CN106968454B - A kind of repair method of removing stage makeup and costume of curtain wall panel - Google Patents

A kind of repair method of removing stage makeup and costume of curtain wall panel Download PDF

Info

Publication number
CN106968454B
CN106968454B CN201710311264.2A CN201710311264A CN106968454B CN 106968454 B CN106968454 B CN 106968454B CN 201710311264 A CN201710311264 A CN 201710311264A CN 106968454 B CN106968454 B CN 106968454B
Authority
CN
China
Prior art keywords
wall panel
curtain wall
support
floor
costume
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201710311264.2A
Other languages
Chinese (zh)
Other versions
CN106968454A (en
Inventor
刘京城
刘梦溪
赵换江
王彪
刘广天
张羽
郭正宏
刘让平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mei Sihu Investment (changsha) Co Ltd
Shenyang Yuanda Aluminium Industry Group Co Ltd
Beijing Urban Construction Group Co Ltd
Original Assignee
Mei Sihu Investment (changsha) Co Ltd
Shenyang Yuanda Aluminium Industry Group Co Ltd
Beijing Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mei Sihu Investment (changsha) Co Ltd, Shenyang Yuanda Aluminium Industry Group Co Ltd, Beijing Urban Construction Group Co Ltd filed Critical Mei Sihu Investment (changsha) Co Ltd
Priority to CN201710311264.2A priority Critical patent/CN106968454B/en
Publication of CN106968454A publication Critical patent/CN106968454A/en
Application granted granted Critical
Publication of CN106968454B publication Critical patent/CN106968454B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F3/00Devices, e.g. jacks, adapted for uninterrupted lifting of loads
    • B66F3/08Devices, e.g. jacks, adapted for uninterrupted lifting of loads screw operated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D15/00Apparatus or tools for roof working
    • E04D15/04Apparatus or tools for roof working for roof coverings comprising slabs, sheets or flexible material

Abstract

The invention discloses a kind of repair method of removing stage makeup and costume of curtain wall panel, including the support being made up of floor, floor bottom is connected with regulation leg;Cradle top is connected with support platform, and self-locking thread ground jack is connected with support platform;The self-locking thread ground jack includes threaded rod, and the lower end of threaded rod is connected with hook member through support platform;Threaded rod is connected with anti-eccentric mobile sliding block, and anti-eccentric movement sliding block is connected with bracket slide, anti-eccentric mobile sliding block and the neighbouring setting of hook member;Support is removably connected with detachable support chain-wales.The present invention can lift the fast quick-detach of the curtain wall panel of plane or curved roof and installation resets, and facilitates the maintenance to roof, improves operating efficiency and manual security.

Description

A kind of repair method of removing stage makeup and costume of curtain wall panel
Technical field
The invention belongs to building field, the repair method of removing stage makeup and costume of more particularly to a kind of curtain wall panel.
Background technology
The alien invasion of existing building is often provided with curtain wall panel, such as GRC plates.The curtain wall of existing building especially higher buildings The alien invasion of building is generally arranged on by tower crane etc., after building binds, for the construction requirement in safety and remaining place etc., Tower crane can be removed.But after the completion of construction, the top surface of building needs to carry out waterproof detection.When go wrong, it is necessary to check and , it is necessary to which the curtain wall panel that roof is corresponded to place is removed when repairing waterproof layer, then overhauled.But curtain wall panel typically compares Weight, such as GRC plates, one piece of jin up to a hundred, it is placed into after being dismantled in the curtain wall panel on side, also easily by the curtain wall panel pressure on side It is broken, cause damage.Current method is manually or using the machinery such as large-scale crane by the curtain wall panel for needing to overhaul place to sling, Ground is put into, after maintenance, then building top is hung again and is installed.So install time-consuming.Especially for one A little roof shapes are the building such as theater of curved surface, artificial to move up and down, not only waste time and energy, are easily damaged curtain wall panel, Er Qierong Easily cause danger, not only expended using large-scale crane higher, be easily damaged curtain wall panel, and be not suitable for higher building and super Cross the curtain wall panel of arm of crane.
The content of the invention
To solve the above problems, the invention provides a kind of repair method of removing stage makeup and costume of curtain wall panel, the present invention can by plane or The fast quick-detach lifting of curtain wall panel and installation of curved roof reset, and facilitate the maintenance to roof, improve operating efficiency and people Work safety.
To reach above-mentioned technique effect, the technical scheme is that:
A kind of repair method of removing stage makeup and costume of curtain wall panel, comprises the following steps:
Step 1: the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is separately fixed at Awaiting Overhaul by the space between roof curtain wall panel Locate the corner of curtain wall panel;
Step 2: the curtain wall panel at Awaiting Overhaul is sling using self-locking thread ground jack;
Step 3: installing detachable support chain-wales on support, the curtain wall panel at Awaiting Overhaul is placed in detachable branch Support on chain-wales;
Checked and repaired Step 4: treating maintenance department;
Step 5: the curtain wall panel at Awaiting Overhaul is sling, detachable support chain-wales are removed;
Step 6: the curtain wall panel at Awaiting Overhaul is installed back into original position.
It is further to improve, in the step 1, it is to be checked that the support of the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is arranged on remaining Repair the corner of place's curtain wall panel;In the step 3, after the curtain wall panel at Awaiting Overhaul is placed into detachable support chain-wales, dismounting The support platform of the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is installed on the support at remaining Awaiting Overhaul, by the curtain wall at remaining Awaiting Overhaul Plate rises respectively is placed on detachable support chain-wales, to being checked and being repaired simultaneously at each Awaiting Overhaul, then respectively by curtain Wallboard installs back original position.
It is further to improve, when the roof is curved surface, in step 1, the regulation leg for apparatus for examination and repair of removing stage makeup and costume is adjusted, is protected Hold be arrangeding in parallel between support.
The apparatus for examination and repair of removing stage makeup and costume of above-mentioned curtain wall panel, including the support being made up of floor, floor bottom are connected with regulation leg; Cradle top is connected with support platform, and self-locking thread ground jack is connected with support platform;The self-locking thread ground jack includes Threaded rod, the lower end of threaded rod are connected with hook member through support platform;Threaded rod is connected with anti-eccentric mobile sliding block, anti-bias Movement sliding block is connected with bracket slide, anti-eccentric mobile sliding block and the neighbouring setting of hook member;Support is removably connected with detachably Support chain-wales.
The regulation leg includes the T-bolt being connected with breathing out fragrant groove, and adjusting nut, T-bolt are arranged with T-bolt On be arranged with adjusting nut coordinate sleeve, sleeve be provided with floor coordinate link slot.
The self-locking thread ground jack includes limiter, is provided between limiter and support platform and is threadedly coupled with threaded rod Outer-hexagonal circulator, be arranged with spanner outside outer-hexagonal circulator, the top and bottom of outer-hexagonal circulator pass through load-bearing respectively Bearing connects limiter and support platform.
The anti-eccentric mobile sliding block includes the cage plate being set on support, and cage plate axis connection has the pulley coordinated with floor Structure;Cage plate is provided with the connecting hole with shaft.
The floor includes the first floor and the second floor;First floor and the second floor are disposed adjacent, on the first floor The first mounting hole provided with inverted L shape, the first mounting hole include transverse holes and vertical hole;Second floor is provided with the second mounting hole, Second mounting hole is slotted hole;The peace for connecting the first mounting hole and the second mounting hole respectively is fixed with detachable support chain-wales Bolt is filled, installation bolt is threaded with installation nut.
Further to improve, the threaded rod is trapezoidal screw.
Further to improve, the support includes four floors, and the section of support is crosswise.
Further to improve, the detachable support chain-wales include top plate, left plate and dorsal plate;Left plate and dorsal part Plate is connected to reinforcing plate, and the junction indent of left plate and dorsal plate is formed with interior to groove.
Further to improve, the pulley structure includes the connector being fixed on cage plate, and connector is fixed with rotating shaft, turns Bearing is fixed with axle, bearing is provided with the chute coordinated with floor.
Further to improve, the support platform is provided with the slot coordinated with floor, and support platform passes through fixing bolt It is detachably connected with floor.
Further to improve, the transverse holes are wider than vertical hole.
The present invention can lift the fast quick-detach of the curtain wall panel of plane or curved roof and installation resets, and facilitates to roof Maintenance, improves operating efficiency and manual security.
Brief description of the drawings
Fig. 1 installs and uses schematic diagram for the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel;
Fig. 2 is the overall structure diagram of the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel;
Fig. 3 is the dimensional structure diagram of the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel;
Fig. 4 is the structural representation tank figure of regulation leg;
Fig. 5 is the structural representation of the first floor and the second floor;
Fig. 6 is the side structure schematic diagram of detachable support chain-wales;
Fig. 7 is the perspective structure perspective diagram of detachable support chain-wales;
Fig. 8 is the dimensional structure diagram of detachable support chain-wales;
Fig. 9 is the overlooking the structure diagram of anti-eccentric mobile sliding block;
Figure 10 is the demountable structure schematic diagram of support platform.
Embodiment
Illustrated below by way of embodiment and with reference to accompanying drawing to technical scheme.
Embodiment 1
The installation method of the apparatus for examination and repair of removing stage makeup and costume of the present invention is as shown in Figure 1.Curtain wall panel of the invention as shown in Figures 2 and 3 Apparatus for examination and repair of removing stage makeup and costume, including the support 2 being made up of floor 1, the bottom of floor 1 is connected with regulation leg 3;The top of support 2 connects There is support platform 4, self-locking thread ground jack 5 is connected with support platform 4;The self-locking thread ground jack 5 includes threaded rod 51, The lower end of threaded rod 51 is connected with hook member 52 through support platform 4;Threaded rod 51 is connected with anti-eccentric mobile sliding block 6, anti-bias The heart moves sliding block 6 and is slidably connected with support 2, anti-eccentric mobile sliding block 6 and the neighbouring setting of hook member 52;Support 2 is detachably connected There are detachable support chain-wales 7.
The utility model makes the support 2 of curtain wall panel corner be vertically arranged or phase in use, adjustment regulation leg 3 first Mutually be arranged in parallel, then sling curtain wall panel using the rotating threaded rod 51 of self-locking thread ground jack 5, then install detachably support it is small Platform 7 is fixed to supporting curtain wall panel on floor 1, by roof maintenance corresponding to curtain wall panel after, disassemble detachable support Chain-wales 7, curtain wall panel is fallen using the rotating threaded rod 51 of self-locking thread ground jack 5, makes curtain wall panel homing.
As shown in figure 4, the regulation leg 3 includes the T-bolt 32 being connected with breathing out fragrant groove 31, it is arranged on T-bolt 32 There is adjusting nut 33, the sleeve 34 coordinated with adjusting nut 33 is arranged with T-bolt 32, sleeve 34 is provided with matches somebody with somebody with floor 1 The link slot 35 of conjunction.It can so be jacked up by rotating adjusting nut 33 or fall sleeve 34, so as to adjust the height of each floor 1 Degree, and then adjust the gradient of each support 2.
As shown in Fig. 2 the self-locking thread ground jack 5 includes limiter 53, it is provided between limiter 53 and support platform 4 The outer-hexagonal circulator 54 being threadedly coupled with threaded rod 51, outer-hexagonal circulator are arranged with spanner 55, outer-hexagonal circulator 54 outside Top and bottom pass through load-bearing bearing 56 respectively and connect limiter 53 and support platform 4.So outer six are pulled using spanner 55 Angle circulator 54 can elevating screw thread bar 51.Spanner 55 rotates outer-hexagonal circulator 54 to after certain angle, and upstream or downstream arrive Load-bearing bearing 56, reversely rotate to original position and pack into outer-hexagonal circulator 54 again, so that spanner 55 is only in the side of threaded rod 51 Activity can be achieved lifting to threaded rod 51, influence each other during four station manipulations for preventing curtain wall panel corner.
The anti-eccentric mobile sliding block 6 includes the cage plate 61 being set on support 2, and the axis connection of cage plate 61 has matches somebody with somebody with floor 1 The pulley structure 62 of conjunction;Cage plate 61 is provided with the connecting hole 63 coordinated with threaded rod 51.Anti- eccentric mobile sliding block 6, which has, undertakes water Divide the effect of power equally, when anti-eccentric mobile sliding block 6 is used to prevent that support 2 from tilting, curtain wall panel is to torque mistake caused by threaded rod 51 Greatly, threaded rod 51 is bent or fractureed.Due to the mobile sliding block 6 of anti-bias and the neighbouring setting of hook member 52, therefore anti-bias is mobile Curtain wall panel is to oblique pressure conduction caused by threaded rod 51 to support member when sliding block 6 can tilt support 2, so as to prevent threaded rod 51 are bent or fracture.
As shown in Figure 2 and Figure 5, the floor 1 includes the first floor 11 and the second floor 12;First floor 11 and the second rib Plate 12 is disposed adjacent, and the first floor 11 is provided with the first mounting hole 13 of inverted L shape, and the first mounting hole 13 includes the He of transverse holes 131 Vertical hole 132;Second floor 12 is provided with the second mounting hole 14, and the second mounting hole 14 is slotted hole;Detachable support chain-wales 7 On be fixed with the installation bolt 71 for connecting the first mounting hole 13 and the second mounting hole 14 respectively, installation bolt 71 is threaded with peace Loading nut 72.Such setting is easy to Fast Installation detachably to support chain-wales 7.Transverse holes 131 are preferably wider than vertical hole 132. The installation bolt 71 of dorsal plate 75 is inserted into transverse holes 131 first during installation, then moved inward so that the installation of left plate 74 Bolt 71 inserts the second mounting hole 14, and then detachably support chain-wales 7 move downward so that the installation bolt 71 of dorsal plate 75 The bottom of the vertical mounting hole 14 of hole 132 and second is reached with the installation bolt 71 of left plate 74, then can quickly be fixed. So eliminating must can just enter detachable support chain-wales 7 while the mounting hole of the first floor 11 of alignment and the second floor 12 The trouble of row installation, accelerate the installation and removal speed of detachable support chain-wales 7.Transverse holes 131 are wider than vertical hole 132, During so that pulling down and install detachable support chain-wales 7, only installation bolt 71 is unscrewed, without taking completely, enters one Step accelerates installation rate.
Threaded rod 51 is trapezoidal screw.
Support 2 preferably includes four floors 1, and the section of support 2 is crosswise.Support 2 only includes the first floor 11 and the Two floors 12 can also be used, but not as setting four floors 1 firm.
As Figure 6-Figure 8, the detachable support chain-wales 7 include top plate 73, left plate 74 and dorsal plate 75;Left side Plate 74 and dorsal plate 75 are connected to reinforcing plate 76, and the junction indent of left plate 74 and dorsal plate 75 is formed with interior to groove 77.Reinforcing plate 76 make it that detachable support chain-wales 7 are firmer, interior to groove 77 detachable support chain-wales 7 to be installed Activity space big Shi Yougeng, do not have because making not accurate enough so that part is difficult to coordinate and causes installation difficulty, simultaneously Support further is formd to left plate 74 and dorsal plate 75.
As shown in figure 9, pulley structure 62 includes the connector 621 being fixed on cage plate 61, connector 621 is fixed with rotating shaft 622, bearing 623 is fixed with rotating shaft 622, bearing 623 is provided with the chute 624 coordinated with floor 1.
As shown in Figure 10, support platform 4 is provided with the slot 41 coordinated with floor 1, and support platform 4 passes through fixing bolt 42 It is detachably connected with floor 1.Such structure is easy to continuous while constructed.
Embodiment 2
A kind of repair method of removing stage makeup and costume of curtain wall panel, comprises the following steps:
Step 1: the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is separately fixed at Awaiting Overhaul by the space between roof curtain wall panel Locate the corner of curtain wall panel;When the roof is curved surface, regulation is removed stage makeup and costume the regulation leg 3 of apparatus for examination and repair, keeps flat between support 2 Row is set;
Step 2: the curtain wall panel at Awaiting Overhaul is sling using self-locking thread ground jack 5;
Step 3: installing detachable support chain-wales 7 on support 2, the curtain wall panel at Awaiting Overhaul is placed in detachably Support on chain-wales 7;
Checked and repaired Step 4: treating maintenance department;
Step 5: the curtain wall panel at Awaiting Overhaul is sling, detachable support chain-wales 7 are removed;
Step 6: the curtain wall panel at Awaiting Overhaul is installed back into original position.
In order to accelerate construction progress, above-mentioned step can carry out following improve:In the step 1, by removing stage makeup and costume for curtain wall panel The support 2 of apparatus for examination and repair is arranged on the corner of curtain wall panel at remaining Awaiting Overhaul;In the step 3, by the curtain wall panel at Awaiting Overhaul After being placed into detachable support chain-wales 7, the support platform 4 for dismantling the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is installed to remaining Awaiting Overhaul On the support at place, the curtain wall panel at remaining Awaiting Overhaul is risen respectively and is placed on detachable support chain-wales 7, at each Awaiting Overhaul Checked and repaired simultaneously, curtain wall panel is then installed back into original position respectively.So can be right with a set of equipment and multiple supports 2 Multiple stations are overhauled simultaneously, accelerate overhaul efficiency.
The specific guiding embodiment of the present invention is above are only, but the design concept of the present invention is not limited thereto, All changes for carrying out unsubstantiality to the present invention using this design, all should belong to the behavior for invading protection scope of the present invention.

Claims (8)

1. the repair method of removing stage makeup and costume of a kind of curtain wall panel, it is characterised in that comprise the following steps:
Step 1: the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel is separately fixed at curtain at Awaiting Overhaul by the space between roof curtain wall panel The corner of wallboard;
The apparatus for examination and repair of removing stage makeup and costume of the curtain wall panel includes the support (2) being made up of floor (1), and floor (1) bottom is connected with regulation Leg (3);Support platform (4) is connected with the top of support (2), self-locking thread ground jack (5) is connected with support platform (4);Institute Stating self-locking thread ground jack (5) includes threaded rod (51), and the lower end of threaded rod (51) is connected with hook member through support platform (4) (52);Threaded rod (51) is connected with anti-eccentric mobile sliding block (6), and anti-eccentric mobile sliding block (6) is slidably connected with support (2), prevented The mobile sliding block (6) of bias and the neighbouring setting of hook member (52);Support (2) is removably connected with detachable support chain-wales (7);
The regulation leg (3) includes the T-bolt (32) being connected with breathing out fragrant groove (31), and T-bolt is arranged with regulation on (32) Nut (33), the sleeve (34) coordinated with adjusting nut (33) is arranged with T-bolt (32), sleeve (34) is provided with and floor (1) link slot (35) coordinated;
The self-locking thread ground jack (5) includes limiter (53), is provided between limiter (53) and support platform (4) and screw thread The outer-hexagonal circulator (54) of bar (51) threaded connection, outer-hexagonal circulator are arranged with spanner (55), outer-hexagonal circulator outside (54) top and bottom connect limiter (53) and support platform (4) by load-bearing bearing (56) respectively;
The anti-eccentric mobile sliding block (6) includes the cage plate (61) being set on support (2), and cage plate (61) axis connection has and floor (1) pulley structure (62) coordinated;Cage plate (61) is provided with the connecting hole (63) coordinated with threaded rod (51);
The floor (1) includes the first floor (11) and the second floor (12);First floor (11) and the second floor (12) are adjacent Set, the first floor (11) be provided with inverted L shape the first mounting hole (13), the first mounting hole (13) include transverse holes (131) and Vertical hole (132);Second floor (12) is provided with the second mounting hole (14), and the second mounting hole (14) is slotted hole;Detachable branch The installation bolt (71) for connecting the first mounting hole (13) and the second mounting hole (14) respectively is fixed with support chain-wales (7), is installed Bolt (71) is threaded with installation nut (72);
Step 2: the curtain wall panel at Awaiting Overhaul is sling using self-locking thread ground jack (5);
Step 3: installing detachable support chain-wales (7) on support (2), the curtain wall panel at Awaiting Overhaul is placed in detachably Support on chain-wales (7);
Checked and repaired Step 4: treating maintenance department;
Step 5: the curtain wall panel at Awaiting Overhaul is sling, detachable support chain-wales (7) are removed;
Step 6: the curtain wall panel at Awaiting Overhaul is installed back into original position.
2. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that in the step 1, by curtain wall panel Apparatus for examination and repair of removing stage makeup and costume support (2) be arranged on remaining Awaiting Overhaul at curtain wall panel corner;In the step 3, at Awaiting Overhaul Curtain wall panel be placed into detachable support chain-wales (7) after, dismantle support platform (4) installation of the apparatus for examination and repair of removing stage makeup and costume of curtain wall panel On support at remaining Awaiting Overhaul, the curtain wall panel at remaining Awaiting Overhaul is risen respectively and is placed on detachable support chain-wales (7), to being checked and being repaired simultaneously at each Awaiting Overhaul, curtain wall panel is then installed back into original position respectively.
3. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that when the roof is curved surface, step In one, regulation is removed stage makeup and costume the regulation leg (3) of apparatus for examination and repair, keeps be arrangeding in parallel between support (2).
4. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that the threaded rod (51) is trapezoidal spiral shell Bar.
5. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that the support (2) includes four ribs Plate (1), the section of support (2) is crosswise.
6. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that the detachable support chain-wales (7) top plate (73), left plate (74) and dorsal plate (75) are included;Left plate (74) and dorsal plate (75) are connected to reinforcing plate (76), the junction indent of left plate (74) and dorsal plate (75) is formed with interior to groove (77).
7. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that the pulley structure (62) includes solid The connector (621) being scheduled on cage plate (61), connector (621) are fixed with rotating shaft (622), and rotating shaft is fixed with bearing on (622) (623), bearing (623) is provided with the chute (624) coordinated with floor (1).
8. the repair method of removing stage makeup and costume of curtain wall panel as claimed in claim 1, it is characterised in that the support platform (4) is provided with The slot (41) coordinated with floor (1), support platform (4) are detachably connected by fixing bolt (42) and floor (1).
CN201710311264.2A 2016-06-29 2016-06-29 A kind of repair method of removing stage makeup and costume of curtain wall panel Expired - Fee Related CN106968454B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710311264.2A CN106968454B (en) 2016-06-29 2016-06-29 A kind of repair method of removing stage makeup and costume of curtain wall panel

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610496711.1A CN106044610B (en) 2016-06-29 2016-06-29 Remove stage makeup and costume apparatus for examination and repair and the method for a kind of curtain wall panel
CN201710311264.2A CN106968454B (en) 2016-06-29 2016-06-29 A kind of repair method of removing stage makeup and costume of curtain wall panel

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610496711.1A Division CN106044610B (en) 2016-06-29 2016-06-29 Remove stage makeup and costume apparatus for examination and repair and the method for a kind of curtain wall panel

Publications (2)

Publication Number Publication Date
CN106968454A CN106968454A (en) 2017-07-21
CN106968454B true CN106968454B (en) 2018-04-10

Family

ID=57167410

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610496711.1A Active CN106044610B (en) 2016-06-29 2016-06-29 Remove stage makeup and costume apparatus for examination and repair and the method for a kind of curtain wall panel
CN201710311264.2A Expired - Fee Related CN106968454B (en) 2016-06-29 2016-06-29 A kind of repair method of removing stage makeup and costume of curtain wall panel

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610496711.1A Active CN106044610B (en) 2016-06-29 2016-06-29 Remove stage makeup and costume apparatus for examination and repair and the method for a kind of curtain wall panel

Country Status (1)

Country Link
CN (2) CN106044610B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108824713A (en) * 2018-07-17 2018-11-16 芜湖芬特勘测服务有限公司 A kind of roof is with stablizing strong snow removing equipment
CN111456481B (en) * 2020-05-07 2020-11-10 广州市白云第五建筑工程有限公司 Building curtain wall replacing and maintaining device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008248664A (en) * 2007-03-30 2008-10-16 Shimizu Corp Hoisting method of curtain wall
CN201343871Y (en) * 2008-12-31 2009-11-11 安徽省第一建筑工程公司 Curtain wall moving plate support
CN202280256U (en) * 2011-05-04 2012-06-20 沈阳远大铝业工程有限公司 Lifting tool for unit curtain wall
CN105178979A (en) * 2015-08-28 2015-12-23 中铁二十五局集团第四工程有限公司 Supporting structure of tunnel in bias salt cavity environment and construction method of supporting structure
CN105464269A (en) * 2016-01-13 2016-04-06 南京倍立达新材料系统工程股份有限公司 Roofing curved decorative plate connecting structure and dismounting method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205873774U (en) * 2016-06-29 2017-01-11 北京城建集团有限责任公司 Maintenance device of removing stage makeup and costume of curtain board

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008248664A (en) * 2007-03-30 2008-10-16 Shimizu Corp Hoisting method of curtain wall
CN201343871Y (en) * 2008-12-31 2009-11-11 安徽省第一建筑工程公司 Curtain wall moving plate support
CN202280256U (en) * 2011-05-04 2012-06-20 沈阳远大铝业工程有限公司 Lifting tool for unit curtain wall
CN105178979A (en) * 2015-08-28 2015-12-23 中铁二十五局集团第四工程有限公司 Supporting structure of tunnel in bias salt cavity environment and construction method of supporting structure
CN105464269A (en) * 2016-01-13 2016-04-06 南京倍立达新材料系统工程股份有限公司 Roofing curved decorative plate connecting structure and dismounting method thereof

Also Published As

Publication number Publication date
CN106968454A (en) 2017-07-21
CN106044610A (en) 2016-10-26
CN106044610B (en) 2017-06-06

Similar Documents

Publication Publication Date Title
CN205077845U (en) Building core section of thick bamboo well hydraulic pressure intelligence operation scaffold that climbs
CN108678422B (en) Method for dismantling steel chimney
KR101553966B1 (en) Wall-mounted Tower Crane Climbing Device
CN102155089A (en) Self-jacking construction platform integrating vertical transportation equipment and mold base
CN201826516U (en) Novel attached lifting scaffold
CN101538936A (en) Hydraulic slip-and-lift construction method for water tower, hydraulic slip-form device, lifting device and hanger rod connecting piece thereof
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN106968454B (en) A kind of repair method of removing stage makeup and costume of curtain wall panel
CN103867022B (en) One is carried and is touched formula concrete chimney construction method
CN211971631U (en) Pipeline lifting and transporting device
CN105178584A (en) Assembled house out-hung scaffold system and construction method
CN203654702U (en) Operating platform for construction of reinforced concrete chimney
CN104929353A (en) Detachable stepwise automatic climbing operating platform for elevator shafts
CN205773024U (en) A kind of convenient pipeline lifting auxiliary device
CN202139255U (en) Tooling platform for assembling converter body equipment
CN205873774U (en) Maintenance device of removing stage makeup and costume of curtain board
CN105003070A (en) Bilayer extensible unloading platform for building construction
CN205777648U (en) A kind of curtain wall panel is removed stage makeup and costume the anti-eccentric mobile slide block of apparatus for examination and repair
CN205838435U (en) A kind of have the detachable curtain wall panel supporting chain-wales and remove stage makeup and costume apparatus for examination and repair
CN205838434U (en) A kind of remove stage makeup and costume apparatus for examination and repair with regulation leg curtain wall panel
CN205777649U (en) The curtain wall panel that a kind of band bias moves slide block is removed stage makeup and costume apparatus for examination and repair
CN205777646U (en) A kind of curtain wall panel is removed stage makeup and costume the self-locking thread ground jack of apparatus for examination and repair
CN207144446U (en) A kind of construction Skidproof hanging cradle
CN214995818U (en) Climbing type construction operation platform outside building
CN113309256A (en) Construction device and construction method for prefabricated shear wall with post-pouring section

Legal Events

Date Code Title Description
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180410

CF01 Termination of patent right due to non-payment of annual fee