- CN106703840A CN106703840A CN201710014667.0A CN201710014667A CN106703840A CN 106703840 A CN106703840 A CN 106703840A CN 201710014667 A CN201710014667 A CN 201710014667A CN 106703840 A CN106703840 A CN 106703840A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- shelf
- surrounding rock
- steel arch
- damper
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000011435 rock Substances 0.000 title claims abstract description 34
- 230000021715 photosynthesis, light harvesting Effects 0.000 title abstract 4
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 46
- 239000010959 steel Substances 0.000 claims abstract description 46
- 238000010276 construction Methods 0.000 claims description 18
- 230000006835 compression Effects 0.000 claims description 15
- 238000007906 compression Methods 0.000 claims description 15
- 230000008093 supporting effect Effects 0.000 claims description 13
- 238000009412 basement excavation Methods 0.000 claims description 7
- 230000009916 joint effect Effects 0.000 abstract 1
- 230000000694 effects Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000011218 segmentation Effects 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/008—Anchoring or tensioning means
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明涉及一种用于大变形围岩条件下隧道的消能支护结构。大变形围岩条件下隧道通常表现为围岩变形量大,容易发生坍塌等安全事故。本发明包括隧道开挖轮廓线内的钢拱架,钢拱架的节段之间设置有受压阻尼器;隧道围岩内环周设置有多个受拉锚杆,受拉锚杆端部通过受拉阻尼器固定于钢拱架的翼缘。在钢拱架容易产生变形、错台、扭曲等不利情况下,通过本发明中的受拉锚杆、受压阻尼器和受拉阻尼器与钢拱架的共同作用,在围岩压力释放的初期,达到边放边扛的效果,在围岩压力释放到一定程度后达到增加钢拱架自身刚度的效果,确保隧道安全,并满足净空要求。
Description
技术领域
本发明属于隧道交通工程技术领域,具体涉及一种用于大变形围岩条件下隧道的消能支护结构。
背景技术
我国有大量铁路隧道建设项目,其中大变形围岩条件下隧道的设计与施工问题困扰着广大隧道建设者,这些隧道通常表现为围岩变形量大,容易发生坍塌等安全事故;变更设计多,投资难以控制;施工进度缓慢,严重制约工程的工期等。
选择正确的支护理念,充分利用围岩自身强度,可以达到安全、经济的支护效果。隧道支护方法大体可分为刚性支护、柔性支护、刚柔结合支护等。对于大变形围岩条件下的隧道支护,一味地追求加强刚度是难以奏效的,要先柔后刚,先让后抗,柔让适度,稳定支护。对大变形围岩条件下隧道支护宜采用刚柔结合,前期放,释放围岩压力,以减轻支护结构上的荷载;后期抗,在围岩产生一定变形后,以大刚度的支护结构抵抗围岩的压力,确保隧道安全,并满足净空要求。
发明内容
本发明的目的是提供一种用于大变形围岩条件下隧道的消能支护结构,避免由于隧道变形量大导致初期支护(钢拱架)变形、错台、扭曲,以至于发生坍塌事故等,提高隧道建设过程中的安全性。
本发明所采用的技术方案为:
用于大变形围岩条件下隧道的消能支护结构,包括隧道开挖轮廓线内的钢拱架,其特征在于:
钢拱架的节段之间设置有受压阻尼器;
隧道围岩内环周设置有多个受拉锚杆,受拉锚杆端部通过受拉阻尼器固定于钢拱架的翼缘。
受压阻尼器两端端部通过垫板和螺栓与相邻钢拱架节段相固定。
受拉锚杆端部通过垫板和螺栓与受拉阻尼器一端相固定,受拉阻尼器另一端通过垫板和螺栓与钢拱架翼缘相固定。
本发明具有以下优点:
一、初期支护完成后的初期,通过锚杆和受拉阻尼器对钢拱架的约束,使其在大变形条件下对围岩变形达到边扛边放的效果。
二、围岩变形的发展过程中,通过受压阻尼器使钢拱架能协调变形,确保钢拱架自身不产生变形、错台、扭曲等,初期支护主体结构不破坏,避免对初期支护的拆换。
三、围岩变形达到设计值时,受拉阻尼器和受压阻尼器将对钢拱架提供约束,提高钢拱架的整体刚度和初期支护的整体稳定性,确保隧道安全,并满足净空要求。
附图说明
图1为初期支护的断面图。
图2为图1中的A部初始状态大样图。
图3为图1中的A部稳定状态大样图。
图4为图1中的B部初始状态大样图。
图5为图1中的B部稳定状态大样图。
图中,1-隧道开挖轮廓线,2-钢拱架初始状态中心线,3-钢拱架稳定状态中心线,4-隧道中心线,5-受拉锚杆,6-受压阻尼器,7-受拉阻尼器,8-二次衬砌钢筋混凝土,9-钢拱架,10-螺栓,11-垫板。
具体实施方式
下面结合具体实施方式对本发明进行详细的说明。
本发明涉及的一种用于大变形围岩条件下隧道的消能支护结构,包括隧道开挖轮廓线内的钢拱架9,钢拱架9内侧铺涂二次衬砌钢筋混凝土8。钢拱架9的节段之间设置有受压阻尼器6。隧道围岩内环周设置有多个受拉锚杆5,受拉锚杆5端部通过受拉阻尼器7固定于钢拱架9的翼缘。各部件的数量由隧道开挖面积、开挖方式和受力情况综合确定,钢拱架9的长度由开挖线确定。
受压阻尼器6两端端部通过垫板11和螺栓10与相邻钢拱架9节段相固定,确保受压阻尼器6与钢拱架9共同受力。受拉锚杆5端部通过垫板11和螺栓10与受拉阻尼器7一端相固定,受拉阻尼器7另一端通过垫板11和螺栓10与钢拱架9翼缘相固定,确保受拉锚杆5、受拉阻尼器7和钢拱架9共同受力。
施工过程如下:
在隧道开挖轮廓线1内侧施工受拉锚杆5,长度3-10m,自由端深入隧道变形的塑性区,端头与受拉阻尼器7通过垫板11和螺栓10连接,受拉阻尼器7的初始长度为L1。
受拉锚杆5和受拉阻尼器7施工完成后,沿钢拱架初始状态中心线2施工钢拱架,受拉阻尼器7另一端与钢拱架9翼缘通过垫板11和螺栓10连接,分段的钢拱架9之间通过垫板11和螺栓10用受压阻尼器6连接,受压阻尼器6的初始长度为Y1。
在围岩压力的作用下,受拉阻尼器7初始长度为L1,逐渐被拉长,受压阻尼器6初始长度为Y1,逐渐被压短,一方面对围岩提供抗力,进一步发挥受拉锚杆5的锚固作用,另一方面保证钢拱架9的协调性和完整性前提下,使钢拱架9向隧道内侧收缩,以进一步释放围岩压力。
随着围岩压力的逐渐释放,受拉阻尼器7逐渐被拉长,与此同时,受压阻尼器6逐渐被压短。由于受拉阻尼器7逐渐拉长,进一步发挥了受拉锚杆5的锚固力,达到了对围岩压力边扛边放的效果;受压阻尼器6逐渐被压短,确保了钢拱架在围岩压力逐渐释放的条件下,整体的刚度、协调性以及完整性,避免钢拱架出现变形、错台、扭曲等,也达到了对围岩压力边扛边放的效果。
围岩压力继续释放,受拉阻尼器7继续被拉长,由初始长度L1变为L2,受压阻尼器6继续被压短,由初始长度Y1变为Y2,此时,钢拱架9的中心线由钢拱架初始状态中心线2变为钢拱架9稳定状态中心线3,受拉阻尼器7不能再被拉长,受压阻尼器6不能再被压短,两者均变为刚性连接,与受拉锚杆5和钢拱架9一起共同抵抗围岩压力。在防排水措施施工完成后,最后施工二次衬砌钢筋混凝土确保隧道安全,并满足净空要求。
本发明的内容不限于实施例所列举,本领域普通技术人员通过阅读本发明说明书而对本发明技术方案采取的任何等效的变换,均为本发明的权利要求所涵盖。
Claims (3)
1.用于大变形围岩条件下隧道的消能支护结构,包括隧道开挖轮廓线内的钢拱架(9),其特征在于:
钢拱架(9)的节段之间设置有受压阻尼器(6);
隧道围岩内环周设置有多个受拉锚杆(5),受拉锚杆(5)端部通过受拉阻尼器(7)固定于钢拱架(9)的翼缘。
2.根据权利要求1所述的用于大变形围岩条件下隧道的消能支护结构,其特征在于:
受压阻尼器(6)两端端部通过垫板(11)和螺栓(10)与相邻钢拱架(9)节段相固定。
3.根据权利要求1所述的用于大变形围岩条件下隧道的消能支护结构,其特征在于:
受拉锚杆(5)端部通过垫板(11)和螺栓(10)与受拉阻尼器(7)一端相固定,受拉阻尼器(7)另一端通过垫板(11)和螺栓(10)与钢拱架(9)翼缘相固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710014667.0A CN106703840A (zh) | 2017-01-10 | 2017-01-10 | 用于大变形围岩条件下隧道的消能支护结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710014667.0A CN106703840A (zh) | 2017-01-10 | 2017-01-10 | 用于大变形围岩条件下隧道的消能支护结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106703840A true CN106703840A (zh) | 2017-05-24 |
Family
ID=58907136
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710014667.0A Pending CN106703840A (zh) | 2017-01-10 | 2017-01-10 | 用于大变形围岩条件下隧道的消能支护结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106703840A (zh) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107524457A (zh) * | 2017-10-24 | 2017-12-29 | 仇文革 | 利用材料峰后性能的大行程组合型阻尼器 |
CN110005459A (zh) * | 2019-04-30 | 2019-07-12 | 中铁第四勘察设计院集团有限公司 | 公路隧道钢带的连接结构以及让压锚杆支护系统 |
CN110031289A (zh) * | 2017-08-20 | 2019-07-19 | 韩少鹏 | 岩土工程围岩变形实验装置 |
CN111691901A (zh) * | 2020-06-11 | 2020-09-22 | 中铁工程设计咨询集团有限公司 | 一种隧道消能减震方法 |
CN111691918A (zh) * | 2020-06-11 | 2020-09-22 | 中铁工程设计咨询集团有限公司 | 一种隧道消能减震装置 |
CN111764930A (zh) * | 2020-06-05 | 2020-10-13 | 中南大学 | 一种带蜂窝吸能装置的隧道支护结构及其施工方法 |
CN112282799A (zh) * | 2020-11-02 | 2021-01-29 | 辽宁工程技术大学 | 一种支锚一体限阻耗能大变形隧道初期支护结构与施工方法 |
CN113982628A (zh) * | 2021-10-29 | 2022-01-28 | 成都未来智隧科技有限公司 | 一种隧道支护结构 |
CN114135322A (zh) * | 2021-11-22 | 2022-03-04 | 中铁十六局集团第三工程有限公司 | 一种大变形隧道防钢架扭曲的加强方法 |
CN115013006A (zh) * | 2022-05-05 | 2022-09-06 | 甘肃景礼高速公路陇南管理有限公司 | 可缩拱架装置和拱架 |
CN118462253A (zh) * | 2024-07-15 | 2024-08-09 | 湖南科技大学 | 一种隧道钢拱架支护结构及其让压控制方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3908970C1 (en) * | 1989-03-18 | 1990-08-23 | Bochumer Eisenhuette Heintzmann Gmbh & Co Kg, 4630 Bochum, De | Support element for mine roadways and tunnels |
CN103850688A (zh) * | 2014-03-24 | 2014-06-11 | 昆明理工大学 | 一种复杂断层破碎带大断面巷道动态迭加耦合支护方法 |
CN104047612A (zh) * | 2014-06-25 | 2014-09-17 | 安徽理工大学 | 一种深部巷道可缩性复合支护结构 |
CN106285724A (zh) * | 2016-10-14 | 2017-01-04 | 成都理工大学 | 一种隧道让压式支护体系 |
CN206439059U (zh) * | 2017-01-10 | 2017-08-25 | 中铁第一勘察设计院集团有限公司 | 一种用于大变形围岩条件下隧道的消能支护结构 |
-
2017
- 2017-01-10 CN CN201710014667.0A patent/CN106703840A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3908970C1 (en) * | 1989-03-18 | 1990-08-23 | Bochumer Eisenhuette Heintzmann Gmbh & Co Kg, 4630 Bochum, De | Support element for mine roadways and tunnels |
CN103850688A (zh) * | 2014-03-24 | 2014-06-11 | 昆明理工大学 | 一种复杂断层破碎带大断面巷道动态迭加耦合支护方法 |
CN104047612A (zh) * | 2014-06-25 | 2014-09-17 | 安徽理工大学 | 一种深部巷道可缩性复合支护结构 |
CN106285724A (zh) * | 2016-10-14 | 2017-01-04 | 成都理工大学 | 一种隧道让压式支护体系 |
CN206439059U (zh) * | 2017-01-10 | 2017-08-25 | 中铁第一勘察设计院集团有限公司 | 一种用于大变形围岩条件下隧道的消能支护结构 |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110031289A (zh) * | 2017-08-20 | 2019-07-19 | 韩少鹏 | 岩土工程围岩变形实验装置 |
CN110031289B (zh) * | 2017-08-20 | 2021-12-24 | 河南省地质工程勘察院有限公司 | 岩土工程围岩变形实验装置 |
CN107524457A (zh) * | 2017-10-24 | 2017-12-29 | 仇文革 | 利用材料峰后性能的大行程组合型阻尼器 |
CN107524457B (zh) * | 2017-10-24 | 2019-06-25 | 仇文革 | 利用材料峰后性能的大行程组合型阻尼器 |
CN110005459A (zh) * | 2019-04-30 | 2019-07-12 | 中铁第四勘察设计院集团有限公司 | 公路隧道钢带的连接结构以及让压锚杆支护系统 |
CN111764930A (zh) * | 2020-06-05 | 2020-10-13 | 中南大学 | 一种带蜂窝吸能装置的隧道支护结构及其施工方法 |
CN111691918A (zh) * | 2020-06-11 | 2020-09-22 | 中铁工程设计咨询集团有限公司 | 一种隧道消能减震装置 |
CN111691901A (zh) * | 2020-06-11 | 2020-09-22 | 中铁工程设计咨询集团有限公司 | 一种隧道消能减震方法 |
CN112282799A (zh) * | 2020-11-02 | 2021-01-29 | 辽宁工程技术大学 | 一种支锚一体限阻耗能大变形隧道初期支护结构与施工方法 |
CN113982628A (zh) * | 2021-10-29 | 2022-01-28 | 成都未来智隧科技有限公司 | 一种隧道支护结构 |
CN114135322A (zh) * | 2021-11-22 | 2022-03-04 | 中铁十六局集团第三工程有限公司 | 一种大变形隧道防钢架扭曲的加强方法 |
CN115013006A (zh) * | 2022-05-05 | 2022-09-06 | 甘肃景礼高速公路陇南管理有限公司 | 可缩拱架装置和拱架 |
CN118462253A (zh) * | 2024-07-15 | 2024-08-09 | 湖南科技大学 | 一种隧道钢拱架支护结构及其让压控制方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106703840A (zh) | 用于大变形围岩条件下隧道的消能支护结构 | |
CN206439059U (zh) | 一种用于大变形围岩条件下隧道的消能支护结构 | |
CN202140098U (zh) | 基于变形可控释放的软岩大变形隧道支护结构 | |
CN207080233U (zh) | 软岩大变形隧道支护的刚柔性拱架 | |
CN109989768B (zh) | 一种适用于隧道穿越活断层的衬砌结构及其施工方法 | |
CN204691789U (zh) | 一种可调节的隧道支护结构 | |
CN103527219A (zh) | 用于大变形地层的隧道支护结构及其施工工法 | |
CN201241712Y (zh) | 大变形地层隧道初期支护结构 | |
CN102011595B (zh) | 煤岩巷道冲击让位吸能支护装置 | |
CN101922301A (zh) | 一种穿越上高下深溶洞的隧道防护结构 | |
CN205370580U (zh) | 深部强动载巷道防冲抗压支护结构 | |
CN106523003A (zh) | 一种适于深部开采巷道的刚柔耦合吸能支护技术 | |
JP2023538226A (ja) | 山跳ね坑道の三次予防制御方法 | |
CN108506026A (zh) | 一种高强预压锚杆与流质包裹体联合作用的隧道衬砌结构 | |
CN103061779B (zh) | 矿山隧道新型支护结构的施工方法 | |
CN108360560A (zh) | 一种适用于抢险救灾的装配式钢箱棚洞及施工方法 | |
CN103758125A (zh) | 挤压锁头弹簧承压板应力分散型大吨位扩大头锚索 | |
CN209892222U (zh) | 支护装置 | |
CN202991054U (zh) | 矿山隧道新型支护结构 | |
CN210460696U (zh) | 一种巷道内壁注浆加固结构 | |
CN206785400U (zh) | 一种缓冲型高强度矿井支护体系 | |
CN205117354U (zh) | 具有拱脚临时加强装置的钢筋格栅群 | |
CN111852512A (zh) | 一种煤矿巷道底板型冲击地压防治装置及使用方法 | |
CN102996142B (zh) | 矿山隧道吊环固定式支护结构的施工方法 | |
CN102392662A (zh) | 一种弯曲式动静组合锚杆 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170524 |