CN106759365B - A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall - Google Patents

A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall Download PDF

Info

Publication number
CN106759365B
CN106759365B CN201611205972.XA CN201611205972A CN106759365B CN 106759365 B CN106759365 B CN 106759365B CN 201611205972 A CN201611205972 A CN 201611205972A CN 106759365 B CN106759365 B CN 106759365B
Authority
CN
China
Prior art keywords
foundation pit
wall
steel
wing wall
enclosure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611205972.XA
Other languages
Chinese (zh)
Other versions
CN106759365A (en
Inventor
黄海云
林靖
钱玉奇
马永平
张燕
俞梅欣
周科
王晓冬
李坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN201611205972.XA priority Critical patent/CN106759365B/en
Publication of CN106759365A publication Critical patent/CN106759365A/en
Application granted granted Critical
Publication of CN106759365B publication Critical patent/CN106759365B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of counterfort wing wall waterproof curtain construction methods of foundation pit enclosure wall to specifically include its main feature is that foundation pit enclosure wall uses steel-pipe pile and steel sheet pile assembled wall for the water stop curtain structure of buttress type wing wall:The sealing construction of foundation pit enclosure, excavation of foundation pit and wing wall bottom plate and enclosure wall, after the completion of foundation pit and wing wall bottom plate, it removes the support of foundation pit second and encloses order, then the backfilling of earthwork constructed on rear side of counterfort panel and floor and buttress type wing wall, finally by first of supporting removal of foundation pit, the enclosure wall of foundation pit is then the permanent leaking water curtain structure of buttress type wing wall.The features such as present invention has structure simple compared with prior art, and project cost is low, easy for construction, and construction quality is reliable is particularly suitable for the water-stop curtain using foundation pit support method construction buttress type wing wall.

Description

A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall
Technical field
The present invention relates to dock engineering technical field, a kind of especially a kind of foundation pit enclosure wall suitable for building dock Counterfort wing wall waterproof curtain construction method.
Background technique
Currently, the water-stop curtain of the buttress type wing wall for dock engineering, common pattern have single steel sheet pile, single company Continuous overlapped high-pressure rotary jet grouting pile, or common grout curtain pattern etc. in batholith.Since the water-stop curtain of these patterns is logical Be with interim curtain needed for excavation of foundation pit often separate, once after dock engineering, setting when also removing excavation of foundation pit Temporary leaking water curtain.
The Water sealing in dock curtain of the prior art is built, long construction period, and project cost is high, not only increase engineering cost and Labour, but also waste a large amount of construction material.
Summary of the invention
The purpose of the present invention is in view of the deficiencies of the prior art and the counterfort wing wall of a kind of foundation pit enclosure wall that designs stops Water curtain construction method, the foundation pit enclosure wall for using steel-pipe pile to combine with steel sheet pile is the sealing curtain of excavation of foundation pit and counterfort wing wall Curtain structure saves a large amount of construction materials, substantially reduces and apply so that excavation of foundation pit does not have to reset one of temporary leaking water curtain The work period reduces project cost, and simple and reasonable for structure, sealing performance has fully met the requirement of dock buttress type wing wall, reliably Property it is high.
The object of the present invention is achieved like this:A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall, Its main feature is that foundation pit enclosure wall uses steel-pipe pile and steel sheet pile assembled wall for the water stop curtain structure of buttress type wing wall, it is specific Construction carries out in the steps below:
(One)Foundation pit enclosure
The enclosure wall that foundation pit enclosure is composed using steel-pipe pile and steel sheet pile, the enclosure wall by steel sheet pile two sides with Half steel sheet pile steel-pipe pile adjacent thereto is welded;Half steel sheet pile side is connect by fore shaft with steel sheet pile, another Side and steel-pipe pile weld;The steel-pipe pile bottom application work piles set into rock, bored concrete pile one end insertion in weathered rock formation, the other end It protrudes into the steel pipe of steel pipe pile bottom.
(Two)Excavation of foundation pit
It is supported in first of foundation pit for going along with sb. to guard him the top beam of coping construction reinforced bar concrete and being connect with top beam, Then the earth excavation in foundation pit is carried out, enclosing for the second armored concrete in the middle part of enclosure wall of then constructing is enabled and enabled with enclosing The foundation pit second of connection supports, and continues the earth excavation in foundation pit.
(Three), wing wall bottom plate and enclosure wall sealing
Construction wing wall bottom plate after earth excavation to designed elevation, and the enclosure wall of wing wall floor rear and foundation pit is used and is stopped Water steel plate carries out the patching that node connects with anchor bar, and the steel plate for sealing water is that one end is bonded retaining wall and and steel plate Stake and steel-pipe pile welding, the other end are then anchored in the deformed steel flats in wing wall bottom plate;Described anchor bar one end is welded in steel pipe In stake or steel sheet pile, the other end is anchored in wing wall bottom plate.
(Four), foundation pit backfill
After the completion of base pit engineering and bottom slab, removes the support of foundation pit second and enclose order, then construct counterfort panel and rib Backfilling of earthwork on rear side of plate and buttress type wing wall, finally by first of supporting removal of foundation pit, the enclosure wall of foundation pit is then to help The permanent leaking water curtain structure of wall type wing wall.
The present invention has structure simple compared with prior art, and project cost is low, easy for construction, and construction quality reliably waits spies Point is particularly suitable for the water-stop curtain using foundation pit support method construction buttress type wing wall.
Detailed description of the invention
Fig. 1 is schematic structural view of the invention;
Fig. 2 is assembled wall structural schematic diagram;
Fig. 3 is the A node enlarged diagram of Fig. 1;
Fig. 4 is the B-B the schematic diagram of the section structure of Fig. 3.
Specific embodiment
Refering to attached drawing 1, the present invention is made of buttress type wing wall 1 and foundation pit enclosure wall 2, and the foundation pit enclosure wall 2 uses steel Tubular pole 11 and 13 assembled wall of steel sheet pile are the water stop curtain structure of buttress type wing wall 1;At the top of the foundation pit enclosure wall 2 be equipped with The top beam 5 of first of foundation pit support, 6 connection, middle part enable 7 equipped with enclosing for connecting with foundation pit second support 8;The buttress type The wing wall bottom plate 9 of wing wall 1 is connect by steel plate for sealing water 15 with the assembled wall of steel-pipe pile 11 and steel sheet pile 13;11 bottom of steel-pipe pile Portion is equipped with bored concrete pile 4, weathered rock formation in the insertion of 4 one end of bored concrete pile, and the other end is embedded in 11 bottoms of steel-pipe pile.
Refering to attached drawing 2, the steel-pipe pile 11 is with 13 assembled wall of steel sheet pile by 13 two sides of steel sheet pile with half steel sheet pile 12 Steel-pipe pile 11 adjacent thereto is welded, and 12 side of half steel sheet pile is connect by fore shaft 14 with steel sheet pile 13, another Side and steel-pipe pile 11 weld.
Refering to 3~attached drawing of attached drawing 4, described 15 one end of steel plate for sealing water is anchored in wing wall bottom plate 9, and the other end is bonded described group It closes wall and is welding with steel sheet pile 13 and steel-pipe pile 11, the wing wall bottom plate 9 is equipped with several anchor bars 16, anchor bar 16 weld with steel-pipe pile 11 or steel sheet pile 13.
The present invention is performed such construction:The assembled wall for carrying out steel-pipe pile 11 and steel sheet pile 13 first is constructed, in steel 13 bottom application work piles set into rock 4 of tubular pole, decomposed rock certain depth in the insertion of 4 one end of bored concrete pile, 4 other end of bored concrete pile protrudes into steel Certain depth in the steel pipe of 11 bottom of tubular pole.The top construction reinforced bar concrete of foundation pit enclosure wall 2 top beam 5 and with top First of the foundation pit support 6 that collar tie beam 5 connects, then carries out earth excavation;Then construct second armored concrete enclose enable 7 with And 8 are supported with the foundation pit second for enabling 7 connections is enclosed, earth excavation is carried out to designed elevation.Finally construction wing wall bottom plate 9, wing wall 9 rear side of bottom plate carries out node connection, wing wall bottom plate 9 using the steel plate for sealing water 15 of anchor bar 16 and abnormity with foundation pit enclosure wall 2 A fixed gap is reserved between steel-pipe pile 11, welds elongated steel plate for sealing water on the wall combined with steel sheet pile 13 of steel-pipe pile 11 15 and anchor bar 16,16 side of anchor bar be welded on steel-pipe pile 11 or steel sheet pile 13,9 anchor of wing wall bottom plate is then goed deep into the other side Gu length, described 15 one end of steel plate for sealing water are the deformed steel flats for being bonded the assembled wall, the deformed steel flats and steel sheet pile 13 and The assembled wall of steel-pipe pile 11 is welding, and 15 other end of steel plate for sealing water is then anchored in wing wall bottom plate 9.When construction pit engineering and After the completion of wing wall bottom plate 9, dismounting foundation pit second, which supports 8 and encloses, enables 7, then construct counterfort panel and floor 17 and buttress type The backfilling of earthwork of 1 rear side of wing wall, finally removes first of foundation pit support 6, sealing of the remaining enclosure wall as buttress type wing wall 1 Curtain.The present invention is using foundation pit enclosure wall 2 as the water-stop curtain of buttress type wing wall 1, without resetting stopping for one of wing wall Water curtain can save a large amount of construction materials, reduce project cost.In addition, due in Excavation Process, the sealing of enclosure wall It can be verified, as the water-stop curtain of counterfort wing wall, construction quality is reliable, is particularly suitable for applying using foundation pit support method The water-stop curtain of work buttress type wing wall.
Above only the present invention is further illustrated, and not to limit this patent, all is equivalence enforcement of the present invention, It is intended to be limited solely by within the scope of the claims of this patent.

Claims (1)

1. a kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall, it is characterised in that foundation pit enclosure wall uses steel pipe Stake is the water stop curtain structure of buttress type wing wall with steel sheet pile assembled wall, and Specific construction carries out in the steps below:
(One)Foundation pit enclosure
The enclosure wall that foundation pit enclosure is composed using steel-pipe pile and steel sheet pile, the enclosure wall is by steel sheet pile two sides with half Steel sheet pile steel-pipe pile adjacent thereto is welded;Half steel sheet pile side is connect by fore shaft with steel sheet pile, the other side It is welded with steel-pipe pile;The steel-pipe pile bottom application work piles set into rock, weathered rock formation in the insertion of bored concrete pile one end, the other end protrudes into In the steel pipe of steel pipe pile bottom;
(Two)Excavation of foundation pit
In first of the foundation pit support going along with sb. to guard him the top beam of coping construction reinforced bar concrete and being connect with top beam, then The earth excavation in foundation pit is carried out, enclosing for the second armored concrete in the middle part of enclosure wall of then constructing enables and enable connection with enclosing Foundation pit second support, continue the earth excavation in foundation pit;
(Three), wing wall bottom plate and enclosure wall sealing
Construction wing wall bottom plate after earth excavation to designed elevation, and the enclosure wall of wing wall floor rear and foundation pit is used into water-stopping steel Plate and anchor bar carry out the patching that node connects, the steel plate for sealing water be one end be bonded retaining wall and with steel sheet pile and Steel-pipe pile welding, the other end are then anchored in the deformed steel flats in wing wall bottom plate;Described anchor bar one end be welded in steel-pipe pile or On steel sheet pile, the other end is anchored in wing wall bottom plate;
(Four), foundation pit backfill
After the completion of base pit engineering and bottom slab, remove foundation pit second support and enclose orders, then construction counterfort panel and floor with And the backfilling of earthwork on rear side of buttress type wing wall, finally by first of supporting removal of foundation pit, the enclosure wall of foundation pit is then buttress type The permanent leaking water curtain structure of wing wall.
CN201611205972.XA 2016-12-23 2016-12-23 A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall Active CN106759365B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611205972.XA CN106759365B (en) 2016-12-23 2016-12-23 A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611205972.XA CN106759365B (en) 2016-12-23 2016-12-23 A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall

Publications (2)

Publication Number Publication Date
CN106759365A CN106759365A (en) 2017-05-31
CN106759365B true CN106759365B (en) 2018-11-27

Family

ID=58919878

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611205972.XA Active CN106759365B (en) 2016-12-23 2016-12-23 A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall

Country Status (1)

Country Link
CN (1) CN106759365B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108118790A (en) * 2017-12-22 2018-06-05 上海紫宝住宅工业有限公司 Edge joint position waterproofing node construction and construction method among a kind of prefabricated composite wallboard in underground
CN108286255A (en) * 2018-01-10 2018-07-17 上海公路桥梁(集团)有限公司 Foundation pit enclosure structure and its construction method
CN111364472B (en) * 2020-03-20 2021-10-15 中交第三航务工程局有限公司 Construction process of dry dock wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2737646A1 (en) * 1977-08-20 1979-02-22 Hochtief Ag Hoch Tiefbauten Tunnel construction for high water content strata - uses concrete walls and low grade concrete pilings which are drilled out to allow water flow after completion
CN101289861A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Pile foundation construction method for foundation ditch in water
KR100991208B1 (en) * 2010-07-12 2010-11-01 노윤근 Prestress composite wale for earth retaining scaffolding and this construction technique
CN202610816U (en) * 2012-04-11 2012-12-19 中交第三航务工程勘察设计院有限公司 Overwater anti-storm foundation pit enclosure structure
CN103669375A (en) * 2013-12-27 2014-03-26 张安政 Double-layer steel sheet pile soil core composite cofferdam structure without inner support and application thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2737646A1 (en) * 1977-08-20 1979-02-22 Hochtief Ag Hoch Tiefbauten Tunnel construction for high water content strata - uses concrete walls and low grade concrete pilings which are drilled out to allow water flow after completion
CN101289861A (en) * 2008-04-10 2008-10-22 中交三航局第二工程有限公司 Pile foundation construction method for foundation ditch in water
KR100991208B1 (en) * 2010-07-12 2010-11-01 노윤근 Prestress composite wale for earth retaining scaffolding and this construction technique
CN202610816U (en) * 2012-04-11 2012-12-19 中交第三航务工程勘察设计院有限公司 Overwater anti-storm foundation pit enclosure structure
CN103669375A (en) * 2013-12-27 2014-03-26 张安政 Double-layer steel sheet pile soil core composite cofferdam structure without inner support and application thereof

Also Published As

Publication number Publication date
CN106759365A (en) 2017-05-31

Similar Documents

Publication Publication Date Title
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR101179770B1 (en) Soil protection against build structure and the method
CN108316339B (en) Construction method of water-permeable geological large arch bridge foundation
CN106759365B (en) A kind of counterfort wing wall waterproof curtain construction method of foundation pit enclosure wall
CN105971306A (en) Unilateral formwork structure of external shearing wall of basement and construction method of unilateral formwork structure
CN103088830A (en) Construction method for composite outer wall structure of ultra-deep basement
KR20090007826A (en) Process of blocking water penetration and blocking earth collapsing by using impermeable wall without strut
KR101169462B1 (en) Top-down construction method using post member
CN113882896A (en) Underground recyclable flexible filling retaining wall and construction method thereof
CN102220764B (en) Construction method of deep foundation pit bracing system
JP5351125B2 (en) Open shield machine start method of open shield method
KR101469603B1 (en) Pipe for piperoof with multipurpose solidarizing tube and construction method using this pipe
KR101567742B1 (en) PHC pile and construction method of underground structure using the same
CN104153347A (en) Repair structure of underground diaphragm wall panel notch and construction method of repair structure
CN208870053U (en) A kind of deep-well retaining wall steel structure support
KR100989984B1 (en) Bult-in timbering roof type tunnel method
CN103132531A (en) Foundation pit supporting system construction method
KR200407437Y1 (en) Construction establishment method and the structure for underground tunnel formation
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN207228173U (en) A kind of underground project waterproof structure
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
CN210888953U (en) Tunnel pile and arch combined primary support system
JP2001271365A (en) Construction method for underground structure
JP7094717B2 (en) Press-fit method
JPH0762436B2 (en) Open shield method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant