The reparation remodeling method of bridge central partition Download PDFInfo
- Publication number
- CN106894348A CN106894348A CN201710224679.6A CN201710224679A CN106894348A CN 106894348 A CN106894348 A CN 106894348A CN 201710224679 A CN201710224679 A CN 201710224679A CN 106894348 A CN106894348 A CN 106894348A
- Authority
- CN
- China
- Prior art keywords
- bridge
- lightweight concrete
- ground floor
- central partition
- crash bearer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of reparation remodeling method of bridge central partition, it comprises the following steps:Remove face brick, antiglare shield, crash bearer and the former fill concrete of former bridge central partition to girder top surface;Both sides are installed by crash bearer, the built-in drainpipe of crash bearer;The first plank is set on two width bridge preset slot tops, is poured ground floor lightweight concrete and is formed two-way horizontal wall inscription, toe position is alignd with the spilled water hole lower edge of the drainpipe of crash bearer;In ground floor lightweight concrete upper berth ground floor SBS waterproof rolls;The second plank is set on ground floor SBS waterproof rolls;Then second layer lightweight concrete is poured;Second layer lightweight concrete is wrapped up with second layer SBS waterproof rolls;French drain is set in second layer lightweight concrete both sides, french drain Bian wraps up big particle diameter gravel with geotextiles;Laying planted agent mortar and Footpath brick.Improved central partition not ponding, impermeable, lifts bridge durability in the method.
Description
Technical field
The present invention relates to bridge technology field, more particularly to a kind of reparation remodeling method of bridge central partition.
Background technology
In existing highway bridge central partition structure, with benzene plate is embedded, waterproof layer is neoprene to two width bridge beam body preset slots
Newborn pitch, is filled, last upper berth Footpath brick with foam concrete.Benzene plate is only leaned in the built-in gap of compression of itself in itself, with
Two width bridges deform the changing of the relative positions up and down, and benzene plate material in itself is aging, and gap cannot effectively be filled up.Foam concrete itself hole
Rate is larger, and permeability rate is larger, and is not provided with preset slot in the middle of two width bridges, it can be caused to ftracture in the presence of mobile load, thus
Present situation beam body preset slot is caused to seep water.
The content of the invention
In order to solve the above technical problems, the present invention provides a kind of reparation remodeling method of bridge central partition.
The present invention provides a kind of reparation remodeling method of bridge central partition, and it comprises the following steps:
Step 1), face brick, antiglare shield, crash bearer and the former fill concrete of removing former bridge central partition to girder top
Face;
Step 2), both sides crash bearer is installed, the built-in drainpipe of crash bearer, the drainpipe dips down in the horizontal direction
Tiltedly set;The preset slot of crash bearer is closed with polyurethane sealant;
Step 3), two width bridge preset slots, the continuous gap and beam body expansion joint between of beam body bridge floor are used into asphalt mixtures modified by epoxy resin
Fat glue vinylacetic acid cellucotton is jumped a queue closing;
Step 4), two width bridge preset slot tops set the first plank, pour ground floor lightweight concrete and formed
Two-way horizontal wall inscription, toe position is alignd with the spilled water hole lower edge of the drainpipe of crash bearer, the seam of the reserved 1 × 1cm of concrete at toe,
Clogged with polyurethane sealant;
Step 5), in ground floor lightweight concrete upper berth ground floor SBS waterproof rolls;
Step 6), the second plank is set on ground floor SBS waterproof rolls, the second plank and the first plank are vertically
Alignment is set;Then second layer lightweight concrete is poured, and gap is clogged with vinylacetic acid cellucotton;
Step 7), with second layer SBS waterproof rolls by second layer lightweight concrete wrap up;
Step 8), in second layer lightweight concrete both sides, french drain is set, french drain Bian wraps up big particle diameter gravel with geotextiles;
Step 9), laying planted agent mortar and Footpath brick, and on Footpath brick reserve concrete longitudinal direction anchor band, install it is anti-dazzle
Plate.
Further,
The thickness of the ground floor lightweight concrete is 20cm~40cm, and the top surface gradient is not less than 2%;
The gradient of the drainpipe is not less than 1%.
The reparation remodeling method of the bridge central partition for providing of the invention, the method presses down by way of stifled row combines
Side bar flange plate processed, web are produced by water erosion disease, effectively improve bridge member durability.The method by center every
Ethylene vinyl acetate cellucotton is pasted from band inside beam body movement joint, while release beam body deforms, effectively suppresses the infiltration of water;Centering
Isolation strip interior construction seam in centre forms two-way horizontal wall inscription using the closing of polyurethane closed glue by pouring lightweight concrete, and laying is anti-
Water coiled material, sets up the system of french drain, and water leaking-in is discharged into central partition, and bridge zone is discharged on slope in length and breadth along deck paving, in making
Entreat isolation strip not ponding, impermeable, lifting bridge durability.
Brief description of the drawings
Fig. 1 isolates for the bridge center repaired after remodeling method is constructed of the bridge central partition provided according to the present invention
Band structure schematic diagram.
Description of reference numerals:
1- crash bearers
2- drainpipes
The planks of 3- first
4- ground floor lightweight concretes
5- ground floor SBS waterproof rolls
The planks of 6- second
7- second layer lightweight concretes
8- second layer SBS waterproof rolls
9- french drains
10- planted agent's mortars
11- Footpath bricks
12- antiglare shields
Specific embodiment
In order that those skilled in the art more fully understand the present invention program, with reference to the accompanying drawings and detailed description
The present invention is described in further detail.
For problems of the prior art, the present invention provides a kind of reparation remodeling method of bridge central partition,
The method is effectively sealed not only for gap so that whole central partition turns into a closed space, more passes through
The water guiding discharge central partition that effective manner will be penetrated into.Fig. 1 is referred to, the figure shows the bridge provided according to the present invention
The bridge central partition structural representation repaired after remodeling method construction of beam central partition.
In a kind of specific embodiment, the invention provides a kind of reparation remodeling method of bridge central partition,
It comprises the following steps:
Step 1), face brick, antiglare shield 12, crash bearer 1 and the former fill concrete of removing former bridge central partition to master
Top surface of the beam;
Step 2), both sides install crash bearer 1, the built-in drainpipe 2 of the crash bearer 1, the drainpipe 2 in the horizontal direction to
Under be obliquely installed;The preset slot of crash bearer 1 is closed with polyurethane sealant;
Step 3), two width bridge preset slots, the continuous gap and beam body expansion joint between of beam body bridge floor are used into asphalt mixtures modified by epoxy resin
Fat glue vinylacetic acid cellucotton is jumped a queue closing;
Step 4), on two width bridge preset slot tops, the first plank 3 is set, pour ground floor lightweight concrete 4 and shape
In pairs to horizontal wall inscription, toe position is alignd with the spilled water hole lower edge of the drainpipe 2 of crash bearer 1, the reserved 1 × 1cm of concrete at toe
Seam, clogged with polyurethane sealant;
Step 5), in the upper berth ground floor SBS waterproof roll 5 of ground floor lightweight concrete 4;
Step 6), the second plank 6 is set on ground floor SBS waterproof rolls 5, the second plank 6 is with the first plank 3 along vertical
Direction alignment is set;Then second layer lightweight concrete 7 is poured, and gap is clogged with vinylacetic acid cellucotton;
Step 7), second layer lightweight concrete 7 is wrapped up with second layer SBS waterproof rolls 8;
Step 8), in the both sides of second layer lightweight concrete 7, french drain 9 is set, the Bian of french drain 9 wraps up big particle diameter sand with geotextiles
Gravel;
Step 9), laying planted agent mortar 10 and Footpath brick 11, and on Footpath brick 11 reserve concrete longitudinal direction anchor band, peace
Dress antiglare shield 12.
Further, the thickness of the ground floor lightweight concrete 4 is 20cm~40cm, and the top surface gradient is not less than 2%;Institute
The gradient for stating drainpipe 2 is not less than 1%.
In the reparation modification scheme that the present invention is provided, former central partition face brick, antiglare shield, crash bearer and concrete are removed
To girder top surface;Bridge floor is continuous, gap is jumped a queue closing using epoxy resin glue vinylacetic acid cellucotton between expansion joint;
Crash bearer is installed, space is closed using polyurethane sealant between crash bearer.One layer of lightweight concrete is poured in central partition,
Bidirectional horizontal domatic into charge for remittance point is set, SBS waterproof rolls are laid, levelling lightweight concrete is poured, SBS waterproof rolls are re-layed,
Both sides set the gravel of geotextiles parcel, form closing waterproof system, install face brick and antiglare shield.
As shown in the above, the reparation remodeling method of the bridge central partition that the present invention is provided, is combined by stifled row
Mode, suppress side bar flange plate, web and produced by water erosion disease, effectively improve bridge member durability.The method is led to
Cross and ethylene vinyl acetate cellucotton is pasted to central partition inside beam body movement joint, while release beam body deforms, effectively suppress water
Infiltration;To central partition interior construction seam using the closing of polyurethane closed glue, form two-way by pouring lightweight concrete
Horizontal wall inscription, laying water-proof coiled material sets up the system of french drain, and water leaking-in is discharged into central partition, and slope is arranged in length and breadth along deck paving
Go out bridge zone, make central partition not ponding, impermeable, lifting bridge durability.
The reparation remodeling method to bridge central partition provided by the present invention is described in detail above.Herein
Apply specific case to be set forth principle of the invention and implementation method, the explanation of above example is only intended to help
Understand the method for the present invention and its core concept.It should be pointed out that for those skilled in the art, not taking off
On the premise of the principle of the invention, some improvement and modification can also be carried out to the present invention, these are improved and modification also falls into this
In invention scope of the claims.
Claims (2)
1. a kind of reparation remodeling method of bridge central partition, it is characterised in that comprise the following steps:
Step 1), face brick, antiglare shield, crash bearer and the former fill concrete of removing former bridge central partition to girder top surface;
Step 2), both sides install crash bearer, the built-in drainpipe of crash bearer, the drainpipe is downward-sloping in the horizontal direction to be set
Put;The preset slot of crash bearer is closed with polyurethane sealant;
Step 3), two width bridge preset slots, the continuous gap and beam body expansion joint between of beam body bridge floor are used into epoxide-resin glue
Vinylacetic acid cellucotton is pasted to jump a queue closing;
Step 4), two width bridge preset slot tops set the first plank, pour ground floor lightweight concrete and form two-way
Horizontal wall inscription, toe position is alignd with the spilled water hole lower edge of the drainpipe of crash bearer, the seam of the reserved 1 × 1cm of concrete at toe, with poly-
Urethane fluid sealant is clogged;
Step 5), in ground floor lightweight concrete upper berth ground floor SBS waterproof rolls;
Step 6), the second plank is set on ground floor SBS waterproof rolls, the second plank is vertically aligned with the first plank
Set;Then second layer lightweight concrete is poured, and gap is clogged with vinylacetic acid cellucotton;
Step 7), with second layer SBS waterproof rolls by second layer lightweight concrete wrap up;
Step 8), in second layer lightweight concrete both sides, french drain is set, french drain Bian wraps up big particle diameter gravel with geotextiles;
Step 9), laying planted agent mortar and Footpath brick, and on Footpath brick reserve concrete longitudinal direction anchor band, install antiglare shield.
2. the reparation remodeling method of bridge central partition according to claim 1, it is characterised in that
The thickness of the ground floor lightweight concrete is 20cm~40cm, and the top surface gradient is not less than 2%;
The gradient of the drainpipe is not less than 1%.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710224679.6A CN106894348B (en) | 2017-04-07 | 2017-04-07 | The reparation remodeling method of bridge central partition |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710224679.6A CN106894348B (en) | 2017-04-07 | 2017-04-07 | The reparation remodeling method of bridge central partition |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106894348A true CN106894348A (en) | 2017-06-27 |
CN106894348B CN106894348B (en) | 2019-04-05 |
Family
ID=59193644
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710224679.6A Expired - Fee Related CN106894348B (en) | 2017-04-07 | 2017-04-07 | The reparation remodeling method of bridge central partition |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106894348B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20100075419A (en) * | 2010-01-18 | 2010-07-02 | (주)백제건설 | Method and apparatus for improving safety fence structure along a roadside |
JP4618731B2 (en) * | 2006-09-22 | 2011-01-26 | ケイコン株式会社 | Precast concrete guard fence for the median strip of motorway viaduct and its construction method |
KR20120133877A (en) * | 2011-06-01 | 2012-12-11 | 남원길 | Bridge protection partition reform molding apparatus and its reform method |
CN203346829U (en) * | 2013-05-29 | 2013-12-18 | 重庆中设工程设计股份有限公司 | Medial strip |
CN203613487U (en) * | 2013-11-27 | 2014-05-28 | 湖北大成空间建筑科技有限公司 | Changeable emergency median strip |
CN204266150U (en) * | 2014-11-28 | 2015-04-15 | 大连市市政设计研究院有限责任公司 | A kind of hard isolated column for old bridge dividing strip |
-
2017
- 2017-04-07 CN CN201710224679.6A patent/CN106894348B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4618731B2 (en) * | 2006-09-22 | 2011-01-26 | ケイコン株式会社 | Precast concrete guard fence for the median strip of motorway viaduct and its construction method |
KR20100075419A (en) * | 2010-01-18 | 2010-07-02 | (주)백제건설 | Method and apparatus for improving safety fence structure along a roadside |
KR20120133877A (en) * | 2011-06-01 | 2012-12-11 | 남원길 | Bridge protection partition reform molding apparatus and its reform method |
CN203346829U (en) * | 2013-05-29 | 2013-12-18 | 重庆中设工程设计股份有限公司 | Medial strip |
CN203613487U (en) * | 2013-11-27 | 2014-05-28 | 湖北大成空间建筑科技有限公司 | Changeable emergency median strip |
CN204266150U (en) * | 2014-11-28 | 2015-04-15 | 大连市市政设计研究院有限责任公司 | A kind of hard isolated column for old bridge dividing strip |
Also Published As
Publication number | Publication date |
---|---|
CN106894348B (en) | 2019-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106223360B (en) | Using the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN107326940B (en) | basement advanced water stop post-cast strip structure and construction method thereof | |
CN207987983U (en) | A kind of waterproof construction being used for underground engineering main body construction seam and post-cast strip | |
CN107905114B (en) | A kind of construction method of large span Successive interference cancellation | |
CN104264594B (en) | A kind of self-balancing tied arch system for improving PSC continuous box girder bridge bearing ability and the method using it to reinforce | |
CN108589737A (en) | Underground speedy way hands over the construction method that section is built jointly with rail under a kind of major urban arterial highway | |
CN102296546A (en) | Treatment scheme of hollow slab bridge hinge joint defects and construction process thereof | |
CN108797249A (en) | The construction method of soft soil roadbed high roadbed steep slope road section Foam lightweight soil | |
CN109653491A (en) | More gradient Sloping roof concrete construction methods | |
CN101691742B (en) | Construction method for back cable-balancing single-side cantilever concreted beam bodies of slant-legged rigid frame bridges | |
WO2023155469A1 (en) | Road structure transformed from oversized detached underground garage and construction method thereof | |
CN106894347A (en) | A kind of splicing bridge and bridge reorganization and expansion method based on cast-in-place united layer supertronic | |
CN105781570B (en) | A kind of construction method of subway without inner support section of track well | |
CN107090908A (en) | A kind of new vertical prefabricated components joint connecting method | |
CN106894325A (en) | A kind of deck transverse slope adjusts structure and laying method | |
CN107700299B (en) | Overpass lower-layer ground road structure and construction method thereof | |
CN204875556U (en) | PC roof beam cable -stay bridge tower roof beam concreties structure temporarily | |
CN207032022U (en) | Bridge central partition | |
CN106948502A (en) | A kind of water-proof top cover and its construction method | |
CN110042865A (en) | Box top board structure for large span city tunnel | |
CN103306439A (en) | Pouring technology for implanting high anti-leakage and anti-crack protective layer into roof structure layer | |
CN106894333B (en) | Bridge central partition | |
CN106894348A (en) | The reparation remodeling method of bridge central partition | |
CN207905825U (en) | A kind of circular cross section tunnel lining construction device three times | |
CN207919848U (en) | Top plate of underground parking garage is combined the unit with plastics diaphragm capsule |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190405 Termination date: 20200407 |
|
CF01 | Termination of patent right due to non-payment of annual fee |