CN106640193A - Intelligent mine exploration system - Google Patents

Intelligent mine exploration system Download PDF

Info

Publication number
CN106640193A
CN106640193A CN201510716933.5A CN201510716933A CN106640193A CN 106640193 A CN106640193 A CN 106640193A CN 201510716933 A CN201510716933 A CN 201510716933A CN 106640193 A CN106640193 A CN 106640193A
Authority
CN
China
Prior art keywords
mine
sensor
intelligent
production
intelligent mine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510716933.5A
Other languages
Chinese (zh)
Inventor
不公告发明人
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Harbin Yonghengxin Technology Development Co Ltd
Original Assignee
Harbin Yonghengxin Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Harbin Yonghengxin Technology Development Co Ltd filed Critical Harbin Yonghengxin Technology Development Co Ltd
Priority to CN201510716933.5A priority Critical patent/CN106640193A/en
Publication of CN106640193A publication Critical patent/CN106640193A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention discloses an intelligent mine exploration system. The intelligent mine exploration system comprises a sensing system installed under a mine and a production control system, a data transmission system, a data acquisition and analysis system and a feedback system which are electrically connected with the sensing system; the sensing system is composed of multiple sensors. According to the intelligent mine exploration system, the purpose of monitoring, diagnosing, analyzing and metering the work condition of the mine in real time within 24 hours is achieved, mine production is effectively optimized, and then correct decisions are made for optimizing operation on the production field of a single mine or even a whole mine.

Description

A kind of intelligent mine survey system
Technical field
The invention belongs to mineral products energy-saving field, and in particular to a kind of intelligent mine survey system.
Background technology
There is problems with current mine acquisition system:Data admission promptness it is poor, admission data need multiple management personnel process, process is more, anthropic factor is more, time length, impact data application;Time-consuming for data admission, and investigation once needs the time of two to five days, and poor in timeliness, labor intensive is more, and specific aim is poor;Data admission is larger by scene, weather influence;Scene and pit shaft produced problem can not in time be found to mine monitor in real time;The real production time efficiency of mine can not in time be controlled.Therefore, in order to solve problem above, a kind of intelligent mine survey system is designed.
The content of the invention
(One)The technical problem to be solved
To solve the above problems, the present invention proposes a kind of intelligent mine survey system, 24 hours are realized to mine operating mode real-time monitoring, diagnostic analysiss and metering, effectively optimizes shaft production, and then to individual well until correct decisionss are made in the optimization operation at whole shaft production scene.
(Two)Technical scheme
The intelligent mine survey system of the present invention, including the sensor-based system under the mine, and production control system, data transmission system, Data collecting and analysis system and the feedback system electrically connected with sensor-based system;The sensor-based system by multiple sensor groups into.
Further, the sensor includes temperature sensor, pressure transducer, relative density sensor and humidity sensor.
Further, the outfan of the production control system is electrically connected with production equipment.
(Three)Beneficial effect
The present invention is compared with prior art, the intelligent mine survey system of the present invention, the temperature below mine is detected by multiple sensors, pressure, relative density and humidity, and these information are analyzed into process through Data collecting and analysis system, again by the data transmission system that electrically connects with sensor-based system by the data transfer after analysis to production control system, operation is controlled to production equipment by production control system, carry out corresponding action, and utilize feedback system, by feedback of the information, 24 hours can be realized to mine operating mode real-time monitoring, diagnostic analysiss and metering, effectively optimize shaft production, and then to individual well until correct decisionss are made in the optimization operation at whole shaft production scene.
Description of the drawings
Fig. 1 is the structural representation of the present invention.
Specific embodiment
A kind of intelligent mine survey system as shown in Figure 1, including the sensor-based system under mine, and production control system, data transmission system, Data collecting and analysis system and the feedback system electrically connected with sensor-based system;The sensor-based system by multiple sensor groups into.
The sensor includes temperature sensor, pressure transducer, relative density sensor and humidity sensor.
The outfan of the production control system is electrically connected with production equipment.
The operation principle of the intelligent mine survey system of the present invention:The temperature below mine is detected by multiple sensors, pressure, relative density and humidity, and these information are analyzed into process through Data collecting and analysis system, again by the data transmission system that electrically connects with sensor-based system by the data transfer after analysis to production control system, operation is controlled to production equipment by production control system, carry out corresponding action, and utilize feedback system, by feedback of the information, 24 hours can be realized to mine operating mode real-time monitoring, diagnostic analysiss and metering, effectively optimize shaft production, and then to individual well until correct decisionss are made in the optimization operation at whole shaft production scene.
Embodiment described above is only that the preferred embodiment of the present invention is described, and not the spirit and scope of the present invention are defined.On the premise of without departing from design concept of the present invention; various modifications and improvement that this area ordinary person makes to technical scheme; protection scope of the present invention all should be dropped into, the technology contents that the present invention is claimed all have been recorded in detail in the claims.

Claims (3)

1. a kind of intelligent mine survey system, it is characterised in that:Including the sensor-based system under the mine, and production control system, data transmission system, Data collecting and analysis system and the feedback system electrically connected with sensor-based system;The sensor-based system by multiple sensor groups into.
2. intelligent mine survey system according to claim 1, it is characterised in that:The sensor includes temperature sensor, pressure transducer, relative density sensor and humidity sensor.
3. intelligent mine survey system according to claim 1, it is characterised in that:The outfan of the production control system is electrically connected with production equipment.
CN201510716933.5A 2015-10-30 2015-10-30 Intelligent mine exploration system Pending CN106640193A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510716933.5A CN106640193A (en) 2015-10-30 2015-10-30 Intelligent mine exploration system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510716933.5A CN106640193A (en) 2015-10-30 2015-10-30 Intelligent mine exploration system

Publications (1)

Publication Number Publication Date
CN106640193A true CN106640193A (en) 2017-05-10

Family

ID=58830126

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510716933.5A Pending CN106640193A (en) 2015-10-30 2015-10-30 Intelligent mine exploration system

Country Status (1)

Country Link
CN (1) CN106640193A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610279A (en) * 2020-12-18 2021-04-06 福州华虹智能科技股份有限公司 Monitoring system for underground exploration based on Internet of things

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112610279A (en) * 2020-12-18 2021-04-06 福州华虹智能科技股份有限公司 Monitoring system for underground exploration based on Internet of things

Similar Documents

Publication Publication Date Title
CN103115667B (en) A kind of sensor-based vibration monitoring device
WO2007088539A3 (en) Method device and system for monitoring lung ventilation
CN203643834U (en) Fault diagnosis system of mining main ventilator
CA2840969C (en) Systems, computer medium and computer-implemented methods for monitoring and improving biometric health of employees
WO2010089747A3 (en) System and methods for health monitoring of anonymous animals in livestock groups
WO2013006636A3 (en) Systems, computer medium and computer-implemented methods for coaching employees based upon monitored health conditions using an avatar
CN107860425A (en) Bridge structure health monitoring and early warning system and method
MY167414A (en) Modeling an interpretation of real time compaction modeling data from multi-section monitoring system
CN106815667A (en) Large-scale scientific research apparatus monitor in real time based on wireless Internet and use management system
CN204646218U (en) A kind of modernization drilling data acquisition monitoring system
CN106023643A (en) Internet of things-based novel vehicle detection device
CN202494677U (en) Small-size integration multi-parameter water quality digital online detector
CN106092212A (en) Storage environment monitoring system
CN204154335U (en) A kind of silo humiture remote supervision system
CN103899357A (en) System and method for real-time visual monitoring and early warning of mine floor water disasters
CN110195588A (en) Integrating Construction Machinery with Information Technology system, engineering machinery, development machine and information-based method
CN106640193A (en) Intelligent mine exploration system
CN104101382A (en) Monitoring device for health conditions of bridges and buildings
CN102494717A (en) Engineering machinery fault diagnosis system based on sensor data wireless transmission
CN206671361U (en) Mine laneway wind speed and pressure monitoring system
CN206147322U (en) Intelligent control system for metal structure equipment of hydropower station
CN103731446A (en) Workshop environment integrated monitoring system based on wireless sensor network
CN203455673U (en) Fruit catalytic house remote monitoring system
CN106777347A (en) A kind of unmanned plane power-line patrolling big data processing system
CN205373765U (en) Intelligence environmental monitoring system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170510