CN106988301B - A kind of intermediate strutting device for processing round steel reinforcement cage - Google Patents
A kind of intermediate strutting device for processing round steel reinforcement cage Download PDFInfo
- Publication number
- CN106988301B CN106988301B CN201710360669.5A CN201710360669A CN106988301B CN 106988301 B CN106988301 B CN 106988301B CN 201710360669 A CN201710360669 A CN 201710360669A CN 106988301 B CN106988301 B CN 106988301B
- Authority
- CN
- China
- Prior art keywords
- ring
- bar
- reinforcing bar
- reinforcing
- width
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
A kind of intermediate strutting device for processing round steel reinforcement cage of the present invention is mainly used for the processing of building engineering field filling pile cage of reinforcement and uses, its manufacturing cost is low, is quickly and expediently installed, and has versatility;The present invention is mainly made of wheel disc, width bar, casing, bar spacer, axis, support base, pedestal, reinforcing bar fixed ring;Its main operational principle is: first according to the number of steel reinforcement cage stress main reinforcement, determine the number of casing and width bar, and corresponding hole is found on wheel disc, multiple casings are screwed into respectively again in the hole of wheel disc, then multiple width bars are screwed into respectively in multiple casings, more reinforcing bars are put into the groove of bar spacer again, by the lower ring set of reinforcing bar fixed ring in the lower part of steel reinforcement cage, then the upper ring of reinforcing bar fixed ring is rotated, the connecting plate of ring up and down is finally connected with bolt and nut, reinforcing bar fixed ring is connected integral, the elastic slice in multiple card slots compresses more reinforcing bars at this time, installment work is completed, rotation steel reinforcement cage can be carried out normal stirrup welding.
Description
Technical field
Present invention is mainly used for the processing of building engineering field filling pile cage of reinforcement to use.
Background technique
The patent of the intermediate strutting device of related processing circle steel reinforcement cage having applied at present or having authorized, compares
Complexity, component is more, at high cost.
Summary of the invention
The present invention overcomes drawbacks described above, its manufacturing cost is low, are quickly and expediently installed, and have versatility;The present invention is main
By wheel disc (1), width bar (2), casing (3), bar spacer (4), axis (5), support base (7), pedestal (8), reinforcing bar fixed ring
(14) it forms;Wheel disc (1) pass through it is axis (5) and fixed thereto, the outer rim of wheel disc (1) has multiple holes (6), and hole (6) have internal screw thread, set
The lower end of pipe (3) has external screw thread (13), and in the lower end threaded through bores (6) of casing (3), the inner circle of casing (3) has internal screw thread, width bar
(2) there is external screw thread, the external screw thread of width bar (2) is screwed into the internal screw thread of casing (3), the outboard end and bar spacer of width bar (2)
(4) lower end is fixed, and reinforcing bar (11) is put into the groove of bar spacer (4);Reinforcing bar fixed ring (14) is by upper ring and a lower ring group
At the left end of upper ring and the left end of lower ring are hinged, and upper ring and lower ring can be rotated around its hinge joint, and the right end of upper ring and a lower ring is equal
It is fixed with connecting plate (12), connecting plate (12) has link bolt hole, is vertically connected with plate (12) with bolt and nut connection and consolidates reinforcing bar
Determine that ring (14) connection is integral, and upper ring and a lower ring has multiple card slots (9), is fixed with elastic slice (10) in card slot (9);Support base
(7) upper end of lower end and pedestal (8) is fixed, and the upper end of support base (7) has annular groove (15), the outer rim of reinforcing bar fixed ring (14)
It can be rolled along annular groove (15);Its main operational principle is: first according to of the pile foundation steel bar cage stress main reinforcement of layout design
Number, determines the number of casing (3) and width bar (2), and corresponding hole (6) are found on wheel disc (1), then multiple casings (3) are divided
It is not screwed into multiple holes (6) of wheel disc (1) and is arranged in multiple casings (3) equably on wheel disc (1), then by multiple width bars
(2) it is screwed into respectively in multiple casings (3), then more reinforcing bars (11) is put into the groove of bar spacer (4), rotate width bar
(2), the position of more reinforcing bars (11) is made to meet design drawing requirement, the bar spacer (4) on multiple width bars (2) will be more at this time
Root reinforcing bar (11) is withstood, then by the lower ring set of reinforcing bar fixed ring (14) in the lower part of steel reinforcement cage, and makes more reinforcing bars of lower part
(11) it is directed at the card slot (9) of ring under reinforcing bar fixed ring (14), then rotates the upper ring of reinforcing bar fixed ring (14), and makes the more of top
Root reinforcing bar (11) is directed at the card slot (9) of ring on reinforcing bar fixed ring (14), and the connecting plate of ring up and down is finally connected with bolt and nut
(12), reinforcing bar fixed ring (14) connection is integral, the elastic slice (10) in multiple card slots (9) presses more reinforcing bars (11) at this time
Tightly, installment work is completed, and rotation steel reinforcement cage can be carried out normal stirrup welding.
Detailed description of the invention
Description of symbols: 1- wheel disc, 2- width bar, 3- casing, 4- bar spacer, 5- axis, the hole 6-, 7- support base, 8-
Pedestal, 9- card slot, 10- elastic slice, 11- reinforcing bar, 12- connecting plate, 13- external screw thread, 14- reinforcing bar fixed ring, 15- annular groove.
Fig. 1 is side elevational view of the invention.
Fig. 2 is the decomposition diagram of wheel disc of the present invention Yu width bar.
Fig. 3 is the side elevational view of reinforcing bar fixed ring 14.
Fig. 4 is the local drawing of reinforcing bar fixed ring 14.
Fig. 5 is the side elevational view of support base 7, pedestal 8.
Specific embodiment
A specific embodiment of the invention has been described in detail in summary of the invention, is not repeated herein, and need to illustrate: difference is built
Build the stake diameter of the bored concrete pile of object be it is different, the quantity and diameter of steel reinforcement cage stress main reinforcement be also it is different, in order to full
This variation of foot, the present invention design multiple holes 6 on wheel disc 1, according to the number of the pile foundation steel bar cage stress main reinforcement of layout design,
It determines the number of casing 3 and width bar 2 and finds corresponding hole 6 on wheel disc 1, while can also be found in reinforcing bar fixed ring 14
The corresponding card slot 9 of stress main reinforcement thus can satisfy the needs of different stress main reinforcement quantity, and the elastic slice 10 of card slot 9, which has, to be stretched
Contracting thus can satisfy the needs of different stress main reinforcement diameters.
Claims (1)
1. a kind of intermediate strutting device for processing round steel reinforcement cage, it is characterized in that: it is mainly by wheel disc (1), width bar (2), casing
(3), bar spacer (4), axis (5), support base (7), pedestal (8), reinforcing bar fixed ring (14) composition;Wheel disc (1) passes through axis (5)
And it is fixed thereto, the outer rim of wheel disc (1) has multiple holes (6), and hole (6) have internal screw thread, and the lower end of casing (3) has external screw thread (13),
In the lower end threaded through bores (6) of casing (3), the inner circle of casing (3) has internal screw thread, and width bar (2) has external screw thread, the outer spiral shell of width bar (2)
Line is screwed into the internal screw thread of casing (3), and the lower end of the outboard end and bar spacer (4) of width bar (2) is fixed, and reinforcing bar (11) is put into
In the groove of bar spacer (4);Reinforcing bar fixed ring (14) is made of upper ring and a lower ring, and the left end of the left end of upper ring and lower ring is cut with scissors
It connects, upper ring and lower ring can be rotated around its hinge joint, and the right end of upper ring and a lower ring is respectively and fixedly provided with connecting plate (12), connecting plate (12)
Have link bolt hole, with bolt and nut connection be vertically connected with plate (12) by reinforcing bar fixed ring (14) connect it is integral, upper ring and under
Ring has multiple card slots (9), is fixed with elastic slice (10) in card slot (9);The lower end of support base (7) and the upper end of pedestal (8) are fixed,
The upper end of support base (7) has annular groove (15), and the outer rim of reinforcing bar fixed ring (14) can be rolled along annular groove (15);Its main work
It is as principle: first according to the number of the pile foundation steel bar cage stress main reinforcement of layout design, determines the number of casing (3) and width bar (2),
And corresponding hole (6) are found on wheel disc (1), then multiple casings (3) are screwed into respectively in multiple holes (6) of wheel disc (1) and are made
Multiple casings (3) are equably arranged on wheel disc (1), and then multiple width bars (2) are screwed into respectively in multiple casings (3), then will
More reinforcing bars (11) are put into the groove of bar spacer (4), rotate width bar (2), meet the position of more reinforcing bars (11) and set
Drawing requirement is counted, the bar spacer (4) on multiple width bars (2) withstands more reinforcing bars (11) at this time, then by reinforcing bar fixed ring
(14) lower ring set makes the card slot of ring under more reinforcing bars (11) alignment reinforcing bar fixed ring (14) of lower part in the lower part of steel reinforcement cage
(9), the upper ring of reinforcing bar fixed ring (14) is then rotated, and the more reinforcing bars (11) on top is made to be directed at ring on reinforcing bar fixed ring (14)
Card slot (9), finally with bolt and nut connect up and down ring connecting plate (12), by reinforcing bar fixed ring (14) connect it is integral, this
When multiple card slots (9) in elastic slice (10) more reinforcing bars (11) are compressed, installment work is completed, and rotation steel reinforcement cage can be carried out
Normal stirrup welding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710360669.5A CN106988301B (en) | 2017-05-21 | 2017-05-21 | A kind of intermediate strutting device for processing round steel reinforcement cage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710360669.5A CN106988301B (en) | 2017-05-21 | 2017-05-21 | A kind of intermediate strutting device for processing round steel reinforcement cage |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106988301A CN106988301A (en) | 2017-07-28 |
CN106988301B true CN106988301B (en) | 2019-01-04 |
Family
ID=59420596
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710360669.5A Active CN106988301B (en) | 2017-05-21 | 2017-05-21 | A kind of intermediate strutting device for processing round steel reinforcement cage |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106988301B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107685125B (en) * | 2017-08-27 | 2023-08-18 | 保利新联爆破工程集团有限公司 | Device for quickly installing reinforcement cage |
CN109954824B (en) * | 2019-04-29 | 2020-09-22 | 北京天恒建设集团有限公司 | Construction site reinforcement cage processing and manufacturing device and process |
CN111188502B (en) * | 2020-01-09 | 2021-06-04 | 中国建筑第二工程局有限公司 | A adjust bearing structure for operation is pricked to reinforcing bar |
CN111119064B (en) * | 2020-01-16 | 2021-05-04 | 天津新亚太工程建设监理有限公司 | Prefabricated supporting device for reinforcement cage of pier body of cross-sea bridge and supervision method of prefabricated supporting device |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0211268A (en) * | 1988-03-21 | 1990-01-16 | Ed Zueblin Ag | Reinforcing cage production machine |
WO2002064906A1 (en) * | 2001-02-09 | 2002-08-22 | Cagemaker Equipment Pty Ltd | A former associated with an apparatus for making cages |
CN203343650U (en) * | 2013-06-27 | 2013-12-18 | 中建七局第二建筑有限公司 | Positioning steel board for connecting large-diameter steel reinforcement cage |
CN204626440U (en) * | 2015-05-27 | 2015-09-09 | 中国葛洲坝集团股份有限公司 | Adjustable pile foundation bar reinforcement positioning device |
CN205673515U (en) * | 2016-06-12 | 2016-11-09 | 中交一公局第二工程有限公司 | Reinforcing cage stirrup dislocation type comb shape positioner |
CN205763567U (en) * | 2016-07-01 | 2016-12-07 | 安徽省交通控股集团有限公司 | Moulding bed in tunneling boring adjustable reinforced cage |
CN205857165U (en) * | 2016-07-26 | 2017-01-04 | 山东送变电工程公司 | Steel reinforcement cage main muscle position finder |
CN205926945U (en) * | 2016-08-31 | 2017-02-08 | 郑州市聚能建筑机械有限公司 | Numerical control steel reinforcement cage rolls selection dress device |
-
2017
- 2017-05-21 CN CN201710360669.5A patent/CN106988301B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0211268A (en) * | 1988-03-21 | 1990-01-16 | Ed Zueblin Ag | Reinforcing cage production machine |
WO2002064906A1 (en) * | 2001-02-09 | 2002-08-22 | Cagemaker Equipment Pty Ltd | A former associated with an apparatus for making cages |
CN203343650U (en) * | 2013-06-27 | 2013-12-18 | 中建七局第二建筑有限公司 | Positioning steel board for connecting large-diameter steel reinforcement cage |
CN204626440U (en) * | 2015-05-27 | 2015-09-09 | 中国葛洲坝集团股份有限公司 | Adjustable pile foundation bar reinforcement positioning device |
CN205673515U (en) * | 2016-06-12 | 2016-11-09 | 中交一公局第二工程有限公司 | Reinforcing cage stirrup dislocation type comb shape positioner |
CN205763567U (en) * | 2016-07-01 | 2016-12-07 | 安徽省交通控股集团有限公司 | Moulding bed in tunneling boring adjustable reinforced cage |
CN205857165U (en) * | 2016-07-26 | 2017-01-04 | 山东送变电工程公司 | Steel reinforcement cage main muscle position finder |
CN205926945U (en) * | 2016-08-31 | 2017-02-08 | 郑州市聚能建筑机械有限公司 | Numerical control steel reinforcement cage rolls selection dress device |
Also Published As
Publication number | Publication date |
---|---|
CN106988301A (en) | 2017-07-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106988301B (en) | A kind of intermediate strutting device for processing round steel reinforcement cage | |
CN107119673B (en) | A kind of steel reinforcement cage support device being applicable in piles with different diameter | |
CN110630008A (en) | Vertical shuttering | |
US3084964A (en) | Column brace and clamp assembly | |
CN104192734B (en) | General operation method for reaching given pre-tightening torque of high-strength bolt for tower crane | |
CN111203664A (en) | Manufacturing method of steel structure pipe truss | |
CN106938309A (en) | A kind of support meanss for processing circular steel reinforcement cage | |
CN104533970B (en) | A kind of attachment structure of air-expanding shaft and chuck body | |
CN208614641U (en) | A kind of screw rod locking device | |
CN104708589A (en) | Clamping device for expanding a threaded bolt | |
CN207776431U (en) | A kind of adjustable jacking | |
CN204216714U (en) | Elastic adjustable motor base | |
CN208206016U (en) | Auxiliary tripod stage apparatus for deflection of bridge span detection | |
US3883116A (en) | Spring clamp tool for servicing shock absorbers | |
KR101858539B1 (en) | Scaffold clamp for multiple support | |
DE102010034325B4 (en) | Anti-rotation device for borehole pumps | |
CN108798208A (en) | A kind of combined type lifting railing | |
CN107524682A (en) | A kind of fastener being easily installed | |
CN207592505U (en) | A kind of hand-hydraulic pipe bender | |
CN104847828A (en) | Spring hanging support | |
CN106627142A (en) | Detachable automobile instrument | |
CN202280959U (en) | Reinforced concrete tube easy to suspend and rotate in air | |
CN207017685U (en) | Simple jacking bar | |
CN105312117A (en) | Rotary type flask bracket | |
KR102273662B1 (en) | Jointing apparatus for duct and jointing method using this |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200521 Address after: 401420 7-1, building 5, Yangguang Yayuan, No. 2, Jinlan street, Wenlong street, Qijiang District, Chongqing Patentee after: Chongqing Lidong Construction Engineering Co., Ltd Address before: 448000 Hubei Province, Jingmen city Dongbao District Road No. 1 Building 6 401 aquamarine Patentee before: JINGMEN CHUANGJIA MACHINERY TECHNOLOGY Co.,Ltd. |
|
TR01 | Transfer of patent right |