it is simple in construction, reasonable in design, stability is good, by be divided into section, locking nub method, increase and decrease Section number and the locking nub number symmetrically gone are to be applicable to the construction of various sizes of pier and different water depth, it is not necessary to redesigned A variety of steel boxed cofferdams, can reuse steel cofferdam locking nub in various sizes of pier, utilize the level of second section cofferdam watertight Bottom plate, by the buoyancy of water, enables the method that coxopodite top cofferdam is floated to make the cofferdam section recycling of coxopodite top, this Steel boxed cofferdam structure and its construction method can save material, easy construction and reduction construction cost.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or using the present invention, A variety of modifications to the present embodiment will be apparent for those skilled in the art, those skilled in the art's root Go out the product of other structures according to the principle design of the present invention, belong to protection scope of the present invention, the present invention will not be limited In embodiment illustrated herein, and it is to fit to the most wide scope consistent with features of novelty with principles disclosed herein.

Claims (10)

1. a kind of reusable steel boxed cofferdam structure, including outer wall panel(1)With inwall panel(2), it is characterised in that: The steel boxed cofferdam is outer wall panel(1)With inwall panel(2)Pass through horizontal support(4)With horizontal ring flat-plate(5)Connection is formed Body structure, it includes stacking gradually the coxopodite section of connection from bottom to top(J1)And at least one epimerite section, each section It is divided into some locking nubs, the locking nub of same section is highly equal, vertical shifting board is provided between every locking nub(6), the coxopodite section (11)Top be provided with reserved cutting position, with coxopodite section(J1)The bottom of connected section is provided with the horizonal base plate of closing (7), horizonal base plate in each separation(7)Perforate simultaneously sets tremie(8), tremie(8)Through horizonal base plate(7) Into coxopodite section(J1)Wall cabin.
2. a kind of reusable steel boxed cofferdam structure according to claim 1, it is characterised in that:The outside wall surface Plate(1)With inwall panel(2)Inner side be provided with several vertical wallboard ribbed stiffeners(3).
3. a kind of reusable steel boxed cofferdam structure according to claim 1, it is characterised in that:The steel jacket box Cofferdam internal water level land is provided with several inner support steel pipes(9).
4. a kind of reusable steel boxed cofferdam structure according to claim 1, it is characterised in that:The steel jacket box The agent structure in cofferdam is Q235B steel members;The outer wall panel(1)With inwall panel(2)It is 6 millimeters of steel plates, level branch Support(4)For 8 millimeters of angle steel, horizontal ring flat-plate(5)For 10 millimeters of steel plates, shifting board(6)And horizonal base plate(7)It is 10 millimeters of steel Plate;Use and be welded to connect between per section and per locking nub.
5. a kind of construction method of reusable steel boxed cofferdam structure according to claim 1, it is characterised in that Comprise the following steps:
1)Steel boxed cofferdam is divided into some sections, is divided into some locking nubs per section, vertical shifting board is provided between every locking nub (6), with coxopodite section(J1)The bottom of connected section is provided with the horizonal base plate of closing(7), horizonal base plate in each separation(7)Open Hole simultaneously sets tremie(8), tremie(8)Through horizonal base plate(7)Into coxopodite section(J1)Wall cabin, passes through coagulation Native conduit(8)Carry out coxopodite section(J1)Nacelle filling concrete;
2)First assembly coxopodite section during construction(J1), under discharge water, make coxopodite section(J1)Fill concrete is poured to away from horizonal base plate (7)With coxopodite section(J1)Reserved cutting position, and water filling makes first layer epimerite sink in backward wall cabin;According to symmetrical assembled section Block, high cofferdam, the method for piecewise sinking section are connect, the epimerite positioned at first layer epimerite upper strata is sunk section by section, make sinking of cofferdam To designed elevation;
3)After the completion of construction, the water filling into steel bushing tank wall cabin, in reserved cutting position cutting horizontal bottom plate(7)Inside and outside the section of bottom Wallboard, under water divider base section(J1)With first layer epimerite;Utilize the horizonal base plate of watertight(7), extract a certain amount of wall cabin out by several times Water level in interior water, control cabinet body, making cofferdam, section is floated section by section, and locking nub is split along assembled weld seam, by assembled opposite sequence, whole It is used for the construction of next pier after repairing.
6. a kind of construction method of reusable steel boxed cofferdam structure according to claim 5, it is characterised in that: Step 1)The described mode that steel boxed cofferdam is divided into some sections is that along short transverse steel boxed cofferdam is divided into some sections Section;Several locking nubs height divided per section is equal.
7. a kind of construction method of reusable steel boxed cofferdam structure according to claim 5, it is characterised in that: Step 2)Specific implementation method comprise the following steps:
Factory processes locking nub according to design requirement, is assemblied into section in pre-splicing place and is ready for construction after the assay was approved;
High steel cofferdam is followed by completing bored pile construction, sets bracket flat on the water surface, building bracket on the outside of steel pile casting Platform is used for assembled coxopodite section(J1)Cofferdam, measurement rectification work is carried out simultaneously, it is ensured that per locking nub accurate positioning, make every locking nub level With it is vertical;
In cofferdam construction, steel pile casting is slotted and interim hangar system is installed, coxopodite section(J1)After the completion of cofferdam is assembled, cut off Bracket platform, using hoist engine by coxopodite section(J1)Under discharge water, pass through tremie(8)Carry out coxopodite section(J1)Nacelle is mixed Solidifying soil perfusion, makes coxopodite section(J1)Sinking certain altitude, symmetrical assembly first layer epimerite, gradation casting concrete or into wall cabin Water filling makes first layer epimerite sink, in the same way again successively other assembled sections to sinking to completing;Wherein coxopodite section(J1) Fill concrete at most pour to away from first layer epimerite horizonal base plate(7)Reserved cutting position stops, then can be into wall cabin Water filling makes first layer epimerite continue to sink.
8. a kind of construction method of reusable steel boxed cofferdam structure according to claim 5, it is characterised in that: The scope of the reserved cutting position is 0.2~1 meter.
9. a kind of construction method of reusable steel boxed cofferdam structure according to claim 5, it is characterised in that: The construction method is by increasing and decreasing the locking nub number of section number and symmetrical region, to adapt to applying for different size piers and the depth of water Work, realizes that locking nub is reused;According to the actual (real) thickness adjustment of the cushion cap absolute altitude of each pier footing and cushion cap bottom sludge layer Coxopodite(J1)With the height of first layer epimerite, assembled good steel boxed cofferdam has watertightness.
10. a kind of construction method of reusable steel boxed cofferdam structure according to claim 5, its feature exists In:The concrete is C30 grades of concrete.
CN201710464376.1A 2017-06-19 2017-06-19 Construction method of reusable steel pouring jacket cofferdam structure Active CN107059902B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710464376.1A CN107059902B (en) 2017-06-19 2017-06-19 Construction method of reusable steel pouring jacket cofferdam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710464376.1A CN107059902B (en) 2017-06-19 2017-06-19 Construction method of reusable steel pouring jacket cofferdam structure

Publications (2)

Publication Number Publication Date
CN107059902A true CN107059902A (en) 2017-08-18
CN107059902B CN107059902B (en) 2022-08-23

Family

ID=59594668

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710464376.1A Active CN107059902B (en) 2017-06-19 2017-06-19 Construction method of reusable steel pouring jacket cofferdam structure

Country Status (1)

Country Link
CN (1) CN107059902B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108342993A (en) * 2018-02-26 2018-07-31 利越集团有限公司 A kind of underwater support table suspention support platform and its construction
CN109295858A (en) * 2018-10-12 2019-02-01 中铁宝桥(扬州)有限公司 The overall package moulding bed and its working method of a kind of double-walled combination bridge tower steel shell segment
CN109371997A (en) * 2018-12-04 2019-02-22 中铁六局集团有限公司 A kind of double-wall cofferdam and pier construction method
CN110130372A (en) * 2019-05-31 2019-08-16 中建八局第四建设有限公司 A kind of construction method in prestress anchorage cable cofferdam
CN110878556A (en) * 2019-11-08 2020-03-13 中铁大桥局集团有限公司 Construction method of deepwater cofferdam
CN113309121A (en) * 2021-04-27 2021-08-27 中交一公局第八工程有限公司 Construction process of floating-state high-double-wall steel box cofferdam for large-volume foundation in deep water
CN113550340A (en) * 2021-07-23 2021-10-26 广州市市政工程机械施工有限公司 Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN113585344A (en) * 2021-08-10 2021-11-02 中船黄埔文冲船舶有限公司 Immersed tunnel steel shell pipe joint bulkhead control method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101368389A (en) * 2008-09-24 2009-02-18 中铁大桥局集团第五工程有限公司 Single and double-wall combined steel cofferdam construction method and its single and double-wall combined steel cofferdam
CN201372439Y (en) * 2008-09-24 2009-12-30 中铁大桥局集团第五工程有限公司 Single-wall and double-wall combined steel cofferdam
CN201713824U (en) * 2010-06-22 2011-01-19 中交武汉港湾工程设计研究院有限公司 Detachable reusable double-wall steel cofferdam
CN202359566U (en) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 Cofferdam for deep-water soft soil foundation construction of bridge
CN102644290A (en) * 2012-05-14 2012-08-22 中国十九冶集团有限公司 Steel cofferdam construction method suitable for deep silt-layer bridge construction in shallow sea area
CN202689015U (en) * 2012-07-12 2013-01-23 中铁二十局集团第一工程有限公司 Double-wall steel cofferdam for high-span prestressed concrete continuous beam deep water pier construction
CN103835300A (en) * 2014-01-22 2014-06-04 中铁大桥局集团第五工程有限公司 Inner-support-free double-wall locking mouth steel bushing box cofferdam construction method and cofferdam
CN206829158U (en) * 2017-06-19 2018-01-02 石家庄铁道大学 A kind of reusable steel boxed cofferdam structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101368389A (en) * 2008-09-24 2009-02-18 中铁大桥局集团第五工程有限公司 Single and double-wall combined steel cofferdam construction method and its single and double-wall combined steel cofferdam
CN201372439Y (en) * 2008-09-24 2009-12-30 中铁大桥局集团第五工程有限公司 Single-wall and double-wall combined steel cofferdam
CN201713824U (en) * 2010-06-22 2011-01-19 中交武汉港湾工程设计研究院有限公司 Detachable reusable double-wall steel cofferdam
CN202359566U (en) * 2011-12-13 2012-08-01 中交第二公路工程局有限公司 Cofferdam for deep-water soft soil foundation construction of bridge
CN102644290A (en) * 2012-05-14 2012-08-22 中国十九冶集团有限公司 Steel cofferdam construction method suitable for deep silt-layer bridge construction in shallow sea area
CN202689015U (en) * 2012-07-12 2013-01-23 中铁二十局集团第一工程有限公司 Double-wall steel cofferdam for high-span prestressed concrete continuous beam deep water pier construction
CN103835300A (en) * 2014-01-22 2014-06-04 中铁大桥局集团第五工程有限公司 Inner-support-free double-wall locking mouth steel bushing box cofferdam construction method and cofferdam
CN206829158U (en) * 2017-06-19 2018-01-02 石家庄铁道大学 A kind of reusable steel boxed cofferdam structure

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108342993A (en) * 2018-02-26 2018-07-31 利越集团有限公司 A kind of underwater support table suspention support platform and its construction
CN109295858A (en) * 2018-10-12 2019-02-01 中铁宝桥(扬州)有限公司 The overall package moulding bed and its working method of a kind of double-walled combination bridge tower steel shell segment
CN109295858B (en) * 2018-10-12 2023-11-28 中铁宝桥(扬州)有限公司 Integral assembly jig frame for steel shell sections of double-wall combined bridge tower and working method thereof
CN109371997A (en) * 2018-12-04 2019-02-22 中铁六局集团有限公司 A kind of double-wall cofferdam and pier construction method
CN110130372A (en) * 2019-05-31 2019-08-16 中建八局第四建设有限公司 A kind of construction method in prestress anchorage cable cofferdam
CN110878556A (en) * 2019-11-08 2020-03-13 中铁大桥局集团有限公司 Construction method of deepwater cofferdam
CN110878556B (en) * 2019-11-08 2021-07-20 中铁大桥局集团有限公司 Construction method of deepwater cofferdam
CN113309121A (en) * 2021-04-27 2021-08-27 中交一公局第八工程有限公司 Construction process of floating-state high-double-wall steel box cofferdam for large-volume foundation in deep water
CN113550340A (en) * 2021-07-23 2021-10-26 广州市市政工程机械施工有限公司 Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN113585344A (en) * 2021-08-10 2021-11-02 中船黄埔文冲船舶有限公司 Immersed tunnel steel shell pipe joint bulkhead control method

Also Published As

Publication number Publication date
CN107059902B (en) 2022-08-23

Similar Documents

Publication Publication Date Title
CN107059902A (en) A kind of reusable steel boxed cofferdam structure and its construction method
CN101886396B (en) Construction method for special-shaped steel cofferdam
CN104532813B (en) A kind of aquatic building operation platform and erection method, using method
CN109680677A (en) A kind of construction of diaphragm wall technique
CN109629455A (en) The construction method of highway reconstruction bridge
CN206829158U (en) A kind of reusable steel boxed cofferdam structure
CN106836191A (en) The construction method of subway building enclosure ground-connecting-wall under a kind of low clearance
CN108797569A (en) A kind of control method that drilled pile novel energy-conserving pile crown is superfilled
CN109371997A (en) A kind of double-wall cofferdam and pier construction method
CN111980020A (en) Construction method of double-wall steel suspension box cofferdam of main bridge bearing platform of super-large bridge
CN110924307A (en) Trestle construction method for bare rock geology
CN106812144A (en) Double-wall steel cofferdam construction method
CN107152032A (en) The template system and the construction method of cushion cap of a kind of bearing platform construction for offshore wind farm
CN104805857A (en) Detachable cyclic utilization bottomless steel jacket box and construction method thereof
CN109853531A (en) A kind of pile foundation construction process of cast-in-situ bored pile
CN103015442B (en) Method for constructing split type cofferdam
CN103938638A (en) Buoy type deepwater single-wall steel cofferdam construction method
CN103692095B (en) Large-scale single disc-type External floating roof tank construction method of installation
CN110607797A (en) Underwater construction method for water taking head
CN106223355A (en) A kind of high bearing platform supported on piles in deep water Hold Hoop method has device and the construction method of end steel jacket box
CN105040992B (en) Reverse inverted-insertion type construction method for structural steel columns
CN207260295U (en) A kind of steel caisson template for being used for underwater big permeable geology drainage inspection well and pouring
CN204608812U (en) One detachably recycles bottomless steel jacket box
CN206721913U (en) Template system for the bearing platform construction of offshore wind farm
CN108677978A (en) A kind of bridge prestressing without bondn splicing Double-Wall Steel Boxed Cofferdam sinking construction engineering method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Xiang Min

Inventor after: Zhang Zixiao

Inventor after: Li Xuezhou

Inventor after: Zhang Rongbiao

Inventor after: Yang Hui

Inventor after: Yang Congjuan

Inventor after: Zhang Yalei

Inventor after: Li Tian

Inventor before: Xiang Min

Inventor before: Zhang Yalei

Inventor before: Li Tian

Inventor before: Yang Congjuan

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant