CN106569170B - A kind of metering device secondary circuit detector and its detection method - Google Patents

A kind of metering device secondary circuit detector and its detection method Download PDF

Info

Publication number
CN106569170B
CN106569170B CN201610982957.XA CN201610982957A CN106569170B CN 106569170 B CN106569170 B CN 106569170B CN 201610982957 A CN201610982957 A CN 201610982957A CN 106569170 B CN106569170 B CN 106569170B
Authority
CN
China
Prior art keywords
test
mutual inductor
signal
phase
secondary circuit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610982957.XA
Other languages
Chinese (zh)
Other versions
CN106569170A (en
Inventor
王孝帅
高振江
许朋波
马继柏
梅平
李军
李翔
冯勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Linqu Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Linqu Power Supply Co Of State Grid Shandong Electric Power Co
State Grid Corp of China SGCC
Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Linqu Power Supply Co Of State Grid Shandong Electric Power Co, State Grid Corp of China SGCC, Weifang Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Linqu Power Supply Co Of State Grid Shandong Electric Power Co
Priority to CN201610982957.XA priority Critical patent/CN106569170B/en
Publication of CN106569170A publication Critical patent/CN106569170A/en
Application granted granted Critical
Publication of CN106569170B publication Critical patent/CN106569170B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/04Testing or calibrating of apparatus covered by the other groups of this subclass of instruments for measuring time integral of power or current
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • G01R31/66Testing of connections, e.g. of plugs or non-disconnectable joints
    • G01R31/67Testing the correctness of wire connections in electric apparatus or circuits

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The present invention proposes that one kind can judge rapidly whether metering device secondary circuit has the detecting instrument of wiring exception, including secondary circuit route collet, test benchmark signal generation unit, test result signal sampling unit, test result detecting signal unit, display unit.The present invention obtains the test result signal of each phase connection using controllable alternating-current measurement reference signal is intersected, and the phase and its type of error of wiring error are determined by being compared with nominal value.The present invention takes out stitches without energization on-load or power failure and checks by root, can quickly position the false wiring in the types electric energy meter such as phase three-wire three, and judge wiring error type, easy to operate, time saving and energy saving.

Description

A kind of metering device secondary circuit detector and its detection method
Technical field
The present invention relates to power measurement technical field more particularly to a kind of metering device secondary circuit detector and its detections Method.
Background technique
Electric energy metering device towards power supply line mainly includes voltage transformer, current transformer, secondary circuit and electricity It can table.Voltage transformer and current transformer by power supply line load current and load voltage be changed into normalized current and Electric energy meter is provided to respectively after normal voltage to be measured.The secondary terminals of voltage transformer and current transformer are to electric energy meter The connection circuit of table tail, the referred to as secondary circuit of electric energy metering device.
Guarantee that second loop return wiring is correctly the premise that electric energy meter accurately measures electricity consumption.But in reality, misconnection The case where line, emerges one after another.Under error connection state, even if electric energy meter accuracy and reliability itself is very high, also it cannot achieve correct Metering, it is also possible to bring the risk of equipment damage.
The high-pressure system of general 10kV or more is all made of the power supply mode of phase three-wire three, so high-pressure system mostly uses greatly Three-phase three-wire electric energy meter measures electric energy.The wiring of three-phase three-wire electric energy meter is relatively more, and the chance of misconnection is larger, including short circuit, open The problems such as road, mutual inductor generation line reversal and string phase, voltage transformer and current transformer are obscured.Three-phase three-wire electric energy meter is wrong Electric energy meter will generate many abnormal operation phenomenons when wiring: not turning sometimes, invert sometimes, sometimes with the power-factor of load The variation at angle rotates forward reversion alternating, although what is had rotates forward, the electricity number measured is not consistent with practical.Due to voltage transformer Voltage phase sequence can judge that a possibility that mistake is smaller by phase-sequence meter, but current transformer occurs line reversal and goes here and there the showing of phase As in practical projects than more prominent.Moreover, the installation space of electric energy metering device especially mutual inductor room installation space is narrow, Big inconvenience is brought to inspection wiring and misconnection line analysis.
Line inspection mode mainly has energization on-load to detect and have a power failure and detects by root line to core at present, there is certain limitation Property, and it is time-consuming and laborious.The detection of energization on-load samples extraction electricity from the primary side and secondary side of mutual inductor using tester respectively Stream, voltage value carry out verification calculating, and the counting of the variable of tester and electric energy meter are compared, it can be found that secondary Mistake present in circuit, but wiring wrong in secondary circuit cannot be directly positioned, it is also not susceptible to determine in secondary circuit The type of wiring error.Have a power failure to detect core by root line and after power failure dismantle secondary circuit terminal, with multimeter to core inspection, It is time-consuming and laborious when operation, and detection effect is undesirable.
Summary of the invention
In view of above-mentioned problem above existing in the prior art, can judge rapidly to count it is an object of that present invention to provide one kind Whether amount device secondary circuit has the detecting instrument of wiring exception, takes out stitches without energization on-load or power failure and checks by root, can Quickly to position the false wiring in the types electric energy meter such as phase three-wire three, and judge wiring error type, easy to operate, time saving province Power.
In order to reach above-mentioned target, the present invention provides a kind of metering device secondary circuit detectors, which is characterized in that packet Include secondary circuit route collet, test benchmark signal generation unit, test result signal sampling unit, test result signal detection Unit, display unit;Wherein, the secondary circuit route collet shares several, is respectively used to each mutual in connection secondary circuit Each phase connection between sensor secondary side and electric energy meter input terminal;Each secondary circuit route collet is for connecting secondary circuit one The wiring of phase, each secondary circuit route collet include test input mutual inductor, the first test output mutual inductor and the second survey Try output mutual inductor;Wherein test input mutual inductor first siding ring be centered around the test input mutual inductor magnetic core on and The test benchmark signal generation unit is connected, test input mutual inductor is secondary as its using each phase connection in secondary circuit Side;The second siding ring of the first test output mutual inductor and the second test output mutual inductor is centered around described first respectively On the magnetic core of test output mutual inductor and the second test output mutual inductor and it is connected to the test result signal sampling list Member, the first test output mutual inductor and the second test output mutual inductor are using each phase connection in secondary circuit as one Secondary side;The test benchmark signal generation unit is used to generate and inputs the primary side input test base of mutual inductor to the test Calibration signal;The test result signal sampling unit tests output mutual inductor from the first test output mutual inductor and second Second siding ring receive the test of each phase connection generated by the first test output mutual inductor and the second test output mutual inductor Consequential signal;The test result signal of each phase connection is compared test result detecting signal unit with nominal value, judges it In whether there is abnormal test result signal, and determine wiring phase corresponding with the exception of test result signal and wiring mistake Accidentally type;The display unit is used to show the wiring phase and wiring error class that the test result detecting signal unit determines Type.
Preferably, the test benchmark signal generation unit generates alternating-current measurement reference signal, and records the friendship The reference voltage value and reference current value are supplied to test by the reference voltage value and reference current value of current test reference signal Consequential signal detection unit.
Preferably, the first test output mutual inductor is by incuding the alternating-current measurement reference signal on each phase connection Current value generates the current test results signal of each phase connection;The second test output mutual inductor is by incuding on each phase connection The voltage value of alternating-current measurement reference signal generate the voltage tester consequential signal of each phase connection.
Preferably, the test result detecting signal unit is according to the current test results signal, voltage tester knot Fruit signal and the phase angle of the two determine wiring phase corresponding with the exception of test result signal and wiring error type.
Preferably, the test benchmark signal generation unit controls defeated in each phase of secondary circuit according to predetermined scheme The phase angle between alternating-current measurement reference signal entered.
The present invention provides a kind of detection method of metering device second loop return wiring in turn characterized by comprising will Wiring connecting test input mutual inductor, the first test output mutual inductor and the second test output mutual inductance of each phase of secondary circuit Device;Wherein, the first siding ring of test input mutual inductor is centered around on the magnetic core of test input mutual inductor, will be in secondary circuit Each phase connection as test input mutual inductor secondary side;The first test output mutual inductor and the second test output are mutual The second siding ring of sensor is centered around the magnetic core of the first test output mutual inductor and the second test output mutual inductor respectively On, the primary of output mutual inductor is tested using each phase connection in secondary circuit as the first test output mutual inductor and second Side;
Generate and input to the test primary side input test reference signal of mutual inductor;
It receives from the second siding ring of the first test output mutual inductor and the second test output mutual inductor by first Test output mutual inductor and the second test output mutual inductor generate the test result signal of each phase connection;
The test result signal of each phase connection is compared with nominal value, whether judgement wherein has abnormal test knot Fruit signal, and determine wiring phase corresponding with the exception of test result signal and wiring error type;
Wiring phase determined by showing and wiring error type.
It preferably, is alternating-current measurement benchmark to the test benchmark signal that the primary side of the test input mutual inductor inputs Signal, and record the reference voltage value and reference current value of the alternating-current measurement reference signal.
Preferably, the alternating-current measurement reference signal on each phase connection is incuded by the first test output mutual inductor Current value generates the current test results signal of each phase connection;Each phase connection is incuded by the second test output mutual inductor On alternating-current measurement reference signal voltage value, generate the voltage tester consequential signal of each phase connection.
Preferably, it is determined according to the phase angle of the current test results signal, voltage tester consequential signal and the two Wiring phase corresponding with the exception of test result signal and wiring error type.
Preferably, it is controlled according to predetermined scheme between the alternating-current measurement reference signal inputted in each phase of secondary circuit Phase angle.
The present invention can quickly and efficiently detect the wiring error of ic for energy metering secondary circuit, and identify in the presence of wrong Phase accidentally and type of error, so that the inspection maintenance for secondary circuit provides convenience;The present invention exchange controllable using intersection Test benchmark signal, middle compared with the existing technology to be detected using actual power, controllability is high, and it is wrong to be applicable to all kinds of wiring The accidentally investigation of situation;The present invention takes out stitches without energization on-load or power failure and checks by root, easy to operate, time saving and energy saving.
Figure of description
Fig. 1 is the structural schematic diagram of metering device secondary circuit detector of the present invention;
Fig. 2 is the secondary circuit route chuck structure schematic diagram of metering device secondary circuit detector of the present invention.
Specific embodiment
Below by embodiment, technical solution of the present invention is described in further detail.
Fig. 1 is the result schematic diagram of metering device secondary circuit detector of the present invention.It is with phase three-wire three in Fig. 1 Example, shows the circuit structure of electric energy metering device, and wherein L1 to L3 is the triple line of power supply line, current transformer C1, C2 And the primary side of voltage transformer U1, U2 are respectively connected to L1 to L3, the voltage and current signals obtained by induction are from above The secondary side of mutual inductor C1, C2, U1, U2 are exported to electric energy meter B1, each phase connection connection mutual inductor C1, C2 in secondary circuit, The secondary side and electric energy meter B1 of U1, U2.
Metering device secondary circuit detector of the invention includes secondary circuit route collet J1-J6, test benchmark signal Generation unit G, test result signal sampling cell S, test result detecting signal unit R, display unit D.
Wherein, the secondary circuit route collet shares 6, be respectively used to connection secondary circuit in each mutual inductor C1, C2, Each phase connection between the secondary side and electric energy meter input terminal of U1, U2, each secondary circuit route collet is for connecting secondary returning The wiring of Lu Yixiang.Fig. 2 shows the structures of one of secondary circuit route collet, as shown in Fig. 2, each secondary loop wire Road collet includes test input mutual inductor IH1, the first test output mutual inductor OH1 and the second test output mutual inductor OH2;With The mutual inductor of upper secondary circuit route collet is all made of forcipated mutual-inductor, can be convenient be linked into secondary circuit each phase connection it In.Wherein the first siding ring of test input mutual inductor IH1 is centered around on the magnetic core of test input mutual inductor IH1, and even The test benchmark signal generation unit G is met, test input mutual inductor IH1 is secondary as its using each phase connection in secondary circuit Side.The second siding ring of the first test output mutual inductor OH1 and the second test output mutual inductor OH2 are centered around institute respectively It states on the magnetic core of the test of the first test output mutual inductor OH1 and second output mutual inductor OH2 and is connected to the test knot Fruit signal sampling cell S, the first test output mutual inductor OH1 and second test output mutual inductor OH2 for secondary circuit In each phase connection as its primary side.
The test benchmark signal generation unit G is used to generate and the primary side for inputting mutual inductor IH1 to the test is defeated Enter test benchmark signal.The test benchmark signal that the test benchmark signal generation unit G is generated is alternating-current measurement reference signal, And the reference voltage value and reference current value for recording the alternating-current measurement reference signal, by the reference voltage value and benchmark electricity Flow valuve is supplied to test result detecting signal unit R.Alternating-current measurement reference signal is input to the primary of test input mutual inductor IH1 Side is input to each phase connection of secondary circuit by incuding, and simulates electric current and voltage letter that it is acquired from power supply line Number.Test benchmark signal generation unit G can control the alternating-current measurement inputted in each phase of secondary circuit according to predetermined scheme Phase angle between reference signal, to improve the applicability of detection.
First test output mutual inductor OH1 and the second test output mutual inductor OH2 incudes two in the terminals of electric energy meter The signal of each phase of minor loop, the first test output mutual inductor OH1 is by incuding the alternating-current measurement benchmark letter on each phase connection Number current value generate the current test results signal of each phase connection;The second test output mutual inductor OH2 is each by induction The voltage value of alternating-current measurement reference signal on phase connection generates the voltage tester consequential signal of each phase connection.The test result Second siding ring of the signal sampling cell S from the first test output mutual inductor OH1 and the second test output mutual inductor OH2 It receives and is believed by the test result that the first test output mutual inductor OH1 and the second test output mutual inductor OH2 generate each phase connection Number.Test result signal is provided to test result detecting signal unit R by the test result signal sampling cell S.Test knot Fruit detecting signal unit R is by the test result signal of each phase connection, by the current test results signal, voltage tester result Signal and the phase angle of the two are compared with nominal value, and whether judgement wherein has abnormal test result signal, and determines Wiring phase corresponding with the exception of test result signal and wiring error type.The display unit D is for showing the survey The wiring phase and wiring error type that test result detecting signal unit determines.
The detector provided through the invention can realize the inspection to metering device second loop return wiring using following methods It surveys.Firstly, the wiring connecting test input mutual inductor of each phase of secondary circuit, the first test output mutual inductor and second are surveyed Try output mutual inductor;Wherein, the first siding ring of test input mutual inductor is centered around on the magnetic core of test input mutual inductor, will Secondary side of each phase connection as test input mutual inductor in secondary circuit;The first test output mutual inductor and second The second siding ring of test output mutual inductor is centered around the first test output mutual inductor respectively and the second test output is mutual On the magnetic core of sensor, using each phase connection in secondary circuit as the first test output mutual inductor and the second test output mutual inductance The primary side of device.In turn, the primary side input test reference signal for generating and inputting to the test mutual inductor, to the test The test benchmark signal for inputting the primary side input of mutual inductor is alternating-current measurement reference signal, and records the alternating-current measurement base The reference voltage value and reference current value of calibration signal;And it is possible to defeated in each phase of secondary circuit according to predetermined scheme control The phase angle between alternating-current measurement reference signal entered.Then, from the first test output mutual inductor and the second test output The second siding ring of mutual inductor, which is received, generates each phase connection by the first test output mutual inductor and the second test output mutual inductor Test result signal, specifically, by it is described first test output mutual inductor incude the alternating-current measurement base on each phase connection The current value of calibration signal generates the current test results signal of each phase connection;Pass through the second test output mutual inductor induction The voltage value of alternating-current measurement reference signal on each phase connection generates the voltage tester consequential signal of each phase connection.Next, will The test result signal of each phase connection is compared with nominal value, according to the current test results signal, voltage tester result Signal and the phase angle of the two determine wiring phase corresponding with the exception of test result signal and wiring error type.Display institute Determining wiring phase and wiring error type.
The present invention can quickly and efficiently detect the wiring error of ic for energy metering secondary circuit, and identify in the presence of wrong Phase accidentally and type of error, so that the inspection maintenance for secondary circuit provides convenience;The present invention exchange controllable using intersection Test benchmark signal, middle compared with the existing technology to be detected using actual power, controllability is high, and it is wrong to be applicable to all kinds of wiring The accidentally investigation of situation;The present invention takes out stitches without energization on-load or power failure and checks by root, easy to operate, time saving and energy saving.
Above embodiments are merely to illustrate the present invention, and not limitation of the present invention, the common skill in relation to technical field Art personnel can also make a variety of changes and modification without departing from the spirit and scope of the present invention, therefore all etc. Same technical solution also belongs to scope of the invention, and scope of patent protection of the invention should be defined by the claims.

Claims (2)

1. a kind of metering device secondary circuit detector, which is characterized in that including secondary circuit route collet, test benchmark signal Generation unit, test result signal sampling unit, test result detecting signal unit, display unit;Wherein, the secondary circuit Route collet shares several, is respectively used to each between each mutual inductor secondary side and electric energy meter input terminal in connection secondary circuit Phase connection;Each secondary circuit route collet is used to connect the wiring of one phase of secondary circuit, each secondary circuit route collet packet Include test input mutual inductor, the first test output mutual inductor and the second test output mutual inductor;Wherein test input mutual inductor First siding ring be centered around the test input mutual inductor magnetic core on and connect the test benchmark signal generation unit, survey Examination input mutual inductor is using each phase connection in secondary circuit as its secondary side;The first test output mutual inductor and second The second siding ring of test output mutual inductor is centered around the first test output mutual inductor respectively and the second test output is mutual On the magnetic core of sensor and it is connected to the test result signal sampling unit, the first test output mutual inductor and second Output mutual inductor is tested using each phase connection in secondary circuit as its primary side;The test benchmark signal generation unit is used for Alternating-current measurement reference signal is generated, and records the reference voltage value and reference current value of the alternating-current measurement reference signal, it will The reference voltage value and reference current value are supplied to test result detecting signal unit, and input mutual inductor to the test Primary side inputs the alternating-current measurement reference signal, surveys according to the exchange that predetermined scheme control inputs in each phase of secondary circuit The phase angle between reference signal is tried, the electric current and voltage signal acquired from power supply line is simulated;The first test output mutual inductance Device generates the current test results signal of each phase connection by incuding the current value of the alternating-current measurement reference signal on each phase connection; The second test output mutual inductor is respectively connected by incuding the voltage value generation of the alternating-current measurement reference signal on each phase connection The voltage tester consequential signal of line;
The test result signal sampling unit tests output mutual inductor from the first test output mutual inductor and second Second siding ring is received to be surveyed by the electric current that the first test output mutual inductor and the second test output mutual inductor generate each phase connection Test result signal and voltage tester consequential signal;Test result detecting signal unit is by the current test results signal of each phase connection It is compared with the phase angle of voltage tester consequential signal and the two with nominal value, whether judgement wherein has abnormal test knot Fruit signal, and determine wiring phase corresponding with the exception of test result signal and wiring error type;The display unit is used In the wiring phase and wiring error type that show that the test result detecting signal unit determines.
2. a kind of detection method of metering device second loop return wiring characterized by comprising by connecing for each phase of secondary circuit Line connecting test inputs mutual inductor, the first test output mutual inductor and the second test output mutual inductor;Wherein, test input is mutual The first siding ring of sensor is centered around on the magnetic core of test input mutual inductor, using each phase connection in secondary circuit as test Input the secondary side of mutual inductor;The second siding ring point of the first test output mutual inductor and the second test output mutual inductor It is not centered around on the magnetic core of the first test output mutual inductor and the second test output mutual inductor, it will be each in secondary circuit Phase connection is as the first test output mutual inductor and the primary side of the second test output mutual inductor;
Alternating-current measurement reference signal is generated, and records the reference voltage value and reference current of the alternating-current measurement reference signal Value, and the alternating-current measurement reference signal is inputted to the primary side of the test input mutual inductor, exist according to predetermined scheme control The phase angle between alternating-current measurement reference signal inputted in each phase of secondary circuit simulates the electric current and electricity acquired from power supply line Press signal;
The alternating-current measurement benchmark by incuding on each phase connection is received from the second siding ring of the first test output mutual inductor The current test results signal for each phase connection that the current value of signal generates, and the secondary side from the second test output mutual inductor Coil receives the voltage tester of each phase connection generated by the voltage value for incuding the alternating-current measurement reference signal on each phase connection Consequential signal;
The current test results signal of each phase connection and voltage tester consequential signal and the phase angle of the two and nominal value are carried out It compares, whether judgement wherein has abnormal test result signal, and determines connect corresponding with the exception of test result signal Line phase and wiring error type;
Wiring phase determined by showing and wiring error type.
CN201610982957.XA 2016-11-09 2016-11-09 A kind of metering device secondary circuit detector and its detection method Expired - Fee Related CN106569170B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610982957.XA CN106569170B (en) 2016-11-09 2016-11-09 A kind of metering device secondary circuit detector and its detection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610982957.XA CN106569170B (en) 2016-11-09 2016-11-09 A kind of metering device secondary circuit detector and its detection method

Publications (2)

Publication Number Publication Date
CN106569170A CN106569170A (en) 2017-04-19
CN106569170B true CN106569170B (en) 2019-07-19

Family

ID=58540585

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610982957.XA Expired - Fee Related CN106569170B (en) 2016-11-09 2016-11-09 A kind of metering device secondary circuit detector and its detection method

Country Status (1)

Country Link
CN (1) CN106569170B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106990384B (en) * 2017-04-27 2023-06-27 广西网冠电气有限公司 Device and method for detecting faulty wiring of three-phase electric energy meter
CN107102289B (en) * 2017-06-19 2019-10-22 云南电网有限责任公司曲靖供电局 A kind of measurement loop wiring error judgment method and device
CN107526001A (en) * 2017-09-07 2017-12-29 广东电网有限责任公司江门供电局 A kind of intelligent line sequence detector and its detection method
CN108445438B (en) * 2018-03-23 2021-10-15 国网河北省电力有限公司电力科学研究院 Method and device for detecting wrong wiring of electric energy metering device
CN108845225B (en) * 2018-06-28 2020-11-06 云南电网有限责任公司昆明供电局 Method for analyzing wiring correctness of secondary current loop of power capacitor and reactor
CN109782212A (en) * 2018-12-29 2019-05-21 国网山东省电力公司聊城供电公司 Bilateral separate type metering secondary wiring check device and its core line method
CN110045313B (en) * 2019-03-19 2021-08-24 江苏固德威电源科技股份有限公司 Three-phase energy storage system ammeter current transformer connection detection method
CN111650538B (en) * 2020-05-29 2022-07-26 深圳供电局有限公司 Electric energy meter wiring detection device and method
CN111650535B (en) * 2020-05-29 2022-07-15 深圳供电局有限公司 Electric energy meter wiring detection method
CN113820632A (en) * 2020-06-18 2021-12-21 杭州普安科技有限公司 Passive power secondary circuit wiring checking system and method
CN114256746A (en) * 2021-12-20 2022-03-29 江苏弘历电气有限公司 High-safety switch cabinet with misoperation alarming function
CN114859286A (en) * 2022-06-07 2022-08-05 贵州电网有限责任公司 Intelligent detection and diagnosis system for wiring before power transmission of electric energy metering device based on weak signals

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060084125A (en) * 2005-01-17 2006-07-24 삼성에스디아이 주식회사 Blue phosphor layer and a plasma display panel comprising the same
CN2812024Y (en) * 2005-03-29 2006-08-30 郑州西部电子技术有限公司 Remote automatic detection system for electric energy metering device
CN2914101Y (en) * 2005-12-13 2007-06-20 北京潞电电气设备厂 Connection discriminating device
JP2015055610A (en) * 2013-09-13 2015-03-23 日本電気計器検定所 Actual load testing device of watthour meter

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060084125A (en) * 2005-01-17 2006-07-24 삼성에스디아이 주식회사 Blue phosphor layer and a plasma display panel comprising the same
CN2812024Y (en) * 2005-03-29 2006-08-30 郑州西部电子技术有限公司 Remote automatic detection system for electric energy metering device
CN2914101Y (en) * 2005-12-13 2007-06-20 北京潞电电气设备厂 Connection discriminating device
JP2015055610A (en) * 2013-09-13 2015-03-23 日本電気計器検定所 Actual load testing device of watthour meter

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
高压电能计量故障检测电路与系统设计研究;王广飞;《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》;20140215;C042-451

Also Published As

Publication number Publication date
CN106569170A (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN106569170B (en) A kind of metering device secondary circuit detector and its detection method
CN105911420B (en) The method of 192 kinds of three-phase three-wire electric energy meter modes of connection of automatic discrimination
CN102156274A (en) Field integral detecting system of three-phase electric energy measuring system of electric distribution network
CN208818818U (en) A kind of low-power consumption program control type current mutual inductor field detecting device
CN102901621A (en) Method and device for testing solenoid valves
CN106841767B (en) A kind of low current signal monitoring system
CN108761375A (en) A kind of low-power consumption program control type current mutual inductor field detecting device
US11500033B2 (en) Ground fault detection of UPS battery
CN201514473U (en) Error positioning device of high-voltage electric power metering device
CN106546938A (en) A kind of anti-DC component of current transformer and test even system
CN107710008A (en) The method and apparatus for debugging the voltage sensor and branch current sensor for branch road monitoring system
CN107942192A (en) A kind of controller switching equipment CT automatic test approach and system
CN106526527B (en) A method of it finding minimum angle and differentiates four line wiring of low voltage three-phase
CN103605041B (en) Non-contact multi-point grounding detection method and system for secondary circuit of current transformer
CN105467355A (en) Automatic testing method of electric energy meter and automatic testing device of same
CN107636481A (en) The method and apparatus for debugging the voltage sensor and branch current sensor for branch road monitoring system
CN104360296B (en) A kind of metering performance calibration equipment of large ground network earth resistance tester
CN103645415A (en) Practical method of inspecting electric energy metering device wiring in charged mode
CN101750540B (en) Method for detecting parasitic loop of transformer station direct current system
CN105954555A (en) Method and device for detecting null line break-off electricity stealing
CN108051698A (en) Coil turn-to-turn insulation failure detection method, apparatus and system
CN205139349U (en) Arrester discharge counter and leakage current table check gauge
CN107102289B (en) A kind of measurement loop wiring error judgment method and device
CN103197195A (en) Detecting method and detecting system for multipoint earthing of voltage second loop neutral conductor network
CN103176048B (en) A kind of method of quick measuring transformer delta connection mode winding D.C. resistance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190719

CF01 Termination of patent right due to non-payment of annual fee