CN106638208A - Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction - Google Patents
Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction Download PDFInfo
- Publication number
- CN106638208A CN106638208A CN201611008557.5A CN201611008557A CN106638208A CN 106638208 A CN106638208 A CN 106638208A CN 201611008557 A CN201611008557 A CN 201611008557A CN 106638208 A CN106638208 A CN 106638208A
- Authority
- CN
- China
- Prior art keywords
- rolling
- gravel
- gravels
- pavement construction
- roll
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/12—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for distributing granular or liquid materials
- E01C19/20—Apparatus for distributing, e.g. spreading, granular or pulverulent materials, e.g. sand, gravel, salt, dry binders
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C19/00—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
- E01C19/22—Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for consolidating or finishing laid-down unset materials
- E01C19/23—Rollers therefor; Such rollers usable also for compacting soil
- E01C19/28—Vibrated rollers or rollers subjected to impacts, e.g. hammering blows
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C7/00—Coherent pavings made in situ
- E01C7/08—Coherent pavings made in situ made of road-metal and binders
- E01C7/10—Coherent pavings made in situ made of road-metal and binders of road-metal and cement or like binders
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention discloses a process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction. Used macadam is formed by rolling hard, durable and clean gravels or rocks, wherein the gravels include natural gravels, break gravels or mixture of the natural gravels and the break gravels and are hard, durable and free from impurities. An appropriate amount of clay is added into a macadam layer and mixed, an appropriate amount of water is added, and paving and compacting are simultaneously performed. The gravels are rolled by a three-wheel roller or vibratory roller when surfaces are dried while insides are semi-wet, calking is blended at any time, and rolling is performed until obvious wheel tracks are avoided and materials are completely stabilized under rolling. In the rolling compaction process, thin stone chips are spread and uniformly swept after rolling compaction is performed for 1-2 times, and rolling compaction is performed so that slurry in gravel gaps floats to the surfaces and is adhered with the spread stone chips into a whole. The process is simple and convenient in course, the pavement construction quality can be ensured, so that a pavement cannot peel in the use process, and the service life is prolonged.
Description
Technical field
The present invention relates to a kind of technique, more particularly, to one kind clay bound macadam in Furniture Factory's pavement construction can be improved
The technique of construction quality.
Background technology
The literal meaning of highway is public road, the road of public's traffic, numerous traffic such as automobile, bicycle, rickshaw, carriage
Instrument and pedestrian can walk, and certainly difference highway limits different.Also referred to as road among the people, such as " street angel " inner usage,
It is not limited to horses special.There is ordinary highway with expressway other, the latter is more and more, and therefore Class II highway just there are two kinds
Specification.
The annual adapted to generally according to the Highway house volume of traffic and its using task and property round the clock, highway is divided into some
Industrial grade.What Chinese people's traffic publishing house published in 2004《Highway technical standard》, five skills are divided into highway
Art grade.Highway, adapts to annual mechanical transport amount more than 25000 round the clock.Politics with particular importance, Jing
Ji meaning, specializes in automobile shunting high speed, continuously drives, and all arranges crossings on different level and control discrepancy, and based on long-distance transport
Highway.Class I highway can adapt to annual mechanical transport amount 5000~25000 round the clock, in connecting important politics, economy
The heart, towards important industrial and mining area, is available for automobile shunting fast running, part control to come in and go out and partly arrange clover leaf highway.
Class II highway adapts to be converted to the annual of the medium-duty truck volume of traffic 2000~5000 round the clock, connection by various vehicles
The heavy Highway of suburb of politics, economic center or large-scale industrial and mining area and transport.Class III highway adapts to be converted by various vehicles
Annual into medium-duty truck is round the clock below the volume of traffic 2000, and ditch Tong County is public with the general main line in city with county or county
Road.Class IV highway adapts to be converted to the annual of medium-duty truck round the clock below the volume of traffic 200 by various vehicles, links up
Secondary highway between county and township, town.During highway construction, for the construction on road surface is an important job, tradition
Simple, the processing mode without code requirement so that road surface occurs asking in use for some time in the processing procedure of road pavement
Topic, causes highway decortication, hole occur and falls into phenomenon, or even cause road to interrupt.
The content of the invention
It is an object of the invention to overcome the above-mentioned existing processing procedure in road pavement simple, the process without code requirement
Mode so that road surface goes wrong in use for some time, causes highway decortication, hole occur and falls into phenomenon, or even cause road
The problem of interruption, devises a kind of technique that can improve clay bound macadam construction quality in Furniture Factory's pavement construction, the work
The process of skill is easy, ensure that construction quality of pavement so that road surface is not in use the phenomenons such as decortication, it is ensured that
Service life, it is simple to solve the existing processing procedure in road pavement, the processing mode without code requirement so that road surface exists
Using going wrong after a period of time, cause highway decortication, hole occur and fall into phenomenon, or even the problem for causing road interruption.
The purpose of the present invention is achieved through the following technical solutions:Clay bound macadam in Furniture Factory's pavement construction can be improved
The technique of construction quality, comprises the following steps:
(1)Rubble used should be hard by quality, durable clean gravel or rock rolling form, should have enough intensity and resistance to
Mill performance, building stones intensity is not less than 30Mpa, and the rubble of gravel rolling should have more than 90% crushed particles, and gravel includes natural gravel
The compound of stone, cut gravel or gravel by nature and cut gravel, gravel should hard, durable, free from admixture;
(2)Rubble in metalling answers level with well, and maximum particle diameter is not more than 8cm, plus appropriate clay is mixed, and appropriate water mixing,
It is compacted in making, it should be noted that roll under optimum moisture content, compactness is not less than 93%;
(3)Pave metaling:Preprepared building stones are once spread into foot by loose laying depth, coefficient of loose laying is 1.2~1.3 or so
Paved by the width and thickness of design requirement;
(4)Tentatively roll:The purpose just ground is to roll between gravel particle tightly, but still bag leaves a number of space, so as to mud
Slurry can fill, therefore to carry out rolling from vibrated roller being advisable, number of rolling less than 2-4 times, roll to rubble without
Loosening situation is degree;
(5)Roll:When surface has been done and inside is still in half wet condition, then continue to grind with three-roll road roller or vibrated roller
Pressure, and note that calking is anti-even at any time, directly it is rolled by without obvious wheelmark and under muller till material complete stability, rolling
During, after often rolling 1~2 time, that is, spread paving thin layer aggregate chips and sweep even, then rolled, so that the mud in rubble gap is general
It is integral with institute chipping bonding to surface;
(6)Quality requirement:Surface should be smooth, solid, must not there is the phenomenons such as loose, spring, after steamroller, must not have bright
Aobvious wheelmark, surface layer connects suitable with other structures, must not there is seeping phenomenon, and the road surface apparent size tolerance constructed should meet
Relevant code requirement.
In sum, the invention has the beneficial effects as follows:The process of the technique is easy, ensure that construction quality of pavement, makes
It is not in use the phenomenons such as decortication to obtain road surface, it is ensured that service life, solves the existing process in road pavement
Process is simple, and the processing mode without code requirement so that road surface goes wrong in use for some time causes highway to occur
Decortication, hole fall into phenomenon, or even the problem for causing road interruption.
Specific embodiment
With reference to embodiment, the present invention is described in further detail, but embodiments of the present invention are not limited only to
This.
Embodiment:
The technique that clay bound macadam construction quality in Furniture Factory's pavement construction can be improved, comprises the following steps:
(1)Rubble used should be hard by quality, durable clean gravel or rock rolling form, should have enough intensity and resistance to
Mill performance, building stones intensity is not less than 30Mpa, and the rubble of gravel rolling should have more than 90% crushed particles, and gravel includes natural gravel
The compound of stone, cut gravel or gravel by nature and cut gravel, gravel should hard, durable, free from admixture;
(2)Rubble in metalling answers level with well, and maximum particle diameter is not more than 8cm, plus appropriate clay is mixed, and appropriate water mixing,
It is compacted in making, it should be noted that roll under optimum moisture content, compactness is not less than 93%;
(3)Pave metaling:Preprepared building stones are once spread into foot by loose laying depth, coefficient of loose laying is 1.2~1.3 or so
Paved by the width and thickness of design requirement;
(4)Tentatively roll:The purpose just ground is to roll between gravel particle tightly, but still bag leaves a number of space, so as to mud
Slurry can fill, therefore to carry out rolling from vibrated roller being advisable, number of rolling less than 2-4 times, roll to rubble without
Loosening situation is degree;
(5)Roll:When surface has been done and inside is still in half wet condition, then continue to grind with three-roll road roller or vibrated roller
Pressure, and note that calking is anti-even at any time, directly it is rolled by without obvious wheelmark and under muller till material complete stability, rolling
During, after often rolling 1~2 time, that is, spread paving thin layer aggregate chips and sweep even, then rolled, so that the mud in rubble gap is general
It is integral with institute chipping bonding to surface;
(6)Quality requirement:Surface should be smooth, solid, must not there is the phenomenons such as loose, spring, after steamroller, must not have bright
Aobvious wheelmark, surface layer connects suitable with other structures, must not there is seeping phenomenon, and the road surface apparent size tolerance constructed should meet
Relevant code requirement.
The process of the technique is easy, ensure that construction quality of pavement so that road surface is not in use de-
The phenomenons such as skin, it is ensured that service life, solve the existing processing procedure in road pavement simply, the process side without code requirement
Formula so that road surface goes wrong in use for some time, causes highway decortication, hole occur and falls into phenomenon, or even cause in road
Disconnected problem.
The above, is only presently preferred embodiments of the present invention, not does any pro forma restriction to the present invention, it is every according to
According to any simple modification, equivalent variations that technology, the method for the present invention are substantially made to above example, the present invention is each fallen within
Protection domain within.
Claims (1)
1. the technique that clay bound macadam construction quality in Furniture Factory's pavement construction can be improved, it is characterised in that including following
Step:
(1)Rubble used should be hard by quality, durable clean gravel or rock rolling form, should have enough intensity and resistance to
Mill performance, building stones intensity is not less than 30Mpa, and the rubble of gravel rolling should have more than 90% crushed particles, and gravel includes natural gravel
The compound of stone, cut gravel or gravel by nature and cut gravel, gravel should hard, durable, free from admixture;
(2)Rubble in metalling answers level with well, and maximum particle diameter is not more than 8cm, plus appropriate clay is mixed, and appropriate water mixing,
It is compacted in making, it should be noted that roll under optimum moisture content, compactness is not less than 93%;
(3)Pave metaling:Preprepared building stones are once spread into foot by loose laying depth, coefficient of loose laying is 1.2~1.3 or so
Paved by the width and thickness of design requirement;
(4)Tentatively roll:The purpose just ground is to roll between gravel particle tightly, but still bag leaves a number of space, so as to mud
Slurry can fill, therefore to carry out rolling from vibrated roller being advisable, number of rolling less than 2-4 times, roll to rubble without
Loosening situation is degree;
(5)Roll:When surface has been done and inside is still in half wet condition, then continue to grind with three-roll road roller or vibrated roller
Pressure, and note that calking is anti-even at any time, directly it is rolled by without obvious wheelmark and under muller till material complete stability, rolling
During, after often rolling 1~2 time, that is, spread paving thin layer aggregate chips and sweep even, then rolled, so that the mud in rubble gap is general
It is integral with institute chipping bonding to surface;
(6)Quality requirement:Surface should be smooth, solid, must not there is the phenomenons such as loose, spring, after steamroller, must not have bright
Aobvious wheelmark, surface layer connects suitable with other structures, must not there is seeping phenomenon, and the road surface apparent size tolerance constructed should meet
Relevant code requirement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611008557.5A CN106638208A (en) | 2016-11-16 | 2016-11-16 | Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611008557.5A CN106638208A (en) | 2016-11-16 | 2016-11-16 | Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106638208A true CN106638208A (en) | 2017-05-10 |
Family
ID=58805550
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611008557.5A Withdrawn CN106638208A (en) | 2016-11-16 | 2016-11-16 | Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638208A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107151960A (en) * | 2017-06-24 | 2017-09-12 | 中铁十局集团第二工程有限公司 | The soft interim sidewalk laying structure in base and laying method |
-
2016
- 2016-11-16 CN CN201611008557.5A patent/CN106638208A/en not_active Withdrawn
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107151960A (en) * | 2017-06-24 | 2017-09-12 | 中铁十局集团第二工程有限公司 | The soft interim sidewalk laying structure in base and laying method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104532711B (en) | Dual-layer paving method of cement concrete pavement | |
CN106120524A (en) | A kind of road construction method | |
CN104446156A (en) | Mixture for constructing emulsified asphalt and dilute slurry mixture bituminous penetration road | |
CN107151960A (en) | The soft interim sidewalk laying structure in base and laying method | |
JPH05132905A (en) | Paving method for road | |
EP3071753A1 (en) | A mixture for a road formation and methods for blending and compaction thereof | |
CN211922126U (en) | Level crossing road surface structure under heavy traffic | |
CN108301276A (en) | A kind of long-life tencel concrete road surface structure and construction method | |
CN108101449A (en) | Permeable recycled cement stabilization gravel and its construction method | |
CN106638208A (en) | Process capable of improving clay-bound macadam pavement construction quality in furniture factory pavement construction | |
CN204589746U (en) | A kind of composite road surface structure being applicable to saturated dredger soft soil area Heavy Traffic condition | |
CN106517944A (en) | Solidified granular soil produced by utilizing waste and old materials from building project | |
Edeh et al. | Reclaimed asphalt pavements-lime stabilization of clay as highway pavement materials | |
CN210916876U (en) | Urban road rebuilds people's way pavement structure of mating formation that permeates water of engineering | |
CN109423933A (en) | The construction technology of clay bound macadam in cell pavement construction | |
CN207646558U (en) | A kind of road-surface building structure | |
CN205874871U (en) | High carrier block stone road surface structure suitable for heavily traffic | |
CN100338310C (en) | New road surface structure layer | |
CN107740319A (en) | Based on the method for improving rubble basal plane efficiency of construction and quality | |
Rogers et al. | Granular base failures in low-volume roads in Ontario, Canada | |
CN206219936U (en) | Asphalt pavement conserving structure | |
Sharma et al. | Utilization of Quarry dust in cement concrete paver blocks for rural Roads | |
CN218540250U (en) | Wide-spliced road surface structure | |
CN209759935U (en) | Rural tomb highway bituminous paving cold regeneration structure of cement | |
RU2541959C1 (en) | Profile of asphalt concrete road surface |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20170510 |
|
WW01 | Invention patent application withdrawn after publication |