CN106849142A - User's sidelight stores up integral system demand charge capacity configuration software algorithm - Google Patents

User's sidelight stores up integral system demand charge capacity configuration software algorithm Download PDF

Info

Publication number
CN106849142A
CN106849142A CN201710031813.0A CN201710031813A CN106849142A CN 106849142 A CN106849142 A CN 106849142A CN 201710031813 A CN201710031813 A CN 201710031813A CN 106849142 A CN106849142 A CN 106849142A
Authority
CN
China
Prior art keywords
power
energy storage
photovoltaic
charge
difference
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710031813.0A
Other languages
Chinese (zh)
Inventor
牛曙斌
张辉
毛知新
周玉
陈卜云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Gcl Distributed Energy Development Co Ltd
Original Assignee
Wuxi Gcl Distributed Energy Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Gcl Distributed Energy Development Co Ltd filed Critical Wuxi Gcl Distributed Energy Development Co Ltd
Priority to CN201710031813.0A priority Critical patent/CN106849142A/en
Publication of CN106849142A publication Critical patent/CN106849142A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • H02J3/32Arrangements for balancing of the load in a network by storage of energy using batteries with converting means
    • H02J3/383
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy
    • Y02E10/56Power conversion systems, e.g. maximum power point trackers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E70/00Other energy conversion or management systems reducing GHG emissions
    • Y02E70/30Systems combining energy storage with energy generation of non-fossil origin

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Charge And Discharge Circuits For Batteries Or The Like (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

Present invention relates to user's sidelight storage integral system demand charge capacity configuration software algorithm, it is divided into following steps:1) software input, obtains user's year timesharing load curve as the input for calculating;2) according to the annual timesharing load curve of user, distributed rationally by the photovoltaic capacity under locally dissolving and calculate optimal photovoltaic configuration capacity and cost of investment, the charge and discharge time requirement according to the information such as battery types, DOD depth of discharges, the battery efficiency for being equipped with energy-storage system and peak load shifting calculates optimum capacity configuration and the cost of investment of battery;3) demand charge optimization is provided the user:If user pays capacity payment again by demand charge, and daytime is bigger than evening power consumption, and maximum demand time of origin was shorter, less than 1 hour, it is contemplated that by energy storage reduction maximum demand reduction demand charge.0 when energy storage uses evening paddy:00‑8:00 charges, and is discharged when maximum demand occurs.Discharge power can be by PCivil power> PTarget powerSituation is discharged, PCivil power=Ptn* stop electric discharge when 40%.Monthly income:Cin=(PSetting power‑Ptn* 40%) * 40 yuan/months, PCivil power=PLoad‑PPhotovoltaic

Description

User's sidelight stores up integral system demand charge capacity configuration software algorithm
Technical field
The invention belongs to power generation applications software field, it is related to user's sidelight to store up integral system demand charge capacity configuration soft Part algorithm.
Background technology
With society fast-developing new energy in energy resource system proportion it is increasing, miniaturization, modularization, divide Dissipate formula, be arranged near user as the compact electrical generating systems of customer power supply are popularizing installation, distributed generation technology by with Bulk power grid connection provides the user stabilization, the supply of reliable electric energy, and the energy off-grid operation in bulk power grid failure, it is ensured that supply The continuity and the quality of power supply high of electricity.It is the preferable solution of energy scarcity and environmental pollution.
The regenerative resources such as solar energy power generating with its it is inexhaustible the characteristics of, receive extensive concern. The shared ratio in microgrid of photovoltaic generating system is also more come also high.But there is randomness and fluctuation in independent photovoltaic generating system The shortcomings of property, when its permeability is larger, the safe and stable operation of micro-capacitance sensor will be influenceed.In order to solve photovoltaic generation and energy storage The problems such as power-balance, stability and the quality of power supply in the micro-grid system of composition, it is necessary to be equipped with power output more stable Energy-storage system, and according to predetermined control strategy, realize the equilibrium,transient of micro-grid system internal energy, realize photovoltaic energy storage The stable operation of micro-capacitance sensor.
Energy storage can smooth exerting oneself for photovoltaic generation as a kind of energy accumulating device, and appropriate stored energy capacitance can also rise To the effect of peak load shifting, especially in Peak-valley TOU power price, electric energy can be made full use of, moreover it is possible to for user saves energy charge With.
Conventional photovoltaic generation simulation software, be using local photometric data, installation site according to photovoltaic generating system, Mounting means etc. calculates the generated energy of photovoltaic generating system, and economy is calculated according to local subsidy policy, instructs user's light The selection and installation of photovoltaic generating system.
The content of the invention
The present invention provides user's sidelight storage integral system demand charge capacity configuration software algorithm.For user selects to install Light storage integral system provides capacity configuration and instructs and the measuring and calculating of expected economy.Characterisitic parameter by being input into user of the invention With with electrical feature, the capacity of installed capacity and the energy-storage system configuration of best configuration photovoltaic generation is calculated by software, then, The quantity of electricity payment calculates economy before and after contrast is installed, and instructs photovoltaic that user installation is appropriate and reserves most to pass through to reach The system configuration of Ji.
For problem and defect that existing simulation software algorithm is present, the present invention is proposed:
Power load situation according to user, determines the electricity consumption paid mode, gather user of demand charge, electrical capacity charge Information (such as power, electricity), determines voltage class, peak, flat, the paddy electricity valency of user, and daytime and evening electrical characteristics, maximum Requirement time of occurrence and duration, few to evening electricity consumption according to the data results of collection, daytime uses the user of point multiple spot Carry out light storage capacity optimization.
User's sidelight stores up integral system demand charge capacity configuration software algorithm, is divided into following steps:1) software input, User's year timesharing load curve is obtained as the input for calculating;
2) according to the annual timesharing load curve of user, distributed rationally by the photovoltaic capacity under locally dissolving and calculated most preferably Photovoltaic configuration capacity and cost of investment, according to information such as battery types, DOD depth of discharges, the battery efficiencies for being equipped with energy-storage system With optimum capacity configuration and the cost of investment that the charge and discharge time requirement of peak load shifting calculates battery;
3) demand charge optimization is provided the user:
If user pays capacity payment again by demand charge, and daytime is bigger than evening power consumption, maximum demand time of origin compared with It is short, less than 1 hour, it is contemplated that by energy storage reduction maximum demand reduction demand charge.0 when energy storage uses evening paddy:00-8:00 Charge, discharged when maximum demand occurs.Discharge power can be by PCivil power> PTarget powerSituation is discharged, PCivil power=Ptn* stop putting when 40% Electricity.Monthly income:Cin=(PSetting power-Ptn* 40%) * 40 yuan/months, PCivil power=PLoad-PPhotovoltaic
Further, step 3) capacity optimisation strategy is changed to result output.
1) " electrical capacity charge+degree electricity electricity charge " class industrial user electricity optimization,
(under conditions of ensureing civil power peak value no more than transformer capacity, make full use of stored energy capacitance, paddy fill peak put)
0—8h,If{CStorage<CAlways,(CAlways-CStorage)/8,0 } if energy storage electricity is discontented, at the uniform velocity it is charged to full
8—12h,If{PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<PStorage max,PIt is negative-PLight,PStorage max),0),if(CStorage<2000, if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic can be met Power difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, in addition deficiency with civil power 2. If energy storage is empty, load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, earning photovoltaic the online electricity charge 12-17h, If { PIt is negative-PLight>=0,0, if (CStorage<2000,if(PIt is negative-PLight>- PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power.
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
17—21h,If{PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<PStorage max,PIt is negative-PLight,PStorage max),0),if(CStorage<2000, if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic can be met Power difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, in addition deficiency with civil power 2. If energy storage is empty, load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
21—24h,If{PIt is negative-PLight>=0,0, if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
2) " demand charge+degree electricity electricity charge " class industrial user electricity optimization
(under conditions of ensureing civil power peak value no more than limit value, utilization stored energy capacitance as much as possible, paddy is filled peak and puts)
0-8h, If { PIt is negative-PLight>=PCity max, yesterday,if(CStorage>0,PIt is negative-PLight-PCity max, yesterday,0),if(CStorage<2000,PIt is negative-PLight- PCity max, yesterday,0)}
(1) if customer charge more than photovoltaic and yesterday maximum city's electric power sum when 1. energy storage can discharge, load and If other both difference are provided by energy storage, and 2. energy storage is empty, load is all provided with both difference by civil power, demand power It is also possible to therefore raise
(2) if 1. energy storage is chargeable during maximum less than the photovoltaic and yesterday city's electric power sum of customer charge, according to Peak power civil power, if meeting outside load needs, 2. energy storage has been expired to energy storage charging, only powers to the load for needing
8-12h, If { PIt is negative-PLight>PCity, peak clipping, if (CStorage>0,PIt is negative-PLight-PCity, peak clipping,0),if{PIt is negative-PLight>=0,0, if (CStorage< 2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0))}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
12-17h, If { PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<=PCity max, yesterday,0,PIt is negative-PLight-PCity max, yesterday),0),if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
17-21h, If { PIt is negative-PLight>PCity, peak clipping, if (CStorage>0,PIt is negative-PLight-PCity, peak clipping,0),if{PIt is negative-PLight>=0,0, if (CStorage< 2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0))}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
21-24h, If { PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<=PCity max, yesterday,0,PIt is negative-PLight-PCity max, yesterday),0),if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
Brief description of the drawings
Day accumulative electric cost contrast before and after the optimization of Fig. 1 capacity.
Electric cost contrast per hour before and after the optimization of Fig. 2 capacity.
Day accumulative electric cost contrast before and after the optimization of Fig. 3 requirements.
Day accumulative electric cost contrast before and after the optimization of Fig. 4 requirements.
Specific implementation method
User's sidelight stores up integral system demand charge capacity configuration software algorithm, is divided into following steps:1) software input, User's year timesharing load curve is obtained as the input for calculating;
2) according to the annual timesharing load curve of user, distributed rationally by the photovoltaic capacity under locally dissolving and calculated most preferably Photovoltaic configuration capacity and cost of investment, according to information such as battery types, DOD depth of discharges, the battery efficiencies for being equipped with energy-storage system With optimum capacity configuration and the cost of investment that the charge and discharge time requirement of peak load shifting calculates battery;
3) demand charge optimization is provided the user:
If user pays capacity payment again by demand charge, and daytime is bigger than evening power consumption, maximum demand time of origin compared with It is short, less than 1 hour, it is contemplated that by energy storage reduction maximum demand reduction demand charge.0 when energy storage uses evening paddy:00-8:00 Charge, discharged when maximum demand occurs.Discharge power can be by PCivil power> PTarget powerSituation is discharged, PCivil power=Ptn* stop putting when 40% Electricity.Monthly income:Cin=(PSetting power-Ptn* 40%) * 40 yuan/months, PCivil power=PLoad-PPhotovoltaic
Capacity optimisation strategy is exported with result
1) " electrical capacity charge+degree electricity electricity charge " class industrial user electricity optimization
(under conditions of ensureing civil power peak value no more than transformer capacity, make full use of stored energy capacitance, paddy fill peak put)
0—8h,If{CStorage<CAlways,(CAlways-CStorage)/8,0 } if energy storage electricity is discontented, at the uniform velocity it is charged to full
8—12h,If{PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<PStorage max,PIt is negative-PLight,PStorage max),0),if(CStorage<2000, if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic can be met Power difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, in addition deficiency with civil power 2. If energy storage is empty, load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
12—17h,If{PIt is negative-PLight>=0,0, if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power.
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
17—21h,If{PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<PStorage max,PIt is negative-PLight,PStorage max),0),if(CStorage<2000, if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic can be met Power difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, in addition deficiency with civil power 2. If energy storage is empty, load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
21—24h,If{PIt is negative-PLight>=0,0, if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
Before and after capacity optimization before and after day accumulative electric cost contrast and capacity optimization per hour electric cost to such as Fig. 1,2 It is shown.
2) " demand charge+degree electricity electricity charge " class industrial user electricity optimization
(under conditions of ensureing civil power peak value no more than limit value, utilization stored energy capacitance as much as possible, paddy is filled peak and puts)
0-8h, If { PIt is negative-PLight>=PCity max, yesterday,if(CStorage>0,PIt is negative-PLight-PCity max, yesterday,0),if(CStorage<2000,PIt is negative-PLight- PCity max, yesterday,0)}
(1) if customer charge more than photovoltaic and yesterday maximum city's electric power sum when 1. energy storage can discharge, load and If other both difference are provided by energy storage, and 2. energy storage is empty, load is all provided with both difference by civil power, demand power It is also possible to therefore raise
(2) if 1. energy storage is chargeable during maximum less than the photovoltaic and yesterday city's electric power sum of customer charge, according to Peak power civil power, if meeting outside load needs, 2. energy storage has been expired to energy storage charging, only powers to the load for needing
8-12h, If { PIt is negative-PLight>PCity, peak clipping, if (CStorage>0,PIt is negative-PLight-PCity, peak clipping,0),if{PIt is negative-PLight>=0,0, if (CStorage< 2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0))}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
12-17h, If { PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<=PCity max, yesterday,0,PIt is negative-PLight-PCity max, yesterday),0),if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge
17-21h, If { PIt is negative-PLight>PCity, peak clipping, if (CStorage>0,PIt is negative-PLight-PCity, peak clipping,0),if{PIt is negative-PLight>=0,0, if (CStorage< 2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0))}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
21-24h, If { PIt is negative-PLight>=0, if (CStorage>0,if(PIt is negative-PLight<=PCity max, yesterday,0,PIt is negative-PLight-PCity max, yesterday),0),if (CStorage<2000,if(PIt is negative-PLight>-PStorage max,PIt is negative-PLight,-PStorage max),0)}
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and load can be met Both difference with other, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency in addition With civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power also has May therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping controlled during less than photovoltaic and peak valency is highly Three's difference is all provided by civil power during sum
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power is small with load difference In energy storage maximum charge power, then difference is fully absorbed by energy storage, and energy storage is charged by peak power during more than energy storage peak power, Other input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expired by energy storage, and photovoltaic power is more than Loaded portion is directly surfed the Net, the earning photovoltaic online electricity charge.
Add up day before and after electric cost contrast and requirement optimization to add up electric cost day to such as Fig. 3,4 before and after requirement optimization It is shown.

Claims (2)

1. user's sidelight stores up integral system demand charge capacity configuration software algorithm, it is characterized by, it is divided into following steps:1) it is soft Part is input into, and obtains user's year timesharing load curve as the input for calculating;
2) according to the annual timesharing load curve of user, distributed rationally by the photovoltaic capacity under locally dissolving and calculate optimal photovoltaic Configuration capacity and cost of investment, according to the information such as battery types, DOD depth of discharges, battery efficiency for being equipped with energy-storage system and cut The charge and discharge time requirement of peak load calculates optimum capacity configuration and the cost of investment of battery;
3) demand charge optimization is provided the user:
If user pays capacity payment again by demand charge, and daytime is bigger than evening power consumption, and maximum demand time of origin is shorter, low In 1 hour, it is contemplated that by energy storage reduction maximum demand reduction demand charge.0 when energy storage uses evening paddy:00-8:00 charges, Discharged when maximum demand occurs.Discharge power can be by PCivil power> PTarget powerSituation is discharged, PCivil power=Ptn* stop electric discharge when 40%.The moon is received Enter:Cin=(PSetting power-Ptn* 40%) * 40 yuan/months, PCivil power=PLoad-PPhotovoltaic
2. user's sidelight as claimed in claim 1 stores up integral system demand charge capacity configuration software algorithm, it is characterized by, Step 3) capacity optimisation strategy is changed to result output:
1) " electrical capacity charge+degree electricity electricity charge " class industrial user electricity optimization, is ensureing civil power peak value no more than transformer capacity Under the conditions of, making full use of stored energy capacitance, paddy is filled peak and puts;
0-8h, if energy storage electricity is discontented, is at the uniform velocity charged to full;
8—12h,
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic power can be met Difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, if in addition deficiency with civil power 2. Energy storage is empty, and load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic online the electricity charge (0.378+0.42) unit/kWh;If 2. energy storage has been expired, photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
12—17h,
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
17—21h,
(1) if 1. energy storage can discharge customer charge when being more than or equal to photovoltaic generation power, and load and photovoltaic power can be met Difference, then difference completely by energy storage provide, it is impossible to when meeting energy storage by peak power discharge, if in addition deficiency with civil power 2. Energy storage is empty, and load is all provided with photovoltaic power difference by civil power;
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
21—24h,
(1) when customer charge is more than or equal to photovoltaic generation power, without energy storage, supplied with civil power
(2) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
2) " demand charge+degree electricity electricity charge " class industrial user electricity optimization, is ensureing condition of the civil power peak value no more than limit value Under, utilization stored energy capacitance as much as possible, paddy is filled peak and puts;
0-8h, (1) if 1. energy storage can discharge during maximum more than the photovoltaic and yesterday city's electric power sum of customer charge, load If 2. energy storage is empty by energy storage offer for both difference with other, load is all provided with both difference by civil power, requirement work( Rate is also possible to therefore raise;
(2) if 1. energy storage is chargeable during maximum less than the photovoltaic and yesterday city's electric power sum of customer charge, according to maximum Power civil power, if meeting outside load needs, 2. energy storage has been expired to energy storage charging, only powers to the load for needing;
8-12h,
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and can meet load and its The difference of both he, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency city in addition Electricity, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power is also possible to Therefore raise;
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping height sum controlled during less than photovoltaic and peak valency Shi Sanzhe difference is all provided by civil power;
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
12-17h,
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and can meet load and its The difference of both he, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency city in addition Electricity, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power is also possible to Therefore raise;
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping height sum controlled during less than photovoltaic and peak valency Shi Sanzhe difference is all provided by civil power;
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
17-21h,
(1) if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and can meet load and its The difference of both he, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, deficiency city in addition Electricity, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, and demand power is also possible to Therefore raise
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping height sum controlled during less than photovoltaic and peak valency Shi Sanzhe difference is all provided by civil power;
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge;
21-24h, (1) are if 1. energy storage can discharge during electric more than the photovoltaic and peak peak clipping height sum of customer charge, and can meet Load and other both difference, then difference is completely by energy storage offer, it is impossible to which energy storage is discharged by peak power when meeting, in addition Deficiency civil power, if demand power is raised, and 2. energy storage is empty, load is all provided with both difference by civil power, demand power It is also possible to therefore raise;
(2) customer charge is more than or equal to photovoltaic generation power, but the civil power peak clipping height sum controlled during less than photovoltaic and peak valency Shi Sanzhe difference is all provided by civil power;
(3) if 1. energy storage is chargeable when being less than photovoltaic generation power for customer charge, and photovoltaic power and load difference are less than storage Can maximum charge power, then difference fully absorbed by energy storage, during more than energy storage peak power energy storage by peak power charge, in addition Input power network, earning photovoltaic surfs the Net the electricity charge (0.378+0.42) if unit/kWh 2. expire by energy storage, and photovoltaic power is more than load Part is directly surfed the Net, the earning photovoltaic online electricity charge.
CN201710031813.0A 2017-01-17 2017-01-17 User's sidelight stores up integral system demand charge capacity configuration software algorithm Pending CN106849142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710031813.0A CN106849142A (en) 2017-01-17 2017-01-17 User's sidelight stores up integral system demand charge capacity configuration software algorithm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710031813.0A CN106849142A (en) 2017-01-17 2017-01-17 User's sidelight stores up integral system demand charge capacity configuration software algorithm

Publications (1)

Publication Number Publication Date
CN106849142A true CN106849142A (en) 2017-06-13

Family

ID=59123121

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710031813.0A Pending CN106849142A (en) 2017-01-17 2017-01-17 User's sidelight stores up integral system demand charge capacity configuration software algorithm

Country Status (1)

Country Link
CN (1) CN106849142A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786700A (en) * 2017-01-17 2017-05-31 无锡协鑫分布式能源开发有限公司 User's sidelight stores up integral system off-grid operation capacity configuration software algorithm
CN108233422A (en) * 2018-02-09 2018-06-29 大工(青岛)新能源材料技术研究院有限公司 A kind of light storage micro-grid operational control method based on PREDICTIVE CONTROL
CN108767896A (en) * 2018-06-11 2018-11-06 中国科学院电工研究所 A kind of control method for coordinating of light storage charging system
CN110601334A (en) * 2019-08-07 2019-12-20 许继电源有限公司 Charging station and energy dispatching management method thereof
CN110601243A (en) * 2019-10-21 2019-12-20 合肥阳光新能源科技有限公司 Energy storage system and peak clipping, valley filling and demand management cooperative control method thereof
CN107910882B (en) * 2017-11-16 2020-01-03 广州供电局有限公司 Distributed energy storage operation mode optimization design method and system
CN111913110A (en) * 2019-05-10 2020-11-10 维谛技术有限公司 Commercial power battery configuration evaluation method and system
CN113158566A (en) * 2021-04-21 2021-07-23 内蒙古电力(集团)有限责任公司乌兰察布电业局 User ordered electricity utilization control method, system and medium based on demand side
CN113572182A (en) * 2021-07-06 2021-10-29 水发能源集团有限公司 Method for measuring and calculating capacity of storage battery pack of photovoltaic building energy storage system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105005872A (en) * 2015-08-06 2015-10-28 北京交通大学 Capacity configuration method for peak-load-shifting energy storage system
CN105846423A (en) * 2016-03-28 2016-08-10 华北电力大学 Method for photovoltaic microgrid energy storage multi-target capacity configuration by taking demand response into consideration

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105005872A (en) * 2015-08-06 2015-10-28 北京交通大学 Capacity configuration method for peak-load-shifting energy storage system
CN105846423A (en) * 2016-03-28 2016-08-10 华北电力大学 Method for photovoltaic microgrid energy storage multi-target capacity configuration by taking demand response into consideration

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106786700A (en) * 2017-01-17 2017-05-31 无锡协鑫分布式能源开发有限公司 User's sidelight stores up integral system off-grid operation capacity configuration software algorithm
CN107910882B (en) * 2017-11-16 2020-01-03 广州供电局有限公司 Distributed energy storage operation mode optimization design method and system
CN108233422B (en) * 2018-02-09 2021-07-02 大工(青岛)新能源材料技术研究院有限公司 Light storage micro-grid operation control method based on predictive control
CN108233422A (en) * 2018-02-09 2018-06-29 大工(青岛)新能源材料技术研究院有限公司 A kind of light storage micro-grid operational control method based on PREDICTIVE CONTROL
CN108767896A (en) * 2018-06-11 2018-11-06 中国科学院电工研究所 A kind of control method for coordinating of light storage charging system
CN111913110B (en) * 2019-05-10 2023-03-14 维谛技术有限公司 Commercial power battery configuration evaluation method and system
CN111913110A (en) * 2019-05-10 2020-11-10 维谛技术有限公司 Commercial power battery configuration evaluation method and system
CN110601334A (en) * 2019-08-07 2019-12-20 许继电源有限公司 Charging station and energy dispatching management method thereof
CN110601334B (en) * 2019-08-07 2021-11-05 许继电源有限公司 Charging station and energy dispatching management method thereof
CN110601243B (en) * 2019-10-21 2023-02-10 阳光新能源开发股份有限公司 Energy storage system and peak clipping, valley filling and demand management cooperative control method thereof
CN110601243A (en) * 2019-10-21 2019-12-20 合肥阳光新能源科技有限公司 Energy storage system and peak clipping, valley filling and demand management cooperative control method thereof
CN113158566A (en) * 2021-04-21 2021-07-23 内蒙古电力(集团)有限责任公司乌兰察布电业局 User ordered electricity utilization control method, system and medium based on demand side
CN113158566B (en) * 2021-04-21 2023-08-15 内蒙古电力(集团)有限责任公司乌兰察布供电分公司 User ordered power utilization control method, system and medium based on demand side
CN113572182A (en) * 2021-07-06 2021-10-29 水发能源集团有限公司 Method for measuring and calculating capacity of storage battery pack of photovoltaic building energy storage system

Similar Documents

Publication Publication Date Title
CN106849142A (en) User&#39;s sidelight stores up integral system demand charge capacity configuration software algorithm
Saboori et al. Maximizing DISCO profit in active distribution networks by optimal planning of energy storage systems and distributed generators
US9985438B2 (en) Optimization method for independent micro-grid system
CN103986190B (en) Based on the wind-solar-storage joint electricity generation system smooth control method of generated output curve
Rodrigues et al. Modelling and sizing of NaS (sodium sulfur) battery energy storage system for extending wind power performance in Crete Island
CN107681675A (en) Block chain electricity transaction peak-frequency regulation system based on distributed electric power storage facility
CN105205552B (en) A kind of independent new energy hybrid power system Method for optimized planning
CN106953315A (en) User side grid type light stores up integral system capacity optimization software algorithm
CN108767872B (en) Fuzzy control method applied to wind-solar hybrid energy storage micro-grid system
Paliwal et al. Optimal sizing and operation of battery storage for economic operation of hybrid power system using artificial bee colony algorithm
US20140015323A1 (en) Power Management System
CN109829834A (en) A kind of energy-storage system configuration method, device and storage medium
CN107769235A (en) A kind of microgrid energy management method based on hybrid energy-storing and electric automobile
CN103187733A (en) Megawatt liquid flow battery energy storage power station real-time power control method and system thereof
CN109861277A (en) A kind of configuration method and system of charging station photovoltaic and stored energy capacitance
CN106251005A (en) A kind of based on the hybrid energy-storing capacity configuration optimizing method improving particle cluster algorithm
Lam et al. Economics of residential energy arbitrage in california using a PV system with directly connected energy storage
CN107732937A (en) The peak load shifting method of the grid type microgrid of the electric automobile containing wind-light storage
JP2003158825A (en) Hybrid system constituted of power generating device using natural energy and secondary battery for storing power, and usage thereof
CN107846043A (en) A kind of microgrid energy management method for considering charging electric vehicle and influenceing
Zhu et al. Optimal design and management of a smart residential PV and energy storage system
Chen et al. Optimal energy management strategy for an islanded microgrid with hybrid energy storage
CN106953318A (en) A kind of micro-capacitance sensor optimal control method based on cost
Yadav et al. Grey wolf optimization based optimal isolated microgrid with battery and pumped hydro as double storage to limit excess energy
CN106786700A (en) User&#39;s sidelight stores up integral system off-grid operation capacity configuration software algorithm

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613

RJ01 Rejection of invention patent application after publication