CN106638680A - Building method of biogas digester - Google Patents
Building method of biogas digester Download PDFInfo
- Publication number
- CN106638680A CN106638680A CN201611136258.XA CN201611136258A CN106638680A CN 106638680 A CN106638680 A CN 106638680A CN 201611136258 A CN201611136258 A CN 201611136258A CN 106638680 A CN106638680 A CN 106638680A
- Authority
- CN
- China
- Prior art keywords
- digester
- top cover
- methane
- layer
- biogas
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a building method of a biogas digester. The method is characterized by including the following steps that setting-out is conducted according to the design size; a digester pit is dug; a reinforced concrete digester base of a set size is built in the digester pit, wherein the digester base is cylindrical; an arch top cover is spirally built at the upper end of the digester base with bricks, wherein the arch top cover and the digester base serve as a biogas digester base body; one side of the bottom end of the biogas digester is provided with a discharging port, and the top cover is provided with a gas outlet and a feeding port; the exterior of the biogas digester base body is paved with a rebar mesh and three sand-cement coatings, and the inner wall of the biogas digester base body is brushed with cement paste three times. The biogas digester built through the method is solid and durable and does not crack or leak gas or water. The method is beneficial to development, application and popularization of the new energy of biogas.
Description
Technical field
The present invention relates to a kind of preparation method of methane-generating pit, belongs to technical field of new energies.
Background technology
Biogas is that a kind of straw and human and animal excreta of fermentation in new forms of energy, methane-generating pit is produced outside biogas, its methane liquid
And tunning is fertilizer, green plantss cultivation can be promoted to plant application of organic fertilizers, be conducive to health.But
It is that current biogas is promoted the use of and encounters exceptional hardship, one of them is the easy gas leakage of methane-generating pit, and oxygen enters methane-generating pit, and destruction is detested
The growth and breeding of oxygen bacterium, so that methane-generating pit cannot produce biogas.
The purpose of the present invention, is to provide a kind of preparation method of methane-generating pit, and the methane-generating pit prepared using the present invention is firm resistance to
With, it is air tight, be conducive to promoting the use of for biogas.
The content of the invention
It is an object of the invention to provide a kind of preparation method of methane-generating pit, using methane-generating pit made by the inventive method, no
Gas leakage, sturdy and durable, long service life, are conducive to promoting the use of for new forms of energy biogas.
Using technical scheme be:
A kind of manufacture method of methane-generating pit, it is characterised in that comprise the steps:
By design size setting-out, Wa Chikeng, the stall of the armored concrete being sized is built in the hole of pond, stall is cylinder
Shape, in stall upper end, arch top cover is built in brick rotation, and arch top cover is methane-generating pit matrix with stall.
There is discharging opening methane-generating pit bottom side, there is gas outlet and charging aperture on top cover.
Bar-mat reinforcement is spread outside methane-generating pit matrix and adds three layers of husky cementitious coating and methane-generating pit matrix inwall three cement mortars of brush.
The methane-generating pit prepared with the inventive method is sturdy and durable, is not cracked, air tight, water-tight.
The present invention is conducive to the exploitation of biogas new forms of energy and promotes the use of.
Description of the drawings
Fig. 1 is the biomass pool structure schematic diagram of the present invention.
Specific embodiment
Embodiment one
A kind of preparation method of methane-generating pit, it is characterised in that comprise the steps:
1), dig melt pit, diameter 5m, high 4.4m.
2), build a methane generating pit pedestal 1 in hole, the internal diameter r of methane-generating pit pedestal 1 is 4m, and high 1.5m, pedestal 1 is reinforced concrete
Soil matrix seat, wall thickness 120mm.
3), in the upper end brick rotation of pedestal 1 set arch top cover 2, the inside and outside wall of top cover 2 concrete brushing and the thickness one of pedestal 1
Sample, and be biomass pool body for an overall structure.
4), be provided with biomass pool body arch top cover 2 charging aperture 3 and gas outlet 4, discharging opening 5 is left in biomass pool body bottom,
Discharging opening internal diameter is 1.2m, and the bar-mat reinforcement 6 of 100 100mm is laid on biomass pool body outer wall, then erects and applies the thick of 15-20mm thickness
Husky cement layer 7, bar-mat reinforcement is embedded in rough sand cement layer, wet curing 12-24 hours, then laterally brushes husky cement layer 8, thick
10-15mm, vertically applies again fine sand cement layer 9, thick 10-15mm, wet curing after wet curing 12-24 hours.
5), from discharging opening 5 enter biomass pool body in, one layer of cement mortar of vertical brush, slightly dry one layer of cement mortar of horizontal brush again, slightly
It is dry, last one layer of cement mortar of vertical brush again.
6), seal charging aperture, discharging opening and gas outlet, suppress(Water or air pressure), without leakage phenomenon after, from discharging opening by repairing
Expects pipe 10 arrives ground.
7), backfill, compacting.The methane-generating pit arch top cover upper end 400-450cm that bankets is thick, obtains final product.
Claims (1)
1. a kind of preparation method of methane-generating pit, it is characterised in that comprise the steps:
1), dig melt pit, diameter 5m, high 4.4m;
2), build a methane generating pit pedestal in hole(1), methane-generating pit pedestal(1)Internal diameter r be 4m, high 1.5m, pedestal(1)It is mixed for reinforcing bar
Solidifying soil matrix seat, wall thickness 120mm;
3), in pedestal(1)Upper end brick rotation sets arch top cover(2), top cover(2)Inside and outside wall concrete brushing and pedestal(1)It is thick
Degree is the same, and is biomass pool body for an overall structure;
4), in biomass pool body arch top cover(2)It is provided with charging aperture(3)And gas outlet(4), discharging opening is left in biomass pool body bottom
(5), discharging opening internal diameter is 1.2m, and the bar-mat reinforcement of 100 100mm is laid on biomass pool body outer wall(6), then erect and apply 15-20mm
Thick rough sand cement layer(7), bar-mat reinforcement is embedded in rough sand cement layer, wet curing 12-24 hours, then laterally brush husky water
Mud layer(8), thick 10-15mm, after wet curing 12-24 hours again vertically apply fine sand cement layer(9), thick 10-15mm, water spray support
Shield;
5), from discharging opening(5)Into in biomass pool body, one layer of cement mortar of vertical brush, slightly dry one layer of cement mortar of horizontal brush again, slightly
It is dry, last one layer of cement mortar of vertical brush again;
6), seal charging aperture, discharging opening and gas outlet, suppress, without leakage phenomenon after, from discharging opening by repairing expects pipe(10)To ground
Face.
7), backfill, compacting;The methane-generating pit arch top cover upper end 400-450cm that bankets is thick, obtains final product.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611136258.XA CN106638680A (en) | 2016-12-12 | 2016-12-12 | Building method of biogas digester |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611136258.XA CN106638680A (en) | 2016-12-12 | 2016-12-12 | Building method of biogas digester |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106638680A true CN106638680A (en) | 2017-05-10 |
Family
ID=58825494
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611136258.XA Pending CN106638680A (en) | 2016-12-12 | 2016-12-12 | Building method of biogas digester |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638680A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109534637A (en) * | 2018-12-25 | 2019-03-29 | 李建华 | A kind of automatic quickly residue-removing methane tank and its construction method |
-
2016
- 2016-12-12 CN CN201611136258.XA patent/CN106638680A/en active Pending
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109534637A (en) * | 2018-12-25 | 2019-03-29 | 李建华 | A kind of automatic quickly residue-removing methane tank and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206266551U (en) | Wine fermentation tank | |
CN106638680A (en) | Building method of biogas digester | |
CN108911605A (en) | A kind of method that microorganism induction precipitation of calcium carbonate produces prefabricated drainage pipeline under subnormal ambient | |
CN201250233Y (en) | Tunnel biogas pool with water return on the top | |
Kalia et al. | Development of a biogas plant | |
CN205874399U (en) | Large -scale methane system based on boiler room carries out anaerobic digestion | |
CN103215181B (en) | Internal and external sealing treatment method for biogas digester | |
CN105481217B (en) | Harmless biological degraded pond | |
CN101871234A (en) | Biochemical recovery second-generation toilet seat and matching apparatus thereof | |
CN201296753Y (en) | Horizontal-flow biogas tank | |
CN201883091U (en) | Solar energy methane generator | |
CN105441315B (en) | A kind of gas chamber of marsh gas tank builds encapsulation process method | |
CN102190414A (en) | Double-vat type toilet septic tank | |
CN101538529B (en) | Compound water congealing ready-package marsh gas generator and production method | |
CN114808921A (en) | Recyclable spiral-advancing type anchor rod-microorganism grouting reinforcement device and method | |
CN205275582U (en) | Two membrane isolation methane -generating pits | |
CN206902004U (en) | A kind of glass toughening manure pit of antiseep | |
CN106047671A (en) | Integrated biogas production device with circulating heating function | |
CN206692637U (en) | A kind of armored concrete prefabricated biogas generating pit system | |
CN220450912U (en) | Manhole structure of basement wall group sleeve | |
CN108756288B (en) | Traditional soil kiln resident housing surface layer reinforcing and compensating structure and construction process thereof | |
CN202077485U (en) | Subsidence-resistant and easily cleaned culture pond | |
CN108570400B (en) | External thermal insulation system of soft methane tank | |
CN215953601U (en) | Self-flowing type microorganism porous grouting experimental device | |
CN210858142U (en) | Double-pit alternative toilet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170510 |