CN106759388A - 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构 - Google Patents

一种浆体干法赤泥堆场构筑堆积坝的方法及其结构 Download PDF

Info

Publication number
CN106759388A
CN106759388A CN201710078586.7A CN201710078586A CN106759388A CN 106759388 A CN106759388 A CN 106759388A CN 201710078586 A CN201710078586 A CN 201710078586A CN 106759388 A CN106759388 A CN 106759388A
Authority
CN
China
Prior art keywords
red mud
dam
filter cake
dry
slurry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710078586.7A
Other languages
English (en)
Inventor
王胜安
杨小全
陈善应
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN201710078586.7A priority Critical patent/CN106759388A/zh
Publication of CN106759388A publication Critical patent/CN106759388A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Treatment Of Sludge (AREA)

Abstract

本发明公开了一种浆体干法赤泥堆场构筑堆积坝的方法及其结构,是在浆体赤泥堆场初期坝(3)坝体外侧设置赤泥滤饼压滤车间(1);浆体赤泥堆场构筑堆积坝(2)前,先在初期坝(3)坝体内侧抛填块石料或回填滤饼干赤泥构筑基础(4);堆积坝(2)、坝坡稳定安全区域6和干赤泥滤饼堆存区域7均采用赤泥滤饼压滤车间(1)生产的滤饼干赤泥构筑,堆筑时赤泥表面均坡向堆场内调洪池(5)方向,坡度i不小于1%;浆体赤泥堆场除堆积坝(2)、坝坡稳定安全区域6和干赤泥滤饼堆存区域7外的其他区域采用浆体赤泥排放方式,浆体赤泥排放区域(8)堆存标高应始终低于滤饼干赤泥堆存区域并满足国家相关规范要求的赤泥堆场调洪要求。本发明可有效解决浆体干法赤泥堆场堆积坝筑坝困难、筑坝时间长、干滩范围内容易积水而不满足国家相关规范要求等问题。

Description

一种浆体干法赤泥堆场构筑堆积坝的方法及其结构
技术领域
本发明属于氧化铝生产中的赤泥堆存技术领域,具体涉及一种浆体干法赤泥堆场构筑堆积坝的方法及其结构。
背景技术
赤泥是用碱从铝土矿中提取氧化铝后的固体残渣,在赤泥还不能大量利用的情况下,必须建设赤泥堆场将赤泥集中堆存。目前国内新建赤泥堆场普遍采用的堆存工艺为浆体干法堆存或滤饼干法堆存工艺。
浆体干法赤泥堆存工艺流程为:多次洗涤后经沉降槽分离的赤泥浆固体含量在30%~40%左右,再经进一步脱水,使固体含量提高到55%左右,赤泥浆体用隔膜泵经管道送到赤泥堆场。赤泥附液一部分经表面蒸发,另一部分通过排水系统排出堆场。
滤饼干法赤泥堆存工艺流程为:将赤泥过滤到固体含量67%左右后,将滤饼用汽车运送到堆场堆存。干法堆存工艺滤饼赤泥含水量低,经简单晾晒后即具有较好的力学强度,可用于赤泥堆积坝筑坝,但此方法存在运行费用相对较高的缺点。
浆体赤泥堆场初期坝范围即将堆满之前,需构筑堆积坝以满足继续堆存赤泥要求。现浆体赤泥堆场构筑堆积坝的传统方法为:采用浆体赤泥堆场内翻晒后的干赤泥上游法筑坝,但此方法存在晾晒面积过大、堆场内干赤泥往往不能满足筑坝要求的缺点。
发明内容
本发明的目的是提供一种浆体干法赤泥堆场构筑堆积坝的方法及其结构,以解决浆体干法赤泥堆场堆积坝筑坝困难、筑坝时间长、干滩范围内容易积水而不满足国家相关规范要求等问题。
本发明的技术方案是这样的:
本发明的一种浆体干法赤泥堆场构筑堆积坝的方法,是在浆体赤泥堆场旁初期坝外侧设置赤泥滤饼压滤车间;浆体赤泥堆场构筑堆积坝时,先在初期坝坝前抛填块石料或回填滤饼干赤泥构筑基础;堆积坝及赤泥堆场干滩长度区域均采用赤泥滤饼压滤车间生产的滤饼干赤泥构筑,堆筑时赤泥表面均坡向堆场内调洪池方向,坡度i不小于1%;浆体赤泥堆场除干赤泥滤饼堆存区域外的其他区域采用浆体赤泥排放方式,浆体赤泥排放区域堆存标高应始终低于滤饼干赤泥堆存区域并满足国家相关规范要求的赤泥堆场调洪要求。
其中,干赤泥滤饼填筑时分层、分区域进行压实,赤泥堆积坝及坝坡稳定安全区域赤泥压实度要求≥0.95,其余干赤泥滤饼堆存区域压实度≥0.92。
基于上述方法,本发明的一种浆体干法赤泥堆场构筑堆积坝的结构,包括浆体赤泥堆场的初期坝,初期坝旁设有用于生产滤饼干赤泥的赤泥滤饼压滤车间,初期坝在堆场内一侧设有浆体赤泥排放区域;初期坝(3)前干滩范围内的浆体赤泥排放区域之上设有块石料或滤饼干赤泥构筑而成的基础,基础之上设有由滤饼干赤泥构筑而成的堆积坝;堆积坝在堆场内一侧设有赤泥堆场干滩长度区域,赤泥堆场干滩长度区域包括前后相继用滤饼干赤泥构筑的坝坡稳定安全区域和干赤泥滤饼堆存区域;浆体赤泥排放区域(8)内设有堆场内调洪池。
其中,坝坡稳定安全区域和干赤泥滤饼堆存区域的结合部采用阶梯结构错层连接。
本发明能在较短时间内构筑浆体赤泥堆场堆积坝及干滩,显著提高坝体稳定性,保证了浆体赤泥堆场干滩的形成,有利于浆体赤泥堆场安全,可有效解决浆体干法赤泥堆场堆积坝筑坝困难、筑坝时间长、干滩范围内容易积水而不满足国家相关规范要求等问题。
附图说明
图1是本发明的结构示意图。
附图中的标记为:1-赤泥滤饼压滤车间,2-堆积坝,3-初期坝,4-基础,5-调洪池,6-坝坡稳定安全区域,7-干赤泥滤饼堆存区域,8-浆体赤泥排放区域。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明。
如图1所示,本发明的浆体干法赤泥堆场构筑堆积坝的结构是这样的,包括浆体赤泥堆场的初期坝3,初期坝3内侧设有滤饼干赤泥填筑的堆积坝2,初期坝3外侧设有用于生产滤饼干赤泥的赤泥滤饼压滤车间1,初期坝3及干赤泥滤饼堆存区域7内侧设有浆体赤泥排放区域8;初期坝3坝前干滩范围内的浆体赤泥排放区域8之上设有块石料或滤饼干赤泥构筑而成的基础4,基础4之上设有由滤饼干赤泥构筑而成的堆积坝2;堆积坝2内侧设有赤泥堆场干滩长度区域,赤泥堆场干滩长度区域包括前后相继用滤饼干赤泥构筑的坝坡稳定安全区域6和干赤泥滤饼堆存区域7;浆体赤泥排放区域8内设有堆场内调洪池5。坝坡稳定安全区域6和干赤泥滤饼堆存区域7的结合部采用阶梯结构错层连接。
本发明按照如下步骤实施:
步骤一,先在浆体赤泥堆场初期坝3坝体外侧设置赤泥滤饼压滤车间1,其产能需能满足干赤泥滤饼堆存量;
步骤二,浆体赤泥堆场构筑堆积坝2时,先在初期坝3坝体内侧抛填块石料或回填滤饼干赤泥构筑基础4,基础压实度要求≥0.95;
步骤三,堆积坝2、坝坡稳定安全区域6和干赤泥滤饼堆存区域7均采用滤饼干赤泥构筑,堆筑时赤泥表面均坡向堆场内调洪池5方向,坡度i为1%;
步骤四,干赤泥滤饼填筑时应分层、分区域进行压实,碾压时每层赤泥厚度不大于1m,赤泥滤饼土工含水率为最佳含水率±2%,赤泥堆积坝2及坝坡稳定安全区域6赤泥压实度要求≥0.95,其余干赤泥滤饼堆存区域7压实度≥0.92;
步骤五,浆体赤泥堆场除干赤泥滤饼堆存区域外的其他区域仍采用浆体赤泥排放方式。
当然,以上只是本发明的具体应用范例,本发明还有其他的实施方式,凡采用等同替换或等效变换形成的技术方案,均落在本发明所要求的保护范围之内。

Claims (4)

1.一种浆体干法赤泥堆场构筑堆积坝的方法,其特征在于:在浆体赤泥堆场内浆体赤泥将堆满至初期坝(3)坝顶时,先在初期坝(3)坝体外侧设置赤泥滤饼压滤车间(1);浆体赤泥堆场构筑堆积坝(2)前,先在初期坝(3)坝体内侧抛填块石料或回填滤饼干赤泥构筑基础(4);堆积坝(2)及赤泥堆场干滩长度区域(国家相关规范要求的长度范围)均采用赤泥滤饼压滤车间(1)生产的滤饼干赤泥构筑,堆筑时赤泥表面均坡向堆场内调洪池(5)方向,坡度i不小于1%;浆体赤泥堆场除干赤泥滤饼堆存区域外的其他区域采用浆体赤泥排放方式,浆体赤泥排放区域(8)堆存标高应始终低于滤饼干赤泥堆存区域并满足堆场调洪要求。
2.根据权利要求1所述的浆体干法赤泥堆场构筑堆积坝的方法,其特征在于:干赤泥滤饼填筑时分层、分区域进行压实,赤泥堆积坝(2)及坝坡稳定安全区域(6)(国家相关规范要求的长度范围)赤泥压实度要求≥0.95,其余干赤泥滤饼堆存区域(7)压实度≥0.92。
3.一种浆体干法赤泥堆场构筑堆积坝的结构,其特征在于:包括浆体赤泥堆场的初期坝(3),初期坝(3)坝体内侧设置滤饼干赤泥堆积坝(2),初期坝(3)坝体外侧设有用于生产滤饼干赤泥的赤泥滤饼压滤车间(1),初期坝(3)在坝体内侧设有浆体赤泥排放区域(8);初期坝(3)坝前干滩范围内的浆体赤泥排放区域(8)之上设有块石料或滤饼干赤泥构筑而成的基础(4),基础(4)之上设有由滤饼干赤泥构筑而成的堆积坝(2);堆积坝(2)在堆场内一侧设有赤泥堆场干滩长度区域,赤泥堆场干滩长度区域包括前后相继用滤饼干赤泥构筑的坝坡稳定安全区域(6)和干赤泥滤饼堆存区域(7);浆体赤泥排放区域(8)内设有堆场调洪池(5)。
4.根据权利要求3所述的浆体干法赤泥堆场构筑堆积坝的结构,其特征在于:所述坝坡稳定安全区域(6)和干赤泥滤饼堆存区域(7)的结合部采用阶梯结构错层连接。
CN201710078586.7A 2017-02-14 2017-02-14 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构 Pending CN106759388A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710078586.7A CN106759388A (zh) 2017-02-14 2017-02-14 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710078586.7A CN106759388A (zh) 2017-02-14 2017-02-14 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构

Publications (1)

Publication Number Publication Date
CN106759388A true CN106759388A (zh) 2017-05-31

Family

ID=58956977

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710078586.7A Pending CN106759388A (zh) 2017-02-14 2017-02-14 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构

Country Status (1)

Country Link
CN (1) CN106759388A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740428A (zh) * 2017-09-08 2018-02-27 瓮福达州化工有限责任公司 一种堆积坝结构及其筑坝工艺
CN109020142A (zh) * 2018-08-27 2018-12-18 三门峡义翔铝业有限公司 一种基于湿式库区的赤泥干式堆存结构及工艺
CN109930622A (zh) * 2018-12-29 2019-06-25 贵阳铝镁设计研究院有限公司 一种火力发电厂石膏作为灰场堆积坝坝基的构筑方法
CN111042152A (zh) * 2019-12-18 2020-04-21 瓮福(集团)有限责任公司 一种湿法堆存磷石膏库的堆积坝筑坝方法
CN111593742A (zh) * 2020-05-27 2020-08-28 四川会东大梁矿业有限公司 一种基于抛石挤淤法整改尾矿库的施工方法
CN112982612A (zh) * 2021-03-02 2021-06-18 金建工程设计有限公司 一种平地型赤泥堆场及其排放方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4270875A (en) * 1978-04-24 1981-06-02 Nippon Light Metal Company Limited Method of creating landfill from red mud
CN101838992A (zh) * 2010-06-23 2010-09-22 贵阳铝镁设计研究院 一种山谷型湿法赤泥堆场进行干法增容的方法
CN102102367A (zh) * 2009-12-16 2011-06-22 贵阳铝镁设计研究院 一种用三水铝矿生产氧化铝产生的赤泥为材料的堆场堤坝结构
CN103397645A (zh) * 2013-07-22 2013-11-20 中钢集团马鞍山矿山研究院有限公司 一种干堆与湿排相结合的尾矿堆排方法
CN105696543A (zh) * 2014-11-25 2016-06-22 贵阳铝镁设计研究院有限公司 一种赤泥堆场构筑子坝时坝前排渗的方法
CN206986906U (zh) * 2017-02-14 2018-02-09 贵阳铝镁设计研究院有限公司 一种浆体干法赤泥堆场构筑堆积坝的结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4270875A (en) * 1978-04-24 1981-06-02 Nippon Light Metal Company Limited Method of creating landfill from red mud
CN102102367A (zh) * 2009-12-16 2011-06-22 贵阳铝镁设计研究院 一种用三水铝矿生产氧化铝产生的赤泥为材料的堆场堤坝结构
CN101838992A (zh) * 2010-06-23 2010-09-22 贵阳铝镁设计研究院 一种山谷型湿法赤泥堆场进行干法增容的方法
CN103397645A (zh) * 2013-07-22 2013-11-20 中钢集团马鞍山矿山研究院有限公司 一种干堆与湿排相结合的尾矿堆排方法
CN105696543A (zh) * 2014-11-25 2016-06-22 贵阳铝镁设计研究院有限公司 一种赤泥堆场构筑子坝时坝前排渗的方法
CN206986906U (zh) * 2017-02-14 2018-02-09 贵阳铝镁设计研究院有限公司 一种浆体干法赤泥堆场构筑堆积坝的结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王海超: "赤泥滤饼干法堆存工艺探讨", 《有色冶金设计与研究》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107740428A (zh) * 2017-09-08 2018-02-27 瓮福达州化工有限责任公司 一种堆积坝结构及其筑坝工艺
CN109020142A (zh) * 2018-08-27 2018-12-18 三门峡义翔铝业有限公司 一种基于湿式库区的赤泥干式堆存结构及工艺
CN109930622A (zh) * 2018-12-29 2019-06-25 贵阳铝镁设计研究院有限公司 一种火力发电厂石膏作为灰场堆积坝坝基的构筑方法
CN111042152A (zh) * 2019-12-18 2020-04-21 瓮福(集团)有限责任公司 一种湿法堆存磷石膏库的堆积坝筑坝方法
CN111593742A (zh) * 2020-05-27 2020-08-28 四川会东大梁矿业有限公司 一种基于抛石挤淤法整改尾矿库的施工方法
CN112982612A (zh) * 2021-03-02 2021-06-18 金建工程设计有限公司 一种平地型赤泥堆场及其排放方法

Similar Documents

Publication Publication Date Title
CN106759388A (zh) 一种浆体干法赤泥堆场构筑堆积坝的方法及其结构
CN103708703B (zh) 一种建筑泥浆快速深度脱水及资源化系统与工艺
CN102817348B (zh) 新近吹填淤泥地基处理方法
US4270875A (en) Method of creating landfill from red mud
CN206986906U (zh) 一种浆体干法赤泥堆场构筑堆积坝的结构
CN103397645A (zh) 一种干堆与湿排相结合的尾矿堆排方法
CN100453189C (zh) 一种赤泥的堆存方法
CN102817354A (zh) 吹填加固并举的疏浚软土地基处理方法
CN100534935C (zh) 一种拜耳法赤泥干法堆场的子坝构筑方法
CN100347107C (zh) 氧化铝厂赤泥和灰渣干法处置的方法
JP2012143702A (ja) 濁水処理システムおよび濁水処理方法
Theriault et al. Surface disposal of past tailings at the Bulyanhulu gold mine, Tanzania
CN109824290B (zh) 一种工程弃土再生骨料的生产方法
IE48409B1 (en) Process for the disposal of bauxite processing waste and a containment basin for waste
CN207091266U (zh) 一种废渣污泥处理装置
CN110183074B (zh) 一种河道清淤方法
WO2009018719A1 (fr) Procédé de construction de digue de boues rouges perméables provenant d'un procédé de frittage
CN103539330A (zh) 淤泥堆场层叠式淤泥干化法
CN116290182A (zh) 中型船载式移动绞吸与自动压滤淤泥系统及河道清淤工艺
CN111549601B (zh) 过湿软土用于道路路基填料的快速脱水装置及脱水方法
CN102489073A (zh) 一种使用离心和板框的清淤泥浆快速脱水的施工方法
CN101164925B (zh) 烧结法赤泥、拜尔法赤泥混合筑坝方法
CN210419687U (zh) 一种海淤泥资源化利用系统
CA1108319A (en) Disposal of thixotropic muds
CN102409684B (zh) 赤泥混合自凝干法堆场筑坝方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170531