CN106930470A - A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage - Google Patents

A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage Download PDF

Info

Publication number
CN106930470A
CN106930470A CN201710319207.9A CN201710319207A CN106930470A CN 106930470 A CN106930470 A CN 106930470A CN 201710319207 A CN201710319207 A CN 201710319207A CN 106930470 A CN106930470 A CN 106930470A
Authority
CN
China
Prior art keywords
steel pipe
stage
longitudinal
surrendered
ribbing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710319207.9A
Other languages
Chinese (zh)
Inventor
胡红松
王浩祚
郭子雄
柴振岭
高鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaqiao University
Original Assignee
Huaqiao University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaqiao University filed Critical Huaqiao University
Priority to CN201710319207.9A priority Critical patent/CN106930470A/en
Publication of CN106930470A publication Critical patent/CN106930470A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention discloses a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage, including a steel pipe, concrete has been poured in steel pipe, and the inward-facing vertical projection of inwall of the steel pipe is spacedly distributed and some longitudinal floors isometric with steel pipe, the yield strength of each longitudinal floor is below the yield strength of steel pipe, under geological process, above-mentioned some longitudinal floors can be surrendered to consume the energy of Seismic input prior to steel pipe, prevent or delay above-mentioned steel pipe premature harm and destruction;The present invention compensate for the deficiency of common concrete filled steel tubular column, be had broad application prospects in skyscraper.

Description

A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage
Technical field
The invention belongs to building structure technology field, and in particular to a kind of concrete filled steel tube with ribbing combination surrendered stage by stage Rod structure.
Background technology
Steel core concrete column is a kind of new and effective combined member developed in recent years, and it is by steel pipe and steel pipe Coagulation local soil type into.By the performance of compound action, concrete filled steel tube can give full play to the material of both steel and concrete Performance.Due to the effect of pipe inner concrete, the stability of steel pipe wallboard is greatly improved, it is to avoid or delayed steel plate wallboard mistake It is early that local buckling occurs.Further, since effect of contraction of the steel pipe to concrete, the compression strength and deformability of concrete are obtained Significantly improve.Steel pipe is also used as the template of concreting, so as to greatly shorten the duration.Due to above-mentioned advantage, steel pipe is mixed Solidifying earth pillar has obtained increasingly being widely applied in Practical Project.For steel core concrete column, in other conditions identical feelings Under condition, steel yield strength is higher, and the effect of contraction of steel pipe is stronger, and the bearing capacity of post is higher.Therefore in bearing capacity identical feelings Under condition, the sectional dimension of steel core concrete column, saving steel can be reduced using high strength steel pipe.But in high strength steel pipe concrete While post reduces sectional dimension, its rigidity of structure also accordingly reduces, and deformation more difficult satisfaction of the structure under small shake effect Ask.And compared to common steel tube, high strength steel pipe is more easy to local buckling before yield strength is reached, strong so as to constrain steel pipe The performance of degree.
The content of the invention
It is an object of the invention to overcome prior art defect, there is provided a kind of steel tube concrete local soil type with ribbing for surrendering stage by stage Zygostyle structure.
Technical scheme is as follows:
A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage, including a steel pipe, have poured coagulation in steel pipe Soil, and the inward-facing vertical projection of inwall of the steel pipe is spacedly distributed and some longitudinal floors isometric with steel pipe, each longitudinal direction The yield strength of floor is below the yield strength of steel pipe, and under geological process, above-mentioned some longitudinal floors can bend prior to steel pipe Take to consume the energy of Seismic input, prevent or delay above-mentioned steel pipe premature harm and destruction;
Spacing between the adjacent longitudinal ribs plate of above-mentioned some longitudinal floors is the 20~35% of steel pipe width, each longitudinal direction The thickness of floor is the 30~50% of the wall thickness of steel pipe, and the gross area of some longitudinal floors is the gross area of the side wall of steel pipe 30~50%.
In a preferred embodiment of the invention, the spacing between the adjacent longitudinal ribs plate of some longitudinal floors It is the 1/4~1/3 of steel pipe width.
In a preferred embodiment of the invention, the thickness of each longitudinal floor be the wall thickness of steel pipe 1/3~ 1/2。
In a preferred embodiment of the invention, the gross area of some longitudinal floors is the total of the side wall of steel pipe The 1/3~1/2 of area.
It is further preferred that the cross section of the steel pipe is rectangle.
It is further preferred that the cross section of the steel pipe is circle.
Beneficial effects of the present invention:The increasing in steel pipe of the concrete filled steel tube coupled column with ribbing surrendered stage by stage of the invention If longitudinal floor of low-yield.Low-yield longitudinal direction floor enhances the local stability of steel pipe, meanwhile, low-yield is indulged Can be surrendered prior to high strength steel pipe to floor, consume the energy of Seismic input structure, prevent mistake of the high strength steel pipe under big shake effect It is early to damage and destroy, the deficiency of common concrete filled steel tubular column is compensate for, had broad application prospects in skyscraper.
Brief description of the drawings
Fig. 1 is the dimensional structure diagram of the fin steel tube concrete combination column of yield band stage by stage of the embodiment of the present invention 1.
Fig. 2 is the cross-sectional view of the fin steel tube concrete combination column of yield band stage by stage of the embodiment of the present invention 1.
Fig. 3 is the dimensional structure diagram of the fin steel tube concrete combination column of yield band stage by stage of the embodiment of the present invention 2;
Fig. 4 is the cross-sectional view of the fin steel tube concrete combination column of yield band stage by stage of the embodiment of the present invention 2.
Specific embodiment
Technical scheme is further detailed and described below by way of specific embodiment combination accompanying drawing.
Embodiment 1
As depicted in figs. 1 and 2, a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage, an including rectangle is horizontal The steel pipe 2 in section, has poured concrete 1 in steel pipe 2, and the steel pipe 2 the inward-facing vertical projection of inwall be spacedly distributed and with The isometric some longitudinal floor 3 of steel pipe 2, the yield strength of each longitudinal floor 3 is below the yield strength of steel pipe 2, in earthquake Under effect, above-mentioned some longitudinal floors 3 can be surrendered to consume the energy of Seismic input prior to steel pipe 2, prevent or delay above-mentioned steel The premature harm of pipe 2 and destruction;
Spacing between the adjacent longitudinal ribs plate 3 of above-mentioned some longitudinal floors 3 is the 20~35% of the width of steel pipe 2, each The thickness of longitudinal floor 3 is the 30~50% of the wall thickness of steel pipe 2, and the gross area of some longitudinal floors 3 is the side wall of steel pipe 2 The 30~50% of the gross area;Preferably, the spacing between the adjacent longitudinal ribs plate 3 of some longitudinal floors 3 is the 1/ of the width of steel pipe 2 4~1/3, the thickness of each longitudinal floor 3 is the 1/3~1/2 of the wall thickness of steel pipe 2, and the gross area of some longitudinal floors 3 is steel The 1/3~1/2 of the gross area of the side wall of pipe 2.
Concrete construction method is:Longitudinal floor 3, longitudinal direction are first welded on each composition steel plate of steel pipe 2 by predetermined spacing Floor 3 is connected with the plate of steel pipe 2 using twin fillet wolt.The making of each steel plate with ribbing is sequentially completed, and ribbed steel is welded Into a steel pipe 2 with ribbing.Finally, toward cast concrete 1 in the steel pipe 2, when the intensity of concrete 1 reaches requirement, that is, complete Construction of the invention.
Embodiment 2
As shown in Figure 3 and Figure 4, a kind of Combined concrete rod structure of band fin steel tube 2 surrendered stage by stage, including a circular horizontal stroke The steel pipe 2 in section, has poured concrete 1 in steel pipe 2, and the steel pipe 2 the inward-facing vertical projection of inwall be spacedly distributed and with The isometric some longitudinal floor 3 of steel pipe 2, the yield strength of each longitudinal floor 3 is below the yield strength of steel pipe 2, in earthquake Under effect, above-mentioned some longitudinal floors 3 can be surrendered to consume the energy of Seismic input prior to steel pipe 2, prevent or delay above-mentioned steel The premature harm of pipe 2 and destruction;
Spacing between the adjacent longitudinal ribs plate 3 of above-mentioned some longitudinal floors 3 is the 20~35% of the width of steel pipe 2, each The thickness of longitudinal floor 3 is the 30~50% of the wall thickness of steel pipe 2, and the gross area of some longitudinal floors 3 is the side wall of steel pipe 2 The 30~50% of the gross area;Preferably, the spacing between the adjacent longitudinal ribs plate 3 of some longitudinal floors 3 is the 1/ of the width of steel pipe 2 4~1/3, the thickness of each longitudinal floor 3 is the 1/3~1/2 of the wall thickness of steel pipe 2, and the gross area of some longitudinal floors 3 is steel The 1/3~1/2 of the gross area of the side wall of pipe 2.
Concrete construction method is:Longitudinal floor is first welded on the curved plate of each composition of steel pipe 2 by predetermined spacing 3, longitudinal floor 3 is connected with curved plate using twin fillet wolt.It is sequentially completed the making of each curved plate with ribbing, and by band The curved plate of rib is welded into a steel pipe 2 with ribbing.Finally, toward cast concrete 1 in the steel pipe 2, treat that the intensity of concrete 1 reaches When requiring, that is, complete construction of the invention.
The above, only presently preferred embodiments of the present invention, therefore can not according to this limit the scope of present invention implementation, i.e., The equivalence changes made according to the scope of the claims of the present invention and description and modification, all should still belong in the range of the present invention covers.

Claims (6)

1. a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage, it is characterised in that:Including a steel pipe, poured in steel pipe Concrete has been built, and the inward-facing vertical projection of inwall of the steel pipe is spacedly distributed and some longitudinal floors isometric with steel pipe, The yield strength of each longitudinal floor is below the yield strength of steel pipe, and under geological process, above-mentioned some longitudinal floors can be first Surrendered in steel pipe to consume the energy of Seismic input, prevent or delay above-mentioned steel pipe premature harm and destruction;
Spacing between the adjacent longitudinal ribs plate of above-mentioned some longitudinal floors is the 20~35% of steel pipe width, each longitudinal floor Thickness be steel pipe wall thickness 30~50%, the gross area of some longitudinal floors for the gross area of the side wall of steel pipe 30~ 50%.
2. a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage as claimed in claim 1, it is characterised in that:Institute It is the 1/4~1/3 of steel pipe width to state the spacing between the adjacent longitudinal ribs plate of some longitudinal floors.
3. a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage as claimed in claim 1, it is characterised in that:Often The thickness of one longitudinal floor is the 1/3~1/2 of the wall thickness of steel pipe.
4. a kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage as claimed in claim 1, it is characterised in that:Institute It is the 1/3~1/2 of the gross area of the side wall of steel pipe to state the gross area of some longitudinal floors.
5. a kind of concrete filled steel tube coupled column with ribbing surrendered stage by stage as described in any claim in Claims 1-4 Structure, it is characterised in that:The cross section of the steel pipe is rectangle.
6. a kind of concrete filled steel tube coupled column with ribbing surrendered stage by stage as described in any claim in Claims 1-4 Structure, it is characterised in that:The cross section of the steel pipe is circle.
CN201710319207.9A 2017-05-08 2017-05-08 A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage Pending CN106930470A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710319207.9A CN106930470A (en) 2017-05-08 2017-05-08 A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710319207.9A CN106930470A (en) 2017-05-08 2017-05-08 A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage

Publications (1)

Publication Number Publication Date
CN106930470A true CN106930470A (en) 2017-07-07

Family

ID=59430126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710319207.9A Pending CN106930470A (en) 2017-05-08 2017-05-08 A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage

Country Status (1)

Country Link
CN (1) CN106930470A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057158A (en) * 2018-08-29 2018-12-21 悉地(北京)国际建筑设计顾问有限公司 A kind of square shaped pipe concrete column with T-type ribbed stiffener
CN109057160A (en) * 2018-09-10 2018-12-21 李新华 Polygon steel pipe concrete column
CN115217270A (en) * 2021-04-20 2022-10-21 中国建筑设计研究院有限公司 Large-diameter circular steel tube concrete column with built-in vertical ribs and preparation method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5599599A (en) * 1995-07-06 1997-02-04 University Of Central Florida Fiber reinforced plastic ("FRP")-concrete composite structural members
CN200943287Y (en) * 2006-07-17 2007-09-05 福州大学 Light steel pipe/concrete column
CN102535750A (en) * 2012-02-14 2012-07-04 长安大学 Cylindrical construction part provided with holed stiffening ribs and filled with steel fiber reinforced concrete
CN102535748A (en) * 2011-12-31 2012-07-04 北京工业大学 Rectangular concrete-filled steel tube column added with I-shaped rib plate and preparing method of rectangular concrete-filled steel tube column
CN103850392A (en) * 2012-12-04 2014-06-11 北京工业大学 Concrete column with vertical perforated rib plates between outer square steel pipe and inner round steel pipe and manufacturing method of concrete column
CN103938799A (en) * 2014-04-10 2014-07-23 北京工业大学 Ribbed steel plate composite gigantic column and manufacturing method
CN206034757U (en) * 2016-08-19 2017-03-22 深圳大学建筑设计研究院有限公司 Steel core concrete column structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5599599A (en) * 1995-07-06 1997-02-04 University Of Central Florida Fiber reinforced plastic ("FRP")-concrete composite structural members
CN200943287Y (en) * 2006-07-17 2007-09-05 福州大学 Light steel pipe/concrete column
CN102535748A (en) * 2011-12-31 2012-07-04 北京工业大学 Rectangular concrete-filled steel tube column added with I-shaped rib plate and preparing method of rectangular concrete-filled steel tube column
CN102535750A (en) * 2012-02-14 2012-07-04 长安大学 Cylindrical construction part provided with holed stiffening ribs and filled with steel fiber reinforced concrete
CN103850392A (en) * 2012-12-04 2014-06-11 北京工业大学 Concrete column with vertical perforated rib plates between outer square steel pipe and inner round steel pipe and manufacturing method of concrete column
CN103938799A (en) * 2014-04-10 2014-07-23 北京工业大学 Ribbed steel plate composite gigantic column and manufacturing method
CN206034757U (en) * 2016-08-19 2017-03-22 深圳大学建筑设计研究院有限公司 Steel core concrete column structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109057158A (en) * 2018-08-29 2018-12-21 悉地(北京)国际建筑设计顾问有限公司 A kind of square shaped pipe concrete column with T-type ribbed stiffener
CN109057160A (en) * 2018-09-10 2018-12-21 李新华 Polygon steel pipe concrete column
CN115217270A (en) * 2021-04-20 2022-10-21 中国建筑设计研究院有限公司 Large-diameter circular steel tube concrete column with built-in vertical ribs and preparation method thereof
CN115217270B (en) * 2021-04-20 2023-06-13 中国建筑设计研究院有限公司 Large-diameter circular steel tube concrete column with built-in vertical ribs and preparation method thereof

Similar Documents

Publication Publication Date Title
CN201671226U (en) Expanded flanged cross-shaped steel SRC column
CN201661009U (en) Concrete-filled square steel tubular column
CN106930470A (en) A kind of concrete filled steel tube composite column structure with ribbing surrendered stage by stage
CN104963415B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
CN104929278A (en) Assembly type dense column hollow shear wall structure
CN206859520U (en) The concrete filled steel tube composite column structure with ribbing surrendered stage by stage
CN104294920A (en) Joint assembly of U-shaped steel reinforced concrete combined beam and special-shaped concrete-filled steel tube column and manufacturing method of joint assembly
CN208815772U (en) A kind of prompt about column with cross ribbed stiffener
CN206941799U (en) The prestressing force assembling type node construction of beam-ends friction energy-dissipating
CN105604221A (en) Preformed wall formwork with steel bars
CN205399760U (en) Prefabricated belted steel muscle wall body mould shell
CN204715539U (en) A kind of round steel pipe binding type steel concrete column and reinforced concrete beam node structure
CN106894577A (en) A kind of strong constraint rectangular profile concrete filled steel tube rod structure with ribbing
CN103437349B (en) The construction method of steel concrete perfusion shaped pile
CN110219474A (en) A kind of structural column increasing section reinforcement means using steel tube confinement
CN105040828B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
CN214785929U (en) Template structure of constructional column is built in room
CN107829428A (en) A kind of variable diameters bamboo joint type mortar pile
CN204715537U (en) A kind of round steel pipe binding type steel concrete column and reinforced concrete beam node structure
CN108412036A (en) Assembled H profile steel column-isolated footing-concrete collar tie beam cross connecting node
CN206681265U (en) Combination constraint rectangular steel-tube concrete column structure
CN210049428U (en) Sandwich heat-insulating steel concrete composite pipe structure
CN100535270C (en) Irregular steel tube concrete pole with steel bar reinforcement
CN208121961U (en) A kind of assembling frame corner node structure
CN204781613U (en) Cage space grid column structure steel bar connector of an area awl section of thick bamboo

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170707

WD01 Invention patent application deemed withdrawn after publication