CN106842008A - A kind of method of test transformer loaded switch - Google Patents

A kind of method of test transformer loaded switch Download PDF

Info

Publication number
CN106842008A
CN106842008A CN201710004716.2A CN201710004716A CN106842008A CN 106842008 A CN106842008 A CN 106842008A CN 201710004716 A CN201710004716 A CN 201710004716A CN 106842008 A CN106842008 A CN 106842008A
Authority
CN
China
Prior art keywords
loaded switch
test
resistance
instrument
tester
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710004716.2A
Other languages
Chinese (zh)
Other versions
CN106842008B (en
Inventor
黄宝新
陈建
孙锋
陈志国
陈青田
王函
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoding Tianwei Group Tebian Electric Co Ltd
Original Assignee
Baoding Tianwei Group Tebian Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoding Tianwei Group Tebian Electric Co Ltd filed Critical Baoding Tianwei Group Tebian Electric Co Ltd
Priority to CN201710004716.2A priority Critical patent/CN106842008B/en
Publication of CN106842008A publication Critical patent/CN106842008A/en
Application granted granted Critical
Publication of CN106842008B publication Critical patent/CN106842008B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/327Testing of circuit interrupters, switches or circuit-breakers
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R27/00Arrangements for measuring resistance, reactance, impedance, or electric characteristics derived therefrom
    • G01R27/02Measuring real or complex resistance, reactance, impedance, or other two-pole characteristics derived therefrom, e.g. time constant

Abstract

The invention discloses a kind of method of test transformer loaded switch, it is related to electric power repair technical field.Loaded switch tester and tested load switch of transformer are tested and are connected to form test loop, instrument for measuring DC resistance and loaded switch tester are in parallel, using external auxiliary DC source reduce interference fringe in test process come error to improve the acquisition precision of waveform.This method can make the collection effect of waveform more preferably, and the test of loaded switch is more accurate.

Description

A kind of method of test transformer loaded switch
Technical field
The present invention relates to transformer technology field, more particularly to a kind of method of test transformer loaded switch.
Background technology
Loaded switch is the important component of transformer, and safe operation of the load ratio bridging switch field test to transformer is played Vital effect.Exchange loaded switch test experiments are one during electric power has load high-voltage switch gear to test must do project, it Reliability directly determine that can transformer reliability service.Therefore when being installed, being overhauled, related experiment is carried out to it, Ensure that loaded switch being capable of long-term safety operation.The method less stable of existing test loaded switch, contact during switch motion Contact can produce interference, influence the accuracy of loaded switch transition waveform testing.
The content of the invention
The technical problem to be solved in the present invention is directed to above-mentioned the deficiencies in the prior art, there is provided a kind of test transformer has load The method of switch, the method stability is higher, and contact moment produces interference small during switch motion, can effectively improve load and open The accuracy of transition waveform testing is closed, to ensure the safe operation of loaded switch.
In order to solve the above technical problems, the technical solution used in the present invention is:
A kind of method of test transformer loaded switch, is connected by loaded switch tester and tested load switch of transformer are tested Connect composition test loop, it is characterised in that:Instrument for measuring DC resistance and the loaded switch tester is in parallel, using external auxiliary Help the error of interference fringe in DC source reduction test process to improve the acquisition precision of waveform, comprise the following steps that:
1)Oil sample index is checked, the entrance next step of passed examination;
2)Loaded switch D.C. resistance is detected with instrument for measuring DC resistance or loaded switch tester, loaded switch direct current Resistance detection is qualified must to carry out next step;
3)Test transition waveform:
(1)Instrument for measuring DC resistance is opened, mutually applies auxiliary DC source to transformer is tested by instrument for measuring DC resistance, and keep Electric current is constant;
(2)After electric current stabilization to be applied, loaded switch tester is opened, it is in parallel in the loop to apply loaded switch test electricity Source, and keep electric current constant;The sense of current that loaded switch tester is applied is consistent with instrument for measuring DC resistance direction;
(3)After belt current stabilization, loaded switch gear is reopened or changes, loaded switch tester gathers corresponding little bellow Shape;The waveform for collecting waveform for needed for test result.
Preferably, the loaded switch tester can realize transit time, transition waveform, the transition to load ratio bridging switch The measurement of resistance, three-phase synchronism parameter;The instrument for measuring DC resistance measurement output current adjustable and electric current of shelves is comprised at least:1A, The different measurement gears of 3A, 5A, 10A.
Preferably, the step 2)In loaded switch do D.C. resistance detection experiment, arcing contact and main contact need to be measured Between value, it is to avoid roundabout loop is there are between arcing contact and main contact.
Preferably, the step(1)The size of current that middle instrument for measuring DC resistance is applied is 5A;The step(2)In The size of current that loaded switch tester is applied is 1A.
Preferably, the step(1)Before, little bellow is first estimated according to loaded switch type and loaded switch switching time The form of shape;In the step(3)Afterwards, compared with the transition waveform for collecting according to the transition waveform estimated, to there is load The situation of switch testing is analyzed.
Preferably, the switching time of described loaded switch according to different types depending on, specifically include:S types be 35~ 50MS, M type are 35~50MS, and V-type is 45~65MS.
It is using the beneficial effect produced by above-mentioned technical proposal:This method stability is higher, contact during switch motion Contact produces interference small, the accuracy of loaded switch transition waveform testing can be effectively improved, to ensure the peace of loaded switch Row for the national games.The present invention can effectively before detection means system testing precision, reduce and the possibility of error occur.That adds is auxiliary Help DC source to be avoided that and trigger burr phenomena in waveform, improve waveform acquisition effect.
Brief description of the drawings
Fig. 1 is device connection diagram of the invention.
Specific embodiment
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description.
As shown in figure 1, be one embodiment of the present of invention,
A kind of method of test transformer loaded switch, is connected by loaded switch tester and tested load switch of transformer are tested Connect composition test loop, it is characterised in that:Instrument for measuring DC resistance and the loaded switch tester is in parallel, using external auxiliary Help the error of interference fringe in DC source reduction test process to improve the acquisition precision of waveform, comprise the following steps that:
1)Oil sample index is checked, the entrance next step of passed examination;
2)Loaded switch D.C. resistance is detected with instrument for measuring DC resistance or loaded switch tester, loaded switch direct current Resistance detection is qualified must to carry out next step;
3)Test transition waveform:
(1)Instrument for measuring DC resistance is opened, mutually applies auxiliary DC source to transformer is tested by instrument for measuring DC resistance, and keep Electric current is constant;
(2)After electric current stabilization to be applied, loaded switch tester is opened, it is in parallel in the loop to apply loaded switch test electricity Source, and keep electric current constant;The sense of current that loaded switch tester is applied is consistent with instrument for measuring DC resistance direction;
(3)After belt current stabilization, loaded switch gear is reopened or changes, loaded switch tester gathers corresponding little bellow Shape;The waveform for collecting waveform for needed for test result.
The loaded switch tester can realize transit time, transition waveform, transition resistance, three to load ratio bridging switch The measurement of phase synchronism parameter;The instrument for measuring DC resistance measurement output current adjustable and electric current of shelves is comprised at least:1A,3A,5A, The different measurement gears of 10A.
The step 2)In loaded switch do D.C. resistance detection experiment, need to measure between arcing contact and main contact Value, it is to avoid roundabout loop is there are between arcing contact and main contact.
The step(1)The size of current that middle instrument for measuring DC resistance is applied is 5A;The step(2)Middle loaded switch The size of current that tester is applied is 1A.
The step(1)Before, the shape of transition waveform is first estimated according to loaded switch type and loaded switch switching time State;In the step(3)Afterwards, compared with the transition waveform for collecting according to the transition waveform estimated, loaded switch is surveyed The situation of examination is analyzed.
Depending on the switching time of described loaded switch is according to different types, specifically include:S types are 35~50MS, M types It is 35~50MS, V-type is 45~65MS.
The step 2)During middle measurement transition resistance, should avoid whether having roundabout loop between arcing contact and main contact.Such as M Type loaded switch should measure side one group transition resistance of the contact not on position is closed when contactor is in odd or even number, keep away Exempt from roundabout loop and cause measurement error.
After adopting the above technical scheme, the equipment acquisition precision during the test process of load switch of transformer can be improved, ripple More preferably, the test of loaded switch is more accurate for the collection effect of shape.
Presently preferred embodiments of the present invention is the foregoing is only, is not intended to limit the invention, it is all in essence of the invention Any modification, equivalent and improvement made within god and principle etc., should be included within the scope of the present invention.

Claims (6)

1. a kind of method of test transformer loaded switch, phase is tested by loaded switch tester with tested load switch of transformer Connect and compose test loop, it is characterised in that:Instrument for measuring DC resistance and the loaded switch tester is in parallel, using external Aid in the error of interference fringe in DC source reduction test process to improve the acquisition precision of waveform, comprise the following steps that:
1)Oil sample index is checked, passed examination carries out next step;
2)Loaded switch D.C. resistance is detected with instrument for measuring DC resistance or loaded switch tester, loaded switch direct current Resistance detection is qualified must to carry out next step;
3)Test transition waveform:
(1)Instrument for measuring DC resistance is opened, mutually applies auxiliary DC source to transformer is tested by instrument for measuring DC resistance, and keep Electric current is constant;
(2)After electric current stabilization to be applied, loaded switch tester is opened, it is in parallel in the loop to apply loaded switch test electricity Source, and keep electric current constant;The sense of current that loaded switch tester is applied is consistent with instrument for measuring DC resistance direction;
(3)After belt current stabilization, loaded switch gear is reopened or changes, loaded switch tester gathers corresponding little bellow Shape;The waveform for collecting waveform for needed for test result.
2. a kind of method of test transformer loaded switch according to claim 1, it is characterised in that the loaded switch Tester can realize transit time, transition waveform, transition resistance, the measurement of three-phase synchronism parameter to load ratio bridging switch; The instrument for measuring DC resistance measurement output current adjustable and electric current of shelves is comprised at least:The different measurement gears of 1A, 3A, 5A, 10A.
3. a kind of method of test transformer loaded switch according to claim 1, it is characterised in that the step 2)In Loaded switch do D.C. resistance detection experiment, the value between arcing contact and main contact need to be measured, it is to avoid arcing contact and main contact Between there are roundabout loop.
4. a kind of method of test transformer loaded switch according to claim 1, it is characterised in that the step(1)In The size of current that instrument for measuring DC resistance is applied is 5A;The step(2)The electric current that middle loaded switch tester is applied is big Small is 1A.
5. the method for a kind of test transformer loaded switch according to claim 1, it is characterised in that in the step(1) Before, the form of transition waveform is first estimated according to loaded switch type and loaded switch switching time;In the step(3)It Afterwards, compared with the transition waveform for collecting according to the transition waveform estimated, the situation to loaded switch test is analyzed.
6. the method for a kind of test transformer loaded switch according to claim 5, it is characterised in that the described load that has is opened Depending on the switching time of pass is according to different types, specifically include:S types be 35~50MS, M types be 35~50MS, V-type be 45~ 65MS。
CN201710004716.2A 2017-01-04 2017-01-04 Method for testing on-load switch of transformer Active CN106842008B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710004716.2A CN106842008B (en) 2017-01-04 2017-01-04 Method for testing on-load switch of transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710004716.2A CN106842008B (en) 2017-01-04 2017-01-04 Method for testing on-load switch of transformer

Publications (2)

Publication Number Publication Date
CN106842008A true CN106842008A (en) 2017-06-13
CN106842008B CN106842008B (en) 2020-07-03

Family

ID=59118545

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710004716.2A Active CN106842008B (en) 2017-01-04 2017-01-04 Method for testing on-load switch of transformer

Country Status (1)

Country Link
CN (1) CN106842008B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109061459A (en) * 2018-08-30 2018-12-21 国网北京市电力公司 The fault determination method and device of on-load voltage regulating switch, storage medium, processor
CN110763992A (en) * 2019-11-28 2020-02-07 国网河北省电力有限公司电力科学研究院 AC/DC comprehensive test method for on-load tap-changer of large transformer
CN113030790A (en) * 2021-02-04 2021-06-25 华能(天津)煤气化发电有限公司 Method for checking whether contact of tap changer of transformer is good or not

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201935973U (en) * 2010-12-31 2011-08-17 上海市电力公司 Integrative test device of electric test of transformer
CN102707181A (en) * 2012-06-29 2012-10-03 广州供电局有限公司 Multi-parameter electrical test control device of power transformer
CN103063924A (en) * 2012-12-27 2013-04-24 江苏省电力公司电力科学研究院 Vehicle-mounted integral three-phase direct-current resistance and transformation ratio and load comprehensive testing device and method
CN103293413A (en) * 2013-05-19 2013-09-11 国家电网公司 Special high-voltage testing device for transformers
CN103698621A (en) * 2013-09-05 2014-04-02 国家电网公司 Vehicle-mounted transformer comprehensive test system
US20150035538A1 (en) * 2012-04-27 2015-02-05 Alfred Bieringer Method for monitoring an on-load tap changer
CN205594052U (en) * 2016-05-10 2016-09-21 国网江苏省电力公司电力科学研究院 Vehicular body jie decreases and direct current resistance transformation ratio has measurement of carrying an automatic switching device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201935973U (en) * 2010-12-31 2011-08-17 上海市电力公司 Integrative test device of electric test of transformer
US20150035538A1 (en) * 2012-04-27 2015-02-05 Alfred Bieringer Method for monitoring an on-load tap changer
CN102707181A (en) * 2012-06-29 2012-10-03 广州供电局有限公司 Multi-parameter electrical test control device of power transformer
CN103063924A (en) * 2012-12-27 2013-04-24 江苏省电力公司电力科学研究院 Vehicle-mounted integral three-phase direct-current resistance and transformation ratio and load comprehensive testing device and method
CN103293413A (en) * 2013-05-19 2013-09-11 国家电网公司 Special high-voltage testing device for transformers
CN103698621A (en) * 2013-09-05 2014-04-02 国家电网公司 Vehicle-mounted transformer comprehensive test system
CN205594052U (en) * 2016-05-10 2016-09-21 国网江苏省电力公司电力科学研究院 Vehicular body jie decreases and direct current resistance transformation ratio has measurement of carrying an automatic switching device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109061459A (en) * 2018-08-30 2018-12-21 国网北京市电力公司 The fault determination method and device of on-load voltage regulating switch, storage medium, processor
CN110763992A (en) * 2019-11-28 2020-02-07 国网河北省电力有限公司电力科学研究院 AC/DC comprehensive test method for on-load tap-changer of large transformer
CN113030790A (en) * 2021-02-04 2021-06-25 华能(天津)煤气化发电有限公司 Method for checking whether contact of tap changer of transformer is good or not

Also Published As

Publication number Publication date
CN106842008B (en) 2020-07-03

Similar Documents

Publication Publication Date Title
CN106842008A (en) A kind of method of test transformer loaded switch
CN104898052B (en) The check system and method for switch mechanical characteristic testing device based on IEC61850
WO2015117466A1 (en) Anti-interference integrated testing device for ultra-high voltage line parameters
Cataliotti et al. Current transformers effects on the measurement of harmonic active power in LV and MV networks
CN102435941A (en) Method for simulating very fast transient over-voltage during opening/closing process of isolating switch
JP2014521980A (en) Adaptive voltage divider with corrected frequency characteristics for measuring high voltages
CN106526317B (en) The phasor measurement precision assessment method and assessment device of synchronous phasor measurement unit
CN103135087A (en) Electronic transformer integral detecting and evaluating system
Cataliotti et al. Metrological performances of voltage and current instrument transformers in harmonics measurements
CN205176248U (en) Intelligent substation electronic transformer measures accuracy emulation test and compares system
Arri et al. Diagnosis of the state of power transformer windings by on-line measurement of stray reactance
Novotny et al. Frequency response of revenue meters in measured active energy
CN108761223B (en) System and method for testing output synchronism of traveling wave protection testing device
CN212872872U (en) Clamp-on leakage ammeter calibrating device
CN103823198A (en) Relay protection testing device time measurement accuracy degree detection system and method
Silva et al. Noninvasive ageing assessment by means of polarization and depolarization currents analysis and its correlation with moisture content for power transformer life management
CN103176048B (en) A kind of method of quick measuring transformer delta connection mode winding D.C. resistance
CN202563014U (en) Transformer loss measurement control console
CN103712537B (en) Measurement apparatus for high-voltage switch cabinet mechanical stroke
CN202939297U (en) Verification system for ground resistance tester
Simon et al. Experimental measurements of frequency-dependent active component impedances for harmonic stability assessment
CN103698728A (en) Tester for testing measurement accuracy of PMU (Pressure Measuring Unit) and testing method thereof
RU2175138C1 (en) Method and device for measuring power circuit insulation resistance in live electrical equipment of vehicles
CN203037779U (en) Test platform of transformer station capacitive device on-line monitoring system
CN112964950A (en) Method for testing power frequency electromagnetic interference resistance of capacitive equipment online monitoring device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant