CN106761390A - Tubing string - Google Patents

Tubing string Download PDF

Info

Publication number
CN106761390A
CN106761390A CN201510800614.2A CN201510800614A CN106761390A CN 106761390 A CN106761390 A CN 106761390A CN 201510800614 A CN201510800614 A CN 201510800614A CN 106761390 A CN106761390 A CN 106761390A
Authority
CN
China
Prior art keywords
wall device
tubing string
scrape
well logging
logging apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510800614.2A
Other languages
Chinese (zh)
Inventor
周建平
张雪松
李元斌
季晓红
练以峰
董仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201510800614.2A priority Critical patent/CN106761390A/en
Publication of CN106761390A publication Critical patent/CN106761390A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B37/00Methods or apparatus for cleaning boreholes or wells
    • E21B37/02Scrapers specially adapted therefor
    • E21B37/04Scrapers specially adapted therefor operated by fluid pressure, e.g. free-piston scrapers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geophysics (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention provides a kind of tubing string, and the tubing string includes:The drilling tool that is arranged in oil well casing, scrape wall device and well logging apparatus;Wherein, scrape wall device and well logging apparatus are arranged on drilling tool.The present invention passes through that wall device will be scraped and well logging apparatus are arranged on drilling tool, realize drilling tool, scrape wall device and the integrated design of well logging apparatus, drilling out operation can be realized in drillng operation simultaneously, scrape wall operation and survey cementing quality operation, avoid in the prior art expend the time it is long, ineffective shortcoming.

Description

Tubing string
Technical field
The present invention relates to oil field development technical field, more particularly to a kind of tubing string.
Background technology
In oilfield development process, when the drillng operation later stage is entered, it is necessary to carry out drilling out, scrape wall With survey the road flow chart of cementing quality three, its specific work process is:Enter for boring under in oil well casing The brill plug tubing string of cement plug, after cement plug is drilled, is risen and to bore plug tubing string, and wall scraper tubing string is then entered down, After complete well liner inwall to be doctored, rise wall scraper tubing string, then under enter logger, carry out survey tail pipe consolidate Well quality, finally plays out logger.
However, it is necessary to enter to bore plug tubing string, wall scraper tubing string and survey down respectively in above-mentioned specific work process Well instrument is, it is necessary to three brills could realize drilling out, scrape wall and survey three kinds of functions of cementing quality, typically For, it is drilled into the 3 day time of few needs for one time, cause the consuming time long, inefficiency.
The content of the invention
The present invention provides a kind of tubing string, drilling out operation can be realized in drillng operation, wall is scraped simultaneously Operation and survey cementing quality operation.
The present invention provides a kind of tubing string, including:The drilling tool that is arranged in oil well casing, scrape wall device and survey Well device;
It is described to scrape wall device and the well logging apparatus are arranged on the drilling tool.
In an embodiment of the present invention, the drilling tool, including:Drilling rod and drill bit;
The well logging apparatus and it is described scrape wall device be axially arranged on the drilling rod and the drill bit it Between.
In an embodiment of the present invention, the drilling tool includes:Drilling rod and drill bit;
Then the well logging apparatus and it is described scrape wall device be axially arranged on the drilling rod and the drill bit it Between.
In an embodiment of the present invention, the drilling tool also includes:Positioned at the drilling rod end, and for even Connect the drill collar of the drilling rod and the drill bit;
Then the well logging apparatus and it is described scrape wall device be axially arranged on the drill collar and the drill bit it Between.
In an embodiment of the present invention, the well logging apparatus are storage type logging instrument.
In an embodiment of the present invention, the wall of scraping is set to scraping wall.
In an embodiment of the present invention, the wall device of scraping includes:Body and with positioned at the body interior Scrape cutter hub;
Wherein, the cutter hub of scraping is locked on the body by pin.
In an embodiment of the present invention, the wall device of scraping also includes:It is arranged on the body and described scrapes Between cutter hub, and for providing the spring and pressure-bearing plug of the shearing force of shear pin.
In an embodiment of the present invention, also include:It is arranged on and is scraped between wall device and the drill bit described, And for controlling described to scrape the sliding sleeve switch that cutter hub is ejected from the body.
In an embodiment of the present invention, the sliding sleeve switch includes:Outer tube body, it is arranged on the outer tube body Axially extending bore that interior sliding sleeve, the pitching mouth being arranged on the sliding sleeve are connected with the pitching mouth and with The radial direction through hole of the axially extending bore connection;
Wherein, one end of the outer tube body is connected with the wall device of scraping, the other end and the drill bit phase Connection.
In an embodiment of the present invention, the drilling rod is hollow structure.
The present invention provides a kind of tubing string, including be arranged in oil well casing drilling tool, scrape wall device and well logging Device;Wherein, scrape wall device and well logging apparatus are arranged on drilling tool.The present invention by will scrape wall device and Well logging apparatus are arranged on drilling tool, realized drilling tool, are scraped wall device and the integrated design of well logging apparatus, Drilling out operation can be realized in drillng operation simultaneously, scrape wall operation and survey cementing quality operation, kept away Exempted from the prior art expend the time it is long, ineffective shortcoming.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to reality The accompanying drawing to be used needed for example or description of the prior art is applied to be briefly described, it should be apparent that, under Accompanying drawing in the description of face is some embodiments of the present invention, for those of ordinary skill in the art, On the premise of not paying creative labor, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the structural representation of tubing string embodiment one provided in an embodiment of the present invention;
Fig. 2 is a structural representation of tubing string embodiment two provided in an embodiment of the present invention;
Fig. 3 is another structural representation of tubing string embodiment two provided in an embodiment of the present invention;
Fig. 4 is a structural representation of tubing string embodiment three provided in an embodiment of the present invention;
Fig. 5 is another structural representation of tubing string embodiment three provided in an embodiment of the present invention;
Fig. 6 is the structural representation for scraping wall device provided in an embodiment of the present invention;
Fig. 7 is the structural representation of tubing string embodiment five provided in an embodiment of the present invention;
Fig. 8 is the structural representation of sliding sleeve switch provided in an embodiment of the present invention.
Specific embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with this hair Accompanying drawing in bright embodiment, is clearly and completely described to the technical scheme in the embodiment of the present invention, Obviously, described embodiment is a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained under the premise of creative work is not made The every other embodiment for obtaining, belongs to the scope of protection of the invention.
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with this hair Accompanying drawing in bright embodiment, is clearly and completely described to the technical scheme in the embodiment of the present invention, Obviously, described embodiment is a part of embodiment of the invention, rather than whole embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained under the premise of creative work is not made The every other embodiment for obtaining, belongs to the scope of protection of the invention.
Fig. 1 is the structural representation of tubing string embodiment one provided in an embodiment of the present invention;As shown in figure 1, The tubing string includes:Including:The drilling tool 10 that is arranged in oil well casing, scrape wall device 20 and well logging apparatus 30。
In the present embodiment, scrape wall device 20 and well logging apparatus 30 are arranged on drilling tool 10.
Specifically, drilling tool 10 is used to carry out drilling out operation in underground, scrapes wall device 20 and be mainly used in Remove the attachments such as the cement of internal surface of sleeve pipe, it is ensured that the cleaning of internal surface of sleeve pipe, well logging apparatus 30 are mainly used in Detection cementing quality is scanned to oil well casing inwall.
Wherein, position of the present invention not to scraping wall device 20 and well logging apparatus 30 limits, specifically , scraping wall device can be arranged on the top of well logging apparatus, it is also possible to be arranged on the lower section of well logging apparatus, It is understood that the present invention is illustrated so that well logging apparatus are arranged on and scrape wall device top as an example.
Illustrate the embodiment of the present invention below by the course of work of tubing string, by under tubing string in oil well casing, To injecting mud in drilling tool 10, carry out boring plug operation by drilling tool 10, bore the cement solids particle that falls with Mud and return out well head, after completing to bore plug operation, after well head is returned out without cement solid particle in well, stop Mud is only injected, then carries out scraping wall operation, move up and down tubing string, using scraping wall device 20 by sleeve pipe The attachments such as the cement on wall are wiped off, make the cement solids wiped off to mud is injected in drilling tool again afterwards Grain returns out well head with mud, stops injection mud, and cementing quality is detected by well logging apparatus 30, according to The data evaluation cementing quality of well logging apparatus collection, acts tubing string.
The tubing string that the present invention is provided includes:The drilling tool that is arranged in oil well casing, scrape wall device and well logging dress Put;Wherein, scrape wall device and well logging apparatus are arranged on drilling tool.The present invention will be by that will scrape wall device and survey Well device is arranged on drilling tool, is realized drilling tool, is scraped wall device and the integrated design of well logging apparatus, energy It is enough that drilling out operation is realized in drillng operation simultaneously, wall operation is scraped and surveys cementing quality operation, it is to avoid It is long to expend the time in the prior art, ineffective shortcoming.
Further, on the basis of the technical scheme of above-described embodiment one, in embodiments of the invention two Technical scheme in, Fig. 2 is a structural representation of tubing string embodiment two provided in an embodiment of the present invention; As shown in Fig. 2 drilling tool 10 includes:Drilling rod 11 and drill bit 12.
Then the well logging apparatus and it is described scrape wall device be axially arranged on the drilling rod and the drill bit it Between.
In the present embodiment, drilling rod 11 is the element of transmission power in drilling tool, and drill bit 12 can be with brill Bar high-speed rotation together, while moving down drilling out, drilling rod 11 is required to bear huge Interior external pressure, distortion, bending and vibration.In addition, drilling rod 11 is hollow structure.Mud can be made to pass through to bore , can be transported to mud at drill bit 12 by drilling rod by tool outflow, and improved together with drill bit 12, Reduce or rotate.Hydrophthalmia with fluid passage in drill bit 12, the mud in drilling rod 11 can be from drill bit Flowed out in 12 hydrophthalmia.
Wherein, position of the present invention not to scraping wall device 20 and well logging apparatus 30 limits, specifically , scraping wall device can be arranged on the top of well logging apparatus, it is also possible to be arranged on the lower section of well logging apparatus, It is understood that the present invention is illustrated so that well logging apparatus are arranged on and scrape wall device top as an example. Fig. 3 is another structural representation of tubing string embodiment two provided in an embodiment of the present invention;With well logging apparatus It is arranged on as a example by the lower section for scraping wall device what is illustrated.
Further, on the basis of the technical scheme of above-described embodiment one and embodiment two, in the present invention Embodiment three technical scheme in, Fig. 4 is of tubing string embodiment three provided in an embodiment of the present invention Structural representation;As shown in figure 4, drilling tool also includes:Positioned at drilling rod end, and for jointed rod 11 With the drill collar 13 of drill bit 12.
In the present embodiment, well logging apparatus 30 are axially arranged on drill collar 13 and brill with wall device 20 is scraped Between first 12.
Specifically, drill collar 13 is mainly characterized by wall thickness greatly, generally 38 to 53mm, equivalent to drilling rod 4 to 6 times of 11 wall thickness, with larger gravity and rigidity.
Wherein, position of the present invention not to scraping wall device 20 and well logging apparatus 30 limits, specifically , scraping wall device can be arranged on the top of well logging apparatus, it is also possible to be arranged on the lower section of well logging apparatus, It is understood that the present invention is illustrated so that well logging apparatus are arranged on and scrape wall device top as an example. Fig. 5 is another structural representation of tubing string embodiment three provided in an embodiment of the present invention;With well logging apparatus It is arranged on as a example by the lower section for scraping wall device what is illustrated.
In the present embodiment, alternatively, well logging apparatus are storage type logging instrument.
Specifically, storage type logging instrument does not need connection cable, can easily G.I.H, with brill Tool 10 is rotated, and the connection without considering cable is designed, and storage type logging instrument is as integrated pipe column is from going into the well During rising, measuring state is constantly in, can arbitrarily obtain required measurement data.
Alternatively, scrape wall and be set to scraping wall.
Further, on the basis of the technical scheme of above-described embodiment, Fig. 6 is carried for the embodiment of the present invention The structural representation for scraping wall device for supplying, as shown in fig. 6, in the present embodiment, scraping wall device includes: Body 21 and scrape cutter hub 22 with inside body 21.
In the present embodiment, cutter hub 22 is scraped to be locked on body 21 by pin 25.When scraping wall device also Do not proceed by when scraping wall operation, scrape cutter hub 22 positioned at the inside of body.
Due in plug operation process is bored, scraping wall device 20 as drilling rod 11 is rotated, therefore scrape wall device 20 are preferably selected to be scraped cutter hub 22 and be received in and scrape in wall device 20, controllable when needing to carry out scraping wall System is scraped cutter hub 22 and is ejected, and the inwall with well inner sleeve is contacted, and carries out scraping wall operation.
In the present embodiment, scraping wall device 20 also includes:It is arranged on body 21 and scrapes between cutter hub 22 Spring 23 and pressure-bearing plug 24.
Specifically, spring 23 and pressure-bearing plug 24 are used to provide the shearing force of shear pin.
When do not proceed by scrape wall when, spring 23 be in compressive state.
Further, on the basis of the technical scheme of above-described embodiment, Fig. 7 is carried for the embodiment of the present invention The structural representation of the tubing string embodiment five of confession, as shown in fig. 7, in the present embodiment, the tubing string is also wrapped Include:It is arranged on scraping between wall device 20 and drill bit 12, and for controlling described to scrape cutter hub from described The sliding sleeve switch 40 of body ejection.
Wherein, if well logging apparatus 30 are arranged on the top for scraping wall device 20, sliding sleeve switch 40 is arranged on Scrape between wall device 20 and drill bit 12, if well logging apparatus 30 are arranged on the lower section for scraping wall device 20, Sliding sleeve switch 40 is arranged on to be scraped between wall device 20 and well logging apparatus 30.That is, sliding sleeve switch 40 will be close to setting with wall device 20 is scraped.
Specifically, when scrape wall operation, by steel ball is put into drilling rod, treating that steel ball drop is arrived Sliding sleeve switch 40, makes the axial seal of sliding sleeve switch 40, and to being suppressed in sliding sleeve switch 40 to a spy Fixed pressure value, power and the shearing force for being more than shear pin with joint efforts of spring 23 that pressure-bearing plug 24 bears, After shear pin stress is interrupted, the inner spring 23 of body 21 will scrape cutter hub 22 and eject, and now scrape cutter hub 22 are close on the inwall of well inner sleeve, just can carry out scraping wall operation by above putting charging integrated tubing string.
Fig. 8 is the structural representation of sliding sleeve switch provided in an embodiment of the present invention, as shown in figure 8, sliding sleeve Switch 40 includes:Outer tube body 41, the sliding sleeve 42 being arranged in outer tube body 41, it is arranged on sliding sleeve 42 The axially extending bore 44 connected with pitching mouth 43 of pitching mouth 43 and the radial direction being connected with axially extending bore 44 Through hole 45.
Wherein, one end of outer tube body 41 is connected with wall device is scraped, the other end and drill bit of outer tube body 41 It is connected.
Specifically, it is necessary to when scrape wall operation after completing to bore plug operation, to putting into steel in drilling rod 11 Ball is blocked the axially extending bore 44 of sliding sleeve 42, by drilling rod 11 to the pitching mouth 43 of sliding sleeve 42 Suppress to a specific pressure value, scraping wall scrapes cutter hub ejection, and now sliding sleeve 42 is in outer tube body Position in 41 is first position, when continuing to be pressurized to a preset value, between sliding sleeve 42 and outer tube body 41 The pin of connection is cut off, and sliding sleeve 42 slides to the second place in outer tube body 41, and now sliding sleeve 42 is stuck in On the inwall of outer tube body 41, the radial direction through hole 45 of sliding sleeve 42 corresponds to the inwall of outer tube body 41 and sliding sleeve 42 Between the annular space 46 that is formed, this annular space 46 connects with one end of outer tube body 41, and mud can In entering to annular space 46 from one end of outer tube body 41, then the radial direction through hole 45 of sliding sleeve 42 is flowed into, Then flow to the other end 3 of outer tube body 41 from the axially extending bore 44 of sliding sleeve 42, outer tube body 41 it is another End connects with drill bit 12, and mud can flow out from bit port.Because mud can be in sliding sleeve switch Circulated between 40 and drill bit 12, therefore in clean-out service, mud can be recycled to the hydrophthalmia position of drill bit Put, the impurity recycling in the space between drill bit 12 and sliding sleeve switch 40 can be gone out.
Finally it should be noted that:Various embodiments above is merely illustrative of the technical solution of the present invention, rather than right Its limitation;Although being described in detail to the present invention with reference to foregoing embodiments, this area it is common Technical staff should be understood:It can still modify to the technical scheme described in foregoing embodiments, Or equivalent is carried out to which part or all technical characteristic;And these modifications or replacement, and The scope of the essence disengaging various embodiments of the present invention technical scheme of appropriate technical solution is not made.

Claims (10)

1. a kind of tubing string, it is characterised in that including:The drilling tool that is arranged in oil well casing, scrape wall device And well logging apparatus;
It is described to scrape wall device and the well logging apparatus are arranged on the drilling tool.
2. tubing string according to claim 1, it is characterised in that the drilling tool includes:Drilling rod and brill Head;
Then the well logging apparatus and it is described scrape wall device be axially arranged on the drilling rod and the drill bit it Between.
3. tubing string according to claim 2, it is characterised in that the drilling tool also includes:Positioned at institute Drilling rod end is stated, and for connecting the drill collar of the drilling rod and the drill bit;
Then the well logging apparatus and it is described scrape wall device be axially arranged on the drill collar and the drill bit it Between.
4. according to any described tubing strings of claim 1-3, it is characterised in that the well logging apparatus are to deposit Storage formula logging instrument.
5. tubing string according to claim 4, it is characterised in that it is described scrape wall and be set to hydraulic pressure scrape wall Device.
6. tubing string according to claim 5, it is characterised in that the wall device of scraping includes:Body And scrape cutter hub with positioned at the body interior;
Wherein, the cutter hub of scraping is locked on the body by pin.
7. tubing string according to claim 6, it is characterised in that the wall device of scraping also includes:If Put the body and it is described scrape cutter hub between, and for provide shear pin shearing force spring and hold Tamponade.
8. the tubing string according to claim 6 or 7, it is characterised in that also include:It is arranged in institute State and scrape between wall device and the drill bit, and for controlling described to scrape the sliding sleeve that cutter hub is ejected from the body Switch.
9. tubing string according to claim 8, it is characterised in that the sliding sleeve switch includes:Outer tube Body, the sliding sleeve being arranged in the outer tube body, the pitching mouth being arranged on the sliding sleeve and the pitching The axially extending bore of mouth connection and the radial direction through hole being connected with the axially extending bore;
Wherein, one end of the outer tube body is connected with the wall device of scraping, the other end and the drill bit phase Connection.
10. tubing string according to claim 9, it is characterised in that the drilling rod is hollow structure.
CN201510800614.2A 2015-11-19 2015-11-19 Tubing string Pending CN106761390A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510800614.2A CN106761390A (en) 2015-11-19 2015-11-19 Tubing string

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510800614.2A CN106761390A (en) 2015-11-19 2015-11-19 Tubing string

Publications (1)

Publication Number Publication Date
CN106761390A true CN106761390A (en) 2017-05-31

Family

ID=58915955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510800614.2A Pending CN106761390A (en) 2015-11-19 2015-11-19 Tubing string

Country Status (1)

Country Link
CN (1) CN106761390A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590583A (en) * 2018-03-30 2018-09-28 中国神华能源股份有限公司 Well washing apparatus
WO2020139918A1 (en) * 2018-12-28 2020-07-02 Saudi Arabian Oil Company Systems and methods for logging while treating

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1092844A (en) * 1993-03-25 1994-09-28 华北石油管理局第一钻井工程公司 A kind of surface casing for well completion process
CN201391259Y (en) * 2009-04-23 2010-01-27 山东荣兴石油工程有限公司 Horizontal well logging conveying device
CN202900168U (en) * 2012-11-15 2013-04-24 中国石油天然气股份有限公司 Hydraulic control sleeve scraper
CN204225817U (en) * 2014-09-09 2015-03-25 西安威盛电子科技股份有限公司 A kind of drifting well-flushing cement bond cementing quality well logging integrated apparatus
CN204386546U (en) * 2014-12-10 2015-06-10 宝鸡瑞通石油装备有限公司 Novel current global mechanism area sliding sleeve switch

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1092844A (en) * 1993-03-25 1994-09-28 华北石油管理局第一钻井工程公司 A kind of surface casing for well completion process
CN201391259Y (en) * 2009-04-23 2010-01-27 山东荣兴石油工程有限公司 Horizontal well logging conveying device
CN202900168U (en) * 2012-11-15 2013-04-24 中国石油天然气股份有限公司 Hydraulic control sleeve scraper
CN204225817U (en) * 2014-09-09 2015-03-25 西安威盛电子科技股份有限公司 A kind of drifting well-flushing cement bond cementing quality well logging integrated apparatus
CN204386546U (en) * 2014-12-10 2015-06-10 宝鸡瑞通石油装备有限公司 Novel current global mechanism area sliding sleeve switch

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘宝和: "《中国石油勘探开发百科全书》", 30 November 2008, 石油工业出版社 *
崔航波等: "新型多合一作业液压刮壁器在超深井的推广应用", 《油气井测试》 *
胡湘炯等: "《油气井工程》", 28 February 2003, 中国石化出版社 *
论文集编委会: "《深层、深水、非常规钻井技术研讨会暨2012年钻井研究院(所)长会议论文集》", 31 March 2013 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108590583A (en) * 2018-03-30 2018-09-28 中国神华能源股份有限公司 Well washing apparatus
WO2020139918A1 (en) * 2018-12-28 2020-07-02 Saudi Arabian Oil Company Systems and methods for logging while treating
US10920586B2 (en) 2018-12-28 2021-02-16 Saudi Arabian Oil Company Systems and methods for logging while treating

Similar Documents

Publication Publication Date Title
US9051792B2 (en) Wellbore tool with exchangeable blades
US3786878A (en) Dual concentric drillpipe
CA2365710C (en) Method and apparatus for drilling and completing a well
CN104428486B (en) The method and system of sub-terrain operations is performed using dual string drilling rod
EP3688271B1 (en) Stress testing with inflatable packer assembly
US10450801B2 (en) Casing windowing method and tool using coiled tubing
CN104884737A (en) Universal downhole probe system
CA2674749A1 (en) Borehole tester apparatus and methods using dual flow lines
CN105064919A (en) Ultra-short-radius radial lateral drilling method for horizontal wells
US8544553B2 (en) Sealing apparatus and method for a downhole tool
CN106761390A (en) Tubing string
US20140224511A1 (en) Pump Drain Arrangements For Packer Systems And Methods For Sampling Underground Formations Using Same
CN100575659C (en) A kind of insufficient balance well completion method
US10024141B2 (en) Apparatus and method of cleaning an oil well-bore
US2838283A (en) Method and apparatus for drilling well holes
US10577874B2 (en) Casing drilling apparatus and system
US9347295B2 (en) Filtration system and method for a packer
CN105221080B (en) Solution cavity protector and the navigation channel drilling on waterways method using this protector
US10301887B2 (en) Drill string sections with interchangeable couplings
JP5853032B2 (en) Method and apparatus for forming a communication between the gap of the drill string and the surrounding material during excavation by the down-the-hole method
US10180058B2 (en) Telemetry module with push only gate valve action
CN207583321U (en) The used drilling rod well logging target drill of drifting
US10871051B2 (en) System and method for drilling a wellbore portion in a subterranean formation
CN111980678A (en) Shearing type horizontal directional drilling geological prospecting in-hole logging instrument protection device
Lopez et al. Fiber-Optic Technology Reduces Production Logging Limitations in Complex Conditions: Case Studies from Mexico

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication