CN107053110A - A kind of transformer breather silica gel replacement operation tool box - Google Patents
A kind of transformer breather silica gel replacement operation tool box Download PDFInfo
- Publication number
- CN107053110A CN107053110A CN201611236194.0A CN201611236194A CN107053110A CN 107053110 A CN107053110 A CN 107053110A CN 201611236194 A CN201611236194 A CN 201611236194A CN 107053110 A CN107053110 A CN 107053110A
- Authority
- CN
- China
- Prior art keywords
- cover plate
- lid
- silica gel
- replacement operation
- tool box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B25—HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
- B25H—WORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
- B25H3/00—Storage means or arrangements for workshops facilitating access to, or handling of, work tools or instruments
- B25H3/02—Boxes
- B25H3/021—Boxes comprising a number of connected storage elements
- B25H3/022—Boxes comprising a number of connected storage elements in fixed relationship
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Casings For Electric Apparatus (AREA)
Abstract
The invention discloses a kind of transformer breather silica gel replacement operation tool box, belong to electrical equipment technical field, solve the unhandy technical problem of operating personnel in transformer breather silica gel replacement operation, the transformer breather silica gel replacement operation tool box of the present invention, including casing and being hinged the lid covered on the casing, the casing is provided with the first incorporating section for being used for storing standby redundancy, the lid is provided with the second incorporating section for being used for storing power tool, the first cover plate and the second cover plate are also rotatably connected on the lid, first cover plate and second cover plate cover above second incorporating section and form operating platform, positive stop lug boss and location structure are additionally provided with the inside of the lid, first cover plate and second cover plate are resisted against on the positive stop lug boss after covering, first cover plate and second cover plate are fitted on the positive stop lug boss by the location structure.
Description
【Technical field】
The invention belongs to electrical equipment technical field, more particularly to a kind of transformer breather silica gel replacement operation instrument
Case.
【Background technology】
The standby redundancy and power tool that transformer breather silica gel replacement operation project needs are relatively more, such as silica gel, wine
Essence, towel, spanner, rubber sealing ring, transformer oil, lubricating cup handling instrument, silica gel screening washer, Hygrothermograph etc..These spare unit
Spare part and power tool are mixed and disorderly to be placed in tool box, is quickly taken and is put so as to can not realize operating personnel, together
When silica gel replacement operation generally require a smooth job platform, in favor of the storage and work of various standby redundancies, still
All it is the goose soft rock of out-of-flatness in main transformer oil pit because silica gel changes scene without smooth place, thus it is current all from work
Carried out on the road of scene farther out, be that operation brings many inconvenience.
【The content of the invention】
The technical problems to be solved by the invention are to overcome the deficiencies in the prior art and provide a kind of transformer breather
Silica gel replacement operation tool box, can realize that standby redundancy and the orderly of power tool are put, while can also provide a profit
In the operating platform for silica gel replacement operation, facilitate operating personnel's operation.
In order to solve the above technical problems, the present invention is adopted the following technical scheme that:
A kind of transformer breather silica gel replacement operation tool box, including casing and being hinged are covered on the casing
Lid, the casing is provided with the first incorporating section for being used for storing standby redundancy, and the lid, which is provided with, to be used to store operation work
Second incorporating section of tool, is also rotatably connected to the first cover plate and the second cover plate on the lid, first cover plate and described the
Two cover plates are covered above second incorporating section and form operating platform, and positive stop lug boss and positioning are additionally provided with the inside of the lid
Structure, first cover plate and second cover plate are resisted against on the positive stop lug boss after covering, and the location structure will be described
First cover plate and second cover plate are fitted on the positive stop lug boss.
In above-mentioned transformer breather silica gel replacement operation tool box, first cover plate is provided with first turn
Axle, second cover plate is provided with the second rotating shaft, the side wall of the lid provided with respectively with the first rotating shaft and described the
First rotating shaft hole and the second shaft hole that two rotating shafts coordinate.
In above-mentioned transformer breather silica gel replacement operation tool box, the covered body wall is provided with mounting hole,
The location structure includes elastic component and alignment pin, and the elastic component is fitted between the alignment pin and the installation hole wall,
The head of the alignment pin is fitted on first cover plate and the second cover plate.
In above-mentioned transformer breather silica gel replacement operation tool box, the top surface of the alignment pin is led provided with first
To inclined-plane, ecto-entad is tilted first guiding surface from up to down.
In above-mentioned transformer breather silica gel replacement operation tool box, the lid madial wall is also slidably fitted with
Shifting block, the shifting block is slided towards the alignment pin direction to be covered first cover plate and second with releasing the positioning pin head part
The locking of plate.
In above-mentioned transformer breather silica gel replacement operation tool box, first cover plate and second cover plate
It is transparent acrylic board.
In above-mentioned transformer breather silica gel replacement operation tool box, the standby redundancy include transformer oil,
Blue silica gel and rust remover, first incorporating section are provided with the matched with the transformer oil, blue silica gel and rust remover
One groove.
In above-mentioned transformer breather silica gel replacement operation tool box, the power tool includes some different rule
The spanner of lattice and several screws, second incorporating section is provided with the second groove with the spanner and screw mates.
In above-mentioned transformer breather silica gel replacement operation tool box, the casing passes through buckle with the lid
Connection.
Beneficial effects of the present invention:
Transformer breather silica gel replacement operation tool box in the present invention, including casing and being hinged are covered on casing
Lid, casing is provided with the first incorporating section for being used for storing standby redundancy, and lid, which is provided with, to be used to store the second of power tool
The first cover plate and the second cover plate are also rotatably connected on incorporating section, lid, the first cover plate and the second cover plate are covered to be stored second
Portion top simultaneously forms operating platform, is additionally provided with positive stop lug boss and location structure on the inside of lid, the first cover plate and the second cover plate are covered
After be resisted against on positive stop lug boss, the first cover plate and the second cover plate are fitted on positive stop lug boss by location structure.In the present invention
One incorporating section is arranged in order to standby redundancy, and the second incorporating section carries out orderly arrangement to power tool, consequently facilitating soon
Speed is taken and put, in addition, the first cover plate and the second cover plate in the present invention form operating platform after covering, in order to silica gel more
The progress of operation is changed, the first cover plate and the second cover plate are firmly covered on the second incorporating section by location structure, to prevent lid
During body closing lid, power tool spins off from the second incorporating section.It follows that compared with prior art, instrument of the invention
Case can realize the arrangement to standby redundancy and power tool, be easy to quickly take and put, while the first cover plate and the second lid
Plate provides an operating platform after covering for silica gel replacement operation, enterprising in the road from working site farther out without operating personnel
OK, the operation to operating personnel brings great convenience.
Covered body wall be provided with mounting hole, location structure include elastic component and alignment pin, elastic component be fitted in alignment pin and
Install between hole wall, the head of alignment pin is fitted on the first cover plate and the second cover plate.It is so designed that, when user covers the first lid
When plate and the second cover plate, in the presence of the first cover plate and the second cover plate, alignment pin is moved and the elasticity of compression to mounting hole direction
Part is to avoid the first cover plate and the second cover plate, so that the first cover plate and the second cover plate are covered, when the first cover plate and the second cover plate
After covering completely, the elastic component after compression outwards drives alignment pin to move, and alignment pin is fitted in the first cover plate and the second cover plate
On, to prevent the first cover plate and the second cover plate from opening, realize the function of the first lid of automatic locking and the second lid.
The top surface of alignment pin is provided with the first guiding surface, and ecto-entad is tilted the first guiding surface from up to down.So set
Meter, can be rotated down when the first cover plate and the second cover plate are covered along the first guiding surface, to avoid damaging alignment pin.
Lid madial wall is also slidably fitted with shifting block, and shifting block slides to release positioning pin head part to the towards alignment pin direction
The locking of one cover plate and the second cover plate.It is so designed that, positioning pin head part can be released to the first cover plate and the by stirring shifting block
The locking of two cover plates, it is easy to operate in order to open the first cover plate and the second cover plate, it is simple in construction.
First cover plate and the second cover plate are transparent acrylic board.It is so designed that, operating personnel's observation determination can be easy to
Required power tool is located at the position in the second incorporating section, in order to quickly take.
Casing is with lid by snapping connection.It is so designed that, it is simple in construction, and it is easy to operating personnel to open or locking lid
Body.
The present invention these features and advantage will be detailed in following embodiment, accompanying drawing exposure.
【Brief description of the drawings】
The present invention is described further below in conjunction with the accompanying drawings:
Fig. 1 is the structural representation (one) in tool box in the preferred embodiment of the present invention;
Fig. 2 is the structural representation (two) in tool box in the preferred embodiment of the present invention;
Fig. 3 is the longitudinal sectional view of lid in the preferred embodiment of the present invention;
Fig. 4 is the top view of shifting block in the preferred embodiment of the present invention.
【Embodiment】
The technical scheme of the embodiment of the present invention is explained and illustrated with reference to the accompanying drawing of the embodiment of the present invention, but under
Embodiment only the preferred embodiments of the present invention are stated, and it is not all.Based on the embodiment in embodiment, those skilled in the art
Other embodiment is obtained on the premise of creative work is not made, protection scope of the present invention is belonged to.
In the following description, there is term " interior ", " outer ", "left", "right", "front", "rear" etc. and indicate
Orientation or position relationship are that, based on orientation shown in the drawings or position relationship, the description present invention merely for convenience and simplification are retouched
State, rather than indicate or imply that the device or element of meaning there must be specific orientation, with specific azimuth configuration and operation,
Therefore it is not considered as limiting the invention.In addition, term " first ", " second " etc. are only used for describing purpose, and it can not manage
Solve to indicate or imply relative importance or the implicit quantity for indicating indicated technical characteristic.
Referring to figs. 1 to shown in Fig. 4, the transformer breather silica gel replacement operation tool box that the present embodiment is proposed, including
Casing 1 and lid 2, lid 2, which is hinged, to be covered in casing 1, and one of them is provided with rotating shaft for lid 2 and casing 1, and another is provided with turning
The shaft hole that axle coordinates, casing 1 is provided with the first incorporating section 11 for being used for storing standby redundancy, and standby redundancy includes transformer
Oil, blue silica gel, rust remover, alcohol, towel, lubricating cup handling instrument, silica gel screening washer and Hygrothermograph etc., the first incorporating section 11
Provided with the first groove 110 matched with above-mentioned standby redundancy.Lid 2, which is provided with, is used for the second storage for storing power tool
Portion 21, power tool includes the spanner and several screws of some different sizes, and the second incorporating section 21 is provided with and spanner and spiral shell
Follow closely the second groove 210 of matching.
The first cover plate 22 and the second cover plate 23 are also rotatably connected on lid 2, the first cover plate 22 and the second cover plate 23 are covered
In the top of the second incorporating section 21 and operating platform 3 is formed, the inner side of lid 2 is additionally provided with positive stop lug boss 24 and location structure 25, first
The cover plate 23 of cover plate 22 and second is resisted against on positive stop lug boss 24 after covering, and location structure 25 is by the first cover plate 22 and the second cover plate 23
It is fitted on positive stop lug boss 24.
It follows that the first incorporating section 11 in the present invention is arranged in order to standby redundancy, the second 22 pairs of incorporating section
Power tool carries out orderly arrangement, consequently facilitating quickly taking and putting, in addition, the first cover plate 22 and second in the present invention
Cover plate 23 forms operating platform 3 after covering, and in order to the progress of silica gel replacement operation, the first cover plate 22 and the second cover plate 23 pass through
Location structure 25 is firmly covered on the second incorporating section 21, to prevent during the 2-in-1 lid of lid, and power tool is from the second incorporating section 21
On spin off.It follows that compared with prior art, tool box of the invention can be realized to standby redundancy and power tool
Arrangement, be easy to quickly take and put, while the first cover plate 22 and the second cover plate 23 are provided after covering for silica gel replacement operation
One operating platform, is carried out, the operation to operating personnel is brought without operating personnel on from working site road farther out
Greatly facilitate.
The first cover plate 22 in the present embodiment is provided with first rotating shaft, and the second cover plate 23 is provided with the second rotating shaft, lid 2
Left and right sides wall is realized provided with the first rotating shaft hole and the second shaft hole that coordinate respectively with first rotating shaft and the second rotating shaft with this
First cover plate 22 is connected with the rotation of lid 2 and the second cover plate 23 is connected with the rotation of lid 2, rotation connection structure of the invention
Simply, it is easy to machine-shaping.
Mounting hole 26 is provided with the front-rear side walls of lid 2, location structure 25 includes elastic component 251 and alignment pin 252, bullet
Property part 251 be spring or shell fragment, the present invention preferably spring, the bottom wall of mounting hole 26 is provided with mounting post 261, alignment pin 252
Afterbody is provided with projection, and the two ends of spring are installed in raised and mounting post 261 respectively, when the first lid 22 and the second lid 23 are covered
During conjunction, the head of alignment pin 252 is fitted on the first cover plate 22 and the second cover plate 23.
It is additionally provided with the front-rear side walls of lid 2 in chute 27, chute 27 and shifting block 28 is installed, the bottom inserting of shifting block 28
In chute 27, shifting block 28 can horizontally slip with respect to chute 27.The left surface of alignment pin 252 is the second guiding surface 2522, and
Ecto-entad is tilted second guiding surface 2522 from left to right, and shifting block 28 during sliding from left to right, the right side of shifting block 28
End can be moved along the second guiding surface 2522, and alignment pin 252 is fitted in into the inner side of shifting block 28, to avoid alignment pin
The opening of 252 pair of first lid 23 of lid 22 and second causes interference.
Handle band 4 is additionally provided with the first lid 22 and the second lid 23, when user needs to open the first lid 22 and the
During two lids 23, shifting block 28 is slided to the right and drives alignment pin 252 to be moved towards the direction of mounting hole 26, until shifting block 28 will be positioned
Pin 252 is all limited between shifting block 28 and mounting hole 26, and now user opens the first lid 22 by lifting handle band 4 upwards
With the second lid 23, the power tool in the second incorporating section 21 is taken.After the first lid 22 and the second lid 23 are covered, first
The edge of the medial surface of the lid 23 of lid 22 and second is resisted against on positive stop lug boss 24, shifting block 28 is slided to the left, now alignment pin
252 eject under the force of a spring, and are fitted on the first lid 22 and the second lid 23, to prevent the first lid 22 and
Two lids 23 are opened.
It is preferred that, the top surface of alignment pin 252 is provided with the first guiding surface 2521, the first guiding surface 2521 from up to down by
It is export-oriented tilted.When user is in the case where slip shifting block 28 ejects alignment pin 252 to the left unintentionally, the first lid is now covered
When body 22 or the second lid 23, the first lid 22 or the second lid 23 can also be rotated down along the first guiding surface 2521, with
Driving alignment pin 252 is moved to the direction of mounting hole 26, so as to avoid the first lid 22 or the second lid 23, when the first lid 22 or
After second lid 23 is covered completely, alignment pin 252 eject and be fitted in the first lid 22 or the second lid 23 on, first be oriented to it is oblique
Face 2521 can avoid the first lid 22 or the second lid 23 from damaging alignment pin 252.
The first cover plate 22 and the second cover plate 23 of the present invention is transparent acrylic board, consequently, it is possible to can be easy to operation
Power tool is located at the position in the second incorporating section 21 needed for personal observations determine, in order to quickly take.
In addition, casing 1 with lid 2 by snapping connection, specifically, casing 1 provided with hook, lid 2 provided with lock
With draw ring set, draw ring is set on lock, and draw ring set is hooked on that hook is upper so that lid 2 is firmly covered on casing 1, case
Handle is additionally provided with body 1, in order to which personnel carry.
The foregoing is only a specific embodiment of the invention, but protection scope of the present invention is not limited thereto, and is familiar with
The those skilled in the art should be understood that the present invention includes but is not limited to accompanying drawing and interior described in embodiment above
Hold.The modification of any function and structure principle without departing from the present invention is intended to be included in the scope of claims.
Claims (9)
1. a kind of transformer breather silica gel replacement operation tool box, it is characterised in that covered including casing and being hinged in institute
The lid on casing is stated, the casing is provided with the first incorporating section for being used for storing standby redundancy, and the lid, which is provided with, to be used for
Store and the first cover plate and the second cover plate are also rotatably connected on the second incorporating section of power tool, the lid, first lid
Plate and second cover plate cover above second incorporating section and form operating platform, are additionally provided with the inside of the lid spacing
Boss and location structure, first cover plate and second cover plate are resisted against on the positive stop lug boss after covering, the positioning
First cover plate and second cover plate are fitted on the positive stop lug boss by structure.
2. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that described first
Cover plate is provided with first rotating shaft, and second cover plate is provided with the second rotating shaft, the side wall of the lid provided with respectively with it is described
First rotating shaft hole and the second shaft hole that first rotating shaft and second rotating shaft coordinate.
3. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that the lid
Side wall be provided with mounting hole, the location structure include elastic component and alignment pin, the elastic component be fitted in the alignment pin and
Between the installation hole wall, the head of the alignment pin is fitted on first cover plate and the second cover plate.
4. transformer breather silica gel replacement operation tool box according to claim 3, it is characterised in that the positioning
The top surface of pin is provided with the first guiding surface, and ecto-entad is tilted first guiding surface from up to down.
5. transformer breather silica gel replacement operation tool box according to claim 3, it is characterised in that the lid
Madial wall is also slidably fitted with shifting block, and the shifting block slides to release the positioning pin head part to institute towards the alignment pin direction
State the locking of the first cover plate and the second cover plate.
6. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that described first
Cover plate and second cover plate are transparent acrylic board.
7. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that the spare unit
Spare part includes transformer oil, blue silica gel and rust remover, and first incorporating section is provided with and the transformer oil, blue silica gel
The first groove matched with rust remover.
8. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that the operation
Instrument includes the spanner and several screws of some different sizes, and second incorporating section is provided with and the spanner and screw
The second groove matched somebody with somebody.
9. transformer breather silica gel replacement operation tool box according to claim 1, it is characterised in that the casing
With the lid by snapping connection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611236194.0A CN107053110A (en) | 2016-12-28 | 2016-12-28 | A kind of transformer breather silica gel replacement operation tool box |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611236194.0A CN107053110A (en) | 2016-12-28 | 2016-12-28 | A kind of transformer breather silica gel replacement operation tool box |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107053110A true CN107053110A (en) | 2017-08-18 |
Family
ID=59623731
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611236194.0A Pending CN107053110A (en) | 2016-12-28 | 2016-12-28 | A kind of transformer breather silica gel replacement operation tool box |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107053110A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108100431A (en) * | 2018-02-09 | 2018-06-01 | 苏州泓聚纤维科技有限公司 | A kind of Weaving device accessory storing unit |
CN110497367A (en) * | 2019-09-24 | 2019-11-26 | 丹阳市剑庐工具有限公司 | A kind of instrument cases with pressing plate |
CN110587561A (en) * | 2019-09-26 | 2019-12-20 | 国网山东省电力公司济南市济阳区供电公司 | Power equipment overhauls uses toolbox |
CN113771772A (en) * | 2021-11-10 | 2021-12-10 | 宁波华众塑料制品有限公司 | Automobile trunk storage box |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2226807A (en) * | 1989-01-04 | 1990-07-11 | James Andrew Cave | Tool chest that converts to a workbench or seat |
US20040160150A1 (en) * | 2003-02-13 | 2004-08-19 | Waterloo Industries, Inc. | Tool storage project center with power strip |
CN201389848Y (en) * | 2008-09-17 | 2010-01-27 | 傅志庆 | Multifunctional combined toolkit |
CN203317054U (en) * | 2013-07-04 | 2013-12-04 | 罗邦才 | Toolset for machine tool |
CN204025261U (en) * | 2014-07-21 | 2014-12-17 | 艾美特电器(深圳)有限公司 | A kind of telescopic pipe and liftable electric heater |
CN204354086U (en) * | 2014-12-22 | 2015-05-27 | 广州车拉夫机电设备有限公司 | Integration dismounting detection platform |
CN204566105U (en) * | 2015-05-05 | 2015-08-19 | 何艺峰 | A kind of electric power tool case |
CN205238016U (en) * | 2015-12-30 | 2016-05-18 | 新乡学院 | Toolbox for art design |
CN205675071U (en) * | 2016-06-02 | 2016-11-09 | 江苏美科硅能源有限公司 | A kind of novel slice tool car |
CN206287117U (en) * | 2016-12-28 | 2017-06-30 | 国网浙江省电力公司湖州供电公司 | A kind of transformer breather silica gel replacement operation tool box |
-
2016
- 2016-12-28 CN CN201611236194.0A patent/CN107053110A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2226807A (en) * | 1989-01-04 | 1990-07-11 | James Andrew Cave | Tool chest that converts to a workbench or seat |
US20040160150A1 (en) * | 2003-02-13 | 2004-08-19 | Waterloo Industries, Inc. | Tool storage project center with power strip |
CN201389848Y (en) * | 2008-09-17 | 2010-01-27 | 傅志庆 | Multifunctional combined toolkit |
CN203317054U (en) * | 2013-07-04 | 2013-12-04 | 罗邦才 | Toolset for machine tool |
CN204025261U (en) * | 2014-07-21 | 2014-12-17 | 艾美特电器(深圳)有限公司 | A kind of telescopic pipe and liftable electric heater |
CN204354086U (en) * | 2014-12-22 | 2015-05-27 | 广州车拉夫机电设备有限公司 | Integration dismounting detection platform |
CN204566105U (en) * | 2015-05-05 | 2015-08-19 | 何艺峰 | A kind of electric power tool case |
CN205238016U (en) * | 2015-12-30 | 2016-05-18 | 新乡学院 | Toolbox for art design |
CN205675071U (en) * | 2016-06-02 | 2016-11-09 | 江苏美科硅能源有限公司 | A kind of novel slice tool car |
CN206287117U (en) * | 2016-12-28 | 2017-06-30 | 国网浙江省电力公司湖州供电公司 | A kind of transformer breather silica gel replacement operation tool box |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108100431A (en) * | 2018-02-09 | 2018-06-01 | 苏州泓聚纤维科技有限公司 | A kind of Weaving device accessory storing unit |
CN110497367A (en) * | 2019-09-24 | 2019-11-26 | 丹阳市剑庐工具有限公司 | A kind of instrument cases with pressing plate |
CN110587561A (en) * | 2019-09-26 | 2019-12-20 | 国网山东省电力公司济南市济阳区供电公司 | Power equipment overhauls uses toolbox |
CN113771772A (en) * | 2021-11-10 | 2021-12-10 | 宁波华众塑料制品有限公司 | Automobile trunk storage box |
CN113771772B (en) * | 2021-11-10 | 2022-01-04 | 宁波华众塑料制品有限公司 | Automobile trunk storage box |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107053110A (en) | A kind of transformer breather silica gel replacement operation tool box | |
US20070008682A1 (en) | Portable DVD player with built-in battery | |
US7559782B2 (en) | Storage device box | |
CN105328673B (en) | A kind of electric power tool containing box | |
CN206287117U (en) | A kind of transformer breather silica gel replacement operation tool box | |
CN214352336U (en) | Excavator toolbox | |
CN101848632A (en) | Electronic part feeding device | |
CN208267552U (en) | A kind of door lock of adjustable gate handle direction | |
CN214607068U (en) | Automobile oil cover with protection mechanism | |
CN205148289U (en) | Electric power examines and repair instrument case | |
CN211710443U (en) | Novel remove archives box | |
CN208773453U (en) | A kind of automobile interior decoration screw cover dismantling device | |
CN208752822U (en) | A kind of train simulation driving instructor control and monitor console | |
CN206925828U (en) | A kind of preventing tool loses tool box | |
CN205344303U (en) | Portable artistic drawing set receiver of pull formula | |
CN207071919U (en) | Portable screwdriver head and magnetic extension bar group set box | |
CN209054843U (en) | Multi-angle enabling car refrigerator | |
CN220439974U (en) | Plug interface protection structure for computer case | |
CN205565384U (en) | Power distribution box's instrument door and power distribution box | |
CN108669767A (en) | A kind of cosmetics pallet | |
CN221577206U (en) | Data classification deposits case | |
CN206252132U (en) | A kind of bullet cabinet rotating switch disk | |
CN218578449U (en) | Environment-friendly baking finish bucket | |
CN218965367U (en) | Tool box | |
CN213796416U (en) | Saddlebag convenient to maintenance machinery flange |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170818 |
|
RJ01 | Rejection of invention patent application after publication |