CN107034760A - A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer - Google Patents

A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer Download PDF

Info

Publication number
CN107034760A
CN107034760A CN201710212424.8A CN201710212424A CN107034760A CN 107034760 A CN107034760 A CN 107034760A CN 201710212424 A CN201710212424 A CN 201710212424A CN 107034760 A CN107034760 A CN 107034760A
Authority
CN
China
Prior art keywords
fire
cover
maintenance area
oil
method described
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710212424.8A
Other languages
Chinese (zh)
Inventor
罗桑
王建伟
陈雄飞
汪锋
魏小皓
刘明莉
钟科
田佳昊
殷俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201710212424.8A priority Critical patent/CN107034760A/en
Publication of CN107034760A publication Critical patent/CN107034760A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/18Coherent pavings made in situ made of road-metal and binders of road-metal and bituminous binders
    • E01C7/187Repairing bituminous covers, e.g. regeneration of the covering material in situ, application of a new bituminous topping
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B26/00Compositions of mortars, concrete or artificial stone, containing only organic binders, e.g. polymer or resin concrete
    • C04B26/02Macromolecular compounds
    • C04B26/26Bituminous materials, e.g. tar, pitch
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/35Toppings or surface dressings; Methods of mixing, impregnating, or spreading them

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of steel bridge deck asphalt concrete pavement Fire-damaged maintenance process, concrete operations are as follows:Step 1:Positioning is measured, breakage subregion Field Number and description are taken pictures;Step 2:Construction area is made an overall screening, it is ensured that bridge floor free from dust and dirt;Step 3:Sticking layer oil is prepared according to repairing consumption and ground brushing is carried out;Step 4:Mix epoxy compound, Manual and vibration, it is levelling by hand;Step 5:After the health of bottom compound to after some strength, carrying out, cover oil is brushed and cover facing material is dispensed;Step 6:Construction starts maintenance after finishing, curing time is according to the strength of materials and temperature conditional decision.Compared with prior art, the present invention is simple to operate, and significantly, feasibility is strong, while Fire-damaged repair place can reach the effect of mating formation of original epoxy asphalt pavement layer, traffic status is good for environmental benefit.

Description

A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer
Technical field
The invention belongs to Communication and Transportation Engineering technical field, and in particular to a kind of fire of steel bridge deck asphalt concrete pavement layer Disaster loss hinders method for maintaining.
Background technology
It is well known that the big-span steel bridge of China generally uses asphalt concrete pavement, it is from bridge floor paving mostly that it, which is destroyed, What the weak link of dress started, and repeated action of the initial weak spot of deck paving except coming from extraneous load, also phase When most comes from the pavement surfaces damage of unexpected initiation, such as fire incident.To the bridge of domestic many big-span steel bridges Face finding of mating formation shows, the damaging oof bridge surface that the contingency such as fire triggers is cause deck paving further to damage important One of reason.Therefore, a kind of maintenance process for being efficiently applied to the maintenance of steel bridge deck asphalt concrete pavement Fire-damaged is sought, Performance and endurance quality to maintaining steel bridge deck asphalt concrete pavement, there is extremely important meaning.
Domestic at present less to the research in terms of steel bridge deck asphalt concrete pavement accidental-damage, existing restorative procedure is not It is enough effective to solve the problems, such as Steel Bridge Deck Pavement Fire-damaged.CN 101906756A disclose a kind of steel bridge deck asphalt Concrete pavement accidental-damage repair materials and restorative procedure, this method not only need to preheat to gathering materials, and in epoxy Heating is needed also exist for during the mix of asphalt and aggregate, preheating and the temperature of mix are 110~130 DEG C.Mixed using heat Restorative procedure, the requirement to place and equipment is higher, while there is the phenomenon of waste of resource, is unfavorable for environmental protection.Therefore, compel to be essential Want a kind of simple and effective steel bridge deck asphalt concrete pavement Fire-damaged method for maintaining.
The content of the invention
The technical problem to be solved in the present invention is to provide a kind of Fire-damaged maintenance of steel bridge deck asphalt concrete pavement layer Method, with solve prior art presence the requirement to place and equipment is higher and the problem of serious waste of resource.
Different from other type of impairments, Steel Bridge Deck occurs after Fire-damaged, and only Surface pavement layer produces different degrees of damage Bad, bottom LIFT is not affected, therefore total need not be excluded, overhauled.Therefore, this time recovery scenario is special Safety pin is to this kind of Failure type, using cold-patch epoxy asphalt mixture renovation technique, and only Surface pavement layer need to be repaired, this It is different from the method for maintaining that other bridge floors are damaged.
In order to solve the above technical problems, the technical solution adopted by the present invention is as follows:
A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer, it includes following method:
(1) maintenance area is positioned, the degree of impairment in region is confirmed;
(2) maintenance area is made an overall screening, except crude removal;
(3) the brushing sticking layer oil in the maintenance area cleared up through step (2);
(4) mix epoxy compound, after paving in the maintenance area after being handled through step (3), vibrate and be levelling, is carried out Health is handled;
(5) brushing cover is oily in the maintenance area after being handled through step (4) and dispenses cover facing material;
(6) after being handled through step (5), maintenance area is open to traffic through conserving to recovery.
In step (2), the described operation made an overall screening is as follows:
In maintenance area, first bridge floor dust, debris are cleared away with mop, broom;Region is loosened to boss and pit Cut;Loosening inspection is carried out to whole construction surface;Air blasting blowing is carried out to surface;Area is burnt using sanding machine cleaning construction Domain, remove surface hide drift along, the debris such as fine particle;Reuse air blower cleaning and purging debris, it is ensured that free from dust, dirt Thing;Again the scope of operation measure taking pictures;Workmen puts on shoe cover, is made an overall screening with cleaning agent;With spray gun to table It is roasting that face carries out spray, it is ensured that no moisture in construction area.
In step (3), the consumption of described sticking layer oil is 0.7~0.9kg/m2;Wherein, described sticking layer oil is at 20 DEG C Tensile strength is not less than fracture elongation at 7.5MPa, 20 DEG C and is not less than 180%.
In step (3),
Vibration:Vibrating compacting is carried out to the compound paved using small vibrating plate compactor, reduces space, and increase mixed Close the compactness of material;
It is levelling:Ensure that the epoxy compound after vibration is substantially in same level, it is ensured that surface evenness, meet row The requirement of car comfortableness.
In step (4), described epoxy compound by bituminous epoxy, gather materials and stirred with limestone dust (0~0.6mm) mixing Mix and form;
Wherein,
Described gathers materials while including coarse aggregate (4.75~13.2mm) and fine aggregate (0.075~4.75mm);
Bituminous epoxy, coarse aggregate, the mass ratio of fine aggregate and limestone dust are 6.3~6.7:30~40:50~65:5 ~10.Bituminous epoxy, coarse aggregate, fine aggregate and limestone dust technical indicator part table 1~4 successively.
The epoxy mixture performance technical indicator of table 1
It is preferred that, it is described to gather materials preferable from hard and compact, wear-resisting, grain shape, and have preferable caking property with binder The hard stone of energy, its technical requirements is as shown in table 2 and table 3;Filler uses limestone dust, and technical requirements are shown in Table 4.
The coarse aggregate technical requirement of table 2
The fine aggregate technical requirement of table 3
The limestone dust technical requirement of table 4
It is preferred that, cover oil coating weight > 0.8kg/m in the step 52, its index be tensile strength (25 DEG C) >= 6.0MPa, fracture elongation (25 DEG C) >=190%;Cover facing material is 0~3mm of particle size fine aggregate, and index meets table 3 will Ask.
In step (4), described health processing refers to placement 1~6 day;Wherein, preferably conditioned time is as follows:
In step (5), the consumption of described cover oil is 0.8~1.0kg/m2;Wherein, cover oil at 25 DEG C Tensile strength is not less than fracture elongation at 6.0MPa, 25 DEG C and is not less than 190%.
It is preferred that, the oily spreading area of the cover should be greater than repaired area.
In step (5), described cover facing material is the fine aggregate that particle size is 0~3mm, the consumption of cover facing material for 1.0~ 1.2kg/m2
In step (6), curing time is 20~48h;Wherein, preferably curing time is as follows:
Temperature (DEG C) 20 30 40
Curing time (h) 48 30 20
Beneficial effect:Compared with prior art, the present invention has following advantage:
Steel bridge deck asphalt concrete pavement Fire-damaged maintenance process technical operation employed in the present invention is simple, energy-conservation Environmental protection, is carried out at normal temperatures, it is not necessary to give material for repairing heating.The technique can ensure that reparation rear region and former pave-load layer simultaneously There is a good collaborative work ability, it is to avoid repair the secondary breakage in area, improve the service life for repairing structure.
Under the same terms, repaired with the present invention, the open time that is open to traffic is more or less the same with prior art, but whole reparation Time used will be less than prior art.Because during reparation, need not be carried out using the present invention program to bottom LIFT Overhaul, and it need not be heated in compound mix, this is not only saved the time, and save material.
Embodiment
According to following embodiments, the present invention may be better understood.However, as it will be easily appreciated by one skilled in the art that real Apply the content described by example and be merely to illustrate the present invention, without should be also without limitation on sheet described in detail in claims Invention.
Embodiment 1
By taking the fire incident that Taizhou bridge occurs as an example, using steel bridge deck asphalt concrete pavement fire proposed by the present invention Maintenance process is damaged, following steps are specifically included:
Step 1:Positioning is measured, breakage subregion Field Number and description are taken pictures, the initial destroyed area in record scene;
Step 2:Construction area first clears away bridge floor dust, debris with mop, broom;Region is loosened to boss and pit Cut;Loosening inspection is carried out to whole construction surface;Air blasting blowing is carried out to surface;Area is burnt using sanding machine cleaning construction Domain, remove surface hide drift along, the debris such as fine particle;Reuse air blower cleaning and purging debris, it is ensured that free from dust, dirt Thing;Again the scope of operation measure taking pictures;Workmen puts on shoe cover, is made an overall screening with cleaning agent;With spray gun to table It is roasting that face carries out spray, it is ensured that no moisture in construction area.Construction area is made an overall screening, it is ensured that bridge floor free from dust and dirt;
Step 3:Sticking layer oil is prepared according to repairing consumption and ground brushing is carried out, wherein sticking layer oil is by host and curing agent group Into host and curing agent are poured into stainless steel using preceding, are no less than using the stirring of small hand-held electronic strong mixer 60s, then carries out hardened coating with palm fiber brush, and coating weight is 0.8kg/m2, its index is tensile strength (20 DEG C) >=7.5MPa, Fracture elongation (20 DEG C) >=180%;
Step 4:Data are measured according to conflagration area and determine consumption, mix epoxy compound is mixed to affected area Material paves, and levelling and vibrating compacting by hand, and wherein epoxy compound is by bituminous epoxy, coarse aggregate, fine aggregate and limestone mine Powder mixing mixing is formed, and mass ratio is 6.5:38:56:6, its performance technologies index is shown in Table 1;
The epoxy mixture performance technical indicator of table 1
It is used to gather materials for hard and compact, wear-resisting, grain shape preferably, and have with binder the hard stone of preferable adhesive property Material, its technical requirements is as shown in table 2 and table 3;Filler uses limestone dust, and technical requirements are shown in Table 4;
The coarse aggregate technical requirement of table 2
The fine aggregate technical requirement of table 3
The miberal powder technical requirement of table 4
Cold-mix is according to level with requiring and (being shown in Table 5) configuration material, and configuration weight is suitably put according to field patch area It is wide;
The requirement of the mineral aggregate gradation of table 5
Step 5:After the health of bottom compound to after some strength, carrying out, cover oil is brushed and cover facing material is dispensed, apply Brush and spreading scope are more than burnt area, wherein cover oil coating weight is 0.8~1.0kg/m2, its index is tensile strength (25 DEG C) >=6.0MPa, fracture elongation (25 DEG C) >=190%;Cover facing material is particle size 0-3mm fine aggregate, and coating weight is 1.0~1.2kg/m2, index meets table 3 and requires.
Step 6:Construction starts maintenance after finishing, curing time is according to the strength of materials and temperature conditional decision, and this is existing Field makes 6 test specimens, is placed on health in outdoor elements, and test intensity finally determines that opening is open to traffic the time daily.It is open to traffic When measure epoxy compound Marshall stability be 50kN, shearing strength is 20MPa, meets code requirement.

Claims (7)

1. a kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer, it is characterised in that it includes following method:
(1) maintenance area is positioned, the degree of impairment in region is confirmed;
(2) maintenance area is made an overall screening, except crude removal;
(3) the brushing sticking layer oil in the maintenance area cleared up through step (2);
(4) mix epoxy compound, after paving in the maintenance area after being handled through step (3), vibrate and be levelling, carries out health Processing;
(5) brushing cover is oily in the maintenance area after being handled through step (4) and dispenses cover facing material;
(6) after being handled through step (5), maintenance area is open to traffic through conserving to recovery.
2. according to the method described in claim 1, it is characterised in that in step (3), the consumption of described sticking layer oil be 0.7~ 0.9kg/m2;Wherein, described sticking layer oil tensile strength at 20 DEG C is not less than fracture elongation at 7.5MPa, 20 DEG C and is not less than 180%.
3. according to the method described in claim 1, it is characterised in that in step (4), described epoxy compound is dripped by epoxy It is blue or green, gather materials mixes together with limestone dust;
Wherein,
Described gathers materials including coarse aggregate and fine aggregate;
Bituminous epoxy, coarse aggregate, the mass ratio of fine aggregate and limestone dust are 6.3~6.7:30~40:50~65:5~10.
4. according to the method described in claim 1, it is characterised in that in step (4), described health processing refers to placement 1~6 My god.
5. according to the method described in claim 1, it is characterised in that in step (5), the consumption of described cover oil for 0.8~ 1.0kg/m2;Wherein, the tensile strength at 25 DEG C of the cover oil is not less than fracture elongation at 6.0MPa, 25 DEG C and is not less than 190%.
6. according to the method described in claim 1, it is characterised in that in step (5), described cover facing material is that particle size is 0 ~3mm fine aggregate, the consumption of cover facing material is 1.0~1.2kg/m2
7. according to the method described in claim 1, it is characterised in that in step (6), curing time is 20~48h.
CN201710212424.8A 2017-04-01 2017-04-01 A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer Pending CN107034760A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710212424.8A CN107034760A (en) 2017-04-01 2017-04-01 A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710212424.8A CN107034760A (en) 2017-04-01 2017-04-01 A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer

Publications (1)

Publication Number Publication Date
CN107034760A true CN107034760A (en) 2017-08-11

Family

ID=59534757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710212424.8A Pending CN107034760A (en) 2017-04-01 2017-04-01 A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer

Country Status (1)

Country Link
CN (1) CN107034760A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102276962A (en) * 2011-08-02 2011-12-14 南京路德金友新材料科技有限公司 Resin for quick cold repair of epoxy asphalt bridge floor and preparation method thereof
CN103086643A (en) * 2012-04-25 2013-05-08 北京仁创科技集团有限公司 Self-compact and quickly-cured pavement patching material, preparation method thereof and application
CN103215874A (en) * 2013-04-11 2013-07-24 同济大学 Construction method for quickly repairing pot hole of epoxy asphalt bridge deck pavement layer
WO2014002140A1 (en) * 2012-06-28 2014-01-03 オサダ技研株式会社 Pavement structure and method for producing same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102276962A (en) * 2011-08-02 2011-12-14 南京路德金友新材料科技有限公司 Resin for quick cold repair of epoxy asphalt bridge floor and preparation method thereof
CN103086643A (en) * 2012-04-25 2013-05-08 北京仁创科技集团有限公司 Self-compact and quickly-cured pavement patching material, preparation method thereof and application
WO2014002140A1 (en) * 2012-06-28 2014-01-03 オサダ技研株式会社 Pavement structure and method for producing same
CN103215874A (en) * 2013-04-11 2013-07-24 同济大学 Construction method for quickly repairing pot hole of epoxy asphalt bridge deck pavement layer

Similar Documents

Publication Publication Date Title
US20100316445A1 (en) Method for continuous on-site repaving of an asphalt mixture layer of paved road pavement and a motor-driven vehicle system therefor
CN101885870B (en) High-viscosity thin-layer bituminous mixture modifier and application thereof
CN104612048B (en) EAC bridge steel deck installation structure and construction method thereof
US20090117265A1 (en) Road and repair materials including magnetite and methods regarding same
CN105036613A (en) Crack pressure-sensitive solidification self-healing asphalt concrete, as well as preparation method and application method thereof
JP5457777B2 (en) Waterproofing method for concrete floor slabs
CN106638295A (en) Pavement method of steel bridge deck made from epoxy asphalt
CN105694786B (en) Blanket type asphaltic road-mix surface course water-base epoxy bonding agent and its construction method
CN109809772B (en) Cement mortar dry-type mixture for quick maintenance of cement pavement
CN107034760A (en) A kind of Fire-damaged method for maintaining of steel bridge deck asphalt concrete pavement layer
CN101323512A (en) Method for avoiding asphalt pavement reflection crack
CN102888808A (en) Surface layer micro-treating method of asphalt concrete pavement
JP6467087B1 (en) Asphalt mixture for thin pavement, repair method for paved road and paved road
CN110593090A (en) Method for repairing bridge expansion joint
CN103233405A (en) Old-new bituminous pavement binder course and application thereof
CN111851193B (en) Environment-friendly asphalt structure and construction method thereof
CN104746402B (en) The restorative procedure of well lid periphery damaged road surface
KR101095462B1 (en) Rapid setting cement zero concrete composition and the repairing method of concrete construction for highways using thereof
CN108516734A (en) A kind of method that oil shale residues prepare long-life environmental protection drain type asphalt road surface
JP2007085013A (en) Concrete floor slab waterproofing construction method and concrete floor slab waterproofing structure
CN109836100B (en) Dry-type repairing agent mixture for rapid maintenance of cement pavement
KR0185286B1 (en) Repairing construction of bridge deck and road
JP4022209B2 (en) Floor slab waterproofing construction method and floor slab waterproof structure
CN1016723B (en) Renewing method for ageing paving
JP2008179993A (en) Rubber latex mortar construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination