CN106741605A - A kind of pipeline for carrying out load test on hull pulls system - Google Patents

A kind of pipeline for carrying out load test on hull pulls system Download PDF

Info

Publication number
CN106741605A
CN106741605A CN201611086532.7A CN201611086532A CN106741605A CN 106741605 A CN106741605 A CN 106741605A CN 201611086532 A CN201611086532 A CN 201611086532A CN 106741605 A CN106741605 A CN 106741605A
Authority
CN
China
Prior art keywords
steel wire
wire rope
winch
hull
rear end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611086532.7A
Other languages
Chinese (zh)
Other versions
CN106741605B (en
Inventor
李家院
陈焕东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Huang Hai Marine Engineering Co Ltd
CSSC Huangpu Wenchong Shipbuilding Co Ltd
Original Assignee
Guangzhou Huang Hai Marine Engineering Co Ltd
CSSC Huangpu Wenchong Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Huang Hai Marine Engineering Co Ltd, CSSC Huangpu Wenchong Shipbuilding Co Ltd filed Critical Guangzhou Huang Hai Marine Engineering Co Ltd
Priority to CN201611086532.7A priority Critical patent/CN106741605B/en
Publication of CN106741605A publication Critical patent/CN106741605A/en
Application granted granted Critical
Publication of CN106741605B publication Critical patent/CN106741605B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B71/00Designing vessels; Predicting their performance

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

System is pulled the invention provides a kind of pipeline for carrying out load test on hull, hull is provided with production line ceiling, and it includes:Front end winch mechanism, it includes front end winch and front end steel wire rope;Front end winch is located in hull, and front end steel wire rope is connected with front end winch;Rear end winch mechanism, it includes rear end winch and rear end steel wire rope;Rear end winch is located on production line ceiling, and rear end steel wire rope is connected with rear end winch;Guide, it includes hull fixed pulley, support and some support pulleys;Hull fixed pulley is arranged on hull, and support is arranged at the stern of hull, and support pulley is arranged on support;Load device, it includes sea pipe and stretcher;Stretcher is located between production line ceiling and the main deck of hull, and stretcher clamps sea pipe;The extra large pipe front end of front end steel wire rope connection, the extra large pipe rear end of rear end steel wire rope connection.The present invention can be greatly decreased workload, save shipyard cost and experimental period, shorten ship building period.

Description

A kind of pipeline for carrying out load test on hull pulls system
Technical field
System is pulled the present invention relates to a kind of pipeline for carrying out load test on hull.
Background technology
On pipe laying barge, its pipelaying work system can set a set of stretcher and A/R hoister systems, for clamping, receiving Put extra large pipe.After stretcher and the shipment of A/R winches, the requirement based on instrument factory and shipowner side can typically pay in ship and advance The load test of row stretcher and A/R winches, to verify that equipment normal work and can reach design performance after loading onto ship.The load The general principle of experiment is:Manage the traction of upper or A/R winches in the sea that stretcher clamping is loaded into by shipyard one external pull of offer Steel wire rope on, if Hai Guanneng is firmly clamped without skidding off in the presence of external pull, or A/R winches can overcome this outer Portion's pulling force does not slip rope, and stretcher or A/R winches parameters normal operation, then test successfully, equipment spreads after being used for Pipe operation.Because the external pull typically requires larger, up to 100 tons or so, therefore for shipyard, the process of the test Middle maximum difficult point is how reliably and securely to provide this external pull.
The method that general shipyard can refer to Fig. 1 is tested:Make stern towards harbour, ship mooring is good, on the quarter open One frock pulley yoke is installed at mouthful, external pull is provided using truck crane.Had the following disadvantages in the method implementation process:
1) a large-scale frock pulley yoke need to be made and need to be welded in the structure being on the quarter open, made and installment work Amount is big;
2) because load is larger, frock installation site needs to carry out calculating and the strength check of complexity;
3) ship need to adjust attitude, make stern towards harbour, it is necessary to move ship;
4) truck crane of extra lease large-tonnage is needed;
5) the method is considered, although but feasible compare consuming time and cost.
In the prior art, Chinese patent 201410491090.9 discloses a kind of tensile test system of pipe laying barge, including: Leading block, frock cable wire, set square, pulling winch cable wire, current nipple, stretcher, pulling winch, pipeline, set square It is connected with pulling winch by pulling winch cable wire, current nipple is connected with the pipeline through stretcher, pulling winch cable wire Through current nipple, leading block is fixedly connected with fixed pedestal, frock cable wire bypass leading block respectively with set square and Current nipple is connected, and current nipple includes pulling eye plate.The invention also discloses a kind of pull force test method of pipe laying barge, The present invention replaces traditional fixed hanger to be equipped with one simultaneously using detachable deflection sheave device can be applicable not by repacking With the general tow attachment of caliber, the space shared by tensile test system is significantly reduced, improve efficiency, while solving Leading block is located at side and miscellaneous equipment afoul problem in ship.
The defect of above-mentioned technical proposal is larger workload, compares consuming time and cost.
Therefore, how providing one kind can be greatly decreased workload, time-consuming and cost, while can also safely and reliably carry Pipeline dragging system for external pull becomes the problem that industry needs to solve.
The content of the invention
In view of the shortcomings of the prior art, it is an object of the invention to provide a kind of pipe for carrying out load test on hull Line pulls system.
To achieve these goals, system is pulled the invention provides a kind of pipeline for carrying out load test on hull System, hull is provided with production line ceiling, and the pipeline pulls system to be included:
Front end winch mechanism, front end winch mechanism includes front end winch (such as A/R winches) and front end steel wire rope;Front end twists In in hull, front end steel wire rope is connected with front end winch for parking stall;
Rear end winch mechanism, rear end winch mechanism includes rear end winch (such as hoister winch) and rear end steel wire rope;Rear end Winch is located on production line ceiling, and rear end steel wire rope is connected with rear end winch;
Guide, guide includes hull fixed pulley, support and some support pulleys;Hull fixed pulley is arranged at ship On body, support is arranged at the stern of hull, and support pulley is arranged on support;
Load device, load device includes sea pipe and stretcher;Stretcher is located at the main deck of production line ceiling and hull Between, stretcher clamps sea pipe;The extra large pipe front end of front end steel wire rope connection, the extra large pipe rear end of rear end steel wire rope connection.
In the present invention, with bow as preceding, after being with stern.
In the present invention, production line ceiling is located on main deck.
In the present invention, hull fixed pulley is located on the main crane foundation of hull.
In the present invention, support is fixed on hull and main crane foundation.
According to another specific embodiment of the invention, rear end steel wire rope includes winch cable and extra large pipe steel wire rope;Winch Steel wire rope is connected with rear end winch, and extra large pipe steel wire rope is connected with extra large pipe rear end.
According to another specific embodiment of the invention, support pulley includes fixed pulley group and running block, fixed pulley group position In on support, running block and fixed pulley group are connected by winch cable;Hull fixed pulley height and fixed pulley group height phase Together.
According to another specific embodiment of the invention, support pulley further includes frock pulley, and frock pulley is located at branch On frame;Frock pulley is fixed on a transversary pipe of support, for guiding extra large pipe steel wire rope, its highly with extra large pipe highly It is identical.
According to another specific embodiment of the invention, guide further includes connecting rod;Connecting rod one end is connected to dynamic cunning In wheel group, the other end is connected with extra large pipe steel wire rope;
According to another specific embodiment of the invention, pipeline pulls system and further includes bindiny mechanism and tensiometer, even Binding structure is located between extra large pipe steel wire rope and extra large pipe;Attachment structure includes enclosed socket, preceding shackle, rear shackle and hangs code;Pulling force Meter is located between preceding shackle and rear shackle;Enclosed socket one end is connected with extra large pipe steel wire rope, and the other end is connected with rear shackle;Front dump Detain and hang code connection.
In this programme, enclosed socket is with extra large pipe steel wire rope by being welded and fixed, and enclosed socket is connected with rear shackle latch closure, preceding Shackle is connected with a yard latch closure is hung;Tensiometer is used to indicate the tractive force size of rear end winch output.
According to another specific embodiment of the invention, sea pipe includes preceding sea pipe and rear sea pipe, and preceding Hai Guanyuhouhai pipes are fixed Connection;Code is hung to be fixedly connected with rear extra large pipe;Preceding Hai Guanyuhouhai pipes hang code solid by welding with rear sea pipe by being welded and fixed It is fixed.
According to another specific embodiment of the invention, stretcher includes preceding stretcher and rear stretcher;Preceding stretcher is clamped Preceding sea pipe, sea is managed after rear stretcher is clamped.
According to another specific embodiment of the invention, front end winch mechanism further includes leading block and measurement pulley; Leading block is located on main deck, and measurement pulley is located in hull;Leading block is connected with measurement pulley by front end steel wire rope.
According to another specific embodiment of the invention, front end steel wire rope is before being removably attachable on extra large pipe.
It is as follows that pipeline of the invention pulls system operation methods:
First, stretcher load test
1st, start stretcher and clamp sea pipe;
2nd, rear end winch, the slow tractive force for increasing the output of rear end winch, to specified value are started;
Whether the parameters that the 3rd, the extra large tube grip situation of observation and tensioning instruments and meters show are normal;If in the work of external pull Can be held firmly clamped with pipe of plunging into the commercial sea and handled without skidding off, and stretcher parameters normal operation, then testing successfully, equipment can be used In later pipelaying work.
2nd, the load test of front end winch
1st, stretcher is unclamped, sea pipe is removed, front end steel wire rope is connected by an enclosed socket with preceding shackle;
2nd, start front end winch, restart rear end winch, the slow tractive force for increasing the output of rear end winch, to specified value Untill;
3rd, whether whether observation front end winch have the parameters that the situation of slipping rope and front end winch instrument show normal;If Front end winch can overcome the external pull not slip rope, and front end winch parameters normal operation, then test successfully, and equipment can be used In later pipelaying work.
Compared with prior art, the present invention possesses following beneficial effect:
The present invention can be greatly decreased workload, save the costs such as shipyard equipment lease, frock making and installation, and save big Amount experimental period, shortens ship building period.
The present invention is described in further detail below in conjunction with the accompanying drawings.
Brief description of the drawings
Fig. 1 is the test method schematic diagram for providing external pull using truck crane in the prior art;
Fig. 2 is the overall structure diagram of the pipeline dragging system of embodiment 1;
Fig. 3 is the winch cable arrangement schematic diagram of the pipeline dragging system of embodiment 1;
Specific embodiment
Embodiment 1
Present embodiments provide a kind of pipeline for carrying out load test on hull and pull system.Such as Fig. 2, Fig. 3 institute Show, the pipeline of the present embodiment pulls system to be included:Hull 1, front end winch mechanism 2, rear end winch mechanism 3, guide 4, branch Frame pulley 5, load device 6, extra large pipe 7, stretcher 8, bindiny mechanism 9 and tensiometer 10.
Hull 1 is provided with production line ceiling 101, main crane foundation 102 and main deck 103.
Front end winch mechanism 2 includes front end winch (A/R winches) 201, front end steel wire rope 202, leading block 203 and measurement Pulley 204;Front end winch 201 is located in hull 1, and front end steel wire rope 202 is connected with front end winch 201;Leading block 203 is located at On main deck 103, measurement pulley 204 is located in hull 1;Leading block 203 passes through front end steel wire rope 202 with measurement pulley 204 Connection.
Rear end winch mechanism 3 includes rear end winch (hoister winch) 301, winch cable 302 and extra large pipe steel wire rope 303; Rear end winch 301 be located at production line ceiling 101 on, winch cable 302 is connected with rear end winch 301, extra large pipe steel wire rope 303 and The rear end of extra large pipe 7 connects.
Guide 4 includes hull fixed pulley 401, support 402, connecting rod 403 and support pulley 5;401, hull fixed pulley In on main crane foundation 102, support 402 is fixed on hull 1 and main crane foundation 102;Support pulley 5 is arranged at support On 402.
Support pulley 5 includes fixed pulley group 501, running block 502 and frock pulley 503;Fixed pulley group 501 is located at support On 402, running block 502 and fixed pulley group 501 are connected by winch cable 302;The height of hull fixed pulley 401 and fixed pulley Group 501 is highly identical;Frock pulley 503 is fixed on a transversary pipe (not shown) of support 402, for guiding sea Pipe steel wire rope 303, it is highly highly identical with extra large pipe 7;The one end of connecting rod 403 is connected on running block 502, and the other end is managed with sea Steel wire rope 303 is connected;
Load device 6 includes extra large pipe 7 and stretcher 8;Stretcher 8 is located between production line ceiling 101 and main deck 103, Stretcher 8 clamps extra large pipe 7.
Extra large pipe 7 includes preceding extra large pipe 701 and rear sea pipe 702;Preceding extra large pipe 701 passes through to be welded and fixed with rear extra large pipe 702, front end steel Cord 202 is before being removably attachable on extra large pipe 701.
Stretcher 8 includes preceding stretcher 801 and rear stretcher 802;Preceding stretcher 801 extra large pipe 701, rear stretcher before clamping Extra large pipe 702 after 802 clampings.
Attachment structure 9 is located between extra large pipe steel wire rope 303 and rear sea pipe 702, and it includes enclosed socket 901, preceding shackle 902nd, rear shackle 903 and code 904 is hung;Tensiometer 10 is used to indicate the tractive force size of rear end winch output, and it is located at preceding shackle Between 902 and rear shackle 903;The one end of enclosed socket 901 with extra large pipe steel wire rope 303 by being welded and fixed, the other end and rear shackle 903 latch closures are connected;Preceding shackle 902 is connected with the latch closure of code 904 is hung, and hangs code 904 with rear extra large pipe 702 by being welded and fixed.
Although the present invention is disclosed above with preferred embodiment, the scope of present invention implementation is not limited to.Any The those of ordinary skill in field, is not departing from invention scope of the invention, when that can make a little improvement, i.e., every according to this hair Bright done equal improvement, should be the scope of the present invention and is covered.

Claims (10)

1. a kind of pipeline for carrying out load test on hull pulls system, and the hull is provided with production line ceiling, its In, the pipeline pulls system to be included:
Front end winch mechanism, the front end winch mechanism includes front end winch and front end steel wire rope;The front end winch is located at institute State in hull, the front end steel wire rope is connected with the front end winch;
Rear end winch mechanism, the rear end winch mechanism includes rear end winch and rear end steel wire rope;The rear end winch is located at institute State on production line ceiling, the rear end steel wire rope is connected with the rear end winch;
Guide, the guide includes hull fixed pulley, support and some support pulleys;The hull fixed pulley is set In on the hull, the support is arranged at the stern of the hull, and the support pulley is arranged on the support;
Load device, the load device includes sea pipe and stretcher;The stretcher be located at the production line ceiling with it is described Between the main deck of hull, the stretcher clamps the sea pipe;The front end steel wire rope connects the extra large pipe front end, it is described after End steel wire rope connects the extra large pipe rear end.
2. pipeline as claimed in claim 1 pulls system, wherein, the rear end steel wire rope includes winch cable and sea Guan Gang Cord;The winch cable is connected with the rear end winch, and the extra large pipe steel wire rope is connected with the extra large pipe rear end.
3. pipeline as claimed in claim 2 pulls system, wherein, the support pulley includes fixed pulley group and running block, The fixed pulley group is located on the support, and the running block and the fixed pulley group are connected by the winch cable.
4. pipeline as claimed in claim 3 pulls system, wherein, the support pulley further includes frock pulley, described Frock pulley is located on the support.
5. pipeline as claimed in claim 2 pulls system, wherein, the guide further includes connecting rod;The connecting rod One end is connected on the running block, and the other end is connected with the extra large pipe steel wire rope.
6. pipeline as claimed in claim 2 pulls system, wherein, the pipeline pull system further include bindiny mechanism and Tensiometer, the attachment structure is located between the extra large pipe steel wire rope and the extra large pipe;The attachment structure include enclosed socket, Preceding shackle, rear shackle and hang code;The tensiometer is located between the preceding shackle and the rear shackle;Described enclosed socket one end It is connected with the extra large pipe steel wire rope, the other end is connected with the rear shackle;The preceding shackle is connected with the code that hangs.
7. pipeline as claimed in claim 6 pulls system, wherein, the sea pipe includes that preceding sea is managed and rear sea pipe, the preceding sea Pipe is fixedly connected with the rear sea pipe;The code that hangs is fixedly connected with the rear sea pipe.
8. pipeline as claimed in claim 7 pulls system, wherein, the stretcher includes preceding stretcher and rear stretcher;Institute State preceding stretcher and clamp the preceding sea pipe, extra large pipe after the rear stretcher clamping is described.
9. pipeline as claimed in claim 8 pulls system, wherein, the front end winch mechanism further include leading block and Measurement pulley;The leading block is located on the main deck, and the measurement pulley is located in the hull;The leading block It is connected by the front end steel wire rope with the measurement pulley.
10. pipeline as claimed in claim 9 pulls system, wherein, the front end steel wire rope be removably attachable to it is described before On extra large pipe.
CN201611086532.7A 2016-11-30 2016-11-30 A kind of pipeline dragging system for the progress load test on hull Active CN106741605B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611086532.7A CN106741605B (en) 2016-11-30 2016-11-30 A kind of pipeline dragging system for the progress load test on hull

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611086532.7A CN106741605B (en) 2016-11-30 2016-11-30 A kind of pipeline dragging system for the progress load test on hull

Publications (2)

Publication Number Publication Date
CN106741605A true CN106741605A (en) 2017-05-31
CN106741605B CN106741605B (en) 2019-02-22

Family

ID=58914985

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611086532.7A Active CN106741605B (en) 2016-11-30 2016-11-30 A kind of pipeline dragging system for the progress load test on hull

Country Status (1)

Country Link
CN (1) CN106741605B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107991114A (en) * 2017-11-21 2018-05-04 中船黄埔文冲船舶有限公司 The depressed place internal load test method of towing winch
CN111591879A (en) * 2020-05-28 2020-08-28 南通振华重型装备制造有限公司 Novel lifeboat static load test method
CN114620198A (en) * 2021-12-24 2022-06-14 武昌船舶重工集团有限公司 Load test method and test tool

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62211529A (en) * 1986-03-12 1987-09-17 Japan Steel Works Ltd:The Tensile force detecting device for hydraulic winch
US6302049B1 (en) * 2000-04-04 2001-10-16 J. Ray Mcdermott, S.A. Multi-use vessel
CN104260826A (en) * 2014-09-23 2015-01-07 南通中远船务工程有限公司 Pull test system and method of pipe-laying ship
CN104697777A (en) * 2015-03-20 2015-06-10 中船黄埔文冲船舶有限公司 Dead load testing device and dead load testing method for large anchor handling lift winch
CN206417146U (en) * 2016-11-30 2017-08-18 中船黄埔文冲船舶有限公司 A kind of pipeline for being used to carry out load test on hull pulls system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62211529A (en) * 1986-03-12 1987-09-17 Japan Steel Works Ltd:The Tensile force detecting device for hydraulic winch
US6302049B1 (en) * 2000-04-04 2001-10-16 J. Ray Mcdermott, S.A. Multi-use vessel
CN104260826A (en) * 2014-09-23 2015-01-07 南通中远船务工程有限公司 Pull test system and method of pipe-laying ship
CN104697777A (en) * 2015-03-20 2015-06-10 中船黄埔文冲船舶有限公司 Dead load testing device and dead load testing method for large anchor handling lift winch
CN206417146U (en) * 2016-11-30 2017-08-18 中船黄埔文冲船舶有限公司 A kind of pipeline for being used to carry out load test on hull pulls system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107991114A (en) * 2017-11-21 2018-05-04 中船黄埔文冲船舶有限公司 The depressed place internal load test method of towing winch
CN111591879A (en) * 2020-05-28 2020-08-28 南通振华重型装备制造有限公司 Novel lifeboat static load test method
CN111591879B (en) * 2020-05-28 2022-03-25 南通振华重型装备制造有限公司 Novel lifeboat static load test method
CN114620198A (en) * 2021-12-24 2022-06-14 武昌船舶重工集团有限公司 Load test method and test tool

Also Published As

Publication number Publication date
CN106741605B (en) 2019-02-22

Similar Documents

Publication Publication Date Title
CN104260826B (en) A kind of tensile test system and method for pipe laying barge
CN106441852B (en) The Tensile Test Method of stretcher and pipeline releasing winch on pipe laying barge
CN106741605B (en) A kind of pipeline dragging system for the progress load test on hull
KR102536839B1 (en) System and method for securing tension rope using wedge thimbles
CN104816806B (en) A kind of Large Underwater combination towing gear and its using method
US9671042B2 (en) Abandonment and recovery system
CN105672138A (en) Through type stayed cable installation circulation system and cable threading construction method thereof
US6044787A (en) Ship and a method adapted to generate tensile stresses in a pull line extended between the ships and an object to which a pull is to be applied
CN206417146U (en) A kind of pipeline for being used to carry out load test on hull pulls system
CN108709012A (en) A kind of vertical laying method of flexible hose
CN107324231B (en) Endless rope winch wire rope distributing technique
CN101195988A (en) Soft, hard composite three-leveltraction technique for stay cables and connecting device thereof
CN111946900B (en) Pipe joint installation device and method
JP2018039475A (en) Method for extension of mooring cable, method for mooring floating body structure and method for construction of floating body type offshore wind power generation facility
CN106568584B (en) A kind of method of pipe laying barge pipe laying static system load test
CN213575898U (en) Pipe joint installation device
CN110789669B (en) System and method for recycling and putting down reclaimed water buoy in deep water single-point mooring
CN106428413B (en) A kind of method of pipe laying barge pipe laying system dynamic load experiment
CN213299025U (en) Pipe joint fastening device
JP2008037143A (en) Holding force testing method and device
CN114348892B (en) Ship deck crane steel wire rope installation process method
NO346098B1 (en) Mooring tensioning arrangement and a method for longitudinal cross tension of a mooring system.
CN214656370U (en) Device for assisting anchor pressing at beam end of stay cable
JP5944361B2 (en) Method for constructing bundled pipelines and method for laying overhead cables
CN107101810A (en) A kind of detection method and detecting system of the brake assemblies of towing winch

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant