CN106779465A - The well choosing method of production is opened between a kind of low yield liquid measure oil well - Google Patents

The well choosing method of production is opened between a kind of low yield liquid measure oil well Download PDF

Info

Publication number
CN106779465A
CN106779465A CN201611262595.3A CN201611262595A CN106779465A CN 106779465 A CN106779465 A CN 106779465A CN 201611262595 A CN201611262595 A CN 201611262595A CN 106779465 A CN106779465 A CN 106779465A
Authority
CN
China
Prior art keywords
oil well
low yield
liquid measure
well
yield liquid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611262595.3A
Other languages
Chinese (zh)
Inventor
李大建
周志平
甘庆明
陆梅
刘涛
张岩
辛宏
房玉凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201611262595.3A priority Critical patent/CN106779465A/en
Publication of CN106779465A publication Critical patent/CN106779465A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0637Strategic management or analysis, e.g. setting a goal or target of an organisation; Planning actions based on goals; Analysis or evaluation of effectiveness of goals
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Mining

Abstract

The invention discloses the well choosing method that production is opened between a kind of low yield liquid measure oil well, comprise the following steps:Calculate the extraction ability Q of low yield liquid measure oil wellAdopt, further according to the extraction ability Q of low yield liquid measure oil wellAdoptOil well is set up for adopting equilibrium equation, then the actual production information according to low yield liquid measure oil well solves oil well for adopting equilibrium equation, obtain the theoretical Liquid output of low yield liquid measure oil well, what the actual Liquid output of theoretical Liquid output and low yield liquid measure oil well finally according to low yield liquid measure oil well opened production between carrying out low yield liquid measure oil well selects well, what the method opened production between can realizing low yield liquid measure oil well selects well, and reliability is higher, operate relatively simple.

Description

The well choosing method of production is opened between a kind of low yield liquid measure oil well
Technical field
The present invention relates to a kind of well choosing method, and in particular to open the well choosing method of production between a kind of low yield liquid measure oil well.
Background technology
It is that domestic hyposmosis, ultra-low penetration oil field carry the major measure hand for imitating consumption reduction at present that production is opened between low liquid measure oil well Section, the subject matter for facing is a choice-start well problem, i.e., production liquid measure boundary is opened between oil well and determines problem.Literature survey, scene Investigation finds mainly have following several to open well choosing method at present:One is produced on-site empirical method, i.e., according to oil well actual production Situation, summarizes well mouth of oil well and goes out liquid law characteristic, substantially determines oil well effective production time, enters in the ranks and opens production, it is clear that be this Method error is larger, is influenceed by the experience managerial skills height of live oil recovery workman, and the specific implementation amount of getting up to work is big;Two are Representative oil well is chosen, well head is carried out and is continuously dynamically tested, grope build-up of fluid rule in oil well liquid output rule or pit shaft Rule, is qualitatively judged, and is opened production between determining oil well and is selected well;The workload of this mode is big, costly, operational not strong;Three It is that, based on oil well digital management system, continuous acquisition oil well production indicator card judges oil well supply and discharge rule, qualitative determination oil well Between choice-start well, although this mode has certain reliability, workload is big, with the proviso that setting up in oil field digital management Or work(figure meter is produced in system-based, is existed compared with big limitation.
The content of the invention
Shortcoming it is an object of the invention to overcome above-mentioned prior art, there is provided open production between a kind of low yield liquid measure oil well Well choosing method, the method opens the well that selects of production between can realizing low yield liquid measure oil well, and reliability is higher, operation more letter It is single.
The well choosing method for opening production between above-mentioned purpose, low yield liquid measure oil well of the present invention to reach includes following step Suddenly:Calculate the extraction ability Q of low yield liquid measure oil wellAdopt, further according to the extraction ability Q of low yield liquid measure oil wellAdoptOil well is set up for adopting flat Weigh equation, and then the actual production information according to low yield liquid measure oil well solves oil well for adopting equilibrium equation, obtains low yield liquid measure oil well Theoretical Liquid output, the actual Liquid output of theoretical Liquid output and low yield liquid measure oil well finally according to low yield liquid measure oil well carries out low That production is opened between Liquid output oil well selects well.
When low yield liquid measure oil well actual Liquid output more than or equal to low yield liquid measure oil well theoretical Liquid output when, then the low yield Liquid measure oil well should not be needed into the ranks opening production.
When low yield liquid measure oil well actual Liquid output less than low yield liquid measure oil well theoretical Liquid output when, then the low yield liquid measure Oil well is needed into the ranks opening production.
The extraction ability Q of low yield liquid measure oil wellAdoptExpression formula be:
Wherein, DpIt is the pump footpath of oil well pump, S is the stroke of oil well pump, and λ is loss of plunger stroke, QLeakageIt is the wastage of oil well pump, ηFillIt is the degree of filling of oil well pump, ηsuoIt is gas compressibility factor.
Wherein, Δ P is the pressure difference of oil pump plunger piston upper and lower side, and δ is the gap of oil pump plunger piston and pump barrel, and T is oil well pump Working time, μ for liquid viscosity, LcIt is the length of oil pump plunger piston.
Wherein, E is the elastic modelling quantity of steel, LbIt is pump setting depth, P' is fluid column weight, f on plungertIt is oil pipe sectional area, fr It is conversion rod string sectional area.
The invention has the advantages that:
The well choosing method of production is opened between low yield liquid measure oil well of the present invention in concrete operations, using theoretical calculation with The mode that produce reality is combined opens the well that selects of production between carrying out low yield liquid measure oil well, specifically first calculate low yield liquid measure oil well Extraction ability, then calculates the theoretical Liquid output of low yield liquid measure oil well using oil well for adopting equilibrium equation, then will be according to low yield liquid The theoretical Liquid output of gauging well and the actual Liquid output of low yield liquid measure oil well open the well that selects of production between carrying out low yield liquid measure oil well, behaviour Make simple, convenient, reliability is higher, provided to open production between hyposmosis, ultra-low penetration oil field low yield liquid measure oil wells in field scale Well means are selected, well choosing method deficiency is opened between efficiently solving the problems, such as at present, for oil field cost efficiency, benefit exploitation provide theory Foundation, has important practical significance to oil field production.
Brief description of the drawings
Fig. 1 be open production in embodiment one between low yield liquid measure oil well select well figure.
Specific embodiment
The present invention is described in further detail below in conjunction with the accompanying drawings:
With reference to Fig. 1, the well choosing method that production is opened between low yield liquid measure oil well of the present invention is comprised the following steps:Calculate low The extraction ability Q of Liquid output oil wellAdopt, further according to the extraction ability Q of low yield liquid measure oil wellAdoptOil well is set up for adopting equilibrium equation, so The actual production information according to low yield liquid measure oil well solves oil well for adopting equilibrium equation afterwards, obtains the theoretical of low yield liquid measure oil well and produces liquid Amount, the actual Liquid output of theoretical Liquid output and low yield liquid measure oil well finally according to low yield liquid measure oil well carries out low yield liquid measure oil well Between open production select well.
When low yield liquid measure oil well actual Liquid output more than or equal to low yield liquid measure oil well theoretical Liquid output when, then the low yield Liquid measure oil well should not be needed into the ranks opening production.
When low yield liquid measure oil well actual Liquid output less than low yield liquid measure oil well theoretical Liquid output when, then the low yield liquid measure Oil well is needed into the ranks opening production.
The extraction ability Q of low yield liquid measure oil wellAdoptExpression formula be:
Wherein, DpIt is the pump footpath of oil well pump, S is the stroke of oil well pump, and λ is loss of plunger stroke, QLeakageIt is the wastage of oil well pump, ηFillIt is the degree of filling of oil well pump, ηsuoIt is gas compressibility factor.
Wherein, Δ P is the pressure difference of oil pump plunger piston upper and lower side, and δ is the gap of oil pump plunger piston and pump barrel, and T is oil well pump Working time, μ for liquid viscosity, LcIt is the length of oil pump plunger piston.
Wherein, E is the elastic modelling quantity of steel, LbIt is pump setting depth, P' is fluid column weight, f on plungertIt is oil pipe sectional area, fr It is conversion rod string sectional area.
Embodiment one
Oil well A, manufacturing parameter is:Stroke is 2.5m, and jig frequency is 1.5 times/min, and it is 1400m that pump is hung, and pump footpath is 28mm, well The single amount liquid measure of mouth is 1.23m3/d。
By theoretical calculation go out the oil well pump of a diameter of 28mm 1.8m*1.5 times/min, 2.1m*1.5 times/min, 2.5m* Under four kinds of 1.5 times/min, 3.0m*1.5 times/min (stroke * jig frequencies) etc. different manufacturing parameters and 600-2200m pump setting depth bars Oil well produced power curve under part, as shown in figure 1, by contrasting the actual well head Liquid outputs of oil well A, theoretical extraction ability, it is found that Oil well A theory extraction abilities are 1.43m3/ d, more than actual well head Liquid output, shows that oil well A fluid supply capacities are not enough, it is necessary to open Production, opens production liquid measure boundary as 1.43m between improvement3/d。

Claims (6)

1. the well choosing method of production is opened between a kind of low yield liquid measure oil well, it is characterised in that comprised the following steps:Calculate low yield liquid measure The extraction ability Q of oil wellAdopt, further according to the extraction ability Q of low yield liquid measure oil wellAdoptOil well is set up for adopting equilibrium equation, then basis The actual production information of low yield liquid measure oil well solves oil well for adopting equilibrium equation, obtains the theoretical Liquid output of low yield liquid measure oil well, most Theoretical Liquid output and the actual Liquid output of low yield liquid measure oil well afterwards according to low yield liquid measure oil well is opened between carrying out low yield liquid measure oil well What is produced selects well.
2. the well choosing method of production is opened between low yield liquid measure oil well according to claim 1, it is characterised in that when low yield liquid measure The actual Liquid output of oil well more than or equal to low yield liquid measure oil well theoretical Liquid output when, then the low yield liquid measure oil well should not need into In the ranks open production.
3. the well choosing method of production is opened between low yield liquid measure oil well according to claim 1, it is characterised in that when low yield liquid measure The actual Liquid output of oil well less than low yield liquid measure oil well theoretical Liquid output when, then the low yield liquid measure oil well is needed into the ranks opening life Produce.
4. the well choosing method of production is opened between low yield liquid measure oil well according to claim 1, it is characterised in that low yield liquid measure oil The extraction ability Q of wellAdoptExpression formula be:
Wherein, DpIt is the pump footpath of oil well pump, S is the stroke of oil well pump, and λ is loss of plunger stroke, QLeakageIt is the wastage of oil well pump, ηFillFor The degree of filling of oil well pump, ηsuoIt is gas compressibility factor.
5. the well choosing method of production is opened between low yield liquid measure oil well according to claim 4, it is characterised in that
Wherein, Δ P is the pressure difference of oil pump plunger piston upper and lower side, and δ is the gap of oil pump plunger piston and pump barrel, and T is the work of oil well pump Make the time, μ is the viscosity of liquid, LcIt is the length of oil pump plunger piston.
6. the well choosing method of production is opened between low yield liquid measure oil well according to claim 5, it is characterised in that
λ = P ′ L b E ( 1 f r + 1 f t ) - - - ( 3 )
Wherein, E is the elastic modelling quantity of steel, LbIt is pump setting depth, P' is fluid column weight, f on plungertIt is oil pipe sectional area, frIt is folding Calculate rod string sectional area.
CN201611262595.3A 2016-12-30 2016-12-30 The well choosing method of production is opened between a kind of low yield liquid measure oil well Pending CN106779465A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611262595.3A CN106779465A (en) 2016-12-30 2016-12-30 The well choosing method of production is opened between a kind of low yield liquid measure oil well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611262595.3A CN106779465A (en) 2016-12-30 2016-12-30 The well choosing method of production is opened between a kind of low yield liquid measure oil well

Publications (1)

Publication Number Publication Date
CN106779465A true CN106779465A (en) 2017-05-31

Family

ID=58954131

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611262595.3A Pending CN106779465A (en) 2016-12-30 2016-12-30 The well choosing method of production is opened between a kind of low yield liquid measure oil well

Country Status (1)

Country Link
CN (1) CN106779465A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4507055A (en) * 1983-07-18 1985-03-26 Gulf Oil Corporation System for automatically controlling intermittent pumping of a well
RO119246B1 (en) * 2000-12-19 2004-06-30 S.N.P.Ápetromás.A.-Institutuládeácercetăriáşiáproiectăriátehnologice Automated plant for intermitent pumping, with cycle programmer
CN2775297Y (en) * 2004-11-24 2006-04-26 田景利 Intelligent controller for oil field intermittent oil pumping well
WO2007027124A1 (en) * 2005-09-02 2007-03-08 Nikolay Petrovich Kuzmichev Method for a short-term well operation by means of an electrically-powered downhole pumping unit (kuzmichev method)

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4507055A (en) * 1983-07-18 1985-03-26 Gulf Oil Corporation System for automatically controlling intermittent pumping of a well
RO119246B1 (en) * 2000-12-19 2004-06-30 S.N.P.Ápetromás.A.-Institutuládeácercetăriáşiáproiectăriátehnologice Automated plant for intermitent pumping, with cycle programmer
CN2775297Y (en) * 2004-11-24 2006-04-26 田景利 Intelligent controller for oil field intermittent oil pumping well
WO2007027124A1 (en) * 2005-09-02 2007-03-08 Nikolay Petrovich Kuzmichev Method for a short-term well operation by means of an electrically-powered downhole pumping unit (kuzmichev method)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
卢琳等: "低产油井间歇生产工作制度的研究与应用", 《断块油气田》 *
李红等: "数学模型法确定油井间开制度探讨", 《录井工程》 *

Similar Documents

Publication Publication Date Title
US10060247B2 (en) Hydrocarbon well performance monitoring system
US9810212B2 (en) Fluid load line calculation and concavity test for downhole pump card
CN104265281B (en) Method for predicting well yield of sealed, unsaturated oil reservoirs through elastic driving water-flooding extraction
CN102243163B (en) Quantitative evaluation method for permeability of faults of coal mine
CN105464652A (en) Dynamic reserve calculation method and system for fracture and cave type carbonatite oil reservoir fracture and cave unit
CN107578342A (en) It is a kind of based on the Model coupling method of exhaustion realize low-permeability oil deposit between open working system method for optimizing
CN109519156A (en) A kind of side water sand rock gas reservoir water drive section model Seepage Experiment method
CN105673001B (en) A kind of carbonate rock individual well drop in formation pressure processing method
CN102748007B (en) Well testing analytical method and device
CN103510940B (en) Mechanical oil well operating mode integrated diagnosing and analyzing method and device
Khakimyanov et al. Control of sucker rod pumps energy consumption
CN107130955B (en) Method for determining bottom hole flowing pressure and method for determining natural energy of reservoir
CN104975827A (en) Substance balance method for predicting carbon dioxide flooding oil reservoir indexes
CN107269265A (en) A kind of system and method for optimizing and revising oilwell produced fluid amount
CN103498661B (en) A kind of method determining oil reservoir physical data under high pressure
CN106285630A (en) A kind of assay method of the peak production capacity of SAGD well
CN109696324A (en) The confining pressure experimental provision in situ of Rock And Soil in a kind of drilling of ground
Estepho Seepage induced consolidation test: characterization of mature fine tailings
CN112183800B (en) Method and device for predicting recoverable reserves of crude oil of water-drive reservoir
CN106779465A (en) The well choosing method of production is opened between a kind of low yield liquid measure oil well
RU2700738C1 (en) Method of improving reliability of water cut monitoring of products of oil producing wells equipped with sucker-rod bottom pumps
RU2539445C1 (en) Method for determining formation pressure in oil producer equipped with submerged electric-driven pump
CN108335221A (en) A kind of oil well oil-pumping pump efficiency Improvement space determines method
CN110552685A (en) Method for calculating working fluid level of oil well by utilizing ground indicator diagram in wax precipitation well
CN106837298A (en) Opening the production time between a kind of low yield liquid measure oil well determines method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531