CN1068923C - Method for storey building construction and its device - Google Patents

Method for storey building construction and its device Download PDF

Info

Publication number
CN1068923C
CN1068923C CN 97115239 CN97115239A CN1068923C CN 1068923 C CN1068923 C CN 1068923C CN 97115239 CN97115239 CN 97115239 CN 97115239 A CN97115239 A CN 97115239A CN 1068923 C CN1068923 C CN 1068923C
Authority
CN
China
Prior art keywords
floor
pipe
steel
fixed
post mould
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 97115239
Other languages
Chinese (zh)
Other versions
CN1172883A (en
Inventor
高启伦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 97115239 priority Critical patent/CN1068923C/en
Publication of CN1172883A publication Critical patent/CN1172883A/en
Application granted granted Critical
Publication of CN1068923C publication Critical patent/CN1068923C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to an architecture construction method, particularly to a construction method for a building. The present invention comprises the main steps that 1), a construction blueprint is analyzed, the non-constructed ground is arranged, and the construction site is sampled; 2) the casting operation for a fiducial foundation R * C is finished on site; 3), a beam film bracket is sheathed at the lower part of a notch of a column mould, a beam film which is precasted is erected to be hung on the beam film bracket and is supported by a supporting rack to be positioned, and a steel bar coop for a beam is embedded into the beam film, and the beam film and a column mould are grouted; 4), a square steel pipe is spanned on the beam film; 5), hydroelectric pipes are matched in an R * C casting mode, and a partition wall is arranged; 6), an interface pad is filled in the floor with a steel supporting plate; 7), a balcony, doors, windows and a washroom are constructed. Thereby, the present invention has the advantages that the construction speed is fast, and the construction quality is guaranteed.

Description

A kind of method for storey building construction
The present invention relates to a kind of construction techniques, especially refer to method for storey building construction.
At present, known construction method for multi-storied building, after system follows closely into default post, beam, balcony, compartment, bathroom with a large amount of wooden forms and gives the model of putting door, window space, grouting one by one in regular turn, this method be prone to spillage, loss concrete and need form removal, when each Structural Engineering construction of floor, need build construction with a large amount of shelfs, template, curing time is long, has much danger.
In view of this, the purpose of this invention is to provide a kind of method for storey building construction, can give according to post, beam, tower, balcony, compartment, door and window, bathroom and cast suitable post mould, beam form combination, finish post, beam body, cooperate square steel or H shaped steel to replace into girder, can lay sunshade, the railing facility of steel board and balcony rapidly, and make up rapidly, with the benefit that prevents spillage in the sound insulation construction of sound insulation, door and window and in the laying work of bathroom.
The object of the present invention is achieved like this: a kind of method for storey building construction comprises post mould, Liang Heng, floor, compartment, balcony, door, window, bathroom, and the step of its feature is:
1) analyze the construction blueprint and plain put in order, field lofting, carry out material preparation, construction equipment and each operation unit materials classification simultaneously, cutting in regular turn is delivered to the scene;
2) level ground, benchmark ground R, C build and finish and preface is buried fixed frame for post mould stationary positioned at the scene, through the terrace setting-out, post muscle group is upright, the post module is stood and proofread and correct through vertical-horizontal, the post mould is connected and fixed the location and two floor gaps are connected by monolithic fixed mount or L shaped fixed mount with two post moulds with post mould fixed frame, in regular turn all post moulds is fixed;
3) be nested with below post mould breach with the beam form carriage, fixing after the vertical-horizontal calibration, precasting beam form group is upright, on the beam form carriage that is hung, support the location with support, insert beam steel dish cage in the beam form, beam form, post mould are in the milk;
4) with square steel pipe across being placed on the beam form, each square steel pipe end, be connected and fixed by receiving side plate, wherein, lay cement fibrolite plate and spot welding steel disk net, the wave groove of laying steel board and spot welding steel disk or steel board supports high spot welding steel mesh reinforcement with steel board pad, and cooperating post die tip height is benchmark;
5) carry out R, C and build the water power pipe arrangement, and the upright panel wall of group can be the dry-and wet-type light compartment wall, fast hard wall revolves work, the hollow light weight concrete wall;
6) in the floor of steel board, insert space between compartment and wall steel board with the interface pad, finish the compartment operation;
7) carry out balcony, door, window, bathroom operation, wherein, the post module system is divided into upper strata post mould and lower floor's post mould, lower floor's post mould is made up by the four sides plate, and upper strata post mould be all the four sides plate form, respectively with the four sides plate symmetry of lower floor's post mould, it offers the beam form groove in plate upper end, four sides of post mould at the middle and upper levels, more than, lower floor post mould nail solid on a fixed frame outside, giving in twos by four fixed hurdles, symmetry is fastened mutually, this four fixed hurdle system is grid paliform, and its two side ends all is provided with catching groove, is fastened with reverse symmetry in twos; Beam form system is by giving the beam fixed frame of casting shape, connect into a Jiong ellbeam horizontal stroke by combination two plates nail is solid at beam fixed frame in twos again, and give in the horizontal implantation of each beam fixed frame and to be embedded with square steel pipe, and in each beam fixed frame, be equiped with disymmetrical L shaped reinforcing cage pad, and in twos the beam fixed frame with the assembled panel junction, each supports the location by a support, this support system is by a square sleeve pipe support body, be nested with two H shape sleeve pipes, two H shape sleeve pipes symmetry and be inserted in two Jiong shape fixed bars, be combined in the v notch v location of beam fixed frame with Jiong shape cover by two Jiong shape fixed bars, at beam form, the post mould carries out R, after C builds, place square steel pipe with square steel pipe C1 or H shaped steel, and connect solid welding on beam form, lay steel board floor system by square steel pipe or H shaped steel, mould is striden on the square steel pipe that is placed in beam form, and one receives the side plate connection in each square steel pipe end, lays the steel board; Compartment ties up to floor when using the steel board, inserts space between panel wall and steel board with the interface pad, and this interface pad is that the entity wave is tabular; Balcony portion ties up to before floor finishes, and after establishing the steel board and receiving side plate in the solid welding of steel board outer peripheral edges, receipts side plate inboard, fix one and have the fixed head that a plurality of bolts are arranged, behind concrete grouting, fixed head is that bolt protrudes above concrete, the floor outer peripheral edges are promptly received the side plate outside, being nested with one has opening and extends into, following dull and stereotyped and be the sunshade lath, the upper flat plate of this sunshade lath is provided with a plurality of perforation, perforation is placed by the bolt of fixed head, and protrude the bolt part on upper flat plate, the perforation default for a railing frame is nested with, fix by the pad nut screwing, the following flat board of sunshade lath by screw at the steel board; Door section system has the big or small Partition wall boards that protruding bamboo shoot, an end have a grooving with an end and connects to form with latch and Jiong shape track, the size Partition wall boards is in the headspace inboard of door, give being pasted with rubber strip earlier, force the packing fit through recessed table caash bar, with screw; Before window partly tied up to window frame and Partition wall boards combination, the grooving opening part of window frame gave earlier being nested with-L shaped press strip, through screw high frame and Partition wall boards is connected and fixed; Bathroom system is one-body molded with the glass fiber precasting, and has the ground template die that flange is the hollow flute profile, this ground template die one side is the bathtub set section, one side is the aisle section of embossing, and place in the middle of ground template die periphery and bathtub set section and the aisle section, give and leave the catch basin that recessed road becomes, and at the bathtub set section, on aisle section and the catch basin, respectively establish a drain hole, catch basin is in parallel by water pipe with the drain hole of cylinder set section, bathtub is respectively offered a Jiong shape grooving with the drain hole of aisle section and the lateral margin of floor intermode for ccontaining strand, Jiong shape grooving locates respectively to establish a fixing hole with the flange symmetry of ground template die, and four jiaos of positions are located in ground template die hollow, respectively establish a screwed pipe with internal thread, screw togather a foot pad with bolt, and in four screwed pipes, be provided with most support chips of arranging with several Jiong shape groovings, the Jiong shape grooving of this support chip is identical, just doing by a spacer with locating hole, counter being nested with, but feed pipe cooperates, also the drain hole of template die connects fixing hole at flange according to the spacer just put and the spacer that is inverted, after water pipe is located from high to lower smoothly, cooperate screwed pipe to screw togather foot pad and adjust ground template die level, the flange of ground template die supplies screw behind the floor of floor, uprightly be arranged on the flange of ground template die by giving the fast hard wall that is embedded with hot water pipe and gutter, give and establish hot water pipe fixing hole and gutter fixing hole place and make the hot water pipe of hard wall and draining piping be set in the ground plate flange, on the ground template die, give in addition and establish two mouths that are in the milk; Above-mentioned ground template die is that concrete gives into the concrete ground template die, it is with high and low water pipe locating rack, fixedly water pipe is done location from high to lower, and its high water pipe locating rack is that an epimere is that pipe clamp portion, hypomere supports from portion, locatees the water pipe support is high, and low water pipe locating rack is a pipe clamp, and the bottom is a planar chip.
Owing to adopt such scheme: construction is rapid, and can guarantee construction quality.
Below in conjunction with drawings and Examples the utility model is further specified.
The construction composition flow chart of Fig. 1 exemplary embodiments of the present invention.
The post mould three-dimensional exploded view of Fig. 2 exemplary embodiments of the present invention.
The fixed hurdle exploded view of Fig. 3 exemplary embodiments of the present invention.
The fixed hurdle schematic diagram of Fig. 4 exemplary embodiments of the present invention.
The beam form exploded view of Fig. 5 exemplary embodiments of the present invention.
The beam form longitudinal section of Fig. 6 exemplary embodiments of the present invention.
The beam form longitudinal section of Fig. 7 exemplary embodiments of the present invention.
The beam of Fig. 8 exemplary embodiments of the present invention, the upright support decomposing schematic representation that reaches of post group.
The square steel pipe of Fig. 9 exemplary embodiments of the present invention and steel board combination schematic diagram.
The floor of Figure 10 exemplary embodiments of the present invention carries out R.C and builds schematic diagram.
The interface pad schematic diagram of Figure 11 exemplary embodiments of the present invention.
The balcony of Figure 12 exemplary embodiments of the present invention, railing three-dimensional exploded view.
The balcony of Figure 13 exemplary embodiments of the present invention, railing combination schematic diagram.
The door combination three-dimensional exploded view of Figure 14 exemplary embodiments of the present invention.
The door combination stereogram of Figure 15 exemplary embodiments of the present invention.
The door combination of Figure 16 exemplary embodiments of the present invention is sectional view fixedly.
The window combination three-dimensional exploded view of Figure 17 exemplary embodiments of the present invention.
The window assembled sectional view of Figure 18 exemplary embodiments of the present invention.
A kind of bathroom stereogram of Figure 19 exemplary embodiments of the present invention.
A kind of bathroom spacer of Figure 20 exemplary embodiments of the present invention is nested with at support chip or ground template die lateral margin schematic diagram.
A kind of bathroom spacer elevation of Figure 21 exemplary embodiments of the present invention.
A kind of bathroom spacer stereogram of Figure 22 exemplary embodiments of the present invention.
The positive and negative fixedly water pipe schematic diagram of putting of a kind of bathroom spacer of Figure 23 exemplary embodiments of the present invention.
A kind of bathroom screwed pipe of Figure 24 exemplary embodiments of the present invention screws togather foot pad and adjusts schematic diagram.
A kind of bathroom ground template die flange of Figure 25 exemplary embodiments of the present invention is fixed on the floor schematic diagram.
The another kind of bathroom ground template die schematic perspective view of Figure 26 exemplary embodiments of the present invention.
The high fixed mount schematic diagram of another kind of bathroom ground template die upper hose of Figure 27 exemplary embodiments of the present invention.
The another kind of bathroom ground template die upper hose of Figure 28 exemplary embodiments of the present invention hangs down the fixed mount schematic diagram.
Among the figure: post mould A, upper strata post mould A1, beam form groove A11, the post mould A2 of lower floor, fixed frame A3, fixed hurdle A4, catching groove A41, beam form carriage A5, beam form B, beam form framework B1, assembled panel B2, square steel pipe B3, L type reinforcing cage pad B4, support B5, square casing support body B51, H molded cannula B52, Jiong shape fixed bar B53, floor C, square steel pipe C1, steel board C2, receive side plate C3, sound insulation D, interface pad D1, panel wall D2, balcony part E, fixed head E1, bolt E11, sunshade lath E2, upper flat plate E21, following dull and stereotyped E22, perforation E23, railing frame E3, perforation E31, pad E4, nut E5, screw E6, concrete E7, door section F, size Partition wall boards F0, protruding bamboo shoot F1, grooving F2, latch F3, Jiong shape track F4, rubber pin F5, caash bar F6, screw F7, the window section H, grooving H0, window frame H1, Partition wall boards H2, L shaped press strip H3, screw H4, bathroom part I, bathtub set section I1, drain hole I10, Jiong shape grooving I11, fixing hole I13, grouting mouthful I14, aisle section I2, drain hole I20, Jiong shape grooving I21, fixing hole I23, flange I3, hot water pipe fixing hole I31, gutter fixing hole I32, catch basin I4, drain hole I40, screwed pipe I5, foot pad I6, support chip I7, Jiong shape grooving I71, spacer I8, locating hole I81, fast hard wall I9, screw I90, concrete ground template die J, high water pipe locating rack J21, the J210 of pipe clamp portion, height supporting part J211, low water pipe locating rack J22, pipe clamp J220, planar chip J221, water pipe J23.
Present embodiment comprises post mould A, beam form B, floor C, compartment D, balcony E, door F, window H, operations such as bathroom I, reaching floor building structure finishes rapidly, system analyzes the blue figure of construction and puts in order plainly, field lofting, carrying out material simultaneously prepares, construction equipment and each operation unit materials classification, cutting in regular turn is delivered to the scene, on-the-spot benchmark ground level ground R.C builds and finishes, and give the fixed frame A3 that buries for post mould stationary positioned, through the terrace setting-out, post muscle group is upright, post mould A group is upright, and proofread and correct through vertical-horizontal, A3 is connected and fixed the location with the post mould with post mould fixed frame, and two floor gaps are connected by monolithic fixed mount or L shaped fixed mount with two post mould A, in regular turn all post mould A are fixed, be nested with below post mould breach with beam form carriage A5, it is fixing that vertical-horizontal is proofreaied and correct the back, it is upright to give casting beam form group, be hung on the beam form carriage A5, support the location with support B5, insert the beam steel cage in the beam form B, beam form B, post mould A is in the milk, with rectangular steel tube C1 across being placed on the beam form B, each rectangular steel tube C1 end is connected and fixed by receiving side plate C3, wherein, 1, lay water combined filament plate and spot welding steel mesh reinforcement, 2, lay the wave groove of steel board C2 and spot welding steel mesh reinforcement or steel board C2; Support high spot welding steel mesh reinforcement with steel board pad, cooperating post mould A top height is benchmark, perhaps 3, lay the hollow floor, exempts to lay the spot welding steel mesh reinforcement; Carry out R.C and build the water power pipe arrangement, and group is found panel wall again, can be: 1, dry-and wet-type light compartment wall; 2, fast hard wall applies; 3, hollow light weight concrete wall; And when floor uses steel board C2, insert space between compartment and wall steel board C2 with interface pad D1, and finish the compartment operation, can carry out balcony E, F, window H, bathroom I operation; Wherein:
Post mould A, as Fig. 2, shown in 3, be divided into upper strata post mould A1 and the post mould A2 of lower floor, the post mould A2 of this lower floor is made up by the four sides plate, and upper strata post mould A1 is all the four sides plate and forms, respectively with the four sides plate symmetry of the post mould A2 of lower floor, wherein, the plate upper end, four sides of upper strata post mould A1 offers beam form groove A11, more than, the post mould A1 of lower floor, A2 nail solid on a fixed frame A3 outside, give in twos by four fixed hurdle A4 that symmetry is fastened mutually, should around decide hurdle A4, as Fig. 3, shown in 4, system is the grille fence shape, and its two side ends all is provided with catching groove A41, is fastened with reverse symmetry in twos, combination is rapid and support force is strong, quick-fried mould when preventing post mould A grouting;
Beam form B, shown in Fig. 5~8, system is by giving the beam fixed frame B1 that casts shape, connect into a ellbeam mould B by assembled panel B2 nail is solid at beam fixed frame B1 in twos again, and give in the horizontal implantation of each beam fixed frame B1 and to be embedded with square steel pipe B3, and in each beam fixed frame 1, be equiped with disymmetrical L shaped reinforcing cage pad B4, fixing reinforcing cage, make it have fixedly topping, and the support force of enhancing beam form B sidewall, and two sides beam fixed frame B1 is with assembled panel B2 junction, each supports the location by a support 5, this support B5 system is by a square sleeve pipe support body B51, be nested with two H shape sleeve pipe B52, and two H shape sleeve pipe B52 symmetries, and be inserted in two Jiong shape fixed bar B53, be combined in v notch v and the location of beam fixed frame B1 with Jiong shape cover by two Jiong shape fixed bar B53, B5 can go up with support, under adjust brace summer mould B, and the support power of enhancing beam form B sidewall, at beam form B, post mould A carries out after R.C builds, put at square steel B3 with square steel pipe C1 or H shaped steel, and connect solid welding on beam form B, for laying steel board C2;
Floor C shown in Fig. 9,10, is by square steel pipe C1 or H shaped steel, and across the square steel B3 that is placed in beam form, and each square steel pipe C1 end is received side plate C3 connection one laying steel board C2 by one;
Compartment D as shown in figure 11, ties up to floor C when using steel to hold C2, inserts space between panel wall D2 and steel board C2 with interface pad D1, and this interface pad D1 is that the entity wave is tabular, and is one-body molded by the PV partition material that foams, and reaches compartment adaptation height;
Balcony part E, as Figure 12, shown in 13, tie up to before floor finishes, and after laying steel board C2 and receiving side plate C3 in the welding of steel board C2 outer peripheral edges, receive side plate C3 inboard, fix one and have the fixed head E1 that a plurality of bolt E11 arrange, after concrete E7 grouting, the bolt E11 of fixed head E1 protrudes above concrete E7, floor C outer peripheral edges are promptly received the side plate C3 outside, being nested with one has opening and extends into, following dull and stereotyped E21, E22 and be sunshade lath E2, the upper flat plate E21 of this sunshade lath E2 is provided with a plurality of perforation E23, this perforation E23 is placed by the bolt E11 that decides plate E1, and protrude the bolt E11 part on upper flat plate E21, giving the perforation E31 that establishes for a railing frame E3 is nested with, screwed fixingly by pad E4 nut E5, following dull and stereotyped 22 of sunshade lath E2 is fixed on steel board C2 by screw E6, makes the sunbreaker of balcony, the moulding of railing Rapid Combination, and can comply with required difform railing, sunbreaker changes;
Door section F, shown in Figure 14~16, system has the big or small Partition wall boards F0 that protruding bamboo shoot F1, an end have grooving F2 with an end, connect to form with latch F3 and Jiong shape track F4, big or small Partition wall boards F0 is pasted with rubber strip F5 in advance in the headspace inboard of door F, force the packing fit through recessed portal moulding F6, F7 fixes with screw, makes Partition wall boards F0 and caash bar F0 and caash bar F0 close driving fit, and combination is seamless rapidly;
The window section H, shown in Figure 17,18, tie up to window frame H1 and Partition wall boards H2 the combination before, the grooving H0 opening part of window frame H1, be nested with a L shaped press strip H3 in advance, through screw H4 with window frame H1 with separate wallboard H2 and be connected and fixed, L shaped press strip H3 has the function that intercepts air, sound insulation, waterproof infiltration;
Bathroom I, shown in Figure 19~25, it is one-body molded that system gives casting with glass fiber, and has the ground template die that flange I3 is the hollow hat, ground template die one side is bathtub set section I1, one side is the aisle section I2 of pressureization, and place in the middle of ground template die I periphery and bathtub set section I1 and the aisle section I2, be reserved with recessed road and become one day catch basin I4, and at bathtub set section I1, on aisle section I2 and the catch basin I4, respectively establish a drain hole I10, I20, I40, the drain hole I40 of catch basin I4 and bathtub set section I1, I10 is by the water pipe parallel connection, the drain hole I10 of bathtub set section I1 and aisle section I2, the lateral margin of I20 and floor intermode is respectively offered a Jiong shape grooving I11, I21, Jiong shape grooving I11, the I21 and the flange I3 symmetry place of ground template die respectively establish a fixing hole I13, I23, and four jiaos of positions are located in ground template die hollow, respectively establish a screwed pipe I5 with internal thread, screw togather, foot pad I6 with bolt, and in four screwed pipe I5, be provided with a plurality of arrangements, and support chip I7 with several Jiong shape groovings I71, Jiong shape grooving I71 and the drain hole I10 of this support chip I7, the Jiong shape grooving I11 at I20 place, I21 is identical, just doing by a spacer I8 with locating hole I81, counter being nested with, but feed pipe is the drain hole I10 of template die I ordinatedly, I20, comply with the fixing hole I13 that the spacer I8 that is just putting and the spacer I8 that is inverted connect at flange I3, I23, after water pipe is located from high to lower smoothly, cooperate screwed pipe I5 to screw togather foot pad I6 and adjust ground template die I level, after the flange I3 of ground template die is fixed on the floor of floor for screw I90, uprightly be arranged on the flange I3 of ground template die by being embedded with the fast hard wall I9 of hot water pipe and gutter, and the hot water pipe of fast hard wall I9 and draining piping are set in the flange I3 default hot water pipe fixing hole I31 of institute and the gutter of ground template die, fixing hole I32 place, reach the construction Rapid Combination and finish the bathroom chamber, on the ground template die, preset two grouting mouthful I14 in addition, can supply concrete grouting, locating hole I81 according to spacer I8 injects, and increases the strength of bearing of ground template die.
Another kind of bathroom ground template die, shown in Figure 26~28, system can cast concrete floor mould J by concrete in advance, be with height water pipe locating rack J21, J22 fixedly water pipe J23 do location from high to lower, for the concrete grouting moulding, its high water pipe locating rack J21 is that an epimere is the J210 of pipe clamp portion, hypomere is height supporting part J211, can be a pipe J220 and hang down water pipe locating rack J22 with the high location of water pipe J23 support, the bottom is planar chip J221, in order to the bottom that water pipe J23 location is in ground template die J.

Claims (2)

1, a kind of method for storey building construction comprises post mould (A), Liang Heng (B), floor (C), compartment (D), balcony (E), door (F), window (H), bathroom (I), and the step of its feature is:
1) analyze the construction blueprint and plain put in order, field lofting, carry out material preparation, construction equipment and each operation unit materials classification simultaneously, cutting in regular turn is delivered to the scene;
2) level ground, benchmark ground R, C build and finish and preface is buried fixed frame (A3) for post mould stationary positioned at the scene, through the terrace setting-out, post muscle group is upright, post mould (A) group is stood and proofreaied and correct through vertical-horizontal, the post mould is connected and fixed the location and two floor gaps are connected by monolithic fixed mount or L shaped fixed mount with two post moulds (A) with post mould fixed frame (A3), in regular turn that all post moulds (A) are fixing;
3) be nested with below post mould breach with beam form carriage (A5), fixing after the vertical-horizontal calibration, precasting beam form group is upright, be hung on the beam form carriage (A5), support the location with support (B5), insert beam steel dish cage in the beam form (B), beam form (B), post mould (A) are in the milk;
4) with square steel pipe (C1) across being placed on the beam form (B), each square steel pipe (C1) end, be connected and fixed by receiving side plate (C3), wherein, (1) lays cement fibrolite plate and spot welding steel disk net, (2) the wave groove of laying steel board (C2) and spot welding steel disk or steel board (C2) supports high spot welding steel mesh reinforcement with steel board pad, and cooperating post mould (A) top height is benchmark;
5) carry out R, C and build the water power pipe arrangement, and the upright panel wall of group can be (1), dry-and wet-type light compartment wall, (2) fast hard wall revolve work, (3) hollow light weight concrete wall;
6) in the floor of steel board (C2), insert space between compartment and wall steel board (C2) with interface pad (D1), finish the compartment operation;
7) carry out balcony (E), door (F), window (H), bathroom (I) operation, wherein, post mould (A) is to be divided into upper strata post mould (A1) and lower floor's post mould (A2), lower floor's post mould (A2) is made up by the four sides plate, and upper strata post mould (A1) be all the four sides plate form, respectively with the four sides plate symmetry of lower floor's post mould (A2), it offers beam form groove (A11) in plate upper end, four sides of post mould (A1) at the middle and upper levels, more than, lower floor's post mould (A1), (A2) nail is solid goes up the outside at a fixed frame (A3), giving in twos by four fixed hurdles (A4), symmetry is fastened mutually, this four fixed hurdle (A4) is to be grid paliform, its two side ends all is provided with catching groove (A41), is fastened with reverse symmetry in twos;
Beam form (B) is a beam fixed frame (B1) of casting shape by giving, connect into a Jiong ellbeam horizontal stroke (B) by combination two plates (B2) nail is solid at beam fixed frame (B1) in twos again, and give in the horizontal implantation of each beam fixed frame (B1) and to be embedded with square steel pipe (B3), and in each beam fixed frame (B1), be equiped with disymmetrical L shaped reinforcing cage pad (B4), and in twos beam fixed frame (B1) with assembled panel (B2) junction, each supports the location by a support (5), this support (B5) is by a square sleeve pipe support body (B51), be nested with two H shape sleeve pipes (B52), two H shape sleeve pipes (B52) symmetry and be inserted in two Jiong shape fixed bars (B53), be combined in the v notch v location of beam fixed frame (B1) with Jiong shape cover by two Jiong shape fixed bars (B53), at beam form (B), post mould (A) carries out R, after C builds, place square steel pipe (B3) with square steel pipe C1 or H shaped steel, and connect solid welding on beam form (B), laying steel board (C2) floor (C) is by square steel pipe (C1) or H shaped steel, mould is striden on the square steel pipe (B3) that is placed in beam form (B), and one received side plate (C3) connection in each square steel pipe (C1) was terminal, laid steel board (C2);
Compartment (D) ties up to floor (C) when using steel board (C2), inserts space between panel wall (D2) and steel board (C2) with interface pad (D1), and this interface pad (D1) is that the entity wave is tabular; Balcony portion (E) ties up to before floor finishes, and after establishing steel board (C2) and receiving side plate (C3) in the solid welding of steel board (C2) outer peripheral edges, receive side plate (C3) inboard, fix one and have the fixed head (E1) that a plurality of bolts (E11) are arranged, after concrete (E7) grouting, fixed head (E1) is that bolt (E11) protrudes in concrete (E7) top, floor (C) outer peripheral edges are promptly received side plate (C3) outside, being nested with one has opening and extends into, following dull and stereotyped (E21), (E22) and be sunshade lath (E2), the upper flat plate (E21) of this sunshade lath (E2) is provided with a plurality of perforation (E13), perforation (E23) is placed by the bolt (E11) of fixed head (E1), and protrude bolt (E11) part on upper flat plate (E21), be nested with for the default perforation (E31) of a railing frame (E3), screwed fixingly by pad (E4) nut (E5), the following flat board (E22) of sunshade lath (E2) is fixed on steel board (C2) by screw (E6);
Door section (F) is to have the big or small Partition wall boards (F0) that protruding bamboo shoot (F1), an end have a grooving (F2) with an end to connect to form with latch (F3) and Jiong shape track (F4), size Partition wall boards (F0) is in the headspace inboard of door (F), give and be pasted with rubber strip (F5) earlier, force the packing fit through recessed table caash bar (F6), fixing with screw (F7);
Before window part (H) tied up to window frame (H1) and Partition wall boards (H2) combination, grooving (H0) opening part of window frame (H1) gave and is nested with a L shaped press strip (H3) earlier, through screw (H4) high frame (H1) and Partition wall boards (H2) is connected and fixed;
Bathroom (I) is one-body molded with the glass fiber precasting, and has the ground template die that flange (13) is the hollow flute profile, this ground template die one side is bathtub set section (I1), one side is the aisle section (I2) of embossing, and ground template die (I) periphery and bathtub set section (I1) and the middle place of aisle section (I2), give the catch basin (I4) that leaves recessed road and become, and at bathtub set section (I1), on aisle section (I2) and the catch basin (I4), respectively establish a drain hole (I10), (I20), (I40), the drain hole (I40) of catch basin (I4) and cylinder set section (I1), (I10) by the water pipe parallel connection, the drain hole (I10) of ccontaining thigh of bathtub (I1) and aisle section (I2), (I20) respectively offer a Jiong shape grooving (I11) with the lateral margin of floor intermode, (I21), Jiong shape grooving (I11), (I21) flange (I3) the symmetry place with the ground template die respectively establishes a fixing hole (I13), (I23), and four jiaos of positions are located in ground template die hollow, respectively establish a screwed pipe (15) with internal thread, screw togather a foot pad (I6) with bolt, and in four screwed pipes (I5), be provided with most support chips (I7) of arranging with several Jiong shape groovings (I71), the Jiong shape grooving (I11) of this support chip (I7), (I21) identical, just doing by a spacer (I8) with locating hole (I81), counter being nested with, but feed pipe cooperates, the also drain hole (I10) of template die (I), (I20) connect fixing hole (I13) according to the spacer (I8) just put and the spacer (I8) that is inverted at flange (I3), (I23), after water pipe is located from high to lower smoothly, cooperate screwed pipe (I5) to screw togather foot pad (I6) and adjust ground template die (I) level, after the flange (I3) of ground template die is fixed on the floor of floor for screw (I90), uprightly be arranged on the flange (I3) of ground template die by giving the fast hard wall (I9) that is embedded with hot water pipe and gutter, give and establish hot water pipe fixing hole (I31) and locate, on the ground template die, give in addition and establish two grouting mouths (I14) and make the hot water pipe of hard wall (I9) and draining piping be set in ground plate flange (I3) with gutter fixing hole (I32).
2, by the described a kind of method for storey building construction of claim 1, it is characterized in that: above-mentioned ground template die is that concrete gives into concrete ground template die (J), it is with high and low water pipe locating rack (J21), (J22), fixedly water pipe (J23) is done location from high to lower, its high water pipe locating rack (J21) is that an epimere is that pipe clamp portion (J210), hypomere support from portion (J211), with the high location of water pipe (J23) support, and low water pipe locating rack (J22) is a pipe clamp (J220), and the bottom is planar chip (J221).
CN 97115239 1997-08-22 1997-08-22 Method for storey building construction and its device Expired - Fee Related CN1068923C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 97115239 CN1068923C (en) 1997-08-22 1997-08-22 Method for storey building construction and its device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 97115239 CN1068923C (en) 1997-08-22 1997-08-22 Method for storey building construction and its device

Publications (2)

Publication Number Publication Date
CN1172883A CN1172883A (en) 1998-02-11
CN1068923C true CN1068923C (en) 2001-07-25

Family

ID=5173229

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 97115239 Expired - Fee Related CN1068923C (en) 1997-08-22 1997-08-22 Method for storey building construction and its device

Country Status (1)

Country Link
CN (1) CN1068923C (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101498159B (en) * 2008-02-02 2010-07-14 润弘精密工程事业股份有限公司 Grid precasting storey structure
CN102637329A (en) * 2011-02-11 2012-08-15 吴江庭 Building access turning auto-control traffic light warning device
CN102400563A (en) * 2011-10-10 2012-04-04 钱卫胜 Concrete construction foot pad
CN103233520B (en) * 2013-01-21 2017-03-22 宿迁市明远建筑安装工程有限公司 Self-waterproof construction method of building external wall structure
CN103321996A (en) * 2013-06-25 2013-09-25 向荣集团有限公司 Bridge buckle lock
JP6786583B2 (en) * 2015-03-25 2020-11-18 クオリティー マット カンパニー Mat construction with environmentally resistant core
CN104929241B (en) * 2015-07-10 2017-03-15 刘伟东 The beam slab rod structure of green ecological feasibility building system
CN106271065A (en) * 2016-08-09 2017-01-04 郭颂怡 The slag container of beams of concrete

Also Published As

Publication number Publication date
CN1172883A (en) 1998-02-11

Similar Documents

Publication Publication Date Title
US20180355600A1 (en) Building structure and construction method for same
CN1786364A (en) Composite warm preservation heat insulation concrete graded layer integrated pouring system and its construction method
CN1068923C (en) Method for storey building construction and its device
CN205369689U (en) Keep warm and decorate assembled precast floor plank of integration
AU2006302743A1 (en) Concrete floor system, incorporating foundation footing
AU2010354402A1 (en) Method for producing compact modules for construction
CN109629714A (en) A kind of prefabricated partition wall of the staircase with installation base and its installation method
CN217151235U (en) Beam bottom template supporting system
CN216921349U (en) Concrete cast-in-place pitched roof construction template device
CN111809792B (en) Assembled precast concrete wallboard
CN212388680U (en) Closed structure of vertical drainage pipe in kitchen and toilet of residence
CN112012382B (en) Floor heat-insulation sound-insulation structure applying microcrystal heat-insulation self-leveling mortar
CN213359377U (en) Building templates support frame
CN208415810U (en) A kind of caisson type accomodation ground assembling mounting structure
CN111894266A (en) Integral construction method for primary formwork support of plate-rafter integrated roof of antique building
JP2002095347A (en) Greening structure of construction
CN1584240A (en) Plaster hollow large panel pouring concrete wall and manufacturing method thereof
CN211816354U (en) Assembly type prefabricated plate disassembly-free thin plate and tire mold combined type fixing system
CN220486863U (en) Sound-insulation and heat-insulation integrated assembled composite floor slab
CN203867175U (en) Adjustable partition assembling support formwork
CN221422834U (en) Railway shade canopy with adjustable height
CN203782759U (en) Construction elevator foundation reinforcing device
CN220905900U (en) Support frame is placed to assembled prefabricated plate
CN211647448U (en) Shaped supporting system for laminated floor slab
CN217079341U (en) Novel assembly type system capable of realizing rapid indoor decoration

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee