CN106638556A - Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method - Google Patents

Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method Download PDF

Info

Publication number
CN106638556A
CN106638556A CN201710028541.9A CN201710028541A CN106638556A CN 106638556 A CN106638556 A CN 106638556A CN 201710028541 A CN201710028541 A CN 201710028541A CN 106638556 A CN106638556 A CN 106638556A
Authority
CN
China
Prior art keywords
heat energy
soft soil
evacuation
soil foundation
vacuum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710028541.9A
Other languages
Chinese (zh)
Inventor
刘晓立
成子育
聂宁
刘广斌
高长满
李俊明
付旭
赵新春
赵少锋
李志�
王海鸥
蒙艳蕾
马晋峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Institute of Aerospace Engineering
Original Assignee
North China Institute of Aerospace Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Institute of Aerospace Engineering filed Critical North China Institute of Aerospace Engineering
Priority to CN201710028541.9A priority Critical patent/CN106638556A/en
Publication of CN106638556A publication Critical patent/CN106638556A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/11Improving or preserving soil or rock, e.g. preserving permafrost soil by thermal, electrical or electro-chemical means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0053Production methods using suction or vacuum techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0032Steel; Iron in sheet form, i.e. bent or deformed plate-material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention relates to a foundation treatment technology, in particular to a heat energy reinforced vacuum preloading soft foundation drainage structure and a drainage method. A vacuum preloading method is used for forming vacuum negative pressure in a soft foundation, and meanwhile, heat energy is conveyed into the soft foundation through a heat energy injecting system by a certain injecting pressure, so that the temperature of the soft foundation in a certain range with a heat energy injecting well as center is increased. According to the thermodynamic principle, the air pressure is lower, the boiling point of water is lower; the water in holes of soft soil can be boiled more quickly to form free-state water vapor; and gas in the holes is heated to expand to accelerate flowing. As the injecting pressure is higher than the pressure of the holes in the soft soil, the injected heat energy drives the free-state water vapor and the thermal expansion gas to permeate to a drainage system in the soft soil and to extract out from the soft foundation by a vacuumizing device, the foundation is settled, and the purposes of shortening the construction period and accelerating the reinforcing rate are achieved.

Description

A kind of heat energy strengthens vacuum pre-pressed soft soil foundation discharge structure and water discharge method
Technical field
The present invention relates to foundation treatment technology, more particularly to a kind of heat energy strengthen vacuum pre-pressed soft soil foundation discharge structure and Water discharge method.
Background technology
The eighties in 20th century, so far vacuum preloading reinforcement of soft soil technology was in the very big development of China, substantial amounts of engineering It was verified that vacuum method becomes one of effective technology of process Soft Clay Foundation.Vacuum method is usually by draining System, compression system and the part of sealing system three collectively constitute.Vacuum method is first to set on the soft soil foundation to be reinforced The plastic draining board or sand wick of one determining deviation, then lays on the ground certain thickness sand bedding course, then will be air-locked Thin film is laid on sand bedding course, by means of the pipeline being embedded in sand bedding course, by vacuum extractor by the gas in the soil body under film Body and water are extracted out, enable soil body discharging consolidation, reach the purpose of reinforcing.The method is, by atm difference, to be formed in the soil body Negative vacuum pressure, makes the water in the soil body gentle to vertical drain seepage flow, so as to improve soil body compactness, strengthens the soil body strong Degree.However, vacuum method still suffers from several weak points when saturation soft clay is processed:1st, vacuum method can apply Peak load there was only 95kPa or so, such as need high again, then must be used in combination with other soft base processing methods;2nd, due to saturation Soft clay permeability is low, and the vacuum method construction period is longer, general up to 3~24 months;3rd, vacuum is in transmittance process Affected by sand bedding course and lost larger, be only capable of forming the thick crust layers of 1m in earth's surface, deep weak soil is unable to reach design requirement Consolidation effect;4th, plastic draining board top layer filter membrane easily receives surrounding fine grained silting so as to which water passing capacity weakens, vacuum transmission It is obstructed, so as to cause vacuum method later stage treatment effeciency to reduce;5th, affected larger by construction technology quality control, soil is softer, It is then easier to produce crack in stabilization zone boundary, cause sealing system to fail.
The content of the invention
An object of the present invention is to provide a kind of heat energy to strengthen vacuum pre-pressed soft soil foundation discharge structure, and the structure can On a large scale interior raising soft soil foundation temperature, increases the permeability of water and gas in deep soil, with low engineering cost, work of constructing Skill is simple, the good advantage of discharging consolidation effect.
To achieve these goals, the technical scheme taken is:A kind of heat energy strengthens vacuum pre-pressed soft soil foundation draining Structure, it is characterised in that:Including heat energy injected system, drainage system and sealing system, the heat energy injected system is included in soft The some evenly distributed heat energy injection well that is drilled with soil base, the heat energy ascending pipe in heat energy injection well, it is connected to The heat energy injection pump of heat energy ascending pipe rear end and heat energy produce equipment, and the drainage system includes vaccum-pumping equipment and draining pad Layer, vaccum-pumping equipment is including the plastic draining board being distributed between adjacent heat energy injection well, positioned at plastic draining board top Evacuation chimney filter, the evacuation that evacuation chimney filter is linked together supervisor, the vacuum pumping pump that rear end is responsible for positioned at evacuation, institute State drainage blanket and be arranged on need soft soil foundation surface to be processed, including the working cushion layer and horizontal row water cushion of bottom-up distribution Layer, the sealing system includes the diaphragm seal being distributed in above horizontal drainage bed course and the sealing for being distributed in drainage system periphery Ditch, diaphragm seal is extended to along sealing ditch bottom, and evacuation supervisor is provided with membrane device with diaphragm seal contact site;The evacuation Supervisor and evacuation chimney filter are horizontally embedded in horizontal drainage bed course, and the tube wall of the heat energy ascending pipe is provided with staggered Dispersion hole, the heat energy injection well arranges pillar during being drilled with the borehole wall, pacifies between heat energy ascending pipe and heat energy injection pump Dress closes well device, and the top of heat energy injection well arranges the packer of fixed heat energy ascending pipe.
Further, the pillar of the heat energy injection well is rolled using 10mm steel plates, and pillar wall is provided with dispersion hole, shield Bottom of the tube is provided with the bottom closure of cement mortar cast.
Further, construction monitoring equipment is laid with the soft soil foundation, construction monitoring equipment includes:Temperature sensing Device, pressure vacuum gauge, single point settlement gage and underground level gauge.
Further, the heat energy ascending pipe tubing adopts high temperature resistant stainless steel pipe, polyfluortetraethylene pipe, plain concrete One or more in pipe, concrete reinforced pipe.
Heat energy of the present invention strengthens vacuum pre-pressed soft soil foundation discharge structure, by heat energy injection well with certain note Enter pressure and convey heat energy in soft soil foundation, so that a range of soft soil foundation temperature centered on heat energy injection well Raise, increase the permeability of water and gas in deep soil, eliminate differential settlement and accelerate Soft Soil Consolidation speed.
Another object of the present invention is to providing a kind of heat energy strengthens vacuum pre-pressed soft soil foundation water discharge method, the method exists Increase heat energy implantation step, and then interior raising soft soil foundation temperature on a large scale on the basis of conventional vacuum preloading method, increase deep The permeability of water and gas in the soil body, eliminates differential settlement and accelerates Soft Soil Consolidation speed.
A kind of heat energy strengthens vacuum pre-pressed soft soil foundation water discharge method and specifically includes following steps:
One)Preparation of construction:The barrier of earth's surface, underground and periphery is removed, stabilization zone place is tentatively flattened;
Two)Heat energy injected system is constructed:Heat energy injection well is drilled with to desired depth, drilling well is made in soft soil foundation using boring machine Inject into well the injection of right angle setting heat energy in heat energy to shaft bottom injection cement mortar cast bottom closure using conduit after the completion of industry Pipe, and heat energy ascending pipe is fixed in heat energy injection well using packer, while playing the purpose of sealing wellhead;Heat energy injects The rear end connection heat energy injection pump of pipe, while install that between heat energy ascending pipe and heat energy injection pump well device is closed, heat energy injection Pump rear end produces equipment and is connected with heat energy;
Three)Drainage system is constructed and construction monitoring implantation of device:On stabilization zone surface chaste tree basketry or geotextiles are laid as work pads Layer, using mechanical system or manual type the plastic draining board as vertical drain is set between adjacent heat energy injection well, Construction monitoring equipment is laid in soft soil foundation, horizontal drainage bed course is laid on working cushion layer, in the middle of horizontal drainage bed course Level laying evacuation supervisor, evacuation chimney filter, evacuation supervisor and evacuation chimney filter are directly connected to, evacuation chimney filter and plastics Draining board is directly connected to, and evacuation supervisor be connected with vacuum pumping pump, and horizontal drainage course preferably adopts medium coarse sand;
Four)Sealing system is constructed:Sealing ditch is excavated along reinforced soft soil ground area periphery, is sealed in the laying of horizontal drainage mat surface Film, while installing evacuation supervisor's membrane device, in diaphragm seal periphery embedment sealing ditch, covers thereon cohesive soil and is layered pressure It is real;
Five)Evacuation:Open vacuum extractor and carry out continuous evacuation, it is ensured that constant 90kPa negative pressure of vacuum is formed under film;
Six)Injection heat energy and monitoring:Open vacuum means to postpone, open heat energy and produce equipment and heat energy injection pump, by heat energy Injected system injects heat energy in soft soil foundation, and using construction monitoring equipment to work progress in various situations carry out continuously Monitoring.
Further, step 6)Inject in middle soft soil foundation after heat energy, keep soil body mean temperature at 55-65 DEG C, if Soil temperature rising is too fast, can stop injecting heat energy and closing heat energy injection well, continues when soil temperature drops to 55-65 DEG C Injection heat energy.
Further, the heat energy of the heat energy ascending pipe injection is high temperature air, and high temperature air temperature is more than 80 DEG C, heat energy High 1~the 3MPa of pore water pressure in the injection pressure ratio soft soil foundation of injection well, heat injection speed is 3~5m3/h。
This method forms the negative pressure of vacuum of about 90kPa first with vacuum method in soft soil foundation, then using heat Energy injected system conveys heat energy with certain injection pressure in soft soil foundation, so that certain centered on heat energy injection well In the range of soft soil foundation temperature raise.According to thermodynamic principles, air pressure is lower, water boiling point is lower, the pore water in weak soil Can more quickly seethe with excitement and formed free state water vapour, the gas in hole then expanded by heating and accelerate flowing.In weak soil body The water vapour and inflation gas of free state are ordered about to drainage system seepage flow, and soft soil foundation is extracted out by drainage system, ground is sent out Raw sedimentation, reaches the reduction of erection time, improves the purpose for reinforcing speed.
Description of the drawings
Fig. 1 is the principle schematic that a kind of heat energy of the present invention strengthens vacuum pre-pressed soft soil foundation discharge structure.
Symbol description in figure:1 soft soil foundation;2 heat energy injection wells;3 heat energy produce equipment;4 heat energy injection pumps;5 heat energy are noted Enter pipe;6 packers;7 close well device;8 working cushion layers;9 plastic draining boards;10 construction monitoring equipment;11 horizontal drainage bed courses;12 Evacuation is responsible for;13 evacuation chimney filters;14 sealing ditches;15 diaphragm seals;16 membrane devices;17 vacuum pumping pumps;18 bottoms block.
Specific embodiment
Below in conjunction with the accompanying drawings technical scheme is described further with specific embodiment.
As shown in figure 1, the present invention provides a kind of heat energy strengthens vacuum pre-pressed soft soil foundation discharge structure, including heat energy injection System, drainage system and sealing system, the heat energy injected system is included in soft soil foundation 1 be drilled with some evenly distributed Heat energy injection well 2, the heat energy ascending pipe 5 in heat energy injection well, the heat energy injection pump 4 for being connected to heat energy ascending pipe rear end Equipment 3 is produced with heat energy, the drainage system includes vaccum-pumping equipment and drainage blanket, and vaccum-pumping equipment is adjacent including being distributed in Heat energy injection well between plastic draining board 9, the evacuation chimney filter 13 positioned at plastic draining board top, by evacuation chimney filter connect The evacuation supervisor 12 being connected together, the vacuum pumping pump 17 that rear end is responsible for positioned at evacuation, the drainage blanket is arranged on needs The soft soil foundation surface of process, including the working cushion layer 8 and horizontal drainage bed course 11 of bottom-up distribution, the sealing system bag The diaphragm seal 15 being distributed in above horizontal drainage bed course and the sealing ditch 14 for being distributed in drainage system periphery are included, diaphragm seal is extended to Along sealing ditch bottom, evacuation supervisor is provided with membrane device 16 with diaphragm seal contact site;The evacuation supervisor and evacuation Chimney filter is horizontally embedded in horizontal drainage bed course, and the tube wall of the heat energy ascending pipe is provided with staggered dispersion hole, described Heat energy injection well arranges pillar during being drilled with the borehole wall, installs between heat energy ascending pipe and heat energy injection pump and closes well device 7, The top of heat energy injection well arranges the packer 6 of fixed heat energy ascending pipe, is to prevent the borehole wall from collapsing in heat energy injection well drilling process Collapse, pillar is transferred simultaneously in drilling well, the pillar is rolled using 10mm steel plates, and pillar outer wall is provided with dispersion hole.Pillar bottom Portion is provided with the bottom closure 18 of cement mortar cast, and construction monitoring equipment 10, construction monitoring equipment are laid with the soft soil foundation Including:Temperature sensor, pressure vacuum gauge, single point settlement gage and underground level gauge.The heat energy ascending pipe tubing adopts resistance to height One or more in warm stainless steel tube, polyfluortetraethylene pipe, plain concrete pipe, concrete reinforced pipe.
In Specific construction, hydrogeologic data is investigated first, check electric power system and construction material quality, with clearing The barrier of table, underground and periphery, measures ground elemental height, in this way rectangle place, it should be ensured that the advance raising in middle part some, 30~50cm of filled slope, the gradient 1%~2%, are tentatively flattened to reinforced soft soil ground area place.Then in soft soil foundation 1 In be drilled with heat energy injection well 2 to desired depth according to design pitch, the right angle setting heat energy ascending pipe 5 in heat energy injection well 2, and Heat energy ascending pipe 5 is fixed in heat energy injection well 2 using packer 6, while playing the purpose of sealing wellhead.Described heat energy The arrival end of ascending pipe 5 is connected with the port of export of heat energy injection pump 4, while in the arrival end of heat energy ascending pipe 5 and heat energy injection pump 4 Install between the port of export and close well device 7, the controllable heat energy injection rate when the rising of soft soil foundation temperature is too fast, described heat energy note Enter pump intake end to be connected with heat energy generation equipment 3, complete the installation of heat energy injected system.
Further, chaste tree basketry or geotextiles are laid as working cushion layer 8 on stabilization zone surface, laying chaste tree basketry is appropriate to the occasion by place Surrounding is progressively laid to center position, and geotextiles are appropriate to the occasion is progressively laid into area from side for laying.Using mechanical system or Manual type sets plastic draining board 9 in adjacent heat energy injection well spacing according to square or equilateral triangle arrangement, used as vertical In line aquaporin, the spacing of plastic draining board is preferably 0.7~1.5m.After the completion of plastic draining board sets, the cloth in soft soil foundation Facility work monitoring device 10, construction monitoring equipment 10 includes temperature sensor, pressure vacuum gauge, single point settlement gage and level of ground water Meter, for monitoring soil temperature, vacuum pressure, ground settlement and level of ground water etc..Horizontal drainage is laid on working cushion layer Bed course 11, course is preferably not more than 5% medium coarse sand using clay content, and its infiltration coefficient is not preferably less than 5 × 10-3cm/s.In level Drainage blanket by-level laying evacuation supervisor 12, evacuation chimney filter 13, used as horizontal drainage passage, evacuation is responsible for 12 Hes Evacuation chimney filter 13 is directly connected to, and evacuation chimney filter 13 is directly connected to plastic draining board 9, and evacuation is responsible for and vacuum pumping pump phase Connection, completes drainage system construction and construction monitoring implantation of device.
Further, sealing system is laid:Sealing ditch 14 is excavated along reinforced soft soil ground area periphery, in horizontal drainage bed course Two-layer diaphragm seal 15 is laid on surface, and the diaphragm seal length of side should be greater than more than stabilization zone length of side 4m, while installing evacuation supervisor's membrane Device 16.Embedment after the completion of diaphragm seal 15 is laid is sealed in ditch 14, and cohesive soil and compaction in layers are covered thereon.As in deep soil With the presence of pervious bed, need to take the deep encapsulating method such as double mixing pile to block pervious bed, mixing pile diameter is not preferably less than 700mm。
Open vacuum pumping pump 17 and carry out continuous evacuation, it is ensured that constant 90kPa negative pressure of vacuum, evacuation are formed under film The power of pump 17 not preferably less than 7.5kW, often covering vacuum pumping pump 17 can bear area for 500~600m2, then it is by heat energy injection Unite in soft soil foundation 1 inject high temperature air as heat energy, and to work progress in various situations continuously monitor.Keep Soil body mean temperature is at 55-65 DEG C or so, if soil temperature rising is too fast, can stop injecting heat energy and by closing well device 7 Heat energy injection well 2 is closed, continues to inject heat energy when soil temperature drops to 55-65 DEG C.High temperature air temperature is more than 80 DEG C, heat High 1~the 3MPa of pore water pressure in the injection pressure ratio soft soil foundation of energy injection well, charge velocity is 3~5m3/h.The note Enter the total amount of heat energy, according to soft soil foundation depth, stabilization zone area and reinforcing speed determine.After considering various heat-energy losses, can Mean temperature of the soft soil foundation after heat energy transmits realization in the range of the radius 10m centered on heat energy injection well is set to be increased to 60 DEG C and more than.
The present invention operation principle be:The vacuum that about 90kPa is formed in soft soil foundation first with vacuum method is born Pressure, while heat energy is conveyed in soft soil foundation with certain injection pressure by heat energy injected system, so that with heat energy injection A range of soft soil foundation temperature centered on well is raised.According to thermodynamic principles, air pressure is lower, water boiling point is lower, Pore water in weak soil can more quickly seethe with excitement and form the water vapour of free state, the gas in hole then expanded by heating and accelerate Flowing.Due to injecting pressure more than the pore pressure in weak soil, the heat energy for being injected orders about the water of free state in weak soil body and steams Vapour and inflation gas are evacuated device extraction soft soil foundation to drainage system seepage flow, and ground is settled, and reaches shortening Duration, the purpose for improving reinforcing speed.
The above, is only highly preferred embodiment of the present invention, and any pro forma restriction is not made to the present invention, is appointed What those of ordinary skill in the art, under without departing from technical solution of the present invention ambit, using in the method for the disclosure above Appearance makes many possible variations and modification to technical solution of the present invention, belongs to the scope of claims protection.

Claims (7)

1. a kind of heat energy strengthens vacuum pre-pressed soft soil foundation discharge structure, it is characterised in that:Including heat energy injected system, draining system System and sealing system, the heat energy injected system be included in be drilled with soft soil foundation some evenly distributed heat energy injection well, Heat energy ascending pipe in heat energy injection well, the heat energy injection pump for being connected to heat energy ascending pipe rear end and heat energy are produced and set Standby, the drainage system includes vaccum-pumping equipment and drainage blanket, and vaccum-pumping equipment includes being distributed in adjacent heat energy injection well Between plastic draining board, the evacuation chimney filter positioned at plastic draining board top, take out true by what evacuation chimney filter linked together Sky supervisor, the vacuum pumping pump that rear end is responsible for positioned at evacuation, the drainage blanket is arranged on needs soft soil foundation surface to be processed, Working cushion layer and horizontal drainage bed course including bottom-up distribution, the sealing system includes being distributed on horizontal drainage bed course The diaphragm seal in face and be distributed in the sealing ditch of drainage system periphery, diaphragm seal is extended to along sealing ditch bottom, evacuation supervisor with Diaphragm seal contact site is provided with membrane device;The evacuation supervisor and evacuation chimney filter are horizontally embedded in horizontal drainage bed course In, the tube wall of the heat energy ascending pipe is provided with staggered dispersion hole, and the heat energy injection well is during being drilled with well Wall arranges pillar, installs between heat energy ascending pipe and heat energy injection pump and closes well device, and the top of heat energy injection well arranges fixed heat The packer of energy ascending pipe.
2. a kind of heat energy according to claim 1 strengthens vacuum pre-pressed soft soil foundation discharge structure, it is characterised in that:It is described The pillar of heat energy injection well is rolled using 10mm steel plates, and pillar bottom is provided with the bottom closure of cement mortar cast.
3. a kind of heat energy according to claim 1 strengthens vacuum pre-pressed soft soil foundation discharge structure, it is characterised in that:It is described Construction monitoring equipment is laid with soft soil foundation, construction monitoring equipment includes:Temperature sensor, pressure vacuum gauge, single-point sedimentation Meter and underground level gauge.
4. a kind of heat energy according to claim 1 strengthens vacuum pre-pressed soft soil foundation discharge structure, it is characterised in that:It is described Heat energy ascending pipe tubing is using the one kind in high temperature resistant stainless steel pipe, polyfluortetraethylene pipe, plain concrete pipe, concrete reinforced pipe Or it is several.
5. a kind of heat energy strengthens vacuum pre-pressed soft soil foundation water discharge method, it is characterised in that:Specifically include following steps:
One)Preparation of construction:The barrier of earth's surface, underground and periphery is removed, stabilization zone place is tentatively flattened;
Two)Heat energy injected system is constructed:Heat energy injection well is drilled with to desired depth, drilling well is made in soft soil foundation using boring machine Inject into well the injection of right angle setting heat energy in heat energy to shaft bottom injection cement mortar cast bottom closure using conduit after the completion of industry Pipe, and heat energy ascending pipe is fixed in heat energy injection well using packer, while playing the purpose of sealing wellhead;Heat energy injects The rear end connection heat energy injection pump of pipe, while install that between heat energy ascending pipe and heat energy injection pump well device is closed, heat energy injection Pump rear end produces equipment and is connected with heat energy;
Three)Drainage system is constructed and construction monitoring implantation of device:On stabilization zone surface chaste tree basketry or geotextiles are laid as work pads Layer, using mechanical system or manual type the plastic draining board as vertical drain is set between adjacent heat energy injection well, Construction monitoring equipment is laid in soft soil foundation, horizontal drainage bed course is laid on working cushion layer, in the middle of horizontal drainage bed course Level laying evacuation supervisor, evacuation chimney filter, evacuation supervisor and evacuation chimney filter are directly connected to, evacuation chimney filter and plastics Draining board is directly connected to, and evacuation supervisor be connected with vacuum pumping pump, and horizontal drainage course preferably adopts medium coarse sand;
Four)Sealing system is constructed:Sealing ditch is excavated along reinforced soft soil ground area periphery, is sealed in the laying of horizontal drainage mat surface Film, while installing evacuation supervisor's membrane device, in diaphragm seal periphery embedment sealing ditch, covers thereon cohesive soil and is layered pressure It is real;
Five)Evacuation:Open vacuum extractor and carry out continuous evacuation, it is ensured that constant 90kPa negative pressure of vacuum is formed under film;
Six)Injection heat energy and monitoring:Open vacuum means to postpone, open heat energy and produce equipment and heat energy injection pump, by heat energy Injected system injects heat energy in soft soil foundation, and using construction monitoring equipment to work progress in various situations carry out continuously Monitoring.
6. a kind of heat energy according to claim 5 strengthens vacuum pre-pressed soft soil foundation water discharge method, it is characterised in that:Step Six)Inject in middle soft soil foundation after heat energy, keep soil body mean temperature at 55-65 DEG C, if soil temperature rising is too fast, can stop Only inject heat energy and close heat energy injection well, continue to inject heat energy when soil temperature drops to 55-65 DEG C.
7. a kind of heat energy according to claim 5 strengthens vacuum pre-pressed soft soil foundation water discharge method, it is characterised in that:It is described The heat energy of heat energy ascending pipe injection is high temperature air, and high temperature air temperature is more than 80 DEG C, and the injection pressure ratio of heat energy injection well is soft High 1~the 3MPa of pore water pressure in soil base, heat injection speed is 3~5m3/h。
CN201710028541.9A 2017-01-16 2017-01-16 Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method Pending CN106638556A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710028541.9A CN106638556A (en) 2017-01-16 2017-01-16 Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710028541.9A CN106638556A (en) 2017-01-16 2017-01-16 Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method

Publications (1)

Publication Number Publication Date
CN106638556A true CN106638556A (en) 2017-05-10

Family

ID=58844039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710028541.9A Pending CN106638556A (en) 2017-01-16 2017-01-16 Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method

Country Status (1)

Country Link
CN (1) CN106638556A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338782A (en) * 2017-06-20 2017-11-10 中交天津港湾工程研究院有限公司 A kind of processing method of vacuum pre-pressed joint ground heating reinforcing soft ground
CN107338784A (en) * 2017-06-20 2017-11-10 中交天津港湾工程研究院有限公司 A kind of basement process system of vacuum pre-pressed joint ground heating
CN107524137A (en) * 2017-09-01 2017-12-29 陕西华路达公路勘察设计有限公司 A kind of construction technology of deep soft soil treatment
CN107829425A (en) * 2017-11-06 2018-03-23 汤连生 One kind tool circulation air emptying function column type forced-ventilated water pipe, device and method
CN109736293A (en) * 2018-12-25 2019-05-10 浙江华东工程咨询有限公司 The intelligent information makeup of pressurization heat treatment soft soil foundation is set and method for processing foundation
CN110761267A (en) * 2019-11-18 2020-02-07 清华大学 Rapid prepressing and consolidating device and method for underwater soft soil foundation
CN111691394A (en) * 2020-05-19 2020-09-22 宁波大学 Pile end soil body reinforcing system
CN112281807A (en) * 2020-09-27 2021-01-29 江苏鑫泰岩土科技有限公司 Pressurizing heat-sensitive vaporization phase-change consolidation method and heat-desensitization intermittent evaporator thereof
CN112502130A (en) * 2020-11-03 2021-03-16 广州市设计院 Soft soil foundation treatment system and soft soil foundation treatment method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5330291A (en) * 1991-11-13 1994-07-19 Battelle Memorial Institute Heating of solid earthen material, measuring moisture and resistivity
CN103061230A (en) * 2013-01-18 2013-04-24 湖南城市学院 Construction method of technology utilizing ground source heat pump to cool and melt frozen road surfaces and drain boards for construction
CN103255761A (en) * 2012-02-16 2013-08-21 同济大学 Method for reinforcing soft soil foundation by using calescence type vacuum preloading way
CN104790372A (en) * 2015-04-28 2015-07-22 上海大学 Vibration-compressed air-vacuum combination foundation reinforcement system and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5330291A (en) * 1991-11-13 1994-07-19 Battelle Memorial Institute Heating of solid earthen material, measuring moisture and resistivity
CN103255761A (en) * 2012-02-16 2013-08-21 同济大学 Method for reinforcing soft soil foundation by using calescence type vacuum preloading way
CN103061230A (en) * 2013-01-18 2013-04-24 湖南城市学院 Construction method of technology utilizing ground source heat pump to cool and melt frozen road surfaces and drain boards for construction
CN104790372A (en) * 2015-04-28 2015-07-22 上海大学 Vibration-compressed air-vacuum combination foundation reinforcement system and method

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107338782A (en) * 2017-06-20 2017-11-10 中交天津港湾工程研究院有限公司 A kind of processing method of vacuum pre-pressed joint ground heating reinforcing soft ground
CN107338784A (en) * 2017-06-20 2017-11-10 中交天津港湾工程研究院有限公司 A kind of basement process system of vacuum pre-pressed joint ground heating
CN107524137A (en) * 2017-09-01 2017-12-29 陕西华路达公路勘察设计有限公司 A kind of construction technology of deep soft soil treatment
CN107524137B (en) * 2017-09-01 2019-08-02 陕西华路达公路勘察设计有限公司 A kind of construction technology of deep soft soil treatment
CN107829425A (en) * 2017-11-06 2018-03-23 汤连生 One kind tool circulation air emptying function column type forced-ventilated water pipe, device and method
CN107829425B (en) * 2017-11-06 2023-12-29 汤连生 Device and method for soft foundation drainage consolidation
CN109736293A (en) * 2018-12-25 2019-05-10 浙江华东工程咨询有限公司 The intelligent information makeup of pressurization heat treatment soft soil foundation is set and method for processing foundation
CN110761267A (en) * 2019-11-18 2020-02-07 清华大学 Rapid prepressing and consolidating device and method for underwater soft soil foundation
CN111691394A (en) * 2020-05-19 2020-09-22 宁波大学 Pile end soil body reinforcing system
CN112281807A (en) * 2020-09-27 2021-01-29 江苏鑫泰岩土科技有限公司 Pressurizing heat-sensitive vaporization phase-change consolidation method and heat-desensitization intermittent evaporator thereof
CN112281807B (en) * 2020-09-27 2022-07-22 江苏鑫泰岩土科技有限公司 Pressurizing heat-sensitive vaporization phase-change consolidation method and heat-desensitization intermittent evaporator thereof
CN112502130A (en) * 2020-11-03 2021-03-16 广州市设计院 Soft soil foundation treatment system and soft soil foundation treatment method

Similar Documents

Publication Publication Date Title
CN106638556A (en) Heat energy reinforced vacuum preloading soft foundation drainage structure and drainage method
CN103233454B (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN103255761B (en) A kind of temperature-increasing type Vacuum Preloading Method for Consolidation of Soft Soil Foundation method
CN208328950U (en) A kind of In-pit water drainage friction pile suitable for dregs loose structure slope
CN103046565B (en) Draining method for ultra-deep batholith deep foundation pit
CN101949153B (en) Foundation drainage control method
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN107829425A (en) One kind tool circulation air emptying function column type forced-ventilated water pipe, device and method
CN216108436U (en) Circulation adds pressure release precipitation system and ground treatment system thereof
CN107178077B (en) karst area karst cave overburden grouting reinforcement structure and design method thereof
CN110387896A (en) Base pit dewatering well design method
CN101225654B (en) Blow fill foundation treating method and gas injection draining device therefor
CN206829119U (en) A kind of prewetting method for ground treatment structure of collapsible loess
CN104047280B (en) Soft foundation sharp separation compacting method
CN107130580A (en) New independent well point integrate draining combined vacuum ground preloading method and hardened system
CN206448286U (en) It is a kind of to be used to reduce the radial system of grey field dam seepage line
CN105926579B (en) A kind of adding pressure type sleeve pipe impact drain consolidation system and method
CN109505211A (en) Reinforcement of Soft Soil Subgrade method
KR20120050010A (en) A reinforcement method of weak stratum use of suction drainage
CN111411639B (en) Shallow foundation pit dewatering construction method for water-rich pebble layer
CN113279388A (en) Foundation treatment system adopting combination of cyclic pressurization, pressure relief and dewatering grouting and construction method thereof
CN102787608B (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN110939121A (en) Drainage consolidation construction method combining hot water pipe and plastic drainage plate
CN108824113B (en) Soft soil foundation treatment method
CN110670613A (en) Anti-seepage structure of foundation pit elevator shaft and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510