CN106780041A - Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm - Google Patents

Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm Download PDF

Info

Publication number
CN106780041A
CN106780041A CN201710072622.9A CN201710072622A CN106780041A CN 106780041 A CN106780041 A CN 106780041A CN 201710072622 A CN201710072622 A CN 201710072622A CN 106780041 A CN106780041 A CN 106780041A
Authority
CN
China
Prior art keywords
project
transmitting
converting electricity
cost
investment forecasting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710072622.9A
Other languages
Chinese (zh)
Inventor
李涛
朱晓虎
刘士李
李建青
刘丽
殷敏
陈付雷
沈思
方天睿
王道静
姚兰波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd
Original Assignee
Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd filed Critical Economic and Technological Research Institute of State Grid Anhui Electric Power Co Ltd
Priority to CN201710072622.9A priority Critical patent/CN106780041A/en
Publication of CN106780041A publication Critical patent/CN106780041A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q40/00Finance; Insurance; Tax strategies; Processing of corporate or income taxes
    • G06Q40/06Asset management; Financial planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm, including the analysis of project of transmitting and converting electricity cost investment forecasting key index;Project of transmitting and converting electricity construction unit is analyzed;Project of transmitting and converting electricity investment forecasting system anlysis.Application of the invention can enable investor that the situation of new construction cost is accurately held in first stage of construction, censorship personnel can carry out rational, quick examination to specific preliminary project cost condition, the subjective factor influence during Cost Management is reduced, the target that investment decision provides foundation is reached for.From the decision phase of project of transmitting and converting electricity, it is determined that the key index of influence project of transmitting and converting electricity investment forecasting, excavate history engineering data, determine the crucial construction unit of project of transmitting and converting electricity, project of transmitting and converting electricity investment forecasting system is built using particle cluster algorithm, so that for power network authorities at different levels and relevant unit control project of transmitting and converting electricity cost, construction investment of making rational planning for provide theoretical foundation.

Description

Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm
Technical field
The present invention relates to a kind of power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm, belong to power engineering skill Art field.
Background technology
Power industry is a capital-intensive industry, and power engineering construction is also a system engineering for complexity how On the premise of completion time of project and construction quality is ensured, rational control engineering cost, be in electric power infrastructure one it is eternal Theme.In the last few years, Cost for Electric Power Engineering goes up very fast, and capital collection difficulty is very big, Engineering Cost Management Levels into It is the fast-developing key of influence power construction.Power engineering design is universal design, and the performance space of design is smaller, deposits In some problems, for example:Construction criteria, design style disunity;Type of equipment is more, standby redundancy poor universality;Design is commented Examine, reply dispute is more, time-consuming;Build high with operating cost etc., the thing followed is the numerous difficulties in Engineering Cost Management.
At present, Cost for Electric Power Engineering method is mainly based upon the construction costs method of quota of budgetary estimate, is covered by according to quota For amount of calculation, budgetary estimate accurately can be carried out to construction investment.But the use of method is excessively stiff, market warp is not met The demand of Ji.For especially for a new construction, on the premise of non-comprehensive collection engineering information amount, it is impossible to which cost is given Give and fast and effectively instructing, usually influenced whether the enthusiasm and creativeness of investor and manager.Therefore, set up a kind of The method of science, rational project of transmitting and converting electricity investment forecasting is very necessary.
The content of the invention
The purpose of the present invention is directed to a kind of not enough power network project of transmitting and converting electricity based on particle cluster algorithm of offer of prior art Investment forecasting method.
The technology path that the present invention takes is:By Analysis on Data Mining electricity grid substation engineering and line project Historical data, determines the key index of project of transmitting and converting electricity investment forecasting, determines that the key of project of transmitting and converting electricity is single using statistical check Position engineering, is finally based on particle cluster algorithm and builds a power network project of transmitting and converting electricity cost investment forecasting model, and by actual defeated The validity of investment forecasting model is verified in the analysis of cases of power transformation engineering.
Forecasting Methodology of the present invention includes:
(1)Project of transmitting and converting electricity cost investment forecasting key index is analyzed
Labor project of transmitting and converting electricity development, project of transmitting and converting electricity cost investment forecasting principle, by the comparative analysis of document, Excavate project of transmitting and converting electricity cost investment forecasting in terms of advantage and deficiency, summarize project of transmitting and converting electricity cost investment forecasting influence because Element, including external environment condition, the market factor and construction scale of projects;
For more scientific discussion project of transmitting and converting electricity investment forecasting key index applicability in the present invention, the present invention is using master The mathematical statistics instrument such as constituent analysis, correlation analysis and regression analysis, analyzes the historical data of power network project of transmitting and converting electricity, including become Electrical engineering, overhead transmission line engineering, cable run engineering, explore influence journey of the engineering technology index to project of transmitting and converting electricity investment forecasting Degree, sets up the key index collection of project of transmitting and converting electricity investment forecasting;
On the basis of data statistic analysis, it is determined that it is suitable for the key index of project of transmitting and converting electricity investment forecasting, to power transmission and transformation work The importance degree of the key index of journey investment forecasting is scored, and project of transmitting and converting electricity investment forecasting is determined using analytic hierarchy process (AHP) The weight of key index, and build project of transmitting and converting electricity investment forecasting index system.
(2)Project of transmitting and converting electricity construction unit is analyzed
There is substantial amounts of engineering surplus phenomenon in project of transmitting and converting electricity, in order to deeper into analysis be specifically which expense occurs finishing It is remaining, project of transmitting and converting electricity budgetary estimate and Engineering Settlement are analyzed respectively using mathematical statistics software, find Budgetary Estimates and work The construction unit that journey clearing conspicuousness is differed;In order to analyze the crucial construction unit of project of transmitting and converting electricity, examined using paired sample T Test and analysis is compared to the different construction unit budgetary estimates of construction cost, mounting cost and cost of equipment and clearing average;Pairing Sample T inspections are the differences that value is observed by obtaining each pair, if sample average differential nearly zero, paired sample does not exist significance difference It is different;Conversely, if sample average is significantly not zero, there is significant difference in paired sample;In the application, if paired sample T test T values more than 2, sig values less than 0.05, then it is assumed that there is significant difference in the average of paired sample.By the result of statistical analysis, enter One step combines proportion of the different construction units in whole engineering cost, determines the crucial list of the engineering of substation project and line project Position engineering.
(3)Project of transmitting and converting electricity investment forecasting system anlysis
The crucial construction unit of importance and project of transmitting and converting electricity according to project of transmitting and converting electricity investment forecasting key index, the present invention Project of transmitting and converting electricity investment forecasting model is built based on particle cluster algorithm, using the historical data of project of transmitting and converting electricity, by model Optimization is calculated, to reach the purpose of the precision for improving project of transmitting and converting electricity investment estimation;According to the research of Kennedy, population is calculated Method has and is different from the characteristic of other evolution algorithms, such as orthomutation, quantization show and operate, locally optimal solution and the overall situation Optimal solution, to improve the efficiency of decision-making of objective optimization;
Project of transmitting and converting electricity investment forecasting model based on particle cluster algorithm, a set of Pareto optimal solutions are drawn by aid decision making person; First, first object function is that project of transmitting and converting electricity cost is minimized, including cost of construction, installation fee and installation cost;Second, entirely comment Estimate model need meet two constraintss include:(1)The requirement of project of transmitting and converting electricity cost no more than Quota design,(2)Often Individual key index should control to change interval rational;Whole model needs to be calculated by MATLAB;In calculating process, grain The thought and step of swarm optimization include new after initialization particle-renewals particle rapidity and the renewal of each particle of position-calculating Fitness value-determination individuality optimal value and global optimum;It is final realize the control of power network project of transmitting and converting electricity surplus rate 10% with Interior target.
Beneficial effects of the present invention:It is newly-built that application of the invention can enable investor accurately be held in first stage of construction The situation of construction costs, censorship personnel can carry out rational, quick to specific preliminary project cost condition Examine, reduce the subjective factor influence during Cost Management, be reached for the target that investment decision provides foundation.From power transmission and transformation work The decision phase of journey sets out, it is determined that the key index of influence project of transmitting and converting electricity investment forecasting, excavates history engineering data, determines defeated The crucial construction unit of power transformation engineering, project of transmitting and converting electricity investment forecasting system is built using particle cluster algorithm, so that for power network is each Level authorities and relevant unit control project of transmitting and converting electricity cost, construction investment of making rational planning for provide theoretical foundation.
Specific embodiment
Forecasting Methodology of the present invention includes:
(1)Project of transmitting and converting electricity cost investment forecasting key index is analyzed
Labor project of transmitting and converting electricity development, project of transmitting and converting electricity cost investment forecasting principle, by the comparative analysis of document, Excavate project of transmitting and converting electricity cost investment forecasting in terms of advantage and deficiency, summarize project of transmitting and converting electricity cost investment forecasting influence because Element, including external environment condition, the market factor and construction scale of projects;
For more scientific discussion project of transmitting and converting electricity investment forecasting key index applicability in the present invention, the present invention is using master The mathematical statistics instrument such as constituent analysis, correlation analysis and regression analysis, analyzes the historical data of power network project of transmitting and converting electricity, including become Electrical engineering, overhead transmission line engineering, cable run engineering, explore influence journey of the engineering technology index to project of transmitting and converting electricity investment forecasting Degree, sets up the key index collection of project of transmitting and converting electricity investment forecasting;
On the basis of data statistic analysis, it is determined that it is suitable for the key index of project of transmitting and converting electricity investment forecasting, to power transmission and transformation work The importance degree of the key index of journey investment forecasting is scored, and project of transmitting and converting electricity investment forecasting is determined using analytic hierarchy process (AHP) The weight of key index, and build project of transmitting and converting electricity investment forecasting index system.
(2)Project of transmitting and converting electricity construction unit is analyzed
There is substantial amounts of engineering surplus phenomenon in project of transmitting and converting electricity, in order to deeper into analysis be specifically which expense occurs finishing It is remaining, project of transmitting and converting electricity budgetary estimate and Engineering Settlement are analyzed respectively using mathematical statistics software, find Budgetary Estimates and work The construction unit that journey clearing conspicuousness is differed;In order to analyze the crucial construction unit of project of transmitting and converting electricity, examined using paired sample T Test and analysis is compared to the different construction unit budgetary estimates of construction cost, mounting cost and cost of equipment and clearing average;Pairing Sample T inspections are the differences that value is observed by obtaining each pair, if sample average differential nearly zero, paired sample does not exist significance difference It is different;Conversely, if sample average is significantly not zero, there is significant difference in paired sample;In the application, if paired sample T test T values more than 2, sig values less than 0.05, then it is assumed that there is significant difference in the average of paired sample.By the result of statistical analysis, enter One step combines proportion of the different construction units in whole engineering cost, determines the crucial list of the engineering of substation project and line project Position engineering.
(3)Project of transmitting and converting electricity investment forecasting system anlysis
The crucial construction unit of importance and project of transmitting and converting electricity according to project of transmitting and converting electricity investment forecasting key index, the present invention Project of transmitting and converting electricity investment forecasting model is built based on particle cluster algorithm, using the historical data of project of transmitting and converting electricity, by model Optimization is calculated, to reach the purpose of the precision for improving project of transmitting and converting electricity investment estimation;According to the research of Kennedy, population is calculated Method has and is different from the characteristic of other evolution algorithms, such as orthomutation, quantization show and operate, locally optimal solution and the overall situation Optimal solution, to improve the efficiency of decision-making of objective optimization;
Project of transmitting and converting electricity investment forecasting model based on particle cluster algorithm, a set of Pareto optimal solutions are drawn by aid decision making person; First, first object function is that project of transmitting and converting electricity cost is minimized, including cost of construction, installation fee and installation cost;Second, entirely comment Estimate model need meet two constraintss include:(1)The requirement of project of transmitting and converting electricity cost no more than Quota design,(2)Often Individual key index should control to change interval rational;Whole model needs to be calculated by MATLAB;In calculating process, grain The thought and step of swarm optimization include new after initialization particle-renewals particle rapidity and the renewal of each particle of position-calculating Fitness value-determination individuality optimal value and global optimum;It is final realize the control of power network project of transmitting and converting electricity surplus rate 10% with Interior target.

Claims (1)

1. the power network project of transmitting and converting electricity investment forecasting method of particle cluster algorithm is based on, it is characterised in that:The Forecasting Methodology bag Include:
(1)Project of transmitting and converting electricity cost investment forecasting key index is analyzed
Labor project of transmitting and converting electricity development, project of transmitting and converting electricity cost investment forecasting principle, by the comparative analysis of document, Excavate project of transmitting and converting electricity cost investment forecasting in terms of advantage and deficiency, summarize project of transmitting and converting electricity cost investment forecasting influence because Element, including external environment condition, the market factor and construction scale of projects;
For more scientific discussion project of transmitting and converting electricity investment forecasting key index applicability in the present invention, the present invention is using master The mathematical statistics instrument such as constituent analysis, correlation analysis and regression analysis, analyzes the historical data of power network project of transmitting and converting electricity, including become Electrical engineering, overhead transmission line engineering, cable run engineering, explore influence journey of the engineering technology index to project of transmitting and converting electricity investment forecasting Degree, sets up the key index collection of project of transmitting and converting electricity investment forecasting;
On the basis of data statistic analysis, it is determined that it is suitable for the key index of project of transmitting and converting electricity investment forecasting, to power transmission and transformation work The importance degree of the key index of journey investment forecasting is scored, and project of transmitting and converting electricity investment forecasting is determined using analytic hierarchy process (AHP) The weight of key index, and build project of transmitting and converting electricity investment forecasting index system;
(2)Project of transmitting and converting electricity construction unit is analyzed
There is substantial amounts of engineering surplus phenomenon in project of transmitting and converting electricity, in order to deeper into analysis be specifically which expense occurs finishing It is remaining, project of transmitting and converting electricity budgetary estimate and Engineering Settlement are analyzed respectively using mathematical statistics software, find Budgetary Estimates and work The construction unit that journey clearing conspicuousness is differed;In order to analyze the crucial construction unit of project of transmitting and converting electricity, examined using paired sample T Test and analysis is compared to the different construction unit budgetary estimates of construction cost, mounting cost and cost of equipment and clearing average;Pairing Sample T inspections are the differences that value is observed by obtaining each pair, if sample average differential nearly zero, paired sample does not exist significance difference It is different;Conversely, if sample average is significantly not zero, there is significant difference in paired sample;In the application, if paired sample T test T values more than 2, sig values less than 0.05, then it is assumed that there is significant difference in the average of paired sample;By the result of statistical analysis, enter One step combines proportion of the different construction units in whole engineering cost, determines the crucial list of the engineering of substation project and line project Position engineering;
(3)Project of transmitting and converting electricity investment forecasting system anlysis
The crucial construction unit of importance and project of transmitting and converting electricity according to project of transmitting and converting electricity investment forecasting key index, the present invention Project of transmitting and converting electricity investment forecasting model is built based on particle cluster algorithm, using the historical data of project of transmitting and converting electricity, by model Optimization is calculated, to reach the purpose of the precision for improving project of transmitting and converting electricity investment estimation;According to the research of Kennedy, population is calculated Method has and is different from the characteristic of other evolution algorithms, such as orthomutation, quantization show and operate, locally optimal solution and the overall situation Optimal solution, to improve the efficiency of decision-making of objective optimization;
Project of transmitting and converting electricity investment forecasting model based on particle cluster algorithm, a set of Pareto optimal solutions are drawn by aid decision making person; First, first object function is that project of transmitting and converting electricity cost is minimized, including cost of construction, installation fee and installation cost;Second, entirely comment Estimate model need meet two constraintss include:(1)The requirement of project of transmitting and converting electricity cost no more than Quota design,(2)Often Individual key index should control to change interval rational;Whole model needs to be calculated by MATLAB;In calculating process, grain The thought and step of swarm optimization include new after initialization particle-renewals particle rapidity and the renewal of each particle of position-calculating Fitness value-determination individuality optimal value and global optimum;It is final realize the control of power network project of transmitting and converting electricity surplus rate 10% with Interior target.
CN201710072622.9A 2017-02-10 2017-02-10 Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm Pending CN106780041A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710072622.9A CN106780041A (en) 2017-02-10 2017-02-10 Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710072622.9A CN106780041A (en) 2017-02-10 2017-02-10 Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm

Publications (1)

Publication Number Publication Date
CN106780041A true CN106780041A (en) 2017-05-31

Family

ID=58956021

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710072622.9A Pending CN106780041A (en) 2017-02-10 2017-02-10 Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm

Country Status (1)

Country Link
CN (1) CN106780041A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109685558A (en) * 2018-12-14 2019-04-26 国网辽宁省电力有限公司经济技术研究院 A kind of Cost for Electric Power Engineering evaluation system based on BIM technology
CN109934455A (en) * 2019-01-26 2019-06-25 国家电网有限公司 A kind of electricity power engineering construction cost assessment method
CN112541631A (en) * 2020-12-10 2021-03-23 国网湖北省电力有限公司 Expense prediction method for transformer substation engineering

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109685558A (en) * 2018-12-14 2019-04-26 国网辽宁省电力有限公司经济技术研究院 A kind of Cost for Electric Power Engineering evaluation system based on BIM technology
CN109934455A (en) * 2019-01-26 2019-06-25 国家电网有限公司 A kind of electricity power engineering construction cost assessment method
CN112541631A (en) * 2020-12-10 2021-03-23 国网湖北省电力有限公司 Expense prediction method for transformer substation engineering

Similar Documents

Publication Publication Date Title
CN106780041A (en) Power network project of transmitting and converting electricity investment forecasting method based on particle cluster algorithm
CN105303452A (en) Power-grid regulation and control real-time data distributed processing method and system
CN108053110A (en) A kind of transformer state inline diagnosis method based on PMU data
CN102868224A (en) Secondary network measurement and multimode decision-making method and device for intelligent substation
CN103198222A (en) Balance optimization method for comprehensive interruption maintenance plan
CN115801412B (en) Extraction method of electric power Internet of things information network attack behavior characteristics
CN111027886A (en) Evaluation method of low-voltage treatment scheme considering unit cost effectiveness
CN202872464U (en) Secondary network measurement and multimode decision apparatus of intelligent substation
CN113036915B (en) Intelligent gateway-based park power supply equipment remote monitoring and control method
CN111208384A (en) Smart power grid management system
CN111756031B (en) Power grid operation trend estimation method and system
CN104834986B (en) Tunnel construction progress dynamic control method based on the analysis of global overall sensitivity
CN116526553A (en) Management method and system for improving power generation capacity of photovoltaic power station
CN102946109B (en) Wide area damping control system of electric system based on event trigger
CN113675953A (en) Low-voltage distribution area topology identification method based on voltage similarity clustering
CN101620250B (en) Self-adaptive monitoring method for measuring quality
CN106452822A (en) Online energy consumption management method and apparatus of large-scale server cluster
CN111027829B (en) Benefit-based power grid planning system
CN109767062B (en) Dynamic generation method of power grid task disposal scheme
CN112510704A (en) Online coal consumption curve real-time generation method and system
CN104200390A (en) Power network reliability analysis method based on cellular automaton
Peng et al. A New Dispatch Control Integration System of the Smart Grid Based on the Regional Network Centralized Protected Mode
LU505190B1 (en) Method, Device and Equipment for Monitoring the Operation State of Photovoltaic Power Station
CN106845823A (en) One kind is ice-covering-proof to wave technological transformation project Benefit Evaluation Method and system
CN114414938B (en) Dynamic response method and system for power distribution network faults

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170531

WD01 Invention patent application deemed withdrawn after publication