CN106759559A - A kind of steel pipe reinforces piling strtucture and its construction method - Google Patents

A kind of steel pipe reinforces piling strtucture and its construction method Download PDF

Info

Publication number
CN106759559A
CN106759559A CN201611168099.1A CN201611168099A CN106759559A CN 106759559 A CN106759559 A CN 106759559A CN 201611168099 A CN201611168099 A CN 201611168099A CN 106759559 A CN106759559 A CN 106759559A
Authority
CN
China
Prior art keywords
pile
stake
steel
steel pipe
summits
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611168099.1A
Other languages
Chinese (zh)
Inventor
苏伟
刘辉
王立军
岳巍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201611168099.1A priority Critical patent/CN106759559A/en
Publication of CN106759559A publication Critical patent/CN106759559A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures

Abstract

The present invention provides a kind of steel pipe and reinforces piling strtucture and its construction method, its piling strtucture includes the pile foundation body with defect area, drilling is vertically offered in pile foundation body, steel-pipe pile is provided with drilling, steel-pipe pile passes through defect area, and the upper and lower ends of steel-pipe pile extend defect area upper and lower ends complete pile foundation at least 1m respectively, steel-pipe pile includes seamless steel pipe and the reinforcing bar being arranged in seamless steel pipe, is fixed by pouring micro-expansion cement mortar between seamless steel pipe and reinforcing bar.There is gap, local pile body breaking to solve existing hole stake pile body, and have slag inclusion, it is necessary to carry out consolidation process, and the method that can not more efficiently solve the problems, such as above-mentioned problem at this stage.The invention belongs to pile foundation construction field.

Description

A kind of steel pipe reinforces piling strtucture and its construction method
Technical field
The present invention relates to a kind of defect of pile foundation solution, belong to pile foundation construction field.
Background technology
At present, in project construction, after pile foundation construction is finished, detected through live core pulling, indivedual hole stake pile bodies are less than The gap of 50cm, local pile body breaking, and have slag inclusion, detection unit is judged to the stake of three classes, it is necessary to carry out consolidation process, but existing rank Section does not have the pile foundation reinforcement method after more effective pile.
The content of the invention
It is an object of the invention to:A kind of steel pipe is provided and reinforces piling strtucture and its construction method, to solve existing hole stake Pile body has gap, local pile body breaking, and has slag inclusion, it is necessary to carry out consolidation process, and can not have more at this stage The method that effect ground solves the problems, such as above-mentioned problem.
To solve the above problems, intend being reinforced using such a steel pipe the construction method of piling strtucture, including:
Step one, positioning drillings:Determine drilling hole position in the upper end of pile foundation, rig is moved to and drilled in hole position, drilling is fixed Position is accurate, and rig is installed steadily firmly, and support level, vertical shaft is vertical, accomplishes that the line of three summit one, i.e. hole position, vertical shaft, overhead traveling crane exist On same straight line, to ensure that drilling does not offset vertically.Drilling will be stablized, and creep into always to the super 1m of full pile, meanwhile, lacking Place's processing extravasating hole is fallen into, extravasating hole is in quincuncial arrangement, and per 4 extravasating holes of pile, aperture is 100mm;
Step 2 high pressure clear water rotary spray wash:High-pressure injector is put down respectively from each hole, on control high-pressure injector High-pressure rotary injection cutting cleaning is back and forth carried out down, sprays pressure 20-26MPa, discharge capacity 70-90L/min, rotary speed 10- 28r/min, lifts speed 10-15cm/min, and cutting clean range respectively increases 0.5m up and down from defective section, until pile foundation upper end is bored Hole is all got through, and then, press-in clear water is using water circulation just waste residue discharge pile body;
Step 3 installs steel-pipe pile:Steel-pipe pile includes seamless steel pipe and the reinforcing bar being arranged in steel pipe, and perfusion is micro- swollen in steel pipe Swollen cement mortar, the steel-pipe pile extexine for processing carries out antirust treatment, steel-pipe pile is vertically put into the drilling being drilled, steel pipe By inserting complete pile body at least 1m after defect area, the reinforcing bar on steel-pipe pile need to anchor into cushion cap no less than 35d for stake;
Step 4 apertures mud jacking:After cutting cleaning terminates, carried out at mud jacking by the extravasating hole got out on former pile defect Reason.
In the step of foregoing construction method two, the lance lift speed of high-pressure injector is 10cm/min, and rotary speed is 20 turns/min, a hole cleaned and another Kong Youshui overflow when, show that rejected region has been got through, other holes are shifted to, until stake The drilling of base upper end is all got through;
In the step of foregoing construction method two, after being connected between the drilling of pile foundation upper end, clear water is pressed into, using water circulation just waste residue Discharge pile body, when the water of delivery port is clear by turbid change, then changes other holes wheel stream process, until all of pile foundation upper end drilling current When being all clear water, cutting cleaning terminates.
In the step of foregoing construction method three, pipe piling bar is by external diameter 127mm, the seamless steel pipe of wall thickness 6mm and a C The reinforcing bar composition of HRB400 a diameter of 25, interior perfusion M35 micro-expansion cement mortars, the steel-pipe pile extexine brushing red lead for processing Antirust paint;Inner sleeve is needed to be attached welding if length is more long, steel pipe pile body is advisable with without faying surface.
Slip casting raw material in the step of foregoing construction method four is cement mortar, cement mortar use strength grade for 42.5 silicon Acid salt cement is formulated with clear water, the cement grout ratio of mud 1 ~ 1.2, and slurries are prepared by first dilute rear dense principle, then mixed by water 1% addition waterproofing agent of consumption, to increase the workability and mobility of cement mortar, leaves test specimen sampling when preparing cement slurry, match somebody with somebody Liquid processed and additive will ensure quality, and measurement dress liquor ratio weight at any time, it is ensured that concentration of slurry reaches design requirement, and slurries should pass through 14*14 ~ 18*18 mesh sieves hole, in order to avoid being mixed into bag of cement bits or other debris, preparing dress liquid should be finished within the presetting period;
In the step of foregoing construction method four, high-pressure injection is repeated in the range of defective section with water under high pressure slurry liquid, makes each The stake rubble of defective section, rock, medium coarse sand and cement grout are thoroughly mixed, grouting pressure according to the foundation strength of supporting course and Depending on the compression strength of concrete piles, the foundation strength of supporting course and the compression strength of concrete piles, by taking embedded rock pile as an example, note need to be less than Dress pressure is 7-10MPa, press-fits stabilization time for 8-12min, during the bored grouting of pile foundation upper end, by other hole plugs, slip casting pressure Power increases 2-3MPa, after voltage stabilizing 5min, is judged whether to stop slip casting according to mud jacking resistance;Or when grout in other holes, stop Slip casting.
In the step of foregoing construction method one, drilling and positioning method is:
When stake footpath is 1m, five summits into regular pentagon distribution centered on the stake heart, each summit are chosen in pile foundation upper end Distance to the stake heart is 0.31m, and five selected summits are five centers of circle of drilling;
When stake footpath is 1.2m, three summits and into positive four into equilateral triangle distribution centered on the stake heart are chosen in pile foundation upper end Four summits of side shape distribution, in three summits of equilateral triangle distribution, each summit is 0.25m to the distance of the stake heart, just In four summits of quadrangle distribution, each summit to the distance of the stake heart is 0.25m, and 7 selected summits are 7 brills The center of circle in hole;
When stake footpath is 1.4m, eight summits into octagon distribution centered on the stake heart are chosen in pile foundation upper end, each top Point is 0.51m to the distance of the stake heart, and eight selected summits are eight centers of circle of drilling;
When stake footpath is 1.8m, eight summits and into positive seven into octagon distribution centered on the stake heart are chosen in pile foundation upper end Seven summits of side shape distribution, in eight summits of octagon distribution, each summit is 0.61m to the distance of the stake heart, just In seven summits of heptagon distribution, each summit to the distance of the stake heart is 0.30m, and 15 selected summits are 15 The center of circle of drilling;
When stake footpath is 1.6m, 2.0m and 2.2m, the two composition octagon distributions centered on the stake heart are chosen in pile foundation upper end Eight summits, 16 selected summits be 16 drilling the centers of circle, stake footpath be 1.6m when, one of which octagon In, each summit to the distance of the stake heart is 0.30m, and in another group of octagon, each summit is to the distance of the stake heart 0.61m;When stake footpath is 2.0m, in one of which octagon, each summit to the distance of the stake heart is 0.50m, and another group just In octagon, each summit is 0.81m to the distance of the stake heart;When stake footpath is 2.2m, in one of which octagon, each top Point is 0.508m to the distance of the stake heart, and in another group of octagon, each summit is 0.91m to the distance of the stake heart.
Meanwhile, reinforce piling strtucture, including the pile foundation body with defect area, pile foundation sheet the invention provides a kind of steel pipe Drilling vertically being offered in vivo, steel-pipe pile being provided with drilling, steel-pipe pile passes through defect area, and the upper and lower ends of steel-pipe pile to divide Defect area upper and lower ends complete pile foundation at least 1m is not extended, and steel-pipe pile includes seamless steel pipe and the steel being arranged in seamless steel pipe Muscle, is fixed between seamless steel pipe and reinforcing bar by pouring micro-expansion cement mortar.
In foregoing piling strtucture, the top construction of pile foundation body has cushion cap, and the upper end of reinforcing bar anchors into cushion cap not in steel-pipe pile Less than 35d;
In foregoing piling strtucture, the specification of seamless steel pipe is external diameter 127mm, wall thickness 6mm, and the specification of reinforcing bar is C HRB400 diameters It is 25mm, M35 micro-expansion cement mortars is irrigated therebetween, steel-pipe pile extexine is painted with red lead anti-corrosive paint.
Compared with prior art, the ruggedized construction and method can fast and effeciently to unqualified or second-rate pile foundation Consolidation process is carried out, solving existing hole stake pile body has gap, local pile body breaking, and has slag inclusion, and existing method cannot The problem effectively reinforced, construction method is easy and effective, and with low cost, the process-cycle is short, is particularly suited for solution cavity, fluid bowl and more sends out The southwest educated.
Brief description of the drawings
Fig. 1 is the main view cross-sectional view that steel pipe of the present invention reinforces piling strtucture;
Fig. 2 is the top view of steel-pipe pile.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, will make further detailed to the present invention below Description.
Embodiment:
Referring to Figures 1 and 2, the present embodiment provides a kind of steel pipe and reinforces piling strtucture, including the pile foundation body with defect area 11 1, drilling 12 is vertically offered in pile foundation body 1, steel-pipe pile 2 is provided with drilling 12, steel-pipe pile 2 passes through defect area 11, and The upper and lower ends of steel-pipe pile 2 extend the upper and lower ends of defect area 11 complete pile foundation at least 1m respectively, and steel-pipe pile 2 includes seamless steel pipe 21 With the reinforcing bar 22 being arranged in seamless steel pipe 21, the specification of seamless steel pipe 21 is external diameter 127mm, wall thickness 6mm, the specification of reinforcing bar 22 It is a diameter of 25mm of C HRB400, M35 micro-expansion cement mortars 23 is irrigated therebetween, the extexine of steel-pipe pile 2 is painted with red lead Antirust paint, the top construction of pile foundation body 1 has cushion cap 3, and the upper end of reinforcing bar 22 anchors into the 40d of cushion cap 3 in steel-pipe pile 2.
The construction method of above-mentioned piling strtucture is as follows:
Step one, positioning drilling 12:Determine 12 hole positions of drilling in the upper end of pile foundation, rig is moved to and drilled in hole position, bore Hole is positioned to accurately, and rig installs steady firm, and support level, vertical shaft is vertical, accomplishes the line of three summit one, i.e. hole position, vertical shaft, day Car on the same line, is not offset vertically with ensureing to drill.Drilling will be stablized, and creep into always to the super 1m of full pile, meanwhile, Extravasating hole is processed in fault location, extravasating hole is in quincuncial arrangement, and per 4 extravasating holes of pile, aperture is 100mm;
Drilling 12 localization method be:
When stake footpath is 1m, five summits into regular pentagon distribution centered on the stake heart, each summit are chosen in pile foundation upper end Distance to the stake heart is 0.31m, and five selected summits are five centers of circle of drilling 12;
When stake footpath is 1.2m, three summits and into positive four into equilateral triangle distribution centered on the stake heart are chosen in pile foundation upper end Four summits of side shape distribution, in three summits of equilateral triangle distribution, each summit is 0.25m to the distance of the stake heart, just In four summits of quadrangle distribution, each summit to the distance of the stake heart is 0.25m, and 7 selected summits are 7 brills The center of circle in hole 12;
When stake footpath is 1.4m, eight summits into octagon distribution centered on the stake heart are chosen in pile foundation upper end, each top Point is 0.51m to the distance of the stake heart, and eight selected summits are eight centers of circle of drilling 12;
When stake footpath is 1.8m, eight summits and into positive seven into octagon distribution centered on the stake heart are chosen in pile foundation upper end Seven summits of side shape distribution, in eight summits of octagon distribution, each summit is 0.61m to the distance of the stake heart, just In seven summits of heptagon distribution, each summit to the distance of the stake heart is 0.30m, and 15 selected summits are 15 The center of circle of drilling 12;
When stake footpath is 1.6m, 2.0m and 2.2m, the two composition octagon distributions centered on the stake heart are chosen in pile foundation upper end Eight summits, 16 selected summits be 16 drilling 12 the centers of circle, stake footpath be 1.6m when, one of which octagon In, each summit to the distance of the stake heart is 0.30m, and in another group of octagon, each summit is to the distance of the stake heart 0.61m;When stake footpath is 2.0m, in one of which octagon, each summit to the distance of the stake heart is 0.50m, and another group just In octagon, each summit is 0.81m to the distance of the stake heart;When stake footpath is 2.2m, in one of which octagon, each top Point is 0.508m to the distance of the stake heart, and in another group of octagon, each summit is 0.91m to the distance of the stake heart.
Step 2 high pressure clear water rotary spray wash:Put down high-pressure injector respectively from each hole, control high-pressure injection Device up and down reciprocatingly carries out high-pressure rotary injection cutting cleaning, sprays pressure 20-26MPa, discharge capacity 70-90L/min, rotary speed 20r/min, lifts speed 10cm/min, and cutting clean range respectively increases 0.5m up and down from defective section, and a hole is cleaned and another When one hole has water to overflow, show that rejected region has been got through, shift to other holes, until pile foundation upper end drilling 12 is all got through, then, Press-in clear water, using water circulation just waste residue discharge pile body, when delivery port water by it is turbid become clear when, then change other holes and locate in turn Reason, until when all of pile foundation upper end drilling current are all clear water, cutting cleaning terminates;
Step 3 installs steel-pipe pile 2:Steel-pipe pile 2 is vertically put into the drilling 12 being drilled, steel-pipe pile is by after defect area Complete pile body at least 1m is inserted, the reinforcing bar 22 on steel-pipe pile 2 need to anchor into cushion cap 3, need inner sleeve to carry out if length is more long Connecting welding, steel pipe pile body is advisable with without faying surface;
Step 4 apertures mud jacking:After cutting cleaning terminates, carried out at mud jacking by the extravasating hole got out on former pile defect Reason, slip casting raw material is cement mortar, and cement mortar uses strength grade to be formulated with clear water for 42.5 portland cement, cement mortar The liquid ratio of mud 1 ~ 1.2, slurries are prepared by first dilute rear dense principle, then add waterproofing agent by the 1% of the water amount of using with, to increase cement The workability and mobility of slurry, leave test specimen sampling when preparing cement slurry, preparing liquid and additive will ensure quality, and at any time Measurement dress liquor ratio weight, it is ensured that concentration of slurry reaches design requirement, slurries should be by 14*14 ~ 18*18 mesh sieves hole, in order to avoid be mixed into water Mud bag bits or other debris, preparing dress liquid should be finished within the presetting period.
High-pressure injection is repeated in the range of defective section with water under high pressure slurry liquid, make the rubble of each stake defective section, rock, in Coarse sand is thoroughly mixed with cement grout, and grouting pressure is according to the foundation strength of supporting course and the compression strength of concrete piles It is fixed, the foundation strength of supporting course and the compression strength of concrete piles need to be less than, by taking embedded rock pile as an example, filling pressure is 7-10MPa, pressure Dress stabilization time is 8-12min, and during the bored grouting of pile foundation upper end, by other hole plugs, grouting pressure increases 2-3MPa, voltage stabilizing After 5min, judged whether to stop slip casting according to mud jacking resistance;Or when grout in other holes, stop slip casting.

Claims (10)

1. a kind of steel pipe reinforces the construction method of piling strtucture, it is characterised in that comprise the following steps:
Step one, positioning drillings:Determine drilling hole position in the upper end of pile foundation, rig is moved to and drilled in hole position, bore always Untill proceeding to the super 1m of full pile, meanwhile, process extravasating hole in fault location;
Step 2 high pressure clear water rotary spray wash:High-pressure injector is put down respectively from each hole, on control high-pressure injector High-pressure rotary injection cutting cleaning is back and forth carried out down, pressure 20-26MPa is sprayed, and cutting clean range respectively increases up and down from defective section Plus 0.5m, until the drilling of pile foundation upper end is all got through, then, press-in clear water is using water circulation just waste residue discharge pile body;
Step 3 installs steel-pipe pile:Steel-pipe pile includes seamless steel pipe and the reinforcing bar being arranged in steel pipe, and perfusion is micro- swollen in steel pipe Swollen cement mortar, the steel-pipe pile extexine for processing carries out antirust treatment, steel-pipe pile is vertically put into the drilling being drilled, steel pipe By inserting complete pile body at least 1m after defect area, the reinforcing bar on steel-pipe pile need to anchor into cushion cap no less than 35d for stake;
Step 4 apertures mud jacking:After cutting cleaning terminates, carried out at mud jacking by the extravasating hole got out on former pile defect Reason.
2. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:It is high in step 2 Jet pipe discharge capacity 70-90L/min, the rotary speed 10-28r/min of injector are pressed, speed 10-15cm/min is lifted, a hole is carried out Cleaning and another Kong Youshui overflow when, show that rejected region has been got through, shift to other holes, until pile foundation upper end drilling all beat It is logical.
3. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:In step 2, stake After being connected between the drilling of base upper end, clear water is pressed into, using water circulation just waste residue discharge pile body, when the water of delivery port becomes clear by turbid When, then other holes wheel stream process are changed, until when all of pile foundation upper end drilling current are all clear water, cutting cleaning terminates.
4. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:In step 3, pipe Piling bar is by external diameter 127mm, the seamless steel pipe of wall thickness 6mm and a reinforcing bar composition of C HRB400 a diameter of 25, and interior perfusion M35 is micro- Expansive cement mortar, the steel-pipe pile extexine brushing red lead anti-corrosive paint for processing.
5. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:Note in step 4 Slurry raw material is cement mortar, and cement mortar uses strength grade to be formulated with clear water for 42.5 portland cement, cement grout water Gray scale 1 ~ 1.2, prepares slurries, then add waterproofing agent by the 1% of the water amount of using with by first dilute rear dense principle.
6. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:In step 4, use Water under high pressure slurry liquid is repeated high-pressure injection in the range of defective section, makes rubble, rock, medium coarse sand and the cement of each stake defective section Slurries are thoroughly mixed, depending on grouting pressure is according to the foundation strength of supporting course and the compression strength of concrete piles, pile foundation upper end During bored grouting, by other hole plugs, grouting pressure increases 2-3MPa, after voltage stabilizing 5min, judges whether to stop according to mud jacking resistance Only slip casting;Or when grout in other holes, stop slip casting.
7. a kind of steel pipe reinforces the construction method of piling strtucture according to claim 1, it is characterised in that:In step one, bore Hole localization method is:
When stake footpath is 1m, five summits into regular pentagon distribution centered on the stake heart, each summit are chosen in pile foundation upper end Distance to the stake heart is 0.31m, and five selected summits are five centers of circle of drilling;
When stake footpath is 1.2m, three summits and into positive four into equilateral triangle distribution centered on the stake heart are chosen in pile foundation upper end Four summits of side shape distribution, in three summits of equilateral triangle distribution, each summit is 0.25m to the distance of the stake heart, just In four summits of quadrangle distribution, each summit to the distance of the stake heart is 0.25m, and 7 selected summits are 7 brills The center of circle in hole;
When stake footpath is 1.4m, eight summits into octagon distribution centered on the stake heart are chosen in pile foundation upper end, each top Point is 0.51m to the distance of the stake heart, and eight selected summits are eight centers of circle of drilling;
When stake footpath is 1.8m, eight summits and into positive seven into octagon distribution centered on the stake heart are chosen in pile foundation upper end Seven summits of side shape distribution, in eight summits of octagon distribution, each summit is 0.61m to the distance of the stake heart, just In seven summits of heptagon distribution, each summit to the distance of the stake heart is 0.30m, and 15 selected summits are 15 The center of circle of drilling;
When stake footpath is 1.6m, 2.0m and 2.2m, the two composition octagon distributions centered on the stake heart are chosen in pile foundation upper end Eight summits, 16 selected summits be 16 drilling the centers of circle, stake footpath be 1.6m when, one of which octagon In, each summit to the distance of the stake heart is 0.30m, and in another group of octagon, each summit is to the distance of the stake heart 0.61m;When stake footpath is 2.0m, in one of which octagon, each summit to the distance of the stake heart is 0.50m, and another group just In octagon, each summit is 0.81m to the distance of the stake heart;When stake footpath is 2.2m, in one of which octagon, each top Point is 0.508m to the distance of the stake heart, and in another group of octagon, each summit is 0.91m to the distance of the stake heart.
8. a kind of steel pipe reinforces piling strtucture, including the pile foundation body (1) with defect area (11), it is characterised in that:Pile foundation sheet Vertically offers drilling (12) in body (1), drilling (12) is interior to be provided with steel-pipe pile (2), steel-pipe pile (2) is through defect area , and the upper and lower ends of steel-pipe pile (2) extend defect area (11) upper and lower ends complete pile foundation at least 1m, steel-pipe pile (2) respectively (11) Including seamless steel pipe (21) and the reinforcing bar (22) being arranged in seamless steel pipe (21), lead between seamless steel pipe (21) and reinforcing bar (22) Cross and pour micro-expansion cement mortar (23) fixation.
9. a kind of steel pipe reinforces piling strtucture according to claim 8, it is characterised in that:The top construction of pile foundation body (1) There is cushion cap (3), the upper end of reinforcing bar (22) anchors into cushion cap (3) no less than 35d in steel-pipe pile (2).
10. a kind of steel pipe reinforces piling strtucture according to claim 8, it is characterised in that:The specification of seamless steel pipe (21) is External diameter 127mm, wall thickness 6mm, the specification of reinforcing bar (22) is a diameter of 25mm of C HRB400, and the microdilatancy of M35 is irrigated therebetween Cement mortar (23), steel-pipe pile (2) extexine is painted with red lead anti-corrosive paint.
CN201611168099.1A 2016-12-16 2016-12-16 A kind of steel pipe reinforces piling strtucture and its construction method Pending CN106759559A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611168099.1A CN106759559A (en) 2016-12-16 2016-12-16 A kind of steel pipe reinforces piling strtucture and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611168099.1A CN106759559A (en) 2016-12-16 2016-12-16 A kind of steel pipe reinforces piling strtucture and its construction method

Publications (1)

Publication Number Publication Date
CN106759559A true CN106759559A (en) 2017-05-31

Family

ID=58892166

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611168099.1A Pending CN106759559A (en) 2016-12-16 2016-12-16 A kind of steel pipe reinforces piling strtucture and its construction method

Country Status (1)

Country Link
CN (1) CN106759559A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853538A (en) * 2018-12-12 2019-06-07 湖南化工地质工程勘察院有限责任公司 Cast-in-place concrete pile pile foundation reinforcing structure and its construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006336294A (en) * 2005-06-02 2006-12-14 Fujita Corp Reinforcing method of pile head section
CN103437351A (en) * 2013-09-18 2013-12-11 浙江省岩土基础公司 Treatment method of deviation and fracture remediation of pile body of filling pile
CN103541359A (en) * 2013-09-18 2014-01-29 浙江省岩土基础公司 Method for repairing and treating quality defect of cast-in-place pile
CN203878590U (en) * 2014-05-14 2014-10-15 江苏南通三建集团有限公司 Post-reinforcement structure for cast-in-place piles
CN206319347U (en) * 2016-12-16 2017-07-11 中建四局第一建筑工程有限公司 A kind of steel pipe reinforces piling strtucture

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006336294A (en) * 2005-06-02 2006-12-14 Fujita Corp Reinforcing method of pile head section
CN103437351A (en) * 2013-09-18 2013-12-11 浙江省岩土基础公司 Treatment method of deviation and fracture remediation of pile body of filling pile
CN103541359A (en) * 2013-09-18 2014-01-29 浙江省岩土基础公司 Method for repairing and treating quality defect of cast-in-place pile
CN203878590U (en) * 2014-05-14 2014-10-15 江苏南通三建集团有限公司 Post-reinforcement structure for cast-in-place piles
CN206319347U (en) * 2016-12-16 2017-07-11 中建四局第一建筑工程有限公司 A kind of steel pipe reinforces piling strtucture

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853538A (en) * 2018-12-12 2019-06-07 湖南化工地质工程勘察院有限责任公司 Cast-in-place concrete pile pile foundation reinforcing structure and its construction method

Similar Documents

Publication Publication Date Title
CN104594348B (en) Enlarged footing bellows anchor pole and construction method thereof
CN101638891B (en) Construction method of all casing precessing isolation pile
CN103437351B (en) Treatment method of deviation and fracture remediation of pile body of filling pile
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN104831734B (en) A kind of deep basal pit building rotary churning pile Composition Soil Nailing Walls construction method
CN104818991A (en) Construction method of residual slope wash tunnel with shallow cover and unsymmetrical pressure
CN207362897U (en) For shale layer anti-float anchor rod, rope can churning hole flushing umbrella steel reinforcement cage enlarged footing
CN108951612A (en) A kind of subway tunnel shield end reinforcement means
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN102943466A (en) Construction method for miniature steel pipe concrete pile to penetrate through roadbed layer for reinforcing soft foundation construction
CN206015669U (en) Pile foundation reinforcement system based on reinforcement synthesis pillared clay
CN103215953A (en) Construction method of anti-floating anchor in super-large super-deep basement engineering
CN107816324A (en) A kind of tiltedly steel-pipe pile borehole cleaning and the construction method and system for reducing sediment thickness
CN101333815B (en) Concrete anchor rod and its construction method
CN205329689U (en) Lower part enlarges compound stock of section pressure type
CN106759311A (en) A kind of defect of pile foundation injecting treatment method under complex geological condition
CN106677168A (en) Construction method of cast-in-place superfluid concrete pile
CN109113087A (en) Hole pile water stopping curtain integral structure and its construction technology
CN206319347U (en) A kind of steel pipe reinforces piling strtucture
CN103147707B (en) Complete treatment method for pile bottom sediment
CN106759559A (en) A kind of steel pipe reinforces piling strtucture and its construction method
CN211713954U (en) Cast-in-situ bored pile in deep fine sand stratum
CN101514549B (en) Method using intermediate mixing piles for treating three-layer soft foundation
CN109854281A (en) The method for protecting support of the lower rock compound cross-section stratum jacking construction of upper soil
CN110344418A (en) The structure and its construction technology of support system in a kind of deep basal pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531

RJ01 Rejection of invention patent application after publication