CN107058657B - A kind of central throat tube and its replacing options of blast furnace roof - Google Patents

A kind of central throat tube and its replacing options of blast furnace roof Download PDF

Info

Publication number
CN107058657B
CN107058657B CN201710463652.2A CN201710463652A CN107058657B CN 107058657 B CN107058657 B CN 107058657B CN 201710463652 A CN201710463652 A CN 201710463652A CN 107058657 B CN107058657 B CN 107058657B
Authority
CN
China
Prior art keywords
jam
central throat
throat tube
boss
lower clamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710463652.2A
Other languages
Chinese (zh)
Other versions
CN107058657A (en
Inventor
张文凤
刘斌奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wisdri Engineering and Research Incorporation Ltd
Original Assignee
Wisdri Engineering and Research Incorporation Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wisdri Engineering and Research Incorporation Ltd filed Critical Wisdri Engineering and Research Incorporation Ltd
Priority to CN201710463652.2A priority Critical patent/CN107058657B/en
Publication of CN107058657A publication Critical patent/CN107058657A/en
Application granted granted Critical
Publication of CN107058657B publication Critical patent/CN107058657B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21BMANUFACTURE OF IRON OR STEEL
    • C21B7/00Blast furnaces

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)
  • Blast Furnaces (AREA)

Abstract

The invention discloses a kind of central throat tube of blast furnace roof and its replacing options, jam lower clamping ring be fixed on distributing device it is suitable for reading on, central throat tube trunnion ontology is put into opposite with distributor chute in distributing device, pressing ring in jam lower clamping ring and jam is mutually fixed by boss.The overhanging boss of pressing ring can pass through the groove gap between the two neighboring boss of jam lower clamping ring in jam;Lifting lug is set on the overhanging boss of pressing ring in jam, amounts at least four lifting lugs of setting.It is used in the handover of 2 groups of entire replacement process totally 4 lifting lugs primary.Without promoting central throat tube at lower sealing valve maintenance door, directly central throat tube can be dropped to close at distributor chute without cutting upper pressing ring.Reach central throat tube replacement speed faster, saves human and material resources, the high purpose of safety coefficient.

Description

A kind of central throat tube and its replacing options of blast furnace roof
Technical field
The invention belongs to metallurgy high furnace furnace top equipment technical field, in particular to the central throat tube of a kind of blast furnace roof and its Replacing options.
Background technique
In furnace roof gear-box inside center, main function is to prevent iron-smelting raw material directly and in gear-box for central throat tube position Shell contact, prevents gear-box worn out, and gas leakage and gear structure inside is caused to damage.Central throat tube is iron-smelting raw material from batch can to furnace Interior unique passage, the erosion by the impact wear of iron-smelting raw material and furnace roof high temperature, abrasion loss are larger for a long time.According to its use Period needs that adequate measures and method is taken to safeguard and replace central throat tube.
Before of the invention propose, the structure type of central throat tube mainly uses to be added in pressing ring welding outer barrel and cylinder The form of wear-resistant liner.The central throat tube for adopting the structure design generally uses two kinds of replacing options: one is, remove center Lower clack box above trunnion hangs out central throat tube, and it is bothersome laborious to remove lower clack box, it is also desirable to by related hydraulic tube, lubrication management It is removed with tracheae, returning dress, there is also difficulty, can reduce relevant apparatus performance, it is therefore desirable to sizable workload, the people of consuming Power is more, the time is also longer, and security risk is also more.
Another is in Chinese public patent application CN103571987A " the central throat tube replacing options of blast furnace roof " Used method takes out 3 top wear-resistant liner of central throat tube as shown in Figure 1, being first turned on down close 1 two sides maintenance door of clack box, 3 vertical centred position of central throat tube welds lifting lug in close clack box 1 under, is sling central throat tube 3 with chain block 2, will thereon The pressing ring in portion is cut into three sections and takes out, and loosens chain block 2, central throat tube 3 is hoisted to the cloth being vertically arranged out of furnace and is slipped At slot 4, then notify operative employee change distributor chute 4 turning angle to 75 degree (i.e. change distributor chute turning angle extremely At the big square hole of furnace roof), furnace roof driving 5 hooks mouth under central throat tube 3 with sharing suspension hook, discharges jack on one side, gradually slips to cloth Moved below slot 4, penetrate wirerope and tie central throat tube 3, and using furnace roof driving 5 by chain block 2 by central throat tube 3 from It is hung at the big square hole 6 of furnace roof.Present invention replacement speed is fast, uses manpower and material resources sparingly, and safety coefficient is high.In the process, need into Row cutting operation, it is time-consuming bothersome, in addition, distributor chute length is longer, penetrates wirerope and bottle up central throat tube, it is not easy to operate, such as If saving the process that cutting is taken out fixed ring and reeved, it will become more convenient for replacement central throat tube, operate The danger of personnel can also lower.
Summary of the invention
The technical problem to be solved by the present invention is to, the central throat tube and its replacing options of a kind of blast furnace roof are provided, with gram The defect for taking the prior art reaches central throat tube replacement speed faster, saves human and material resources, the high purpose of safety coefficient.
In order to solve the above technical problems, the present invention adopts the following technical scheme:
A kind of central throat tube of blast furnace roof mainly includes outer barrel, support sleeve and wear-resistant liner, it is characterised in that: The wear-resistant liner is divided into the first wear-resistant liner, the second wear-resistant liner, third wear-resistant liner, and three kinds of wear-resistant liners are hollow convex Mesa-shaped cylinder and be that major diameter one end is arranged upward;Multiple support sleeves, multiple thirds are successively stacked in outer barrel from the bottom to top Wear-resistant liner is overlapped is fixed in support sleeve up and down, further includes pressing ring in mutually matched jam lower clamping ring and jam, first is resistance to Mill lining plate and the second wear-resistant liner are from top to bottom stacked and upper limb is all fixed in jam on pressing ring;Pressing ring outer rim is set in jam Set the multiple overhanging boss stretched out toward center of circle opposite direction, multiple overhanging circumferentially spaced distributions of boss;Jam lower clamping ring Along the circumferential direction toward center of circle interior direction it is uniformly distributed in stretch boss, both pressing rings boss number and arrangement on jam lower clamping ring and jam Angle is consistent, and pressing ring in jam lower clamping ring and jam is mutually fixed by boss;And pressing ring is overhanging convex in jam Platform can pass through the groove gap between the two neighboring boss of jam lower clamping ring;Lifting lug is set on the overhanging boss of pressing ring in jam, At least four lifting lugs of total setting.
Further, pressing ring diameter dimension in jam lower clamping ring and jam are as follows: So that jam lower clamping ring and card Hanging up pressing ring can mutually be fixed by boss;And pressing ring is both respective two neighboring boss in jam lower clamping ring and jam Between groove gap angle [alpha] be greater than the angle beta of boss itself, enable the overhanging boss of pressing ring in jam to pass through jam lower clamping ring Groove gap between two neighboring boss.
Further, the upright projection of both pressing ring and lifting lug is included in outer barrel in jam, so that pressing ring in jam Central throat tube ontology is constituted with outer barrel inner part.
Further, jam lower clamping ring be fixed on distributing device it is suitable for reading on, central throat tube trunnion ontology is put into distributing device In it is opposite with distributor chute, pressing ring in jam lower clamping ring and jam is mutually fixed by boss.
Further, multiple third wear-resistant liner overlappings are welded in support sleeve, and use bayonet lock with hole is made in circumferencial direction Spot welding after fixation.
Further, when needing replacing central throat tube, the turning angle of distributor chute is first adjusted to maximum position, is rotated Distributor chute makes it just towards burner maintenance door;Then chain hoist at the top of batch can is installed at the top of batch can, it is successively close under The wear-resistant liner taken out in the expansion bellows being located above central throat tube ontology is sealed in valve maintenance door;Chain type at the top of batch can is risen Two chain slings of heavy-duty machine are hung on axisymmetric 2 lifting lugs of central throat tube ontology, slightly lift central throat tube ontology, at this time except card The central throat tube ontology hung outside lower clamping ring is all raised;
Central throat tube ontology is rotated horizontally into set angle and reduces chain sling, so that the overhanging boss of pressing ring passes through in jam The groove gap formed between boss is stretched in jam lower clamping ring, by the uni-drive gear box of blast furnace by central throat tube ontology from cloth It is decreased until and reaches close to distributor chute in device, observed by burner maintenance door;
The outer chain hoist of burner maintenance door on the outside of burner maintenance door is reused, central throat tube ontology feeding tank deck is hooked Portion's chain hoist chain sling loosens chain hoist chain sling at the top of batch can and shortens hanging for the outer chain hoist of burner maintenance door Central throat tube is pulled to burner maintenance door by chain, until that can be hooked to two chain slings of chain hoist outside burner maintenance door separately On outer two axial symmetry lifting lugs;Two chain slings of chain hoist at the top of batch can are unclamped, with outside the burner maintenance door outside burner Two chains of chain hoist draw central throat tubes, until central throat tube is located at the outside of burner maintenance door, removes hang over lifting lug at this time On batch can at the top of chain hoist chain sling, using chain hoist outside the burner maintenance door on the outside of burner maintenance door by center Trunnion is hung from burner maintenance door;It is used in the handover of 2 groups of whole process totally 4 lifting lugs primary.
For compared with the existing technology, the central throat tube and its replacing options of blast furnace roof of the invention, jam lower clamping ring Be fixed on distributing device it is suitable for reading on, central throat tube trunnion ontology is put into it is opposite with distributor chute in distributing device so that under jam Pressing ring can mutually be fixed by boss on pressing ring and jam.It is adjacent can to pass through jam lower clamping ring for the overhanging boss of pressing ring in jam Groove gap between two boss;It, can be straight without cutting upper pressing ring without promoting central throat tube at lower sealing valve maintenance door It connects and drops to central throat tube close at distributor chute.Reach central throat tube replacement speed faster, save human and material resources, safety is The high purpose of number.
Detailed description of the invention
Fig. 1 is prior art attached drawing.
Fig. 2 is the central throat tube main view for the blast furnace roof that the present invention is implemented.
Fig. 3 is the top view of Fig. 2.
Fig. 4 is 8 top view of pressing ring in jam of the present invention.
Fig. 51 top view of jam lower clamping ring of the present invention.
Fig. 6 is replacement central throat tube schematic diagram of the invention.
Appended drawing reference correspondence is as follows in attached drawing 2-6:
Jam lower clamping ring 1, it is interior stretch boss 1-1, the first wear-resistant liner 2, the second wear-resistant liner 3, third wear-resistant liner 4, weldering Connect outer barrel 5., support sleeve, bayonet lock 7, pressing ring 8 in jam, overhanging boss 8-1, lifting lug 9, central throat tube 10, chain type at the top of batch can Crane 11, expansion bellows 12, wear-resistant liner 13, distributor chute 14, the outer chain hoist 15 of burner maintenance door, burner maintenance Door 16, lower sealing valve 17, distributing device 18.
Specific embodiment
The central throat tube for the blast furnace roof implemented according to the present invention is as shown in figures 2-6, wear-resisting by jam lower clamping ring 1, first Liner plate 2, the second wear-resistant liner 3, third wear-resistant liner 4, welding outer barrel 5, support sleeve, bayonet lock 7, pressing ring 8, lifting lug 9 in jam Composition.First wear-resistant liner 2, the second wear-resistant liner 3, third wear-resistant liner 4 are hollow convex mesa-shaped cylinder and are major diameters One end is arranged upward.
Support sleeve 6 is successively stacked in the welding outer barrel 5 from the bottom to top, multiple overlappings of third wear-resistant liner 4 are welded on In support sleeve 6, and matches in circumferencial direction and make hole, spot welding after being fixed with bayonet lock 7;First wear-resistant liner 2 and the second wear-resistant liner 3, It successively stacks and upper limb is all fixed in jam on pressing ring 8, as shown in Fig. 2, pressing ring 8 and lifting lug 9 are included in welding in jam It is two parts therein in outer barrel 5.The ontology of composition described above central throat tube is placed in the interior of jam lower clamping ring 1 and stretches boss On 1-1.
8 matching design of pressing ring is processed on the jam lower clamping ring 1 and jam, and jam lower clamping ring 1 is along the circumferential direction toward the center of circle Boss 1-1 is stretched in interior direction is 6 (but being not limited to 6) uniformly distributed, pressing ring is along the processing of 8 circumferencial directions and jam lower clamping ring in jam The 1 consistent overhanging boss 8-1 of distribution, i.e., the two boss number and layout angle are consistent, while guaranteeing diameter dimensionAnd the bigger about β of angle [alpha] of processing.Pressing ring 8 in jam lower clamping ring 1 and jam is enabled to consolidate fixing.
9 numbers of the lifting lug are 4, are welded in jam on the overhanging boss 8-1 of pressing ring 8.
In use, as shown in fig. 6, central throat tube 10 is put into distributing device 18 fixed.
When needing replacing central throat tube 10, it is first turned on 17 maintenance door of lower sealing valve, opens distributor chute maintenance door, it will The turning angle of distributor chute 14 is adjusted to maximum position, and rotating cloth chute makes it just towards burner maintenance door 16;On batch can top Chain hoist 11 at the top of batch can is installed in portion, from the expansion ripple taken out above central throat tube in 17 maintenance door of lower sealing valve Wear-resistant liner 13 (signal arrow step A) in pipe 12, wear-resistant liner 13 herein is not to belong to central throat tube, and swollen What swollen bellows 12 carried, 11 two chain slings of chain hoist are hung on 10 axisymmetric 2 lifting lugs 9 of central throat tube, slightly Lift central throat tube 10, the remaining part in addition to jam lower clamping ring 1 is all raised at this time;Central throat tube 10 is rotated horizontally 30 ° And chain sling is reduced, the overhanging boss 8-1 of pressing ring 8 in jam is formed by being stretched between boss 1-1 in jam lower clamping ring 1 Groove, central throat tube 10 is decreased until from distributing device 18 by the uni-drive gear box of blast furnace and is reached close to distributor chute 14 (signal arrow step B), is observed by burner maintenance door.It is designed in this way without promoting central throat tube 10 to lower sealing valve 17 At maintenance door, directly central throat tube 10 can be dropped to close at distributor chute 14 without cutting upper pressing ring;It is examined using burner Repair another chain hoist (the outer chain hoist 15 of burner maintenance door) in 16 outside of door, the outer chain type lifting of the burner maintenance door The pipe hook of fixing belt suspension hook lives the chain sling of chain hoist 11 at the top of the material feeding jar of central throat tube 10 on machine 15, loosens at the top of batch can Central throat tube 10 is pulled to burner maintenance by 11 chain sling of chain hoist and the chain sling for shortening the outer chain hoist 15 of burner maintenance door Door, until two chain slings of chain hoist 15 outside burner maintenance door can be hooked on other two axial symmetry lifting lug 9 to (signal Arrow step C);Two chain slings of chain hoist 11 at the top of batch can in batch can are unclamped, with outside the burner maintenance door outside burner 15 two chain slings of chain hoist draw central throat tube, until central throat tube is located at outside (the signal arrow D step of burner maintenance door 16 Suddenly), the chain sling for hanging over the chain hoist of the top on lifting lug 9 11 is removed at this time, recycles the outer chain hoist of burner maintenance door 15 hang central throat tube 10 from burner maintenance door.The handover of 2 groups of 4 lifting lugs uses so that replacement process safety coefficient is higher, It is more easy.
The central throat tube of blast furnace roof of the present invention, structure is simple, easily facilitates repair and replacement, saves human and material resources, Safety coefficient is high.

Claims (6)

1. a kind of central throat tube of blast furnace roof mainly includes outer barrel, support sleeve and wear-resistant liner, it is characterised in that: institute It states wear-resistant liner and is divided into the first wear-resistant liner, the second wear-resistant liner, third wear-resistant liner, three kinds of wear-resistant liners are cannular boss Shape cylinder and be that major diameter one end is arranged upward;Multiple support sleeves are successively stacked in outer barrel from the bottom to top, multiple thirds are resistance to Mill lining plate is overlapped is fixed in support sleeve up and down, further includes pressing ring in mutually matched jam lower clamping ring and jam, first is wear-resisting Liner plate and the second wear-resistant liner are from top to bottom stacked and upper limb is all fixed in jam on pressing ring;Pressing ring outer rim is arranged in jam The multiple overhanging boss stretched out toward center of circle opposite direction, multiple overhanging circumferentially spaced distributions of boss;Jam lower clamping ring edge Circumferencial direction toward center of circle interior direction it is uniformly distributed in stretch boss, both pressing rings boss number and cloth angle setting on jam lower clamping ring and jam Degree is consistent, and pressing ring in jam lower clamping ring and jam is mutually fixed by boss;And the overhanging boss of pressing ring in jam The groove gap between the two neighboring boss of jam lower clamping ring can be passed through;Lifting lug is set on the overhanging boss of pressing ring in jam, altogether Meter at least four lifting lugs of setting.
2. the central throat tube of blast furnace roof according to claim 1, it is characterised in that:
Pressing ring diameter dimension on jam lower clamping ring and jam are as follows: pressing ring outer diameter A < jam lower clamping ring boss internal diameter B < card in jam Hang up pressing ring boss outer diameter C < jam lower clamping ring internal diameter D so that pressing ring can pass through boss phase on jam lower clamping ring and jam Mutually fix;And pressing ring is both that the groove gap angle [alpha] between respective two neighboring boss is greater than in jam lower clamping ring and jam The angle beta of boss itself enables the overhanging boss of pressing ring in jam to pass through the groove between the two neighboring boss of jam lower clamping ring Gap.
3. the central throat tube of blast furnace roof according to claim 1, it is characterised in that:
The upright projection of both pressing ring and lifting lug is included in outer barrel in jam, so that pressing ring and outer barrel inner part in jam Constitute central throat tube ontology.
4. the central throat tube of blast furnace roof according to claim 1, it is characterised in that:
Jam lower clamping ring be fixed on distributing device it is suitable for reading on, central throat tube trunnion ontology is put into distributing device and distributor chute phase It is right, pressing ring in jam lower clamping ring and jam is mutually fixed by boss.
5. the central throat tube of blast furnace roof according to claim 1, it is characterised in that:
Multiple third wear-resistant liner overlappings are welded in support sleeve, and fix rear spot welding with bayonet lock with hole is made in circumferencial direction.
6. the replacing options of the central throat tube of blast furnace roof described in one of -5 according to claim 1, it is characterised in that:
When needing replacing central throat tube, the turning angle of distributor chute is first adjusted to maximum position, rotating cloth chute makes it Just towards burner maintenance door;Then chain hoist at the top of batch can is installed at the top of batch can, successively from lower sealing valve maintenance door Take out the wear-resistant liner in the expansion bellows being located above central throat tube ontology;By two chain slings of chain hoist at the top of batch can It hangs on axisymmetric 2 lifting lugs of central throat tube ontology, slightly lifts central throat tube ontology, at this time in addition to jam lower clamping ring Central throat tube ontology is all raised;
Central throat tube ontology is rotated horizontally into set angle and reduces chain sling, so that the overhanging boss of pressing ring passes through jam in jam The groove gap formed between boss is stretched in lower clamping ring, by the uni-drive gear box of blast furnace by central throat tube ontology from distributing device Decline is observed close to distributor chute by burner maintenance door;
The outer chain hoist of burner maintenance door on the outside of burner maintenance door is reused, chain at the top of central throat tube ontology material feeding jar is hooked Formula crane chain sling loosens batch can top chain hoist chain sling and shortens the chain sling of the outer chain hoist of burner maintenance door, will Central throat tube pulls to burner maintenance door, until that two chain slings of chain hoist outside burner maintenance door can be hooked to other two On axial symmetry lifting lug;Two chain slings of chain hoist at the top of batch can are unclamped, are risen with chain type outside the burner maintenance door outside burner Two chains of heavy-duty machine draw central throat tubes, until central throat tube is located at the outside of burner maintenance door, remove the material hung on lifting lug at this time The chain sling of tank top chain hoist, using chain hoist outside the burner maintenance door on the outside of burner maintenance door by central throat tube from Burner maintenance door is hung;2 groups of whole process totally 4 lifting lugs handover use it is primary.
CN201710463652.2A 2017-06-19 2017-06-19 A kind of central throat tube and its replacing options of blast furnace roof Active CN107058657B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710463652.2A CN107058657B (en) 2017-06-19 2017-06-19 A kind of central throat tube and its replacing options of blast furnace roof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710463652.2A CN107058657B (en) 2017-06-19 2017-06-19 A kind of central throat tube and its replacing options of blast furnace roof

Publications (2)

Publication Number Publication Date
CN107058657A CN107058657A (en) 2017-08-18
CN107058657B true CN107058657B (en) 2019-04-19

Family

ID=59594959

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710463652.2A Active CN107058657B (en) 2017-06-19 2017-06-19 A kind of central throat tube and its replacing options of blast furnace roof

Country Status (1)

Country Link
CN (1) CN107058657B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109576426A (en) * 2018-12-18 2019-04-05 山东钢铁股份有限公司 A kind of replacing options of blast furnace roof central throat tube

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1013482A1 (en) * 1981-12-25 1983-04-23 Ленинградский государственный институт по проектированию металлургических заводов Blast furnace grate
SU1113414A1 (en) * 1982-08-11 1984-09-15 Днепропетровский Завод Металлургического Оборудования Charge distributor for blast furnace charging apparatus
SU1671702A1 (en) * 1989-08-07 1991-08-23 Производственное объединение "Азовмаш" Device for preparation of cone and cup for work
CN2518868Y (en) * 2001-05-24 2002-10-30 攀枝花钢铁有限责任公司机械制造公司 Quick-changing combined central throat tube
CN201670847U (en) * 2010-04-30 2010-12-15 武汉钢铁(集团)公司 Central throat at central part of bell-less top gearbox of blast furnace
CN103571987A (en) * 2012-07-30 2014-02-12 上海宝冶集团有限公司 Method for replacing central throat pipe at blast furnace roof
CN106148622A (en) * 2015-04-24 2016-11-23 周南夫 A kind of blast-furnace distributor of Novel chute hang

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1013482A1 (en) * 1981-12-25 1983-04-23 Ленинградский государственный институт по проектированию металлургических заводов Blast furnace grate
SU1113414A1 (en) * 1982-08-11 1984-09-15 Днепропетровский Завод Металлургического Оборудования Charge distributor for blast furnace charging apparatus
SU1671702A1 (en) * 1989-08-07 1991-08-23 Производственное объединение "Азовмаш" Device for preparation of cone and cup for work
CN2518868Y (en) * 2001-05-24 2002-10-30 攀枝花钢铁有限责任公司机械制造公司 Quick-changing combined central throat tube
CN201670847U (en) * 2010-04-30 2010-12-15 武汉钢铁(集团)公司 Central throat at central part of bell-less top gearbox of blast furnace
CN103571987A (en) * 2012-07-30 2014-02-12 上海宝冶集团有限公司 Method for replacing central throat pipe at blast furnace roof
CN106148622A (en) * 2015-04-24 2016-11-23 周南夫 A kind of blast-furnace distributor of Novel chute hang

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
PW炉顶系统(并罐)中心喉管快速更换方法研究;芦涛;《企业技术开发》;20150430;第34卷(第12期);第20-23页 *

Also Published As

Publication number Publication date
CN107058657A (en) 2017-08-18

Similar Documents

Publication Publication Date Title
CN105849028A (en) Lifting crane and method for refurbishing such a lifting crane
CN107058657B (en) A kind of central throat tube and its replacing options of blast furnace roof
CN106272223B (en) A kind of attaching/detaching apparatus for being used for super-huge autogenous tumbling mill or semi-autogenous mill feeding seal ring
CN209702121U (en) Suspender is used in the production of axle sleeve retaining ring
CN204954202U (en) Blast furnace stove outer covering inner wall welded platform
CN103571987A (en) Method for replacing central throat pipe at blast furnace roof
CN204778345U (en) Vertical round steel -casting anchor clamps
CN206447894U (en) A kind of blast furnace gun machine slew gear equipment integral replacement device
CN108015519B (en) The drawing process covered in blast furnace
CN210103297U (en) Diesel engine cylinder liner hanger
CN103803403A (en) Special hook for hoisting wringing roller
CN204198656U (en) A kind of rotary coke tank apparatus for examination and repair
CN210596129U (en) Mud gun slewing mechanism replacing device
CN206427917U (en) A kind of diesel locomotive cylinder jacket lifting device
CN208103695U (en) Special suspending device for diesel locomotive cylinder jacket
CN201077712Y (en) Small lifting ring wide-body hanging belt
CN213104468U (en) Ladle lug pivot wear resistant device
CN113814273B (en) Device convenient for replacing heavy-duty roll collar and application method
CN108455447A (en) A kind of Novel crane suspension hook equipment
CN216272699U (en) A simple and easy hoist device for hard felt section of thick bamboo of graphite
CN212863774U (en) Lifting appliance for rapidly replacing roller of pipe mill
CN213834236U (en) Novel lifting hook anti-falling device capable of disassembling lifting chain by single person
CN208472131U (en) A kind of steel steel-making blast furnace air port
CN208713832U (en) It is a kind of for replacing the tool of peach-shaped ring on elevator
CN218062248U (en) Universal loading and unloading basket for different-caliber gear wheels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant