CN106639291A - Mounting method for bowl-type embedded cushion block of scaffold upright rod - Google Patents

Mounting method for bowl-type embedded cushion block of scaffold upright rod Download PDF

Info

Publication number
CN106639291A
CN106639291A CN201611150193.4A CN201611150193A CN106639291A CN 106639291 A CN106639291 A CN 106639291A CN 201611150193 A CN201611150193 A CN 201611150193A CN 106639291 A CN106639291 A CN 106639291A
Authority
CN
China
Prior art keywords
upright rod
scaffold upright
parallels
pedestal
cushion block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611150193.4A
Other languages
Chinese (zh)
Inventor
孙高军
甘伟
刘勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA 19TH METALLURGICAL CORP (FANGCHENGGANG) EQUIPMENT STRUCTURE Co Ltd
Original Assignee
CHINA 19TH METALLURGICAL CORP (FANGCHENGGANG) EQUIPMENT STRUCTURE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA 19TH METALLURGICAL CORP (FANGCHENGGANG) EQUIPMENT STRUCTURE Co Ltd filed Critical CHINA 19TH METALLURGICAL CORP (FANGCHENGGANG) EQUIPMENT STRUCTURE Co Ltd
Priority to CN201611150193.4A priority Critical patent/CN106639291A/en
Publication of CN106639291A publication Critical patent/CN106639291A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/02Scaffold feet, e.g. with arrangements for adjustment

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a mounting method for a bowl-type embedded cushion block of a scaffold upright rod. The mounting method comprises the implementing steps that a cylindrical sizing block is made, a notch is formed in the center of the top of the sizing block according to the rod diameter of the scaffold upright rod, and the bottom size of the notch is matched with the rod diameter of the scaffold upright rod; a base is made of a friction type material, and the sizing block adopting an embedded structure is mounted on the upper portion of the base; and the sizing block and the base are cushioned between the scaffold upright rod and an adhering structure, specifically, the base is placed on the adhering structure, and the bottom of the scaffold upright rod is supported in the notch of the sizing block. A set of special-use cushioning pieces is made purposely, so that the scaffold upright rod and the adhering structure are reliably connected, stability of the scaffold upright rod is achieved, the situation that the surface of the adhering structure is not destroyed is guaranteed, the transmission force effect is good, and the safety and quality of construction are effectively guaranteed.

Description

The embedded cushion block installation method of scaffold upright rod bowl formula
Technical field
The present invention relates to construction equipment is used, the embedded cushion block installation method of specially a kind of scaffold upright rod bowl formula.
Background technology
With domestic all kinds of construction market expanding days, the security to constructing proposes requirements at the higher level, to Architectural Construction The high-quality of thing requires also more and more urgent.
Former scaffold upright rod bottom is typically using plank or flitch cushion block, and its non-skid property is poor, easily produces slip, and Scratch structure surface;It is easily rotten under the long-term wet environment such as rainwater, is likely to result in the potential safety hazard and construction of construction The mass defect of thing.
The content of the invention
For the deficiencies in the prior art, the technical problem to be solved is to propose one kind to guarantee scaffold upright rod Being reliably connected between attaching structure thing, does not destroy original structure thing surface quality, it is ensured that the scaffold of construction safety and quality The embedded cushion block installation method of vertical rod bowl formula.
The embedded cushion block installation method of scaffold upright rod bowl formula of above-mentioned technical problem is can solve the problem that, implementation step is:
1st, cylindrical pad iron is made, recess is opened up out in the center of top of parallels according to the bar footpath of scaffold upright rod, it is described The bottom size of recess matches the bar footpath of scaffold upright rod.
2nd, pedestal is made using friction type material, the parallels is installed on pedestal top using damascene structures.
3rd, parallels and pedestal are paid for first between scaffold upright rod and attaching structure thing, i.e., pedestal is positioned over attaching structure thing On, the bottom of scaffold upright rod is supported in the recess of parallels.
The parallels is with the embedded structure of pedestal:Parallels gap is matched with the blind hole that pedestal center of top is opened up.
To ensure embedded stability, the depth that the parallels gap is matched with pedestal blind hole is at least 1/2 parallels height.
The recess preferably adopts the rim of a bowl shape.
For durable in use, the parallels is made using high-strength steel.
To avoid sliding, the pedestal is made using friction type material.
Beneficial effects of the present invention:
1st, the present invention disposed it is a set of it is special pay for part first, scaffold upright rod is reliably connected with attaching structure thing, solve A difficult problem for scaffold upright rod stability of having determined, it is ensured that the surface of attaching structure thing is not destroyed, power transmission effect is good, is effectively ensured and applies The safety and quality of work.
2nd, in present configuration, parallels can be separately fabricated according to different vertical rod external diameters, strong adaptability.
3rd, the present invention takes pedestal and parallels to make respectively, can be mass, favourable reduces cost.
4th, the present invention takes parallels and pedestal embedding grammar to be connected scheme, simple structure, easy to manufacture, using spirit Living, effect is obvious, beneficial to popularization and application.
Description of the drawings
Fig. 1 is the structural front view of one embodiment of the present invention.
Fig. 2 is the top view of Fig. 1 embodiments.
Figure number is identified:1st, parallels;2nd, pedestal;3rd, recess;4th, scaffold upright rod;5th, attaching structure thing.
Specific embodiment
Below in conjunction with the accompanying drawings illustrated embodiment is described further to technical scheme.
Scaffold upright rod bowl formula of the present invention is embedded in cushion block installation method, and implementation step is:
1st, cylindrical pad iron 1 is made, the parallels 1 is made using high-strength steel, according to the bar footpath of scaffold upright rod 4 in parallels 1 center of top opens up out a bowl formula recess 3, and the bottom size of bowl formula recess 3 matches the bar footpath of scaffold upright rod 4.
2nd, pedestal 2 is made using friction type material, the pedestal 2 is cube shape, and the parallels 1 is pacified using damascene structures Loaded on the top of pedestal 2, the damascene structures are matched with the blind hole that the center of top of pedestal 2 is opened up for the gap of parallels 1, are embedded in deep Degree is at least the height of 1/2 parallels 1.
3rd, pedestal 2 is positioned on attaching structure thing 5 and corresponding to the support level regulation good position of scaffold upright rod 4, pin hand The bottom setting for erecting bar 4 is supported in the bowl formula recess 3 of parallels 1.

Claims (6)

1. the embedded cushion block installation method of scaffold upright rod bowl formula, it is characterised in that implementation steps are:
1., cylindrical pad iron (1) is made, recess is opened up out in the center of top of parallels (1) according to the bar footpath of scaffold upright rod (4) (3), the bar footpath of bottom size matching scaffold upright rod (4) of the recess (3);
2., pedestal (2) is made using friction type material, the parallels (1) is installed on pedestal (2) top using damascene structures;
3., parallels (1) and pedestal (2) are paid for first between scaffold upright rod (4) and attaching structure thing (5), i.e., pedestal (2) is positioned over On attaching structure thing (5), the bottom of scaffold upright rod (4) is supported in the recess (3) of parallels (1).
2. scaffold upright rod bowl formula according to claim 1 is embedded in cushion block installation method, it is characterised in that:The parallels (1) it is matched with the blind hole that pedestal (2) center of top is opened up for parallels (1) gap with the damascene structures of pedestal (2).
3. scaffold upright rod bowl formula according to claim 2 is embedded in cushion block installation method, it is characterised in that:The parallels (1) gap be matched with pedestal (2) blind hole depth be at least 1/2 parallels (1) height.
4. the embedded cushion block installation method of scaffold upright rod bowl formula according to any one in claims 1 to 3, its feature exists In:The recess (3) is the rim of a bowl shape.
5. the embedded cushion block installation method of scaffold upright rod bowl formula according to any one in claims 1 to 3, its feature exists In:The parallels (1) is made using high-strength steel.
6. the embedded cushion block installation method of scaffold upright rod bowl formula according to any one in claims 1 to 3, its feature exists In:The pedestal (2) is made using friction type material.
CN201611150193.4A 2016-12-14 2016-12-14 Mounting method for bowl-type embedded cushion block of scaffold upright rod Pending CN106639291A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611150193.4A CN106639291A (en) 2016-12-14 2016-12-14 Mounting method for bowl-type embedded cushion block of scaffold upright rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611150193.4A CN106639291A (en) 2016-12-14 2016-12-14 Mounting method for bowl-type embedded cushion block of scaffold upright rod

Publications (1)

Publication Number Publication Date
CN106639291A true CN106639291A (en) 2017-05-10

Family

ID=58825124

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611150193.4A Pending CN106639291A (en) 2016-12-14 2016-12-14 Mounting method for bowl-type embedded cushion block of scaffold upright rod

Country Status (1)

Country Link
CN (1) CN106639291A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB368436A (en) * 1930-12-24 1932-03-10 Ronald William Walker Improvements relating to struts, scaffolds, and the like
CN202672699U (en) * 2012-06-18 2013-01-16 海门市设备安装工程有限公司 Steel pipe scaffold non-metallic chassis
CN203961251U (en) * 2014-04-30 2014-11-26 浙江广厦建设职业技术学院 A kind of console mode scaffold upright rod Prefabricated Concrete cushion block
CN104727540A (en) * 2013-12-19 2015-06-24 孙黎明 Footing plate unit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB368436A (en) * 1930-12-24 1932-03-10 Ronald William Walker Improvements relating to struts, scaffolds, and the like
CN202672699U (en) * 2012-06-18 2013-01-16 海门市设备安装工程有限公司 Steel pipe scaffold non-metallic chassis
CN104727540A (en) * 2013-12-19 2015-06-24 孙黎明 Footing plate unit
CN203961251U (en) * 2014-04-30 2014-11-26 浙江广厦建设职业技术学院 A kind of console mode scaffold upright rod Prefabricated Concrete cushion block

Similar Documents

Publication Publication Date Title
CN203924104U (en) A kind of blower foundation
CN203037472U (en) Static-load test apparatus for petroleum drilling machine
CN204267465U (en) A kind of novel nine point type expansion anchors
CN106639291A (en) Mounting method for bowl-type embedded cushion block of scaffold upright rod
CN206319570U (en) Scaffold upright rod bowl formula insertion cushion block
CN106481063A (en) Scaffold upright rod bowl formula is embedded in cushion block
CN106284403A (en) The construction method of reserving hole
CN202370100U (en) Joint connection device for container reconstructed house
CN205178033U (en) Grounding device
CN205399921U (en) Floor support
CN204609697U (en) Magnetic control sound insulating and absorbing door
CN103762540A (en) Pressure welding type lightning strip support
CN201850688U (en) Novel installing structure for embedding ceilings in hiding manner
CN207609103U (en) A kind of movable railing of flooring platform
CN207392693U (en) Improve the stainless steel door installation tool of installation quality
CN205781418U (en) Adapt to the petroleum pipeline system of sinking geology
CN203174835U (en) Combination hanging piece and beam-free ceramic gravel curtain wall system
CN202658758U (en) Base shock isolation house with anti-rust sheet slot filled with glass beads and fine sand
CN205712165U (en) Stone bolt for heavy equipment fixture
CN205399687U (en) Double tower building vestibule connecting device
CN205781417U (en) It is prone to the petroleum pipeline system of location
CN211058375U (en) Supporting device for repairing ancient buildings
CN204691159U (en) A kind of stone structure with steel construction piece
CN203781568U (en) Height-adjustable elevator buffer cushion abutment
CN204738554U (en) Controllable off -load ware of formula of buryying

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170510