CN106894821A - It is a kind of originate, the monitoring method of received well and jacking construction - Google Patents

It is a kind of originate, the monitoring method of received well and jacking construction Download PDF

Info

Publication number
CN106894821A
CN106894821A CN201710124300.4A CN201710124300A CN106894821A CN 106894821 A CN106894821 A CN 106894821A CN 201710124300 A CN201710124300 A CN 201710124300A CN 106894821 A CN106894821 A CN 106894821A
Authority
CN
China
Prior art keywords
monitoring
point
construction
water
monitoring point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710124300.4A
Other languages
Chinese (zh)
Other versions
CN106894821B (en
Inventor
苏春生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway Construction Bridge Engineering Bureau Group Co Ltd
Priority to CN201710124300.4A priority Critical patent/CN106894821B/en
Publication of CN106894821A publication Critical patent/CN106894821A/en
Application granted granted Critical
Publication of CN106894821B publication Critical patent/CN106894821B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention discloses it is a kind of originate, the monitoring method of received well and jacking construction, including:(1) preparation of construction is carried out at the scene;(2) choose monitoring point and monitoring instrument is set on the monitoring section of monitoring point;(3) monitoring frequency is formulated, information gathering is carried out;(4) information data of collection is recorded, analyzed and is processed, obtain monitoring form;(5) monitoring Warning Index value is formulated;(6) reasonability and science of construction technology are assessed with monitoring Warning Index value according to monitoring form.Of the invention to organically combine monitoring project on the basis of routine monitoring project, the data phase mutual energy of test is checked;Continuously monitored in construction work, it is ensured that the continuity of data;Layout of the monitoring points is reduced using system behavio(u)r, it is cost-effective;With reference to the actual installation position for determining method of testing, the species of monitoring element, adjustment monitoring point of construction, the influence to construction quality is reduced.

Description

It is a kind of originate, the monitoring method of received well and jacking construction
Technical field
The present invention relates to civil engineering monitoring method, it is specially a kind of originate, the monitoring method of received well and jacking construction.
Background technology
With the development of Chinese national economy, to infrastructure, especially to the demand of means of transportation being continuously increased, and The land communications such as railway, highway are even more and stand in the breach;Meanwhile, the high-grade main line of communication has also obtained unprecedented development, Such as:At a high speed, heavy haul railway and highway are respectively the Main ways of the land communications such as railway, highway development, and city ground Iron, vcehicular tunnel build and be relax urban transportation important means.The perfect and capacity expansion revamping of means of transportation, vehicle speed-raising And the development of highway network inevitably results in the neighboring tunneling engineerings such as the newly built tunnels of neighbouring existing buildings and emerges in multitude, This certainly will produce influence to the safety of neighbouring existing structure thing.It is existing neighbouring that Current City Road constructing tunnel runs into passing through Works has superstructure, underground utilities and some special structures such as civil air defense constructions and installations, subway station etc., and these works pair Excavation is more sensitive, and crossing construction influence is big, is easily disturbed.If not taking special countermeasure, the construction of newly built tunnels will Have a negative impact to existing structure thing, such as works bearing capacity declines, even destroys;Deformation is excessive so that invading net It is empty;Differential settlement causes periphery buildings or structures damaged or can not normally use.
Adjacent to existing buildings and the rock tunnel on the mountain ridge is passed through for periphery, its neighboring tunneling is except will consider to excavate influence Outward, vibration effect during blast working is also taken into account, domestic and international such proximity engineering largely occurs.Due to construction complexity Be short in understanding and pay attention to not enough, such issues that the engineering accident that causes also happen occasionally, such as certain single-track railway increases when building two wires, newly Built tunnel adjoins existing tunnel construction, because explosion dosage is too big, causes the existing tunnel structure for having deteriorated originally to aggravate Deterioration;Certain vcehicular tunnel due to pretesting not enough, is designed without taking some countermeasures by goaf, causes lining cutting after construction Cracking etc..Therefore, carrying out construction monitoring as the essential important process of safe construction adjacent to existing buildings to periphery.
The content of the invention
The invention aims to provide a kind of science, the originating of system, received well and the monitoring method of jacking construction, Realize that monitoring is to existing building and the circumferentially influence of quality shape, and profit when starting well, received well and push pipe are in construction Security evaluation analysis is carried out with Monitoring Data, unit in charge of construction adjusts arrangement and method for construction and progress according to assessment result in time, it is ensured that apply Work is smoothed out and safety assurance.
The present invention is achieved through the following technical solutions:It is a kind of originate, the monitoring method of received well and jacking construction, using prison The disturbance situation that survey technology is to originating, produce during received well and jacking construction is monitored, and comprises the following steps:
(1) preparation of construction, including engineering geology and hydrogeological exploration are carried out at the scene;
(2) choose monitoring point and monitoring instrument is set on the monitoring section of monitoring point, monitoring point includes:Benchmark, Settlement monitoring point, horizontal displacement monitoring point, axle power monitoring point, water table measure point and convergence monitoring point in push pipe;
(3) monitoring frequency is formulated, the time according to monitoring frequency carries out information gathering to each monitoring point;
(4) information data of collection is recorded, analyzed and is processed, obtain monitoring form;
(5) monitoring Warning Index value is formulated, data and the value contrast of monitoring Warning Index of form will be monitored;
(6) standard of monitoring Warning Index value is reached, then continues to construct;If being not reaching to monitor the mark of Warning Index value Standard, then assess the reasonability and science of construction technology, adjusts arrangement and method for construction.
Site operation preparation is carried out first, is disclosed according to prospecting and in-situ test and laboratory test achievement, according to physical force Property index and origin cause of formation epoch are learned, and combines advanced exploration data, foundation soil is divided into some engineering geology layers, some engineering geology Subgrade, and hydrogeologic condition is reconnoitred, the geological condition according to prospecting formulates corresponding monitoring scheme and monitoring point Selection, select the corresponding detecting instrument to carry out periodic monitoring according to the monitoring frequency formulated to detection site, and will monitor Information is processed with computer, with it is default monitoring Warning Index value contrasted, thus come judge construct periphery monitoring point Situation whether meet continue construct requirement, continue if requirement is reached construction, if be not reaching to require if assess construction work The reasonability and science of skill, adjust arrangement and method for construction, on the premise of improveing arrangement and method for construction and ensuring not influence engineering safety, then Proceed construction.
Measuring point is laid at the scene according to monitoring scheme, is arranged with the requirement in monitoring scheme in principle.Reality is according to scene Situation can set measuring point design point position is close to, but be principle, the quantity of the type of monitoring point can reach monitoring purpose The combined factors such as incorporation engineering feature, construction characteristic, monitoring expense consider that the point layout set for checking design data is setting Meter most unfavorable combination and section;At first construction part of the point layout set for guiding construction under identical operating mode, its purpose It is that, for timely feedback information, to change design and guidance construction, the position of earth's surface deformation measuring point should consider to reflect object Deformation behaviour, is easy to be observed using instrument again, to be also conducive to the protection of measuring point, and measuring point is once broken in work progress It is bad, measuring point in situ or close proximity to origin-location benefit is set as early as possible, to ensure that the measuring point observes the continuity of data.
Work benchmark is embedded to use the common level mark of concrete, markstone to be embedded in 1.5~2.0 meters of left sides below earth's surface Right depth, lays 2-3 working base point, and base position is in order to observed object and in stabilization or relative settling position Preferably, 3 times of foundation ditch depths be should be greater than away from tunnel axis distance;Or squeezed at the structures such as bridge pier base of the periphery selection in stabilization Reinforcing bar or bolt.
Further, the settlement monitoring point chosen in the step (2) includes:Surface subsidence monitoring point, push pipe inner top And bottom settlement monitoring point, periphery pipeline settlement monitoring point, Building's Subsidence Survey point.
Further, the horizontal displacement monitoring point in the step (2) includes:Building enclosure horizontal deflection on the top of wall is monitored Point, building enclosure deeply mixing cement-soil pile monitoring point, horizontal displacement monitoring point in push pipe.
Further, the axle power monitoring point in the step (2) includes:Bracing members axle power monitoring point, concrete axial force of the supports prison Measuring point.
Further, the detecting instrument in the step (2) includes:
Total powerstation, inclinometer:For the monitoring of horizontal displacement;
Water-level gauge, water level test tube:For the monitoring of level of ground water;
Axle power meter, Reinforcement Stress-count:For the monitoring of axle power;
Electronic level, indium steel ruler:Monitoring for settling situation;
Electronics convergence gauge:For convergent monitoring in push pipe.
Further, it is the step of water table measure information gathering in the step (3):
(3.1) measuring point is buried
A, pore-forming:Water-level observation hole is crept into using clear water, and drilling stops boring after reaching projected depth, in time that drilling cleaning is dry Only, the unobstructed situation of drilling is checked, and carries out cleaning record.
B, well casing processing:The raw material of well casing are the pvc pipe that internal diameter Φ 70, pipe thickness is 2.5;To ensure pvc pipe Water penetration, processes the through hole of cellular Φ 8 in the range of 0~4m of pvc pipe lower end, and the ring spacing in hole is 12mm, axial spacing It is 12mm, and bag geotextiles filter screen.
C, well casing are placed:After pore-forming, PVC well casings are hung, it is ensured that have filter opening end downward;Water-level observation hole should be above ground level 0.5m, sets fixed measuring point mark, and protected with protective case in aperture;
D, backfill gravel material:After observation of groundwater levels hole well casing hangs in hole, particle diameter should be filled out in the periphery of well casing immediately little In the meter Shi of 5mm;
E, well-flushing:After down tube, backfill gravel material terminate, well-flushing should be carried out using clear water in time, and carry out well-flushing record.
(3.2) monitoring method
Observation of groundwater levels equipment uses electric tape ga instrument, and accuracy of observation is 0.5cm, when gauge head touches underground water, Alarm sends alarm signal, now reads the scale label being connected with gauge head, and this reading is water level vertical with fixed measure Distance, then absolute altitude by fixed measuring point and it is converted into the depth to water and water level stake counted from ground with the relative position on ground It is high.
(3.3) data analysis and treatment.
Further, data handling utility computer carries out numbered analog simulation analysis in the step (4).Informationization is applied Work requirement evaluates construction method with monitoring result, determines project slash.Therefore, the monitoring result to each measuring point will basis The safe condition of the comprehensive descision structure such as management standard and rate of displacement (mm/d) and building.To ensure the matter of monitoring result Amount, strengthen feedback of the information speed, whole Monitoring Datas and chart by computer management, and to resident supervising engineer, design Unit and monitoring center submit monitoring weekly or monthly magazine to.The content for monitoring form includes:
1) when daily sheet is usually as construction adjustment and the foundation for arranging, content is including title, the data of test, inscription etc. Part constitutes.Wherein title should indicate Contents for Monitoring, monitoring date, report number.Test data includes measuring point numbering, initial Value, this test value, compared with last time test increment size and accumulative variable quantity.Inscription should indicate monitoring unit, tester, fill in a form people Member etc..
2) weekly return mainly in combination with engineering regular meeting, interim trifle content ibid.
3) moon sheet is mainly included into engineering monitoring final report.
The object of monitoring measurement report submitting is limited in time:
1) (every afternoon 17 in 12 hours after daily sheet is measured on the day of:00 point by electronic document transmission Party A) send and apply Work floor manager portion.
2) weekly return is delivered newspaper floor manager portion and on-site supervision engineer in last day at weekend.
3) moon sheet reported and submitted supervising engineer before the end of month 30.
Further, the content of monitoring form includes in the step (4):Sedimentation deformation versus time curve, water Prosposition moves versus time curve, axle power versus time curve figure, water level versus time curve and convergency value Versus time curve.
Further, the monitoring Warning Index value in the step (5) is to ensure monitoring object before monitoring is implemented Safety and each monitoring index that sets estimates maximum.In monitoring process,
When measured value < 0.85* estimate maximum, safety;
When measured value=(0.85~1.0) * estimates maximum, note;
It is dangerous when measured value > 1.0* estimate maximum;
(0.85* design loads be critical value) monitoring department should in form highlight indication, alarmed.
The present invention compared with prior art, has the advantage that and has the beneficial effect that:
(1) it is of the invention on the basis of routine monitoring project, convergence, top in emphasis monitoring axle power, level of ground water, push pipe The monitoring information of pipe inner top and bottom settlement monitoring point, and monitoring project is organically combined, form effective space-time, test Data phase mutual energy checked;
(2) present invention is continuously monitored in construction work, it is ensured that the continuity of data;Reduced using system behavio(u)r and supervised Measuring point is laid, cost-effective;
(3) present invention combines the actual determination method of testing of construction, the species of monitoring element, the safeguard measure of monitoring point, adjusts The installation position of whole monitoring point, reduces the influence to construction quality as far as possible;
(4) quantity of monitoring point of the present invention, on the premise of comprehensive, safety is ensured, rationally contacts using between monitoring point, Measuring point quantity is reduced, operating efficiency, reduces cost is improved;
(5) determination of present invention monitoring warning value has engineering construction feasibility, on the premise of safety is met, it is contemplated that Improve construction efficiency and reduce operating expenses.
Brief description of the drawings
Fig. 1 is construction flow chart of the invention.
Specific embodiment
The present invention is described in further detail with reference to embodiment, but embodiments of the present invention not limited to this, Without departing from the idea case in the present invention described above, according to ordinary skill knowledge and customary means, various replacing is made Change and change, all should be included within the scope of the invention.
Embodiment:
The present embodiment is to simplify working procedure, accelerating construction progress, it is ensured that architecture quality, saves engineering cost, if Count out be adapted to originate, received well and jacking construction, Optimizing construction flow, improve operating efficiency, reduce material consumption, it is to avoid Energy waste, comply with standardized construction requirement it is a kind of originate, the monitoring method of received well and jacking construction, whole step As shown in Figure 1:
The disturbance situation produced using monitoring technology to originating, during received well and jacking construction is monitored, including Following steps:
(1) preparation of construction, including engineering geology and hydrogeological exploration are carried out at the scene;
(2) choose monitoring point and monitoring instrument is set on the monitoring section of monitoring point, monitoring point includes:Benchmark, Settlement monitoring point, horizontal displacement monitoring point, axle power monitoring point, water table measure point and convergence monitoring point in push pipe;
(3) monitoring frequency is formulated, the time according to monitoring frequency carries out information gathering to each monitoring point;
(4) information data of collection is recorded, analyzed and is processed, obtain monitoring form;
(5) monitoring Warning Index value is formulated, data and the value contrast of monitoring Warning Index of form will be monitored;
(6) standard of monitoring Warning Index value is reached, then continues to construct;If being not reaching to monitor the mark of Warning Index value Standard, then assess the reasonability and science of construction technology, adjusts arrangement and method for construction.
Site operation preparation is carried out first, is disclosed according to prospecting and in-situ test and laboratory test achievement, according to physical force Property index and origin cause of formation epoch are learned, and combines advanced exploration data, foundation soil is divided into some engineering geology layers, some engineering geology Subgrade, and hydrogeologic condition is reconnoitred, the geological condition according to prospecting formulates corresponding monitoring scheme and monitoring point Selection, select the corresponding detecting instrument to carry out periodic monitoring according to the monitoring frequency formulated to detection site, and will monitor Information is processed with computer, with it is default monitoring Warning Index value contrasted, thus come judge construct periphery monitoring point Situation whether meet continue construct requirement, continue if requirement is reached construction, if be not reaching to require if assess construction work The reasonability and science of skill, adjust arrangement and method for construction, on the premise of improveing arrangement and method for construction and ensuring not influence engineering safety, then Proceed construction.
Measuring point is laid at the scene according to monitoring scheme, is arranged with the requirement in monitoring scheme in principle.Reality is according to scene Situation can set measuring point design point position is close to, but be principle, the quantity of the type of monitoring point can reach monitoring purpose The combined factors such as incorporation engineering feature, construction characteristic, monitoring expense consider that the point layout set for checking design data is setting Meter most unfavorable combination and section;At first construction part of the point layout set for guiding construction under identical operating mode, its purpose It is that, for timely feedback information, to change design and guidance construction, the position of earth's surface deformation measuring point should consider to reflect object Deformation behaviour, is easy to be observed using instrument again, to be also conducive to the protection of measuring point, and measuring point is once broken in work progress It is bad, measuring point in situ or close proximity to origin-location benefit is set as early as possible, to ensure that the measuring point observes the continuity of data.
Work benchmark is embedded to use the common level mark of concrete, markstone to be embedded in 1.5~2.0 meters of left sides below earth's surface Right depth, lays 2-3 working base point, and base position is in order to observed object and in stabilization or relative settling position Preferably, 3 times of foundation ditch depths be should be greater than away from tunnel axis distance;Or squeezed at the structures such as bridge pier base of the periphery selection in stabilization Reinforcing bar or bolt.
Settlement monitoring point includes:Surface subsidence monitoring point, push pipe inner top and bottom settlement monitoring point, periphery pipe settlement Monitoring point, Building's Subsidence Survey point.
Push pipe inner top and the monitoring method and basic point repetition measurement method of bottom sedimentation are:First, settlement monitoring is using accurate Leveling measuring method, Monitoring Datum Network is carried out by the technical requirements of II grade vertical displacement monitoring control network, and cloth be set as it is attached Close or closed leveling line.Consolidating settlement monitoring point is carried out by II grade vertical displacement monitoring net technical requirements, and cloth is set as conforming to Or closed leveling line.Control net measurement the key technical indexes is as shown in table 1 below, table 2, table 3.
The main technical requirements of the settlement monitoring of table 1 control net
Note:N is survey station number.
The main technical requirements of the settlement monitoring of table 2
Note:N is survey station number.
The level monitoring main technical requirements of table 3
Then, datum mark as settlement monitoring initial foundation, its stability is particularly significant.Datum mark will aspire for stability can Lean on, away from 3 times of deformed area distance, datum mark should be all laid in pipe jacking tunnel.
Finally, in the range of tunnel ceiling regions, tunnel vault sedimentation one monitoring section of every 8 meters of layings, measuring point is uniform Tunnel top and bottom position are located at, monitoring instrument is observed tunnel bottoms sedimentation prison using precise electronic spirit level Measuring point selects segment bolt or self-control settlement monitoring original paper as monitoring point.
Horizontal displacement monitoring point includes:Building enclosure horizontal deflection on the top of wall monitoring point, building enclosure deeply mixing cement-soil pile prison Horizontal displacement monitoring point in measuring point, push pipe.
Horizontal displacement monitoring control net uses II grade traverse survey method, and horizontal displacement monitoring point uses minor angle method.Water Flat monitoring point for displacement mean square error of coordinate is ± 3.0mm.
The main technical requirements of center line horizontal displacement monitoring control net in the push pipe of table 4
Push pipe inner tunnel horizontal displacement basic point and settlement monitoring datum mark common point, altogether 2-3 datum mark, tunnel Nei Shui It is 8 meters of layings, one monitoring section (12 sections of meter) that prosposition moves layout of the monitoring points spacing, and 12 are amounted to per one measuring point of section Measuring point, is observed using 1 second total powerstation of high accuracy.
The monitoring of building enclosure deeply mixing cement-soil pile uses the type inclinometers of RST 0610 and supporting PVC inclinometer pipes, monitoring essence Degree can reach 0.01mm/0.5m.
First, horizontal displacement situation of the building enclosure at different depth in excavation of foundation pit and structure construction is understood.In base In the digging process of hole, as the foundation ditch inside soil body is largely removed, in the presence of outer lateral earth pressure, the level of being similar to can be produced to answer Power, building enclosure will necessarily produce displacement.Therefore, being necessary in Excavation Process to fender post/wall along depth direction Horizontal displacement be monitored measurement, and feed back in time, to take specific aim measure, it is ensured that foundation ditch, surrounding buildings or structures with And the safety of underground utilities etc..
Monitoring is implemented:
1) measuring point is buried
Building enclosure inclinometer pipe is embedded should to observe following principle with installation:
A, tested in the inclinometer pipe being embedded in building enclosure using inclinometer.Measuring point be preferably selected in deformation it is big (or It is dangerous) exemplary position.
B, ttom of pipe preferably maintain an equal level or slightly below steel reinforcement cage bottom with steel reinforcement cage bottom, and top reaches ground.
The steel reinforcement cage colligation of c, inclinometer pipe and supporting construction is buried, and colligation spacing is not preferably greater than 1.5m.Inclinometer pipe and reinforcing bar The fixation of cage must be sufficiently stable, in case during casting concrete, inclinometer pipe mutually comes off with steel reinforcement cage.Must be noted that inclinometer pipe simultaneously It is longitudinally twisted, the windup-degree of very little may be such that clinometer probe is blocked by guide groove.
Should be docked between d, the upper down tube of inclinometer pipe well, seamless, joint self-tapping screw is fixedly secured, uses joint sealing glue Sealing.
E, pipe should align direction when removing bundle, make to survey groove perpendicular to measuring surface a pair in pipe (i.e. parallel to direction of displacement).
F, bottom and top are sealed, keep the clean, unobstructed and straight of inclinometer pipe.
G, carry out clearly sign and reliable safeguard measure.
2) monitoring method
Deviational survey observation point is positive to survey and anti-survey, is first just surveyed during observation and (one is labeled with the wheel frame of each inclinometer Positive direction), then it is counter surveyed, usually per 0.5m, 1.0m reading once, inclino-probe is put into inclinometer pipe bottom and should wait 5 minutes, Water temperature in pipe is adapted to pop one's head in, the sealing of instrument probe and cable is should be noted that during observation, in case probe data transport part Divide water inlet.
Per 0.5m, 1.0m, mark must be stuck in same position when deviational survey is observed, and each reading must wait magnitude of voltage Stabilization ability reading, it is ensured that reading accuracy.
1., when deviational survey bottom of the tube is higher than excavation of foundation pit designed elevation position, and wall (stake) body produces displacement, can be pushed up using hole Method is pushed up toward bottom hole amendment using wall (stake) body horizontal displacement as reference value from hole.
2., when tested wall (stake) body is deformed, inclinometer pipe axis produces amount of deflection, and inclinometer pipe axis is determined with inclinometer Each section of inclination angle, just can calculate the horizontal displacement of the soil body (pile body, wall).If datum mark is O points, coordinate is (X0, Y0), in It is that the plane coordinates of each measuring point of inclinometer pipe axis is determined by following two formula:
I-measuring point sequence number, i=1,2 ... j in formula;L-inclinometer gauge length or measuring point spacing (m);
F-inclinometer calibration constant;
ΔεxiI-th section of-X-direction is positive and negative to survey reading strain difference half;
ΔεyiI-th section of-Y-direction is positive and negative to survey reading strain difference half;
To eliminate the error that measuring equipment zero shift causes, the inclination angle of each survey section both direction should all carry out positive and negative two Secondary measurement, i.e.,As Δ εxiOr Δ εyiDuring > 0, represent to X-axis or Y-axis Forward direction is inclined, as Δ εxiOr Δ εyiDuring < 0, represent negatively inclined to X-axis or Y-axis, it is each to calculate inclinometer pipe axis by above formula Measuring point horizontal level, it is relatively more different to survey time each measuring point horizontal coordinate, just may know that the horizontal displacement of pile body.
3) data process&analysis
Displacement-duration curve, hole depth should be drawn after measuring every time -- displacement curve.When horizontal displacement-pattern is undue suddenly Increase is a kind of alarm signal, after receiving alarm signal, immediately various measurement informations should be carried out with comprehensive analysis, in judging to construct Any problem is occurred in that, and takes the countermeasure for ensureing construction safety in time.
4) safeguard measure
It is the steel pipe socket of 80mm 1.5m long on the top of inclinometer pipe by Φ, to dig in the future first when inclinometer pipe is embedded Protection of wall when making Guan Liang to inclinometer pipe, the mouth of pipe with brick into inspection shaft, above plus iron covering protects top of inclinometer pipe not to be destroyed.Survey Inclined tube mouth of pipe vinyl cover is sealed in case debris enter.(push up bottom up and down) between the upper down tube of inclinometer pipe carries out one with glass glue It is secondary to be sealed, then be protected by with the wrapping of two layers of plastic woven bag.Carry out clearly protection sign in pipe top.
Axle power monitoring point includes:Bracing members axle power monitoring point, concrete axial force of the supports monitoring point.
Detecting instrument includes:Total powerstation, inclinometer:For the monitoring of horizontal displacement;Water-level gauge, water level test tube:For ground The monitoring of lower water level;Axle power meter, Reinforcement Stress-count:For the monitoring of axle power;Electronic level, indium steel ruler:For settling situation Monitoring;Electronics convergence gauge:For convergent monitoring in push pipe.Specifically used instrument is shown in Table 5,
The specifically used instrument of table 5
The step of water table measure information gathering is:
(3.1) measuring point is buried
A, pore-forming:Water-level observation hole is crept into using clear water, and drilling stops boring after reaching projected depth, in time that drilling cleaning is dry Only, the unobstructed situation of drilling is checked, and carries out cleaning record.
B, well casing processing:The raw material of well casing are the pvc pipe that internal diameter Φ 70, pipe thickness is 2.5;To ensure pvc pipe Water penetration, processes the through hole of cellular Φ 8 in the range of 0~4m of pvc pipe lower end, and the ring spacing in hole is 12mm, axial spacing It is 12mm, and bag geotextiles filter screen.
C, well casing are placed:After pore-forming, PVC well casings are hung, it is ensured that have filter opening end downward;Water-level observation hole should be above ground level 0.5m, sets fixed measuring point mark, and protected with protective case in aperture;
D, backfill gravel material:After observation of groundwater levels hole well casing hangs in hole, particle diameter should be filled out in the periphery of well casing immediately little In the meter Shi of 5mm;
E, well-flushing:After down tube, backfill gravel material terminate, well-flushing should be carried out using clear water in time, and carry out well-flushing record.
(3.2) monitoring method
Observation of groundwater levels equipment uses electric tape ga instrument, and accuracy of observation is 0.5cm, when gauge head touches underground water, Alarm sends alarm signal, now reads the scale label being connected with gauge head, and this reading is water level vertical with fixed measure Distance, then absolute altitude by fixed measuring point and it is converted into the depth to water and water level stake counted from ground with the relative position on ground It is high.
(3.3) data analysis and treatment.
Further, data handling utility computer carries out numbered analog simulation analysis in the step (4).
Further, the content of monitoring form includes in the step (4):Sedimentation deformation versus time curve, water Prosposition moves versus time curve, axle power versus time curve figure, water level versus time curve and convergency value Versus time curve.
Monitoring Warning Index value is each monitoring index set to ensure monitoring object safety before monitoring is implemented Estimate maximum.In monitoring process,
When measured value < 0.85* estimate maximum, safety;
When measured value=(0.85~1.0) * estimates maximum, note;
It is dangerous when measured value > 1.0* estimate maximum;
Wherein, (0.85* design loads be critical value) monitoring department should in form highlight indication, alarmed.
Monitoring and Controlling value and third party monitoring data and construction monitoring number that monitoring and warning rank is proposed according to designing unit According to compared to after relatively, the alert status of monitoring point in work progress are divided into level Four by the order of severity is ascending, normal (green, Level Four), yellow monitoring and warning (three-level), orange monitoring and warning (two grades) and red monitoring and warning (one-level), as shown in table 6.
The Classification Index table of the monitoring and warning rank of table 6
Wherein, the monitoring works warning value of starting well, received well and push pipe is as shown in table 7, table 8, table 9,
The starting well monitoring works warning value of table 7
The received well monitoring works warning value of table 8
The push pipe monitoring works warning value of table 9
Sequence number Project Alarming value Day alarming value
1 Push pipe ground settlement 15mm ±3mm
2 Vault settlement is measured in push pipe 15mm ±2-3mm
3 Arch bottom settlement measurement in push pipe 15mm ±2-3mm
4 Horizontal displacement is measured 10mm ±2mm
5 Horizontal convergence is measured 10mm ±1mm
What the present invention was used originate, the monitoring method of received well and jacking construction, designed compared with routine monitoring method Monitoring project organically combine, and form effective space-time, the data phase mutual energy of test is checked;With, play system Effect carries out comprehensive, stereoscopic monitoring to foundation ditch, it is ensured that survey the accurate, timely of data;Continuously supervised in construction work Survey, it is ensured that the continuity of data, and layout of the monitoring points is reduced using system behavio(u)r, it is cost-effective;Constructed using with design structure It is combined principle;Key parameter to being used in structure design is monitored, and reaches the purpose of further optimization design;Crucial portion Position is preferential, take into account comprehensive principle;Measuring point number and project are encrypted to region quite sensitive in fender body, supporting construction, is carried out Emphasis is monitored;It is uniform on the basis of systematic to lay monitoring point in addition to key position preferentially lays measuring point.Ensure comprehensively, On the premise of safety, rationally contacted using between monitoring point, improve operating efficiency, reduces cost.
The above, is only presently preferred embodiments of the present invention, not does any formal limitation to the present invention, it is every according to Any simple modification, the equivalent variations made to above example according to technical spirit of the invention, each fall within protection of the invention Within the scope of.

Claims (9)

1. a kind of originate, the monitoring method of received well and jacking construction, using monitoring technology to originating, received well and jacking construction During produce disturbance situation be monitored, it is characterised in that:Comprise the following steps:
(1) preparation of construction, including engineering geology and hydrogeological exploration are carried out at the scene;
(2) choose monitoring point and monitoring instrument is set on the monitoring section of monitoring point, monitoring point includes:Benchmark, sedimentation Monitoring point, horizontal displacement monitoring point, axle power monitoring point, water table measure point and convergence monitoring point in push pipe;
(3) monitoring frequency is formulated, the time according to monitoring frequency carries out information gathering to each monitoring point;
(4) information data of collection is recorded, analyzed and is processed, obtain monitoring form;
(5) monitoring Warning Index value is formulated, data and the value contrast of monitoring Warning Index of form will be monitored;
(6) standard of monitoring Warning Index value is reached, then continues to construct;If being not reaching to monitor the standard of Warning Index value, The reasonability and science of construction technology are assessed, arrangement and method for construction is adjusted.
2. it is according to claim 1 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:It is described The settlement monitoring point chosen in step (2) includes:Surface subsidence monitoring point, push pipe inner top and bottom settlement monitoring point, periphery Pipe settlement monitoring point, Building's Subsidence Survey point.
3. it is according to claim 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:It is described Horizontal displacement monitoring point in step (2) includes:Building enclosure horizontal deflection on the top of wall monitoring point, building enclosure deeply mixing cement-soil pile Horizontal displacement monitoring point in monitoring point, push pipe.
4. it is according to claim 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:It is described Axle power monitoring point in step (2) includes:Bracing members axle power monitoring point, concrete axial force of the supports monitoring point.
5. a kind of according to claim any one of 1-4 originate, the monitoring method of received well and jacking construction, its feature exists In:Detecting instrument in the step (2) includes:
Total powerstation, inclinometer:For the monitoring of horizontal displacement;
Water-level gauge, water level test tube:For the monitoring of level of ground water;
Axle power meter, Reinforcement Stress-count:For the monitoring of axle power;
Electronic level, indium steel ruler:Monitoring for settling situation;
Electronics convergence gauge:For convergent monitoring in push pipe.
6. it is according to claim 1 and 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:Institute The step of stating water table measure information gathering in step (3) be:
(3.1) measuring point is buried
A, pore-forming:Water-level observation hole is crept into using clear water, and drilling stops boring after reaching projected depth, in time cleans up drilling, The unobstructed situation of drilling is checked, and carries out cleaning record;
B, well casing processing:The raw material of well casing are the pvc pipe that internal diameter Φ 70, pipe thickness is 2.5;To ensure the permeable of pvc pipe Property, the through hole of cellular Φ 8 is processed in the range of 0~4m of pvc pipe lower end, the ring spacing in hole is 12mm, and axial spacing is 12mm, and bag geotextiles filter screen;
C, well casing are placed:After pore-forming, PVC well casings are hung, it is ensured that have filter opening end downward;0.5m above ground level is answered in water-level observation hole, Fixed measuring point mark is set in aperture, and is protected with protective case;
D, backfill gravel material:After observation of groundwater levels hole well casing hangs in hole, particle diameter no more than 5mm should be filled out in the periphery of well casing immediately Meter Shi;
E, well-flushing:After down tube, backfill gravel material terminate, well-flushing should be carried out using clear water in time, and carry out well-flushing record.
(3.2) level of ground water is observed
Observation of groundwater levels equipment uses electric tape ga instrument, and accuracy of observation is 0.5cm, when gauge head touches underground water, alarm Device sends alarm signal, now reads the scale label being connected with gauge head, and this reading is the vertical range of water level and fixed measure, Again the depth to water and water level elevation counted from ground are converted into by the absolute altitude of fixed measuring point and with the relative position on ground.
(3.3) data for obtaining will be observed to be analyzed and treatment.
7. it is according to claim 1 and 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:Institute Data handling utility computer carries out numbered analog simulation analysis in stating step (4).
8. it is according to claim 1 and 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:Institute The content for stating monitoring form in step (4) includes:Sedimentation deformation versus time curve, horizontal displacement change with time song Line, axle power versus time curve figure, water level versus time curve and convergency value versus time curve.
9. it is according to claim 1 and 2 it is a kind of originate, the monitoring method of received well and jacking construction, it is characterised in that:Institute It is that each monitoring set to ensure monitoring object safety before monitoring is implemented refers to state the monitoring Warning Index value in step (5) Target estimates maximum;In monitoring process,
When measured value < 0.85* estimate maximum, safety;
When measured value=(0.85~1.0) * estimates maximum, note;
It is dangerous when measured value > 1.0* estimate maximum;
Wherein, (0.85* design loads be critical value) monitoring department should in form highlight indication, alarmed.
CN201710124300.4A 2017-03-03 2017-03-03 It is a kind of originate, the monitoring method of received well and jacking construction Active CN106894821B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710124300.4A CN106894821B (en) 2017-03-03 2017-03-03 It is a kind of originate, the monitoring method of received well and jacking construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710124300.4A CN106894821B (en) 2017-03-03 2017-03-03 It is a kind of originate, the monitoring method of received well and jacking construction

Publications (2)

Publication Number Publication Date
CN106894821A true CN106894821A (en) 2017-06-27
CN106894821B CN106894821B (en) 2019-05-10

Family

ID=59184557

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710124300.4A Active CN106894821B (en) 2017-03-03 2017-03-03 It is a kind of originate, the monitoring method of received well and jacking construction

Country Status (1)

Country Link
CN (1) CN106894821B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107177497A (en) * 2017-08-01 2017-09-19 河南理工大学 A kind of mine worked-out section filling straw biological gas production system and its aerogenesis technique
CN108332884A (en) * 2018-02-07 2018-07-27 中铁十八局集团有限公司 Pipeline stress monitoring method in a kind of jacking construction
CN108733933A (en) * 2018-05-24 2018-11-02 奥克斯空调股份有限公司 Circuit design and emulation mode and device
CN109425387A (en) * 2017-08-31 2019-03-05 北京建工路桥集团有限公司 A kind of comprehensive monitoring system of vertical shaft and constructing tunnel
CN110207655A (en) * 2019-07-04 2019-09-06 石家庄铁道大学 Subgrade settlement monitoring settlement gauge and monitoring method
CN110593883A (en) * 2019-09-27 2019-12-20 上海建工集团股份有限公司 Method for indirectly evaluating safety state of existing pipeline under shield tunneling
CN111667246A (en) * 2020-06-09 2020-09-15 中交一公局集团有限公司 Road surface construction control method and device and computer readable storage medium
CN111677519A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield starting end reinforcing structure, reinforcing method and shield starting method
CN112983456A (en) * 2021-04-01 2021-06-18 中铁四局集团第四工程有限公司 Water-rich sand layer multi-row pipe jacking surface deformation control method
CN113339583A (en) * 2021-06-18 2021-09-03 湖北地建集团神龙市政建设工程有限公司 Pipe joint deflection and jacking force transmission state monitoring system and method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5438860A (en) * 1992-12-18 1995-08-08 Kabushiki Kaisha Komatsu Seisakusho Cutter bit abrasive detecting device of shield machine
CN101691840A (en) * 2009-09-21 2010-04-07 天津大学 Water level observation well and construction method thereof
CN102434209A (en) * 2011-11-03 2012-05-02 上海理工大学 Monitoring method for influence on adjacent existing structures from tunnel excavation
CN103471647A (en) * 2013-08-21 2013-12-25 国家电网公司 Long-distance automatic monitoring method for shield tunnel
CN104594911A (en) * 2015-02-16 2015-05-06 中建交通建设集团有限公司 Construction method of close-range down-traversing operation lines at initial stages or receiving stages of shield
CN104655099A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Safe settlement observing method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5438860A (en) * 1992-12-18 1995-08-08 Kabushiki Kaisha Komatsu Seisakusho Cutter bit abrasive detecting device of shield machine
CN101691840A (en) * 2009-09-21 2010-04-07 天津大学 Water level observation well and construction method thereof
CN102434209A (en) * 2011-11-03 2012-05-02 上海理工大学 Monitoring method for influence on adjacent existing structures from tunnel excavation
CN103471647A (en) * 2013-08-21 2013-12-25 国家电网公司 Long-distance automatic monitoring method for shield tunnel
CN104655099A (en) * 2013-11-25 2015-05-27 天津城建隧道股份有限公司 Safe settlement observing method
CN104594911A (en) * 2015-02-16 2015-05-06 中建交通建设集团有限公司 Construction method of close-range down-traversing operation lines at initial stages or receiving stages of shield

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107177497A (en) * 2017-08-01 2017-09-19 河南理工大学 A kind of mine worked-out section filling straw biological gas production system and its aerogenesis technique
CN107177497B (en) * 2017-08-01 2023-11-03 河南理工大学 Mine goaf filling straw biological gas production system and gas production process thereof
CN109425387A (en) * 2017-08-31 2019-03-05 北京建工路桥集团有限公司 A kind of comprehensive monitoring system of vertical shaft and constructing tunnel
CN108332884A (en) * 2018-02-07 2018-07-27 中铁十八局集团有限公司 Pipeline stress monitoring method in a kind of jacking construction
CN108733933A (en) * 2018-05-24 2018-11-02 奥克斯空调股份有限公司 Circuit design and emulation mode and device
CN110207655A (en) * 2019-07-04 2019-09-06 石家庄铁道大学 Subgrade settlement monitoring settlement gauge and monitoring method
CN110593883B (en) * 2019-09-27 2021-04-06 上海建工集团股份有限公司 Method for indirectly evaluating safety state of existing pipeline under shield tunneling
CN110593883A (en) * 2019-09-27 2019-12-20 上海建工集团股份有限公司 Method for indirectly evaluating safety state of existing pipeline under shield tunneling
CN111667246A (en) * 2020-06-09 2020-09-15 中交一公局集团有限公司 Road surface construction control method and device and computer readable storage medium
CN111677519B (en) * 2020-07-08 2022-05-13 北京建工土木工程有限公司 Reinforcing structure and reinforcing method for shield launching end and shield launching method
CN111677519A (en) * 2020-07-08 2020-09-18 北京建工土木工程有限公司 Shield starting end reinforcing structure, reinforcing method and shield starting method
CN112983456A (en) * 2021-04-01 2021-06-18 中铁四局集团第四工程有限公司 Water-rich sand layer multi-row pipe jacking surface deformation control method
CN112983456B (en) * 2021-04-01 2023-01-06 中铁四局集团第四工程有限公司 Water-rich sand layer multi-row pipe jacking ground surface deformation control method
CN113339583A (en) * 2021-06-18 2021-09-03 湖北地建集团神龙市政建设工程有限公司 Pipe joint deflection and jacking force transmission state monitoring system and method
CN113339583B (en) * 2021-06-18 2022-11-15 湖北地建集团神龙市政建设工程有限公司 Pipe joint deflection and jacking force transmission state monitoring system and method

Also Published As

Publication number Publication date
CN106894821B (en) 2019-05-10

Similar Documents

Publication Publication Date Title
CN106894821B (en) It is a kind of originate, the monitoring method of received well and jacking construction
CN107067333B (en) Method for monitoring stability of high-altitude and steep slope at high cold altitude
CN110631560B (en) Underground excavation interval monitoring and measuring method for subway station in dense building area
Chen et al. A new rock mass classification system QHLW for high-level radioactive waste disposal
CN111706362A (en) Karst cave treatment method for tunnel construction
CN204177381U (en) A kind of fiber bragg grating inclinometer device
CN111156006A (en) Construction method for shield underpass of dangerous pipeline
CN108999612A (en) A kind of constructing metro tunnel safety monitoring system Internet-based
CN103628461A (en) Horizontal stiffening treatment and collapse prewarning device for subgrade in soil-void area
CN115235417B (en) Monitoring point setting method based on angle between overlapped tunnels
CN111335904A (en) Shield downward-penetrating building construction monitoring method
CN116398244A (en) Tunnel karst defect fine detection and scale matching construction method
CN111075460A (en) Shield construction and monitoring method for urban dense building
CN106759542A (en) The deformation monitoring of deep basal pit and the method for Deformation Prediction
CN211900605U (en) Shield construction monitoring structure for down-penetrating urban dense building pipeline
Wei et al. Deformation characteristics of existing twin tunnels induced by double shield undercrossing with prereinforcement: A case study in Hangzhou
Wang et al. Height measurement of the water-conducting fracture zone based on stress monitoring
CN212898490U (en) Tunnel construction monitoring devices
CN218293664U (en) Four-line parallel long-span subway tunnel excavation construction monitoring structure
Dong et al. Best practices in water hazards control in coal mines
Perminov Modelling and monitoring of security unique underground structures of the sewerage system of major towns in difficult ground conditions
DOUNIAS MONITORING AND INSTRUMENTATION STRATEGIES FOR NEW AND EXISTING DAMS
Sylla et al. Study on the Safety and Prevention Technology of Coal Mining under the River in Xingyuan Coal Mine
CN115450633A (en) Method for evaluating safety risk of major-diameter water supply pipeline settlement caused by shield tunneling
Satıcı Assessment of plastic zone thickness and convergences for tunnels excavated in weak to fair quality rocks in Turkey

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant