CN106945169B - High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment - Google Patents
High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment Download PDFInfo
- Publication number
- CN106945169B CN106945169B CN201611226169.4A CN201611226169A CN106945169B CN 106945169 B CN106945169 B CN 106945169B CN 201611226169 A CN201611226169 A CN 201611226169A CN 106945169 B CN106945169 B CN 106945169B
- Authority
- CN
- China
- Prior art keywords
- tensioning
- bed seat
- stretching bed
- oil cylinder
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28B—SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
- B28B23/00—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
- B28B23/02—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
- B28B23/04—Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
- B28B23/043—Wire anchoring or tensioning means for the reinforcements
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Chemical & Material Sciences (AREA)
- Ceramic Engineering (AREA)
- Mechanical Engineering (AREA)
- Metal Extraction Processes (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Moulds For Moulding Plastics Or The Like (AREA)
Abstract
A kind of high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, stretching bed seat is supported by universal pearl by the ground support of level altitude, stretching bed seat is fixed with stretch power mechanism, earth's surface is provided with track board assembly line transhipment track on the inside of ground support, and transhipment track both sides are provided with track plates positioning support.Stretching bed seat is highly fixedly installed the present invention, and mould is corresponding with the height of stretching bed seat during operation, is not required to adjust operation height again.Simply, it is time saving, laborsaving.Traversing oil cylinder and feed cylinder are set so that stretching bed seat positioning, it is in place when can it is more flexible, accurately.Stretch power mechanism can reduce equipment volume, stretch power is more abundant, and stretching process is succinct, smooth using double oil cylinders or Multi-cylinder combination.
Description
Technical field
The present invention relates to reinforced bar stretching equipment special on the non-fragment orbit board assembly line laid on a kind of high-speed railway, tool
Body is high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment.
Background technology
The pre-tensioning system production high speed railway fragments-free track slab of prior art mainly uses fixed base method, in this way
Stretching process be to be shared a tensioning walking beam while to drive more reinforced bar stretchings by eight pedestals, the deficiency of this technique is
Tensioning precision is low, and manpower intervention link is more, and the utilization rate of mould is relatively low, and production efficiency is low, and occupation area of equipment is big, soil
Second ploughing difficulty is high, while needs lifting operation more, and equipment investment is larger.
The content of the invention
The present invention is in view of the above-mentioned problems, provide high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment.
It is low to solve automaticity existing for existing similar technique, tensioning mold is in place complicated and the problems such as positioning, tensioning low precision.
A kind of high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, including lateral tensioning equipment and hold to
Tensioning equipment, described lateral tensioning equipment include the base rigidly fixed with ground and the side stretching bed being placed on the base
Seat, described end includes the base rigidly fixed with ground and the end stretching bed seat being placed on the base, institute to tensioning equipment
The side stretching bed seat stated is respectively fixed with side stretch power mechanism and end stretch power mechanism with holding on stretching bed seat, it is characterized in that
The ground support that described base includes at least two independently of each other and height is fixed, described ground support inner side earth's surface are set
Track board assembly line transhipment track is equipped with, described transhipment track both sides are provided with positioning support.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that described ground branch
Seat top is fixed with end plate, and Universal caster is provided with the end plate, and described side stretching bed seat, end stretching bed seat pass through universal
Ball is placed on the ground support of respective bottom.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that being provided with side feeding
Oil cylinder, one end of the side feed cylinder are connected with ground support, and the other end is connected with side stretching bed seat;It is provided with and holds into oil supply
Cylinder, one end of the end feed cylinder are connected with homonymy ground support, and the other end is connected with end stretching bed seat.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that the side stretching bed
The end set of seat has a traversing oil cylinder in side, the base of the traversing oil cylinder of side stretching bed seat be connected respectively with rod end ground support and
Side stretching bed seat;The end set of the end stretching bed seat has the traversing oil cylinder in end, base and the rod end point of the traversing oil cylinder in end
Not Lian Jie homonymy ground support with end stretching bed seat.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that described side tensioning
Actuating unit is made up of at least two tensioning oil cylinders being fixed as one side by side, and the tensioning oil cylinder is fixed by guide plate and guide pillar
On the stretching bed seat of side;Described end stretch power mechanism includes the two tensioning oil cylinder groups vertically overlapped, each tensioning oil cylinder
Group comprises at least two tensioning oil cylinders being fixed as one, and two groups of tensioning oil cylinders are fixed on end tensioning by guide pillar and guide pin bushing
On pedestal, the tension rod chain joint being connected with tension rod is provided with, the tensioning oil cylinder rod end is connected with tension rod chain joint, institute
State and mesopore i.e. tensioning rod aperture is provided with tension rod chain joint.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that being provided with positioning lock
Tight mechanism, described location locking mechanism include a geared sleeve, and the geared sleeve rear end face links end surface phase with tension rod
Connect, geared sleeve central through hole is the tensioning rod aperture concentric with tension rod chain joint, and the tensioning rod aperture of the tension rod chain joint is justified
It is provided with limit screw week, the geared sleeve neighboring is provided with the boss matched with the limit screw, before the geared sleeve
End face is formed with locking groove, has locking gear on the geared sleeve circumference, the top of the geared sleeve is provided with hydraulic motor, described
The drive gear of hydraulic motor engages with locking gear.
Described high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, it is characterized in that tension rod chain joint
Upper and tensioning rod aperture is vertically installed with plugboard trough, has plate in the plugboard trough, dibit rod aperture, adjacent chain are formed with the plate
Plate in joint is engaged, and forms a plate group, and A action tanks and B action oil are respectively arranged with plate group both ends
Cylinder, the A action tanks are engaged with the plate of respective side and associated respectively with the rod end of B action tanks.
The high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment of the present invention, stretching bed seat is highly fixed
Set, and the positioning support of level altitude is set on the inside of pedestal, when mould is positioned on positioning support during operation i.e. and tensioning
The height of pedestal is corresponding, is not required to adjust operation height again.Simply, it is time saving, laborsaving.Ten thousand are used between stretching bed seat and ground support
To pearls knot structure, make stretching bed seat convenient when making longitudinal and transverse mobile, flexibly, resistance is small.Stretching bed seat both sides and rear portion set horizontal stroke respectively
Move oil cylinder and feed cylinder so that stretching bed seat positioning, it is in place when can be more flexible, accurately.Stretch power mechanism is using double oil
Cylinder or Multi-cylinder combination, can reduce equipment volume, and stretch power is more abundant, and stretching process is succinct, smooth.Using hydraulic pressure horse
Covered up to mate gear and carry out positioning and locking, it is ensured that registration, locking are reliable in time.
Production line of the present invention by the way of the high form of support saddle frame rather than melt pit pedestal, transition is simple, and soil second ploughing is difficult
Degree reduces, and floor space is small;Using track operation system, fabrication does not need hanging device intervention, and after track plates
It is continuous pour, solidifying process etc. is not take up tensioning station, production flow efficiency high;The tensioning of tensioning equipment automatic butt tension rod, from
Dynamic to carry out tensioning locking, tensioning process automaticity is high, prosthetic intervention;Single steel bar tensioning makes tensioning precision controlling more smart
Really.
Brief description of the drawings
Fig. 1 is tensioning equipment job state schematic diagram;
Fig. 2 is held to tensioning equipment structural representation;
Fig. 3 is lateral tensioning equipment structural representation;
Fig. 4 is Fig. 3 C portion structure enlarged diagrams;
Fig. 5 is this stretch power mechanism and location locking mechanism structural representation;
Fig. 6 is location locking mechanism fragmentary sectional view in Fig. 5;
Fig. 7 is location locking mechanism assembling schematic diagram;
Fig. 8 is board plug structure schematic diagram;
Fig. 9 is flashboard mechanism schematic diagram;
Figure 10 is double tensile oil cylinder group structural representation.
In figure, 1-A action tanks;2- gear-boxes;3- hydraulic motors;4- fixed plates;5- back guides;6- stretch boards;7-
Draw oil cylinder;8- indulges connecting plate;9- front guides;10- backing plates;11- tensioning rod aperture;12- drive gears;13- geared sleeves;14- is locked
Gear;15- tension rod chain joints;16- external tooth form boss;17- tension rods;18- locking grooves;19- plugboard troughs;20- turning slots;
21- limit screws;22- boss;23- positioning heads;24- oil cylinders are cut somebody's hair;25- push rods;26- plates;27-B action tanks;28- sides
Lian Kong;29- dibit rod aperture;The stretch boards of 30- second;31- the second oil cylinder groups;The plates of 32- second;101- ends are to tensioning equipment;
102- moulds;The lateral tensioning equipments of 103-;104- positioning supports;105- transportation trolleys;106- tracks;107- ground supports;
108- curb girders;110- sides stretching bed seat;111- ends stretching bed seat;The traversing oily cylinder in 113- ends;114- ends oil cylinder in place;115- enters at end
To oil cylinder;116- ends positioning guide pulleys;The traversing oil cylinder in 118- sides;122- sides feed cylinder;123- sides oil cylinder in place;124- determines side
Position directive wheel.
Embodiment
Below in conjunction with accompanying drawing, the present invention is described in detail.
The present invention is one group of key equipment in high speed railway fragments-free track slab flowing water unit production line, its invention thought be with
Hydraulic-driven, control realize tensioning equipment full-automation operation for core.
Shown in Fig. 1-4, according to the type track plates design standard of high-speed railway III, need placement longitudinal in track plates and laterally pre-
Stress reinforcing bar, tensioning is carried out before shaping and is allowed to produce stress and fixation.Accordingly, tensioning equipment bidirectional arrangements, longitudinal direction in figure
Tensioning equipment 101 and lateral tensioning equipment 103 are arranged in the tensioning position of the both sides in length and breadth of railway plate die 102.Mould is by transporting
Turn dolly 105 and be transported to tensioning station along track 106, four positioning supports 104 for waiting height setting are fixed with track both sides.Fortune
Turn that mould is put on four positioning supports after dolly enters setting position, determine on the positioning table and positioning support of mold bottom
Position groove is corresponding to position mould.Now, mould has determined that in the operation height of the station.In Fig. 2, hold to tensioning equipment 101 and wrap
End stretching bed seat 111 is included, the end stretching bed seat is rigidly fixed by two with ground and height identical ground support 107 supports.
Wherein ground support can be more than two, be set according to being actually needed.Lateral tensioning equipment 103 is contour including four in Fig. 3
Ground support 107 and the side stretching bed seat 110 that is fixed thereon.
The height of above-mentioned ground support is fixed.And ground support, end/side stretching bed seat and it is fixed on stretching bed seat
Tensioning equipment overall height is corresponding with the whole height of positioning support, mould, need to only make horizontal location adjustment during tensioning operation i.e.
Can.Horizontal end plate is fixed with ground support top, one or several grooves are formed with end sheet surface, places and rolls in groove
Pearl, referred to as Universal caster, end/side stretching bed seat are placed on the ground support by Universal caster.Adopt the structure so that
Stretching bed seat can make any adjustment in the horizontal direction.
Shown in Fig. 2, the side of end stretching bed seat 111 is provided with the traversing oil cylinder 113 in end, rod end, the base of the traversing oil cylinder
Ground support and end stretching bed seat are connected respectively.By the traversing oil cylinder in the end end stretching bed seat can be made to carry out lateral displacement.It is above-mentioned
Hold traversing oil cylinder at both ends while can set.The rear portion of the end stretching bed seat is provided with one or several end feed cylinders
115, the rod end of described end feed cylinder is also connected ground support and end stretching bed seat with base respectively.Hold feed cylinder 115
Effect be to make stretching bed seat overall in stretching process to be conveniently adjusted positioning to mould longitudinal end is close.Shown in figure, at end
The one or both ends of pedestal are drawn to be also equipped with oil cylinder 114 in place, its effect is to make tensioning oil cylinder and the tensioning on the stretching bed seat of end
Location locking mechanism enters tensioning position.
Shown in Fig. 3 and Fig. 4, the one or both ends of side stretching bed seat 110 are provided with the traversing oil cylinder 118 in side, in side stretching bed
The rear portion of seat is provided with one or more side feed cylinder 122, and the mounting structure of each oil cylinder is equally by rod end and base
Ground support and side stretching bed seat are connected respectively.It is side stretching bed seat carried out transverse shifting or feeding, exited operation that it, which is acted on,.
In side, the both ends of stretching bed seat are also equipped with side oil cylinder 123 in place.
In Fig. 2-4, the front end Angle Position of end stretching bed seat and side stretching bed seat, end positioning guide pulleys 116 are respectively provided with
With side positioning guide pulleys 124, by making stretching bed seat with the positioning table of tensioning mold relevant position/plate matches respectively both this
It is accurate positioning, simplicity, quick.
The tensioning equipment being mounted in shown in Fig. 5 on the stretching bed seat of side, several are arranged in juxtaposition on the stretching bed seat of side
With the one-to-one tensioning equipment of respective side tension rod on railway plate die.The tensioning equipment includes tensioning oil cylinder and positioning and locking
Mechanism, wherein tensioning oil cylinder substantially form a tensioning oil cylinder group or referred to as stretch power mechanism by two tensioning oil cylinders 7,
Pulling force is directly applied to reinforcing bar by it.Tensioning oil cylinder is by being fixed on stretching bed seat horizontally disposed guide pillar and being matched with guide pillar
Guide plate be arranged on stretching bed seat on.Curb girder 108 is provided with tensioning equipment rear portion, each tensioning equipment rigidly connects with curb girder respectively
Connect, the rod end of side oil cylinder 123 in place is connected with curb girder.Two longitudinal directions of tensioning oil cylinder 7 configure and installed in fixation in the present embodiment
Between plate 4 and back guide 5, stretch board 6 is provided with the outside of back guide, the rod end of two tensioning oil cylinders is fixed on the stretch board 6.
A pull bar is fixed with tension rod 6, the front end of the pull bar is fixedly connected with a tension rod chain joint 15.Tension rod chain joint
Mesopore is tensioning rod aperture.Shown in figure, by being fixedly connected to connecting plate 8 between fixed plate 4 and front guide 9, front guide top
For gear-box 2, there is tensioning rod aperture 11 in gear-box front plate, backing plate 10 is fixed with the both sides in hole.
Shown in Fig. 6-7, a geared sleeve 13 is provided with front guide upper gear case 2, the geared sleeve central through hole is
Tie rod hole, there is a locking gear 14 on geared sleeve circumferential body, the drive gear 12 of the locking gear 14 and hydraulic motor 3(It is defeated
Go out gear)Engagement.The rear portion of geared sleeve 13 connects with the front end face of tension rod chain joint 15.In the tensioning of tension rod chain joint
Rod aperture circumference is provided with limit screw 21, there is the boss with limit screw Corresponding matching on the obverse excircle of geared sleeve
22.In order that satisfactorily coordinate between geared sleeve and tension rod chain joint, in tension rod link end surface tension rod hole porch system
Make turning slot 20, the panoramic table accordingly matched is made on the obverse circumference of geared sleeve.The front portion of geared sleeve 13 is provided with opening
Locking groove 18 corresponding to the external tooth form boss 16 of draw lever locking nut.
Shown in Fig. 8-9, on tension rod chain joint, being made with tension rod axially bored line vertical direction has plugboard trough 19, and this is inserted
The width of board slot is corresponding with tensioning displacement stroke and is slightly larger than the displacement stroke length, has plate 26 in plugboard trough, has on plate
Dibit rod aperture 29, small-bore hole position and the neck Corresponding matching on tension rod 17 of the dibit rod aperture.On a side end face of plate
There is screw, there is push rod/bolt in screw, the other end of push rod sets a ball for convexity or directly.Pass through the push rod and phase
The association of adjacent plate, adjacent tensioning mechanism is interleave plate synchronization implementation when locking is with unblock, when entering to give tensioning contact association but
Independently working.
It is placed in the plate on stretching bed seat in several tensioning equipment/mechanisms and forms a connected plate group, the plate
The both ends plate of group is connected with A action tanks 1 and B action tanks 27 respectively, and the rod end of two oil cylinders is fixed with oil cylinder and cut somebody's hair
24, being cut somebody's hair with oil cylinder on corresponding plate side has push rod 25, and the two is equally connected in a manner of being engaged.
Shown in Figure 10, according to III type track plates design standard, there are two row's tension reinforcing steel bars of longitudinal direction track plates axial direction side, right with this
Should, hold each tensioning equipment on stretching bed seat to be formed by two longitudinal directions tensioning oil cylinder group arranged side by side.Stretch board 6 in figure,
Draw oil cylinder 7, the bottom of plate 26 that second stretch board 30, the second oil cylinder group 31 and the second plate 32 be correspondingly installed, while also pair
The the second tension rod chain joint answered.
During work, the transportation trolley of bearing track board mold is moved in place on the inside of tensioning equipment and by track plates along track
Mould is positioned on positioning support.Now, railway plate die height strictly matches with the height of end/side tensioning equipment, and error exists
In scope of design.Hydraulic station works, end/side feed cylinder(115、122), the traversing oil cylinder in end/side(113、118)Work, end/side
Oil cylinder in place(114、123)Work by setup program, both sides tensioning equipment is in place.
Under original state, tension rod is combined in place with tension reinforcing steel bar, and the external screw thread of tension rod is rotary with abnormity nut(Locking screw
It is female);There are two external tooth form boss 16 the cylindrical 180 degree position of abnormity nut;Now the geared sleeve rotation in tensioning retaining mechanism stops
Stay position and do not know, boss 22 is in random site, and reliable docking condition can not be met, it is necessary to be accurately positioned.First, hydraulic pressure
The low pressure low speed rotation of motor 3, motor driven gear wheel 12 also low speed rotation and drive locking gear 14 and the low speed rotation of geared sleeve 13,
Tension rod chain joint 15 moves forward in the axial direction simultaneously and slowly close to geared sleeve 13, when close to geared sleeve, boss 22 is with stopping
The dynamic collision of screw 21 occlusion, is horizontal the locking groove 18 of geared sleeve 13;Stretching bed seat moves in the axial direction, makes to open
Pull bar 17 is sequentially entered in the rod aperture of geared sleeve 13 and tension rod chain joint 15, the external tooth form boss 16 of abnormity nut on tension rod
It is engaged with the collision of locking groove 18.
Now, the piston rod of A action tanks 1 is stretching state, and the piston rod of B action tanks 27 is contraction state, tension rod 17
Enter through the heavy caliber hole position of plate 26 in tension rod chain joint.When locking operation, the rod chamber of A action tanks 1 and rodless cavity pressure
Dynamic balance, piston rod position are in quick condition, and the piston rod of B action tanks 27 stretches out, and drive oil cylinder to cut somebody's hair and 24 translations and promote
Plate group synchronous horizontal displacement, tension rod 17 enter locking position, as illustrated in figures 4-5 state.
Tensioning oil cylinder 7 works, and tension rod chain joint 15, which retreats, initially enters tensile state, while hydraulic motor works, and drives
Dynamic locking gear and geared sleeve rotate, and drive abnormity nut to be locked simultaneously to tension reinforcing steel bar.The hydraulic motor and tensioning
Oil cylinder shares hydraulic station, when tensioning in place when, hydraulic motor is also stopped while tensioning oil cylinder is stopped.Tensioning and lock
Tightly complete simultaneously.
When unlocking operation, the rod chamber of B action tanks 8 and rodless cavity pressure balance, piston rod position are in quick condition, A
The piston rod of action tank 1 stretches out, and drives oil cylinder to cut somebody's hair and promotes plate group synchronous backward displacement, it is big that tension rod 17, which enters solution lock-bit,
Aperture location.
The high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment matching of the present invention has dedicated control device
And program runs software, present invention relates solely to hardware device.
When the one exemplary embodiment to the present invention is described.For clarity and conciseness, in the description not
All features of actual embodiment are described.It is it should be understood, however, that necessary during any this practical embodiments are developed
Make much specific to the decision of embodiment, to realize the objectives of developer, for example, meeting system and business phase
Those restrictive conditions closed, and these restrictive conditions may change with the difference of embodiment.
Herein, it is also necessary to which explanation is a bit, in order to avoid having obscured the present invention because of unnecessary details, in accompanying drawing
In illustrate only with according to the closely related apparatus structure of the solution of the present invention and/or processing step, and eliminating and this hair
The little other details of bright relation.
The foregoing is merely illustrative of the preferred embodiments of the present invention, can not be considered as the implementation model for limiting the present invention
Enclose, all any modification, equivalent and improvement made within the spirit and principles of the invention etc., should be included in this hair
Within bright patent covering scope.
Claims (7)
1. a kind of high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment, including lateral tensioning equipment(103)With
Hold to tensioning equipment(101), described lateral tensioning equipment includes the base rigidly fixed with ground and is placed on the base
Side stretching bed seat(110), described end includes the base that is rigidly fixed with ground to tensioning equipment and is placed on the base
End stretching bed seat(111), described side stretching bed seat on the stretching bed seat of end with being respectively fixed with side stretch power mechanism and end
Stretch power mechanism, it is characterized in that the ground support that described base includes at least two independently of each other and height is fixed
(107), earth's surface is provided with track board assembly line transhipment track on the inside of described ground support(106), described transhipment track two
Side is provided with positioning support(104), several and railway plate die respective side tension rod are provided with described side stretching bed seat
One-to-one side stretch power mechanism, several and railway plate die respective side longitudinal direction are provided with described end stretching bed seat
Double tensile reinforcing bar/tension rod holds stretch power mechanism correspondingly.
2. high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment according to claim 1, it is characterized in that
Described ground support(107)Top is fixed with end plate, is provided with Universal caster on the end plate, described side stretching bed seat,
End stretching bed seat is placed in by Universal caster on the ground support of respective bottom.
3. high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment according to claim 2, it is characterized in that
It is provided with side feed cylinder(122), one end of the side feed cylinder is connected with ground support, the other end and side stretching bed seat phase
Even;It is provided with end feed cylinder(115), one end of the end feed cylinder is connected with homonymy ground support, the other end and end
Pedestal is drawn to be connected.
4. high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment according to claim 3, it is characterized in that
The end set of the side stretching bed seat has the traversing oil cylinder in side(118), the base and rod end of the traversing oil cylinder of side stretching bed seat
Ground support and side stretching bed seat are connected respectively;The end set of the end stretching bed seat has the traversing oil cylinder in end(113), the end
The base of traversing oil cylinder is connected the ground support and end stretching bed seat of homonymy with rod end respectively.
5. the high-speed railway track plate pre-tensioning system flowing water unit production line according to any claim in claim 1-4
Equipment is drawn, it is characterized in that described side stretch power mechanism is made up of at least two tensioning oil cylinders being fixed as one side by side, institute
Tensioning oil cylinder is stated to be fixed on the stretching bed seat of side by guide plate and guide pillar;Described end stretch power mechanism includes what is vertically overlapped
Two tensioning oil cylinder groups, each tensioning oil cylinder group comprise at least two tensioning oil cylinders being fixed as one, two groups of tensioning oil
Cylinder is fixed on the stretching bed seat of end by guide pillar and guide pin bushing, is provided with the tension rod chain joint being connected with tension rod(15), it is described
Tensioning oil cylinder rod end is connected with tension rod chain joint, and mesopore i.e. tensioning rod aperture is provided with the tension rod chain joint(11).
6. high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment according to claim 5, it is characterized in that
Location locking mechanism is provided with, described location locking mechanism includes a geared sleeve(13), the geared sleeve rear end face is with opening
Pull bar link end surface connects, and geared sleeve central through hole is the tensioning rod aperture concentric with tension rod chain joint, the tensioning bar chain
The tensioning rod aperture circumference of joint is provided with limit screw(21), the geared sleeve neighboring is provided with what is matched with the limit screw
Boss(22), the front end face of the geared sleeve is formed with locking groove(18), have locking gear on the geared sleeve circumference(14), it is described
The top of geared sleeve is provided with hydraulic motor(3), the drive gear of the hydraulic motor(12)Engaged with locking gear.
7. high-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment according to claim 5, it is characterized in that
On tension rod chain joint plugboard trough is vertically installed with tensioning rod aperture(19), have plate in the plugboard trough(26), the plate
(26)On be formed with dibit rod aperture(29), the plate in adjacent chain joint(26)It is engaged and forms a plate group, in plate group
Both ends are respectively arranged with A action tanks(1)With B action tanks(27), the rod end difference of the A action tanks and B action tanks
It is engaged with the plate of respective side.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611226169.4A CN106945169B (en) | 2016-12-27 | 2016-12-27 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
PCT/CN2017/118446 WO2018121494A1 (en) | 2016-12-27 | 2017-12-26 | Tensioning device on pre-tensioning flow unit production line for track slab on high-speed rail |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611226169.4A CN106945169B (en) | 2016-12-27 | 2016-12-27 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106945169A CN106945169A (en) | 2017-07-14 |
CN106945169B true CN106945169B (en) | 2018-01-23 |
Family
ID=59465989
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611226169.4A Active CN106945169B (en) | 2016-12-27 | 2016-12-27 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN106945169B (en) |
WO (1) | WO2018121494A1 (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106945169B (en) * | 2016-12-27 | 2018-01-23 | 山西高行液压股份有限公司 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
CN108044789B (en) * | 2018-01-05 | 2023-10-13 | 河北益铁机电科技有限公司 | Pretensioned prestressed concrete track slab production line tensioning system and application thereof |
CN108356972B (en) * | 2018-02-26 | 2019-11-01 | 施伟红 | A kind of track plates automatic production line |
CN108284511B (en) * | 2018-03-10 | 2022-08-16 | 山东高速轨道设备材料有限公司 | Prestressed track slab steel bar stretching machine |
CN114321035A (en) * | 2021-12-29 | 2022-04-12 | 筑友智造智能科技有限公司 | Intelligent tensioning equipment for prestressed reinforcement |
CN114953166B (en) * | 2022-05-10 | 2023-06-20 | 中铁十四局集团房桥有限公司 | Automatic sleeper prestressed tendon stretching and releasing method capable of stretching and releasing single sleeper |
CN114953163A (en) * | 2022-06-16 | 2022-08-30 | 中交(临沂)建筑科技有限公司 | Movable pre-tensioning method prestress hollow slab production pedestal |
CN117943826A (en) * | 2024-03-27 | 2024-04-30 | 山东高速铁建装备有限公司 | Automatic nut screwing-off machine for sleeper |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4447125B2 (en) * | 2000-07-10 | 2010-04-07 | 戸田工業株式会社 | Forming device for half-PC plate manufacturing |
CN1865593A (en) * | 2006-05-05 | 2006-11-22 | 欧阳炎 | Bidirectional pretensioning method prestressed concrete railway board and assembly machine sets method production process |
CN101780691B (en) * | 2009-01-15 | 2012-06-13 | 郭志杰 | Two-way long-line pedestal method production process of prestressed concrete track slab |
CN104441225B (en) * | 2014-11-21 | 2017-04-05 | 天津银龙预应力材料股份有限公司 | A kind of tinuous production for manufacturing prestressed concrete railway board used for high-speed railway |
CN106166796B (en) * | 2016-08-26 | 2019-01-01 | 中铁一局集团物资工贸有限公司 | A kind of stretching bed seat for the production of no tiny fragments of stone, coal, etc. formula high-speed railway track plate |
CN106945169B (en) * | 2016-12-27 | 2018-01-23 | 山西高行液压股份有限公司 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
CN206374023U (en) * | 2016-12-27 | 2017-08-04 | 山西高行液压股份有限公司 | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment |
-
2016
- 2016-12-27 CN CN201611226169.4A patent/CN106945169B/en active Active
-
2017
- 2017-12-26 WO PCT/CN2017/118446 patent/WO2018121494A1/en active Application Filing
Also Published As
Publication number | Publication date |
---|---|
WO2018121494A1 (en) | 2018-07-05 |
CN106945169A (en) | 2017-07-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106945169B (en) | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment | |
DE102008003717B3 (en) | Strand cutting machine | |
CN101929583A (en) | Deep water submarine pipeline axial aiming machine | |
DE3036202A1 (en) | AUTOMATIC MOUNTING DEVICE | |
CN206374023U (en) | High-speed railway track plate pre-tensioning system flowing water unit production line tensioning equipment | |
CN104002377A (en) | Steel bar binding and corrugated pipe locating device for precasting box girder | |
CN106808581A (en) | High-speed railway track plate pre-tensioning system flowing water unit production line puts an equipment | |
CN105170836A (en) | Portable multi-jacking multifunctional high-tensile reinforcement bar bending and straightening machine and operation method thereof | |
EP1407873A1 (en) | Apparatus for producing corrugated pipes | |
CN106945170A (en) | Pre-tensioning system produces the steel bar tensioning device of high speed railway fragments-free track slab | |
CN105584786A (en) | Die assembly conveyor line used for tubular pile automatic production line | |
JP2586324Y2 (en) | Mold changing device | |
CN202325546U (en) | Side slip type needle beam bottom die trolley | |
CN108284509B (en) | A kind of connection locking device | |
DE202004001258U1 (en) | Device for deep drilling in geological structures | |
CN206374024U (en) | Pre-tensioning system produces the steel bar tensioning device of high speed railway fragments-free track slab | |
CN111945781A (en) | Novel steel construction self-propelled pipe gallery formwork trolley | |
CN106180565B (en) | A kind of hand-operated core pulling device | |
CN113602974B (en) | Crane applied to track slab three-dimensional steam curing system and application method | |
CN206913411U (en) | High-speed railway track plate pre-tensioning system flowing water unit production line puts an equipment | |
CN215594110U (en) | Formula of walking piping lane lining cutting system | |
US3593392A (en) | Concrete casting shuttering | |
CN109778838B (en) | Installation device of municipal works precast tubular pile and pile cap | |
EP1238780A2 (en) | Method and apparatus for the manufacture of corrugated pipes made of thermoplastic material | |
CN112982488A (en) | Formula of walking piping lane lining cutting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |