CN106746492A - A kind of horse-shoe flame furnace for preventing regenerator gas room to block - Google Patents

A kind of horse-shoe flame furnace for preventing regenerator gas room to block Download PDF

Info

Publication number
CN106746492A
CN106746492A CN201611251036.2A CN201611251036A CN106746492A CN 106746492 A CN106746492 A CN 106746492A CN 201611251036 A CN201611251036 A CN 201611251036A CN 106746492 A CN106746492 A CN 106746492A
Authority
CN
China
Prior art keywords
blast tube
regenerator
gas room
regenerator gas
horse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611251036.2A
Other languages
Chinese (zh)
Inventor
顾春生
王瞻
张骥
程建强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Jiyao Glass Micro-Fiber Co Ltd
Original Assignee
Anhui Jiyao Glass Micro-Fiber Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Jiyao Glass Micro-Fiber Co Ltd filed Critical Anhui Jiyao Glass Micro-Fiber Co Ltd
Priority to CN201611251036.2A priority Critical patent/CN106746492A/en
Publication of CN106746492A publication Critical patent/CN106746492A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C03GLASS; MINERAL OR SLAG WOOL
    • C03BMANUFACTURE, SHAPING, OR SUPPLEMENTARY PROCESSES
    • C03B5/00Melting in furnaces; Furnaces so far as specially adapted for glass manufacture
    • C03B5/04Melting in furnaces; Furnaces so far as specially adapted for glass manufacture in tank furnaces
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P40/00Technologies relating to the processing of minerals
    • Y02P40/50Glass production, e.g. reusing waste heat during processing or shaping

Abstract

The present invention relates to horse-shoe flame furnace technical field,Specifically,It is a kind of horse-shoe flame furnace for preventing regenerator gas room to block,Including a pair of air regenerators,A pair of regenerator gas rooms,A pair of ports,The rear of port is provided with bocca,Two groups of blast tubes are provided with the side wall of regenerator gas room,Two groups of blast tubes are symmetrical on regenerator gas room,Every group of blast tube is divided into blast tube and lower blast tube,Upper blast tube is shaped as " L " shape with lower blast tube,The lower port of a part more long for upper blast tube is vertically set in the longer portion of lower blast tube,Upper blast tube is hollow with the junction of lower blast tube,The port of a shorter part for upper blast tube is connected on the side wall of regenerator gas room,The junction hollow design of upper blast tube and regenerator gas room side wall is used as fuel gas inlet,Partition wall is provided between the longer portion of upper blast tube and lower blast tube.

Description

A kind of horse-shoe flame furnace for preventing regenerator gas room to block
Technical field
It is a kind of horse for preventing regenerator gas room to block specifically the present invention relates to horse-shoe flame furnace technical field Hoof flame kiln.
Background technology
The kiln flame of horse-shoe flame furnace flows in the shape of a hoof, with efficiency of utilization is high, simple structure, cost it is low excellent Point, typically using producer gas, heavy oil or natural gas as fuel, wherein coal gas horse-shoe flame furnace is in glass for horse-shoe flame furnace Glass cotton industry is widely used.Kiln includes a melting tank, a pair of ports and bocca, a pair of air regenerators and To regenerator gas room, the compound that various raw materials stir melts in melting tank, reacts, clarifies and uniformly to turn to composition equal The satisfactory glass metal of even, temperature;Port sprays into furnace pond combustion gas and combustion air premix merging through bocca, Combustion gas and combustion air are burnt in melting tank for the process that compound is melting into glass metal provides heat;Regenerator gas room and sky Gas regenerator can absorb fume afterheat and preheating gas and combustion air are to improve flame temperature and save fuel;Port, spray Burner, regenerator gas room and air regenerator commutate, alternately through the flue gas after coal gas, air and burning, to prevent in required time Only refractory material crosses cause thermal damage.
The fuel that horse-shoe flame furnace is used is gas generator producing coal gas, and the coal gas of gas generator production is removed through expansion chamber After dirt, cyclone dust removal, horizontal tube dedusting remove more than 80% coal ash dirt and coal tar, two confessions are alternately entered by reversing arrangement Coal gas and exhaust gases after combustion alternately through flue, coal gas carries out heat exchange to reach preheating from flue into regenerator gas room Coal gas, raising gas temperature, the purpose of reducing energy consumption.
Kiln is to obtain stable components, homogeneous glass metal, needs long-term work in high temperature environments, and be subject to for a long time Glass metal erosion in kiln, volatility of raw material dust erosion, combustion flame and flame atmosphere such as corrode at the influence.Each position work shape of kiln State is different, its weather damage the reason for and speed it is also different, be extension kiln service life, kiln difference portion need to be considered Position working condition and working environment, selection meets the refractory material laying of different use requirements, generally according to damageable zone with excellent Material, other positions principle of general material, accomplish Rational Matching, kiln age synchronization.Kiln typically needs cold repair once in several years, Need cold repair situation have local damage seriously cannot hot repair, regenerator jam have a strong impact on the normal reason such as use of kiln.Cold repair Preparation is complicated, maintenance cycle is long, and need to stop production blowing out, it is necessary to do the work such as good material preparation, Communication with Customer in advance.
In actual use, because being influenceed by factors, through being commonly present the situation that kiln portion is damaged in advance. It is one of FAQs that regenerator gas room checker brick are blocked, and is especially using powder ratio factory higher, regenerator gas room Close to furnace pond, not only accumulation of heat indoor temperature is higher for cause, and is highly prone to the influence of volatilization raw material dust, and volatilize raw material Dust accumulated plugging checker passage in the checker of regenerator gas room, even checker are changed the line of production biochemical reaction, so as to enter One step accelerates the blocking even slump of regenerator lattice brick.Coal gas smooth can not pass through after regenerator gas room checker brick are blocked, sternly Ghost image rings the normal combustion of furnace pond flame, and causing furnace glass ability to decline can not meet production requirement, sternly There is potential safety hazard in the gas generator outlet pressure rising extremely that even causes of weight, must now take immediate steps solution combustion The blockage problem of gas regenerator.
The method that air regenerator blocks dredging is used for reference, the dredging method that regenerator gas room blocks mainly has tapping pin method, list To ablation, horizontal flame ablation method etc..Tapping pin method needs many people to assist to enter regenerator bottom, work under bad environment and risk It is higher;Horizontal flame ablation method cannot solve the blockage problem of cartridge type checker brick;Although unidirectional ablation can be to a certain degree Upper alleviation checker chocking-up degree, but when cannot solve the problems, such as regenerator gas room Severe blockage.Unidirectional ablation, horizontal flame Also there is being likely to result in regenerator gas room checker hot-spot so as to cause hidden trouble, and several sides in ablation When method is not suitable for checker Severe blockage in regenerator gas room.
Blowing out cold repair can thoroughly solve regenerator gas room blockage problem, but unplanned cold repair maintenance time is long, high cost, Direct economic loss is very big, and the indirect economic loss such as its stopping production for causing and customer churn cost are bigger, and may because temperature across The damage at too big other positions of aggravation kiln of degree, influences kiln whole service life.
The content of the invention
In order to solve the above-mentioned technical problem, the present invention discloses a kind of horseshoe flame furnace that regenerator gas room can be prevented to block Stove, concrete technical scheme is as follows:
A kind of horse-shoe flame furnace for preventing regenerator gas room to block, including symmetrical a pair of air regenerators, left and right are right A pair of regenerator gas rooms, symmetrical a pair of the ports for claiming, the rear of port is provided with bocca, a pair of regenerator gas rooms Side wall on be provided with two groups of blast tubes, two groups of blast tubes are symmetrical on regenerator gas room, every group of blast tube point It is upper blast tube and lower blast tube, upper blast tube is shaped as " L " shape with lower blast tube, and lower blast tube body of one who has dropped dead by the roadside is put Put, upper blast tube is vertically arranged, upper blast tube it is more long a part lower port be vertically set on lower blast tube compared with On part long, upper blast tube is hollow with the junction of lower blast tube, the port connection of a shorter part for upper blast tube Onto the side wall of regenerator gas room, the junction hollow design of upper blast tube and regenerator gas room side wall as fuel gas inlet, Partition wall is provided between the longer portion of upper blast tube and lower blast tube.
In the technical program, there is provided two combustion gas input modes, combustion gas is gone back in addition to from regenerator gas room bottom input Regenerator gas room top can be input into from upper blast tube, can so be determined to use lower combustion according to regenerator gas room stopping state Gas passage or upper blast tube or the two use simultaneously.Further improvement of the present invention, the internal diameter of upper blast tube is less than lower combustion The internal diameter of gas passage, gaseous-pressure during port is entered with stabilization, promotes upper and lower blast tube while combustion gas is preferentially selected when using Select lower blast tube carries out heat exchange into regenerator, to improve temperature, raising efficiency of combustion of the combustion gas into port.
The junction hollow design of further improvement of the present invention, upper blast tube and regenerator gas room side wall is used as combustion gas Passage, the fuel gas inlet on the wall of regenerator gas room side is located between checker and port tongue arch, and the lower edge of fuel gas inlet is high offscale In more than 100mm, the part of the upper edge less than port tongue arch of fuel gas inlet is in more than 200mm for the part of daughter.
Further improvement of the present invention, upper blast tube is formed with lower blast tube using clay brick masonry.
Further improvement of the present invention, upper blast tube is additionally provided with rock cotton board insulation with the outside of lower blast tube, with Gas-preheating effect is improved as far as possible.
The wall thickness of further improvement of the present invention, upper blast tube and lower blast tube is located between 250-300mm, upper combustion The outside thickness for setting rock cotton board of gas passage and lower blast tube is located between 80-150mm.
Further improvement of the present invention, upper blast tube is 280mm with the wall thickness of lower blast tube, and upper blast tube is with The outside thickness for setting rock cotton board of blast tube is 100mm.
Further improvement of the present invention, the internal cross-sectional area of upper blast tube is 800mm*600mm, lower blast tube Internal cross-sectional area is 800mm*800mm, the cut-off wall thickness set between the longer portion of upper blast tube and lower blast tube It is 200mm to spend.
Beneficial effects of the present invention:Compared with prior art, the present invention is provided with upper and lower two on unilateral regenerator gas room Individual blast tube.Once blocking serious in regenerator gas room, partition wall is removed, combustion gas just can enter combustion gas from upper blast tube In regenerator upper space, the shortest time solves the problems, such as that regenerator gas room blocks influence production.The present invention can also be existing Horse-shoe flame furnace on the basis of transformed, it is conventional criteria refractory material to build by laying bricks or stones with material, easily buying, the simple side of construction Just, it is not required to a large amount of preparations for a long time, and working environment is substantially better than and solves regenerator gas room using artificial dredging mode and block up The method of plug.After material and instrument are ready to, solving unilateral regenerator gas room blockage problem only needs 12-15h, can be complete in one day Into accomplishing to solve regenerator gas room blockage problem in the simple mode of relatively economical within a short period of time, it is to avoid unplanned The larger economic loss that blowing out cold repair is caused.
Brief description of the drawings
Fig. 1 is surface structure schematic diagram of the invention.
Fig. 2 is regenerator gas room of the invention cross-sectional view.
In figure, 1- air regenerators, 2- regenerator gas room, 3- ports, 4- boccas, blast tube under 5-, the upper combustion gas of 6- Passage, 7- partition walls, 8- fuel gas inlets, 9- port tongue arch, 10- regenerator gas room side wall, 11- checkers.
Specific embodiment
In order to deepen the understanding of the present invention, the present invention is done below in conjunction with drawings and Examples is further retouched in detail State, the embodiment is only used for explaining the present invention, protection scope of the present invention is not constituted and is limited.
Embodiment:As depicted in figs. 1 and 2, a kind of horse-shoe flame furnace for preventing regenerator gas room to block, including left and right is right A pair of air regenerators 1, symmetrical a pair of regenerator gas room 2, symmetrical a pair of the ports 3, the rear of port 3 for claiming Be provided with a pair of boccas 4, be provided with two groups of blast tubes on a pair of side walls of regenerator gas room 2, two groups of blast tubes on Regenerator gas room 2 is symmetrical, and every group of blast tube is divided into blast tube 6 and lower blast tube 5, and upper blast tube 6 is with Blast tube 5 is shaped as " L " shape, and the lower body of one who has dropped dead by the roadside of blast tube 5 is placed, and upper blast tube 6 is vertically arranged, upper blast tube 6 compared with The lower port of part long is vertically set in the longer portion of lower blast tube 5, the company of upper blast tube 6 and lower blast tube 5 Connect place it is hollow, upper blast tube 6 it is shorter a part port be connected on regenerator gas room side wall 10, upper blast tube 6 with The junction hollow design of regenerator gas room side wall 10 is used as fuel gas inlet 8, and the longer portion of upper blast tube 6 is logical with lower combustion gas Partition wall 7, the internal diameter of the internal diameter less than lower blast tube 5 of upper blast tube 6 are provided between road 5.
In the present embodiment, it is provided with regenerator gas room 2 in checker 11, regenerator gas room 2 and is provided with port tongue arch 9, checker 11 is located at the lower section of port tongue arch 9, and fuel gas inlet 8 is located between checker 11 and port tongue arch 9, fuel gas inlet 8 Lower edge be higher by the part of checker 11 in more than 100mm, the part of the upper edge less than port tongue arch 9 of fuel gas inlet 8 is in 200mm More than.
In the present embodiment, upper blast tube 6 is formed with lower blast tube 5 using clay brick masonry, upper blast tube 6 with The outside of lower blast tube 5 is additionally provided with rock cotton board for being incubated, and upper blast tube 6 is located at the wall thickness of lower blast tube 5 Between 250-300mm, preferably 280mm, upper blast tube 6 is located at the outside thickness for setting rock cotton board of lower blast tube 5 Between 80-150mm, preferably 100mm.
In the present embodiment, the internal cross-sectional area of upper blast tube 6 is 800mm*600mm, the inside of lower blast tube 5 Cross-sectional area is 800mm*800mm, the thickness of partition wall 7 set between the longer portion of upper blast tube 6 and lower blast tube 5 It is 200mm.
By being provided with upper and lower two blast tubes on unilateral regenerator gas room, regenerator gas room can be prevented to block When there is the not smooth phenomenon of fuel gas flow, can select to use as needed lower blast tube or upper blast tube or the two simultaneously Use.When the blocking of regenerator gas room is serious, partition wall can be removed, promote combustion gas to be directly entered combustion gas from upper blast tube and store Hot cell top, the shortest time solves the problems, such as that regenerator gas room blocks influence production, it is to avoid manual cleaning even blowing out cold repair Situation.
General principle of the invention, principal character and advantage has been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, simply original of the invention is illustrated described in above-described embodiment and specification Reason, without departing from the spirit and scope of the present invention, various changes and modifications of the present invention are possible, these changes and improvements All fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appending claims and its equivalent circle. It is fixed.

Claims (10)

1. a kind of horse-shoe flame furnace for preventing regenerator gas room to block, including symmetrical a pair of air regenerators, left and right Symmetrical a pair of regenerator gas rooms, symmetrical a pair of ports, the rear of the port is provided with bocca, and its feature exists In:Two groups of blast tubes are provided with a pair of side walls of regenerator gas room, two groups of blast tubes are right on regenerator gas room or so Claim, every group of blast tube is divided into blast tube and lower blast tube, the upper blast tube and the lower blast tube shape Be " L " shape, the lower blast tube body of one who has dropped dead by the roadside is placed, and the upper blast tube is vertically arranged, the upper blast tube it is more long by one Partial lower port is vertically set in the longer portion of the lower blast tube, and the upper blast tube is logical with the lower combustion gas The junction in road is hollow, and the port of a shorter part for the upper blast tube is connected on the side wall of the regenerator gas room, The junction hollow design of the upper blast tube and regenerator gas room side wall as fuel gas inlet, the upper blast tube Longer portion and lower blast tube between be provided with partition wall.
2. it is according to claim 1 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion Internal diameter of the internal diameter of gas passage less than the lower blast tube.
3. it is according to claim 2 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the combustion gas Checker is provided with regenerator, port tongue arch is provided with the regenerator gas room, the checker is located at the port tongue The lower section of arch.
4. it is according to claim 3 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion The junction hollow design of gas passage and regenerator gas room side wall as fuel gas inlet, positioned at checker and port tongue arch it Between, the lower edge of the fuel gas inlet is higher by the part of the checker in more than 100mm, and the upper edge of the fuel gas inlet is less than institute The part of port tongue arch is stated in more than 200mm.
5. it is according to claim 4 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion Gas passage is formed with the lower blast tube using clay brick masonry.
6. it is according to claim 5 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion Gas passage is additionally provided with rock cotton board for being incubated with the outside of the lower blast tube.
7. it is according to claim 6 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion The wall thickness of gas passage and the lower blast tube is located between 250-300mm, the upper blast tube and the lower blast tube The outside thickness that rock cotton board is set be located between 80-150mm.
8. it is according to claim 7 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion Gas passage is 280mm with the wall thickness of the lower blast tube, and the upper blast tube is set with the outside of the lower blast tube The thickness of rock cotton board is 100mm.
9. it is according to claim 8 prevent regenerator gas room block horse-shoe flame furnace, it is characterised in that the upper combustion The internal cross-sectional area of gas passage is 800mm*600mm, and the internal cross-sectional area of the lower blast tube is 800mm*800mm, The cut-off wall thickness set between the longer portion of the upper blast tube and the lower blast tube is 200mm.
10. the horse-shoe flame furnace that prevented from the regenerator gas room according to claim any one of 1-9 blocks, its feature exists In, bocca is provided with after the port, the bocca is connected with the horse-shoe flame furnace melting tank.
CN201611251036.2A 2016-12-30 2016-12-30 A kind of horse-shoe flame furnace for preventing regenerator gas room to block Pending CN106746492A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611251036.2A CN106746492A (en) 2016-12-30 2016-12-30 A kind of horse-shoe flame furnace for preventing regenerator gas room to block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611251036.2A CN106746492A (en) 2016-12-30 2016-12-30 A kind of horse-shoe flame furnace for preventing regenerator gas room to block

Publications (1)

Publication Number Publication Date
CN106746492A true CN106746492A (en) 2017-05-31

Family

ID=58928087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611251036.2A Pending CN106746492A (en) 2016-12-30 2016-12-30 A kind of horse-shoe flame furnace for preventing regenerator gas room to block

Country Status (1)

Country Link
CN (1) CN106746492A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101893239A (en) * 2010-08-10 2010-11-24 宁夏华源冶金实业有限公司 Premixing low-pressure injection heat storage type nozzle
CN201785300U (en) * 2010-09-17 2011-04-06 杨月强 Glass kiln anti-blockage regenerator
CN106145613A (en) * 2016-08-26 2016-11-23 成都瀚江新材科技股份有限公司 The triple channel regenerator of kiln
CN206418000U (en) * 2016-12-30 2017-08-18 安徽吉曜玻璃微纤有限公司 A kind of horse-shoe flame furnace for preventing regenerator gas room to block

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101893239A (en) * 2010-08-10 2010-11-24 宁夏华源冶金实业有限公司 Premixing low-pressure injection heat storage type nozzle
CN201785300U (en) * 2010-09-17 2011-04-06 杨月强 Glass kiln anti-blockage regenerator
CN106145613A (en) * 2016-08-26 2016-11-23 成都瀚江新材科技股份有限公司 The triple channel regenerator of kiln
CN206418000U (en) * 2016-12-30 2017-08-18 安徽吉曜玻璃微纤有限公司 A kind of horse-shoe flame furnace for preventing regenerator gas room to block

Similar Documents

Publication Publication Date Title
CN206385021U (en) A kind of glass furnace provided with auxiliary combustion equipment
CN101907298B (en) Hot repair method of port tongue arch of coal-burning glass furnace
CN201225620Y (en) Air single thermal storage combustor
CN201301270Y (en) A heat-accumulating type glass crucible circular kiln
CN206418000U (en) A kind of horse-shoe flame furnace for preventing regenerator gas room to block
CN105002317B (en) Heat-accumulating burner for heating furnace
CN107902870B (en) Energy-saving kiln for environment-friendly unit glass wool
CN106746492A (en) A kind of horse-shoe flame furnace for preventing regenerator gas room to block
CN202328300U (en) Flue structure of kiln
CN103910482B (en) Double-neck float glass melting furnace, and method used for reducing nitrogen oxide emission of double-neck float glass melting furnace
CN101093140A (en) Heat storage type vertical metal magnesium reducing furnace
CN201809370U (en) Vertical top-combustion blast stove improved from pebble stove
CN101020966A (en) Heat accumulating high efficiency green vertical magnesium reducing furnace
CN108793781A (en) A kind of energy-saving and environment-friendly twin furnace lime burner furnace
CN104402194A (en) Oxy-fuel combustion furnace used in low-expansion microcrystalline glass manufacturing
CN104100972A (en) Regenerative burner special for smelting secondary aluminum and implementing method thereof
CN208475974U (en) A kind of energy-saving and environment-friendly reducing crucible furnace (kiln)
CN203147761U (en) Heat accumulating type combustor for secondary aluminum smelting
CN102260034A (en) Novel crucible glass kiln
CN206408085U (en) A kind of tank furnace steel flue gas duct structure for cover-plate glass
CN202519285U (en) Hot-blast stove with sleeve burner and with conical regenerator for rectifying and supporting combustion in combustion chamber
CN217265402U (en) Small furnace connecting structure of regenerative chamber of glass kiln
CN206648021U (en) A kind of novel sealing structure between heat accumulating type burner block and furnace wall
CN206385019U (en) A kind of glass furnace provided with upper arch
CN206385018U (en) A kind of triple channel double back journey glass furnace

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned
AD01 Patent right deemed abandoned

Effective date of abandoning: 20230818