CN106836181A - A kind of filling out to go along with sb. to guard him and synchronous carry out construction method for dredge fill - Google Patents
A kind of filling out to go along with sb. to guard him and synchronous carry out construction method for dredge fill Download PDFInfo
- Publication number
- CN106836181A CN106836181A CN201710021684.7A CN201710021684A CN106836181A CN 106836181 A CN106836181 A CN 106836181A CN 201710021684 A CN201710021684 A CN 201710021684A CN 106836181 A CN106836181 A CN 106836181A
- Authority
- CN
- China
- Prior art keywords
- cofferdam
- construction
- beach
- hydraulic reclamation
- guard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/02—Restraining of open water
- E02D19/04—Restraining of open water by coffer-dams, e.g. made of sheet piles
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Revetment (AREA)
Abstract
Description
Great soil group | The ratio of slope |
Mud, silt | 1:100~1:300 |
Fine sand | 1:50~1:100 |
Middle sand | 1:25~1:50 |
Coarse sand | 1:10~1:25 |
Gravel | 1:5-1:10 |
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710021684.7A CN106836181B (en) | 2017-01-12 | 2017-01-12 | Filling and enclosing construction method for hydraulic filling construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710021684.7A CN106836181B (en) | 2017-01-12 | 2017-01-12 | Filling and enclosing construction method for hydraulic filling construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106836181A true CN106836181A (en) | 2017-06-13 |
CN106836181B CN106836181B (en) | 2020-02-18 |
Family
ID=59124922
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710021684.7A Active CN106836181B (en) | 2017-01-12 | 2017-01-12 | Filling and enclosing construction method for hydraulic filling construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106836181B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101377077A (en) * | 2007-08-29 | 2009-03-04 | 林佳栋 | Blowing, filling, stacking , loading, precipitating, pre-pressing and strong tamping combined soft soil foundation treating method |
CN102493396A (en) * | 2011-11-22 | 2012-06-13 | 中交一航局第四工程有限公司 | Construction method of backfill in layers for sea reclamation |
CN103821105A (en) * | 2014-03-03 | 2014-05-28 | 中交上海航道勘察设计研究院有限公司 | Method for building dike by filling geotextile bag with silt |
CN106120825A (en) * | 2016-08-22 | 2016-11-16 | 中交天航港湾建设工程有限公司 | Small-sized cutter suction dredger is utilized to set construction system and the method for filling sack cofferdam |
CN106223308A (en) * | 2016-08-26 | 2016-12-14 | 上海建工集团股份有限公司 | A kind of vacuum combined water that covers loads pre-pressing system and construction method thereof |
CN106320261A (en) * | 2016-08-22 | 2017-01-11 | 中交天航港湾建设工程有限公司 | Ultra-long harbor basin slope excavation construction method |
-
2017
- 2017-01-12 CN CN201710021684.7A patent/CN106836181B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101377077A (en) * | 2007-08-29 | 2009-03-04 | 林佳栋 | Blowing, filling, stacking , loading, precipitating, pre-pressing and strong tamping combined soft soil foundation treating method |
CN102493396A (en) * | 2011-11-22 | 2012-06-13 | 中交一航局第四工程有限公司 | Construction method of backfill in layers for sea reclamation |
CN103821105A (en) * | 2014-03-03 | 2014-05-28 | 中交上海航道勘察设计研究院有限公司 | Method for building dike by filling geotextile bag with silt |
CN106120825A (en) * | 2016-08-22 | 2016-11-16 | 中交天航港湾建设工程有限公司 | Small-sized cutter suction dredger is utilized to set construction system and the method for filling sack cofferdam |
CN106320261A (en) * | 2016-08-22 | 2017-01-11 | 中交天航港湾建设工程有限公司 | Ultra-long harbor basin slope excavation construction method |
CN106223308A (en) * | 2016-08-26 | 2016-12-14 | 上海建工集团股份有限公司 | A kind of vacuum combined water that covers loads pre-pressing system and construction method thereof |
Non-Patent Citations (2)
Title |
---|
吴子华等: "赣江生米九龙湖段河道疏浚及滩涂填筑工程施工", 《广西水利水电》 * |
杨光煦著: "《岩土工程关键技术研究与实践》", 31 August 2016, 中国水利水电出版社 * |
Also Published As
Publication number | Publication date |
---|---|
CN106836181B (en) | 2020-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104846787B (en) | Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger | |
CN205077453U (en) | Dam structure that panel rock -fill dam and upstream cofferdam combine | |
CN106801424A (en) | A kind of cofferdam construction method | |
WO2020248596A1 (en) | Protection structure for preventing ground heave caused by tunnel grouting reinforcement and grouting method | |
CN101422094A (en) | Thick-bed mining subsidence-land dynamic pre-reclamation method at plane mining-area | |
CN109736338A (en) | A kind of hydraulic engineering foundation pit pipe well combination light well point Yield rainfall relation method | |
CN102926376A (en) | Treatment method for soft soil foundation in coastal reclamation region | |
CN101851929B (en) | Multi-stage light well point dewatering construction process for Yellow River flood plain bearing platform construction | |
CN107761670A (en) | Stockyard dischargeable capacity method for optimally controlling based on the control of dredged mud original state | |
CN110130376A (en) | A kind of method of tailing back production ground water drainage | |
CN105951667B (en) | Using mud filling tube bag in enclosing tideland for cultivation region pre- profit retention river structure | |
CN104929141B (en) | Town road passes through the construction method of river embankment or irrigation canals and ditches | |
CN106761914B (en) | A kind of routed water water damage prevention and controls of shallow buried coal seam mine raceway groove flood | |
CN109469066A (en) | Earthmoving machinery combines excavation construction method and system with hydraulic tunneling boring solid | |
CN106836181A (en) | A kind of filling out to go along with sb. to guard him and synchronous carry out construction method for dredge fill | |
CN104358231B (en) | A kind of Underwater Slope mold-bagged concrete reinforced construction method | |
CN110185051A (en) | Deep narrow excavation water discharge method | |
CN110106886A (en) | A kind of deep pit digging method of underground high water level | |
CN102995646B (en) | Net cage protection pad type revetment structure and construction method thereof | |
CN107642065A (en) | A kind of dredging and reclamation fills sand pocket construction technology | |
CN204899930U (en) | Secretly dig leading dry out well in subway hole | |
CN208563278U (en) | The rainy season construction structure of major diameter vertical shaft in a kind of soft soil layer | |
CN206693206U (en) | A kind of Tailings Dam bottom storehouse row oozes system | |
CN107130644A (en) | Coffering composite geo-membrane and gravelly clay combination against seepage construction method | |
CN210068175U (en) | A protective structure for preventing tunnel slip casting reinforcement from arousing earth's surface uplift |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20211011 Address after: 518000 rooms 2106, 2107, 2108, 2109 and 2110, XinZhuYuan, Nonglin Road, Futian District, Shenzhen, Guangdong Province Patentee after: CCCC TDC SOUTHERN COMMUNICATIONS CONSTRUCTION Co.,Ltd. Patentee after: CCCC TIANJIN DREDGING Co.,Ltd. Patentee after: CCCC-TDC ENVIRONMENTAL ENGINEERING Co.,Ltd. Patentee after: CCCC-TDC BINHAI ENVIRONMENTAL CHANNEL DREDGING Co.,Ltd. Patentee after: CCCC TIANJIN DREDGING HARBOUR CONSTRUCTION ENGINEERING Co.,Ltd. Patentee after: CCCC TIANJIN PORT & WATERWAY PROSPECTION & DESIGN RESEARCH INSTITUTE Co.,Ltd. Patentee after: NATIONAL ENGINEERING RESEARCH CENTER OF DREDGING TECHNOLOGY AND EQUIPMENT Address before: 518000 rooms 2106, 2107, 2108, 2109 and 2110, XinZhuYuan, Nonglin Road, Futian District, Shenzhen, Guangdong Province Patentee before: CCCC TDC SOUTHERN COMMUNICATIONS CONSTRUCTION Co.,Ltd. Patentee before: CCCC TIANJIN DREDGING Co.,Ltd. Patentee before: CCCC-TDC ENVIRONMENTAL ENGINEERING Co.,Ltd. Patentee before: CCCC-TDC BINHAI ENVIRONMENTAL CHANNEL DREDGING Co.,Ltd. Patentee before: CCCC TIANJIN DREDGING HARBOUR CONSTRUCTION ENGINEERING Co.,Ltd. Patentee before: CCCC TIANJIN PORT & WATERWAY PROSPECTION & DESIGN RESEARCH INSTITUTE Co.,Ltd. |