CN106549425A - A kind of failure isolated island fast control method containing flexible direct current - Google Patents

A kind of failure isolated island fast control method containing flexible direct current Download PDF

Info

Publication number
CN106549425A
CN106549425A CN201611131324.4A CN201611131324A CN106549425A CN 106549425 A CN106549425 A CN 106549425A CN 201611131324 A CN201611131324 A CN 201611131324A CN 106549425 A CN106549425 A CN 106549425A
Authority
CN
China
Prior art keywords
direct current
isolated island
power grid
frequency
active
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611131324.4A
Other languages
Chinese (zh)
Other versions
CN106549425B (en
Inventor
林成
马覃峰
瞿艳霞
时伯年
康鹏
孙斌
欧阳可凤
王寅
刘明顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Dispatch Control Center of Guizhou Power Grid Co Ltd
Original Assignee
Electric Power Dispatch Control Center of Guizhou Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Electric Power Dispatch Control Center of Guizhou Power Grid Co Ltd filed Critical Electric Power Dispatch Control Center of Guizhou Power Grid Co Ltd
Priority to CN201611131324.4A priority Critical patent/CN106549425B/en
Publication of CN106549425A publication Critical patent/CN106549425A/en
Application granted granted Critical
Publication of CN106549425B publication Critical patent/CN106549425B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J5/00Circuit arrangements for transfer of electric power between ac networks and dc networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/388Islanding, i.e. disconnection of local power supply from the network

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a kind of failure isolated island fast control method containing flexible direct current, for regional power grid respectively by handing over, the situation of the interconnected network that direct current transportation passage is connected with other electrical networks, calculated by off-line simulation and to form control strategy and carry into execution a plan, by the urgent flexible direct current corresponding with non-emergent control strategy of Off-line control strategy point different control methods, then according to the frequency and frequency variation feature when failure isolated island occurs, search the strategy that prior calculated off line is obtained, and confirm to perform, frequency and frequency variation are persistently judged, can be supplied with the result of the action of security and stability control equipment in power system in real time, islanded system is finally made to recover stable.It is an advantage of the invention that directly determining flexible direct current control method by using the mode for looking into off-line strategy scheme, sampling amount of calculation is few for which, judge that quick, control efficiency is high, so as to improve the frequency stability and performance driving economy of isolated island after failure.

Description

A kind of failure isolated island fast control method containing flexible direct current
Technical field
The invention belongs to technical field of power system operation control, and in particular to a kind of failure isolated island containing flexible direct current is fast Speed control method.
Background technology
Flexible DC power transmission (soft straight) technology employs all-controlling power electronics device, with rapid tidal current control, dynamic Reactive power support, multiport coordinated operation, many-sided advantage such as prevent fault coverage from expanding.Multiple regional power grids are defeated by alternating current-direct current Interconnected network is electrically connected to form, when important section breaks down, area power grid voltage and frequency stable problem is will appear from, seriously Threaten power network safety operation.After system stability is destroyed, generally need to by stability control device action cut machine (or cutting load) with Ensure system stable operation.Flexible direct current is applied to after interconnected network, electrical network objectively requires its above-mentioned advantage of performance and peace Full stability contorting equipment coordination acts on improving system stability.And there is presently no and related solution occur, for this The situation of kind, it is necessary to work out a kind of failure island control method containing flexible direct current, to solve the above problems.
The content of the invention
In view of this, it is an object of the invention to provide a kind of failure isolated island fast control method of flexible direct current.For area The mode of connection that domain electrical network is connected with other electrical networks by AC and DC passway for transmitting electricity respectively, when in ac transmission channel failure Disconnected forming region island-grid, power shortage will cause isolated island to lose stable problem, and the present invention is led to respectively based on regional power grid The mode of connection that AC and DC passway for transmitting electricity is connected with other electrical networks is crossed, calculates to form Off-line control strategy by off-line simulation, The Off-line control strategy that prior calculated off line is obtained is searched according to frequency and frequency change rate in failure isolated island moment, will be flexible straight Flow quick emergent control to organically combine with accurate non-emergent control, in safety stabilization control system two, three lines of defence action Before, make full use of flexible direct current that there is power flow regulating safely and fast and reverse function not available for customary DC, subsequently profit The implementation deviation of safety stabilization control system can persistently be supplied the characteristics of two-way dynamic regulation isolated island frequency with flexible direct current, finally Islanded system is made to recover stable.
The purpose of the present invention is achieved through the following technical solutions:
The method of the present invention, is respectively by AC and DC (flexible direct current) passway for transmitting electricity and other electricity for regional power grid Net connection, when communication channel fault interrupting, therefore the regional power grid forms isolated island, makes which by flexible direct current control strategy Recover stable;Characterized in that, the method comprises the steps:
(1) calculated off line regional power grid communication channel disconnects, and is only connected with other electrical networks by flexible direct current, forms isolated network The Off-line control strategy that frequency change rate df/dt, f afterwards determines;
(2) the soft straight current conveying active-power P of Real-time Collection0, soft straight current maximum active-power P max and region it is electric Net and soft straight junction ac bus voltage;
(3) judging whether regional power grid breaks down causes ac transmission channel interrupt, if now only remain direct current channel with Outer net connects, then isolated island criterion meets, into step (4), otherwise return to step (2);
(4) (traditional soft or hard Frequency Measurement Algorithm) f, df/dt value is calculated in real time according to the busbar voltage for being gathered;
(5) according to regional power grid frequency f and frequency change rate df/dt determination frequencies whether in recovery process, when frequency Rate overrate and on a declining curve or frequency are less than rated value and in rising trend, that is, meet f > fN and df/dt < 0 or Meet f < fN and df/dt > 0 then return to step (4), otherwise into step (6);
(6) judge whether to take tight with reference to Off-line control strategy according to regional power grid frequency f and frequency change rate df/dt It is anxious to control, if then entering step (7), otherwise into step (8);
(7) search in offline emergent strategy corresponding region electrical network in total active difference Pi, according to it is soft directly currently convey it is active Power P0, soft straight current maximum active-power P max, be calculated soft straight measure amount and directly perform, after executive measure, return step Suddenly (4);
(8) start FLC (Frequency limit controller (frequency limit controller, FLC)), carry out soft straight non- Emergent strategy measure is performed, return to step (4) after executive measure.
Especially, in step (1), the calculating of Off-line control strategy is to utilize simulation software, using the interconnected network reality Border parameter carries out failure isolated island simulation calculation, obtains frequency change rate d1~d6, frequency f1~f6 and regional power grid always active The value of difference P1~P6, and confirm the relation of frequency f, df/dt and executive measure:
1. when fN≤f < f4 and d1≤df/dt < d2 is met:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P1;
2. when meet f5≤f < f6 and 0≤df/dt < d3, f4≤f < f5 and d1≤df/dt < d3, fN≤f < f4 and During d1≤df/dt < d2:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P2;
3. when meeting f6≤f and 0≤df/dt or when meeting fN≤f < f6 and d3≤df/dt:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P3;
4. when f3≤f < fN and d5≤df/dt < d4 is met:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P4;
5. when meeting f1≤f < f2 and d6≤df/dt < 0, or meet f2≤f < f3 and d6≤df/dt < d4 or meet When f3≤f < fN and d6≤df/dt < d5:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P5;
6. when meeting f < f1 and df/dt < 0, or when meeting f1≤f < fN and df/dt < d6:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P6;
7. when meeting f2≤f < fN and d4≤df/dt < 0, or when meeting fN≤f < f5 and 0≤df/dt < d1:
Non-emergent control strategy is entered after regional power grid isolated island, off-line simulation calculates the main control parameters for confirming FLC (KP, Ti), can control to adjust soft straight active power by the proportional integral ring of FLC makes isolated island recover stable, and FLC functions belong to ratio More ripe technology, will not be described here.
Especially, in step (7), in searching offline emergent strategy, corresponding region electrical network is in total active difference Pi, soft straight Current conveying active-power P0, soft straight current maximum active-power P max, be calculated soft straight measure amount and directly perform:
1. in emergent strategy control the Pi that finds with meet soft straight current conveying active-power P0Power direction is identical (relative In orphan
Net be send or be into) when:
As | Pi |≤Pmax- | P0|, then directly specified soft straight active reference value is | P0|+| Pi | and lift direct current;
As | Pi | > Pmax- | P0|, then directly specify soft straight active reference value to be Pmax and lift direct current.
2. in emergent strategy control the Pi that finds with meet soft straight current conveying active-power P0Power direction is contrary (relative In isolated network one for send one be into) when:
When | Pi |≤| P0|, then the soft straight active reference value directly after specified reversion is | P0|-| Pi | and return drop direct current;
When | P0| < | Pi |≤Pmax+ | P0|, then first flexible direct current rapid tidal current is inverted, and after directly specifying reversion It is soft directly to have
Work(reference value be | Pi |-| P0| and lift direct current;
As | Pi | > Pmax+ | P0|, then first flexible direct current rapid tidal current is inverted, and directly specify soft directly having after reversion Work(is joined
Value is examined for Pmax and direct current is lifted.
The action of flexible direct current control strategy controls two, before three lines of defence in power system safety and stability, if flexible direct current The margin of power has run out, and system frequency can not still be recovered, and subsequently will be adopted by power system safety and stability control two, three lines of defence The machine of cutting (cutting load) measure is taken, it is by whole electromotor or whole negative that actual safety stabilization control system cuts machine (cutting load) measure Lotus combines, therefore there is deviation with theoretical power (horse-power) vacancy, and caused by this deviation, frequency anomaly is can be straight by the flexibility of the present invention Flow control policy is supplied, and after most making failure at last, isolated network recovers stable.
The invention has the beneficial effects as follows:
For regional power grid respectively by AC and DC passway for transmitting electricity with other electrical networks under the mode of connection being connected, this It is bright to be calculated soft straight Off-line control strategy protocol using system emulation data by offline, when important communication channel interrupts, According to the real-time isolated network frequency for calculating and the value of the frequency change rate for obtaining, search the soft straight control measure of correspondence and perform, and with Caused by safety stabilization control system action deviation is supplied using the failure isolated island fast control method of the present invention afterwards, frequency is different Often.The method sampling amount of calculation is few, judge that quick, control efficiency is high, so as to improve the frequency stability and fortune of isolated island after failure Row economy.
Other advantages of the present invention, target and feature will be illustrated to a certain extent in the following description, and And to a certain extent, based on being will be apparent to investigating hereafter to those skilled in the art, Huo Zheke To be instructed from the practice of the present invention.The target and other advantages of the present invention can pass through description below and right will Seek book to realize and obtain.
Description of the drawings
In order that the object, technical solutions and advantages of the present invention are clearer, below in conjunction with accompanying drawing the present invention is made into The detailed description of one step, wherein:
Fig. 1 show the power network wiring sketch containing flexible direct current;
Fig. 2 show the application example electric network wiring scheme of the present invention;
Fig. 3 show the non-emergent control strategy schematic diagrams of FLC;
Fig. 4 is a kind of failure isolated island stable control method flow chart of the invention;
Specific embodiment
Hereinafter with reference to accompanying drawing, the preferred embodiments of the present invention are described in detail.It should be appreciated that preferred embodiment Only for the explanation present invention, rather than in order to limit the scope of the invention.
Technical scheme is further stated in detail with reference to Figure of description.
The power network wiring containing flexible direct current of indication of the present invention is as shown in figure 1, regional power grid S2 is another by communication channel connection One electrical network S1, while connecting another electrical network S3 by the direct current channel formed by flexible direct current.Friendship between electrical network S2 and S1 Circulation road break down tripping when, regional power grid S2 forms isolated network due to failure.
The application is discussed in detail a kind of failure isolated island containing flexible direct current fast by taking certain practical structures shown in accompanying drawing 2 as an example Speed control method.The systematic parameter adopted by off-line simulation is the power system actual parameter, soft lineal system rated direct voltage For ± 204kV, using based on modularization multi-level converter technology, inverter rated capacity 300MVA is normal to run for inverter When inverter it is maximum active for 290MW, set soft active power 150MW for directly sharing electromagnetic looped network, and not with systems exchange without Work(power.The total installation of generating capacity of S1, S2, S3 is respectively 1200MW, 1740MW, 29890MW.
The step of practical operation is carried out using a kind of failure isolated island fast control method containing flexible direct current of the present invention is such as Under:
(1) flexible direct current Off-line control strategy is calculated using simulation software, using the interconnected network actual parameter shown in Fig. 2 Failure isolated island simulation calculation is carried out, frequency change rate d1~d6 is obtained and is respectively:0.5、0.9、1.3、-0.6、-1.0、-1.5 (Hz/s), frequency f1~f6 is respectively 49.1,49.3,49.6,50.3,50.6,50.8 (Hz):, the total active difference of regional power grid The value of P1~P6 is respectively:220th, 470,600, -230, -454, -590 (MW), electrical network rated frequency fN are 50 (Hz).Confirm The relation control strategy as shown in Figure 3 of frequency f, df/dt and executive measure, it is specific as follows:
1. when 50≤f < 50.3 and 0.5≤df/dt < 0.9 is met:
Emergency control policy is entered after regional power grid isolated island, its total active difference is 220 (MW);
2. when meet 50.6≤f < 50.8 and 0≤df/dt < 1.3,50.3≤f < 50.6 and 0.5≤df/dt < 1.3, When 50≤f < 50.3 and 0.5≤df/dt < 0.9:
Emergency control policy is entered after regional power grid isolated island, its total active difference is 470 (MW);
3. as 50.8≤f of satisfaction and 0≤df/dt or 50≤f of satisfaction < 50.8 and 1.3≤df/dt:
Emergency control policy is entered after regional power grid isolated island, its total active difference is 600 (MW);
4. when 49.6≤f < 50 and -1.0≤df/dt < -0.6 are met:
Emergency control policy is entered after regional power grid isolated island, its total active difference is -230 (MW);
5. when meeting 49.1≤f, 49.3 and -1.5≤df/dt of < < 0, or meet 49.3≤f, 49.6 and -1.5≤df/ of < Dt < -0.6, or meet 49.6≤f < 50 and -1.5≤df/dt < -1.0 when:
Emergency control policy is entered after regional power grid isolated island, its total active difference is -454 (MW);
6. when meeting f < 49.1 and df/dt < 0, or when meeting 49.1≤f < 50 and df/dt < -1.5:
Emergency control policy is entered after regional power grid isolated island, its total active difference is -590 (MW);
7. when meeting 49.3≤f, 50 and -0.6≤df/dt of < < 0, or meet 50≤f < 50.6 and 0≤df/dt < 0.5 When:
Non-emergent control strategy is entered after regional power grid isolated island, off-line simulation calculates the main control parameters for confirming FLC (KP, Ti), by simulation calculation, the control effect when it is 10 that Kp values are for 1.0, Ti values is ideal for this example.Can lead to The soft straight active power of proportional integral ring control and regulation for crossing FLC makes isolated island recover stable, and FLC functions belong to the skill of comparative maturity Art, its control block diagram is using the conventional classics control block diagram of engineering, the non-emergent control strategy of FLC as shown in Figure 3, because which is in ability Domain belongs to known technology, so the present invention is repeated no more.
(2) Real-time Collection obtains soft straight current conveying active-power P0For 150MW, direction is isolated network transport direction, soft straight Current maximum active-power P max is 290MW, while pickup area electrical network and soft straight junction ac bus voltage;
(3) judging whether regional power grid breaks down causes ac transmission channel interrupt, if now only remain direct current channel with Outer net connects, then isolated island criterion meets, into step (4), otherwise return to step (2);
(4) f, df/dt value is calculated in real time according to the busbar voltage for being gathered, (is counted using traditional soft or hard Frequency Measurement Algorithm Calculation method is this area routine techniquess means) f is measured after failure for 49.5 (Hz), df/dt is -1.9 (Hz/s);
(5) it is discontented with whether in recovery process according to regional power grid frequency f and frequency change rate df/dt determination frequencies Sufficient frequency retrieval process conditional, then into step (6);
(6) soft straight emergency control policy is met according to regional power grid frequency f and frequency change rate df/dt, into step (7);
(7) in searching offline emergent strategy, corresponding region electrical network is -590 (MWs) for P6 in total active difference Pi, according to soft Straight current conveying active-power P0, soft straight current maximum active-power P max, meet | Pi | > Pmax+ | P0|, then first will be flexible straight Stream rapid tidal current reversion, and directly specify the soft straight active reference value after reversion to be that Pmax is 290 (MW) and lifts direct current to 290 (MW);Soft straight one hundred percent reserve capacity is finished.Now the active vacancy of isolated network is 150 (MW), is cut off by safety stabilization control system After 190MW loads, it is 50.5 (Hz) now to measure f, and df/dt is 0.3 (Hz/s), meets the non-emergent control condition of flexible direct current, Hence into step (8);
(8) start FLC (Frequency limit controller), carry out soft straight non-emergent Strategic Measures and perform, passing ratio integration control When soft straight reference value is slowly dropped to 255 (MW) by ring processed, isolated network frequency retrieval is to rated value.
It is pointed out that the action of flexible direct current control strategy in power system safety and stability control two, three lines of defence it Before, if the flexible direct current margin of power has run out, system frequency can not still be recovered, subsequently will be by power system safety and stability control 2nd, the machine of cutting (cutting load) measure is taken in three lines of defence, and it is by whole that actual safety stabilization control system cuts machine (cutting load) measure , therefore there is deviation with theoretical power (horse-power) vacancy in electromotor or the combination of whole load, caused by this deviation, frequency anomaly is can be by The flexible direct current control strategy of the present invention is supplied, and after most making failure at last, isolated network recovers stable.
The present invention is calculated soft straight Off-line control strategy protocol using system emulation data by offline, when important exchange During channel interrupt, according to the real-time isolated network frequency for calculating and the value of the frequency change rate for obtaining, the soft straight control measure of correspondence are searched And perform, and the subsequent failure isolated island fast control method using the present invention is supplied safety stabilization control system action deviation and is led The frequency anomaly of cause.The method sampling amount of calculation is few, judge that quick, control efficiency is high, so as to improve the frequency of isolated island after failure Stability and performance driving economy.
Finally illustrate, above example is only unrestricted to illustrate technical scheme, although with reference to compared with Good embodiment has been described in detail to the present invention, it will be understood by those within the art that, can be to the skill of the present invention Art scheme is modified or equivalent, and without deviating from the objective and scope of the technical program, which all should be covered in the present invention Right in the middle of.

Claims (3)

1. a kind of failure isolated island fast control method containing flexible direct current, logical by AC and DC transmission of electricity respectively for regional power grid Road is connected with other electrical networks, and when communication channel fault interrupting, therefore the regional power grid forms the situation of isolated island, by flexibility DC control strategy makes which recover stable, it is characterised in that:Comprise the steps:
(1) calculated off line is only connected with other electrical networks by flexible direct current when the disconnection of regional power grid communication channel, after forming isolated network Frequency change rate df/dt, f determine Off-line control strategy;Wherein, f is regional power grid frequency;Df/dt is frequency change rate;
(2) the soft straight current conveying active-power P of Real-time Collection0, soft straight current maximum active-power P max and regional power grid with it is soft Straight junction ac bus voltage;
(3) judge whether regional power grid occurs the interruption of ac transmission channel failure, if now only remain direct current channel being connected with outer net, Then isolated island criterion meets, into step (4), otherwise return to step (2);
(4) f, df/dt value is calculated in real time according to the busbar voltage for being gathered;
(5) according to regional power grid frequency f and frequency change rate df/dt determination frequencies whether in recovery process, when frequency surpasses Cross rated value and on a declining curve or frequency less than rated value and in rising trend, that is, meet f > fN and df/dt < 0 or meet f < fN and df/dt > 0 then return to step (4), otherwise into step (6);
(6) judge whether to take urgent control with reference to Off-line control strategy according to regional power grid frequency f and frequency change rate df/dt System, if then entering step (7), otherwise into step (8);
(7) in searching offline emergent strategy, corresponding region electrical network directly currently conveys active power according to soft in total active difference Pi P0, soft straight current maximum active-power P max, be calculated soft straight measure amount and directly perform, return to step after executive measure (4);
(8) initiation culture restriction controller FLC, carries out soft straight non-emergent Strategic Measures and performs, return to step after executive measure (4)。
2. the failure isolated island fast control method of a kind of flexible direct current according to claim 1, it is characterised in that:In step (1) in, Off-line control strategy is to utilize power system simulation software, carries out failure isolated island using the interconnected network actual parameter and imitates It is true to calculate, the value of the total active difference P1~P6 of frequency change rate d1~d6, frequency f1~f6 and regional power grid is obtained, and is confirmed The relation of frequency f, df/dt and executive measure:
1. when fN≤f < f4 and d1≤df/dt < d2 is met:Wherein fN is rated frequency;
Emergency control policy is entered after regional power grid isolated island, its total active difference is P1;
2. when meeting f5≤f < f6 and 0≤df/dt < d3, f4≤f < f5 and d1≤df/dt < d3, fN≤f < f4 and d1≤ During df/dt < d2:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P2;
3. when meeting f6≤f and 0≤df/dt or when meeting fN≤f < f6 and d3≤df/dt:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P3;
4. when f3≤f < fN and d5≤df/dt < d4 is met:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P4;
5. when meet f1≤f < f2 and d6≤df/dt < 0, or meet f2≤f < f3 and d6≤df/dt < d4 or meet f3≤ When f < fN and d6≤df/dt < d5:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P5;
6. when meeting f < f1 and df/dt < 0, or when meeting f1≤f < fN and df/dt < d6:
Emergency control policy is entered after regional power grid isolated island, its total active difference is P6;
7. when meeting f2≤f < fN and d4≤df/dt < 0, or when meeting fN≤f < f5 and 0≤df/dt < d1:
Non-emergent control strategy is entered after regional power grid isolated island, off-line simulation calculates the main control parameters (K for confirming FLCP, Ti), Soft straight active power can be controlled to adjust by the proportional integral ring of FLC makes isolated island recover stable.
3. the failure isolated island fast control method of a kind of flexible direct current according to claim 1 and 2, it is characterised in that: In step (7), in searching offline emergent strategy, corresponding region electrical network is in total active difference Pi, soft directly currently to convey active power P0, soft straight current maximum active-power P max, be calculated soft straight measure amount and directly perform:
1. in emergent strategy control the Pi that finds with meet soft straight current conveying active-power P0When power direction is identical, i.e., relatively It is in isolated network and sends or be by fashionable:
As | Pi |≤Pmax- | P0|, then directly specified soft straight active reference value is | P0|+| Pi | and lift direct current;
As | Pi | > Pmax- | P0|, then directly specify soft straight active reference value to be Pmax and lift direct current.
2. in emergent strategy control the Pi that finds with meet soft straight current conveying active-power P0When power direction is contrary, i.e., relatively In isolated network, one is by fashionable to send one:
When | Pi |≤| P0|, then the soft straight active reference value directly after specified reversion is | P0|-| Pi | and return drop direct current;
When | P0| < | Pi |≤Pmax+ | P0|, then first flexible direct current rapid tidal current is inverted, and directly specify soft straight after reversion Active reference value be | Pi |-| P0| and lift direct current;
As | Pi | > Pmax+ | P0|, then first flexible direct current rapid tidal current is inverted, and directly specify the soft straight active ginseng after reversion Value is examined for Pmax and direct current is lifted.
CN201611131324.4A 2016-12-09 2016-12-09 A kind of failure isolated island fast control method containing flexible direct current Active CN106549425B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611131324.4A CN106549425B (en) 2016-12-09 2016-12-09 A kind of failure isolated island fast control method containing flexible direct current

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611131324.4A CN106549425B (en) 2016-12-09 2016-12-09 A kind of failure isolated island fast control method containing flexible direct current

Publications (2)

Publication Number Publication Date
CN106549425A true CN106549425A (en) 2017-03-29
CN106549425B CN106549425B (en) 2019-09-24

Family

ID=58397583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611131324.4A Active CN106549425B (en) 2016-12-09 2016-12-09 A kind of failure isolated island fast control method containing flexible direct current

Country Status (1)

Country Link
CN (1) CN106549425B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107526009A (en) * 2017-09-13 2017-12-29 国电南瑞科技股份有限公司 It is a kind of that Interlocking Methods are detected according to the isolated island of frequency and curent change sequential
CN107769226A (en) * 2017-10-25 2018-03-06 贵州电网有限责任公司电力调度控制中心 A kind of mains frequency control method based on mixed DC feed-in
CN107994598A (en) * 2017-10-31 2018-05-04 中国电力科学研究院有限公司 A kind of alternating current-direct current control method for coordinating and system
CN108695878A (en) * 2018-05-04 2018-10-23 国网重庆市电力公司 A kind of regional power grid height flexible direct current emergency control method and system under by electric ratio
CN109103918A (en) * 2018-10-11 2018-12-28 国网山东省电力公司 A method of considering the soft directly to the active support of island network of frequency change rate
CN109347111A (en) * 2018-10-22 2019-02-15 国网山东省电力公司济南供电公司 A kind of flexible direct current converter station active reactive control method considering voltage change ratio
CN109713664A (en) * 2019-01-10 2019-05-03 清华大学 The net source coordination control strategy calculation method and system of direct current isolated island frequency stabilization
CN110224446A (en) * 2019-06-04 2019-09-10 深圳供电局有限公司 A kind of receiving end city partial electric grid isolated power grid frequency control apparatus

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007116805A (en) * 2005-10-19 2007-05-10 Shikoku Res Inst Inc Control method of autonomous distribution control system of power system
CN103633638A (en) * 2013-11-06 2014-03-12 南方电网科学研究院有限责任公司 Frequency control strategy for multiple DC (Direct Current) send-out island power grid
CN105406496A (en) * 2015-12-15 2016-03-16 北京四方继保自动化股份有限公司 Isolated microgrid frequency modulation control method based on measured frequency response identification
CN106099918A (en) * 2016-06-30 2016-11-09 国家电网公司 A kind of method of simulation calculation multi-infeed DC mains frequency emergency control policy

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007116805A (en) * 2005-10-19 2007-05-10 Shikoku Res Inst Inc Control method of autonomous distribution control system of power system
CN103633638A (en) * 2013-11-06 2014-03-12 南方电网科学研究院有限责任公司 Frequency control strategy for multiple DC (Direct Current) send-out island power grid
CN105406496A (en) * 2015-12-15 2016-03-16 北京四方继保自动化股份有限公司 Isolated microgrid frequency modulation control method based on measured frequency response identification
CN106099918A (en) * 2016-06-30 2016-11-09 国家电网公司 A kind of method of simulation calculation multi-infeed DC mains frequency emergency control policy

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
鲍正杰等: ""基于VSC-HVDC有功支援和自适应低频减载的区域电网频率控制"", 《电力系统保护与控制》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107526009A (en) * 2017-09-13 2017-12-29 国电南瑞科技股份有限公司 It is a kind of that Interlocking Methods are detected according to the isolated island of frequency and curent change sequential
CN107769226A (en) * 2017-10-25 2018-03-06 贵州电网有限责任公司电力调度控制中心 A kind of mains frequency control method based on mixed DC feed-in
CN107994598A (en) * 2017-10-31 2018-05-04 中国电力科学研究院有限公司 A kind of alternating current-direct current control method for coordinating and system
CN107994598B (en) * 2017-10-31 2022-07-26 中国电力科学研究院有限公司 AC/DC coordination control method and system
CN108695878A (en) * 2018-05-04 2018-10-23 国网重庆市电力公司 A kind of regional power grid height flexible direct current emergency control method and system under by electric ratio
CN109103918A (en) * 2018-10-11 2018-12-28 国网山东省电力公司 A method of considering the soft directly to the active support of island network of frequency change rate
CN109347111A (en) * 2018-10-22 2019-02-15 国网山东省电力公司济南供电公司 A kind of flexible direct current converter station active reactive control method considering voltage change ratio
CN109347111B (en) * 2018-10-22 2022-12-13 国网山东省电力公司济南供电公司 Active and reactive control method of flexible direct current converter station considering voltage change rate
CN109713664A (en) * 2019-01-10 2019-05-03 清华大学 The net source coordination control strategy calculation method and system of direct current isolated island frequency stabilization
CN109713664B (en) * 2019-01-10 2021-01-15 清华大学 Network source coordination control strategy calculation method and system with stable direct current island frequency
CN110224446A (en) * 2019-06-04 2019-09-10 深圳供电局有限公司 A kind of receiving end city partial electric grid isolated power grid frequency control apparatus
CN110224446B (en) * 2019-06-04 2023-03-03 深圳供电局有限公司 Isolated network operation frequency control device for local power grid of receiving-end city

Also Published As

Publication number Publication date
CN106549425B (en) 2019-09-24

Similar Documents

Publication Publication Date Title
CN106549425A (en) A kind of failure isolated island fast control method containing flexible direct current
CN106469908B (en) A kind of comprehensive aid decision-making method of the static security that multiple faults is coordinated
JP2018536382A (en) Online evaluation method for safety margin of power system operating reserve
CN106786620B (en) Emergency load control method under island network malfunction
CN105391050B (en) Cut the check method and system of machine allocation plan high week
CN108493998B (en) Robust power transmission network planning method considering demand response and N-1 expected faults
CN105281344A (en) Smart distribution network self-restoration optimization method considering power quality and uncertainty constraint thereof
CN101320914B (en) Emergency scheduling method for reinforcing electric network transportation ability
CN106159985A (en) A kind of anti-isolated island method and apparatus of DC distribution net distributed power source
CN104104102A (en) Voltage source converter type multiport direct current transmission system steady state working point optimization method
CN107681780A (en) A kind of power network section monitors and turns to supply tactful intelligent generating system and method
CN108400597B (en) Direct-current fault static safety analysis method considering security control and primary frequency modulation characteristics
CN108448593A (en) A kind of control system and control method shortening the AGC response times
CN107732953A (en) Machine order determination method is cut after the direct current locking of a kind of considering security and efficiency
CN104393602B (en) Adjusting method and device for distributed energy resource network
CN113964864A (en) Flexible direct grid-connected system receiving end converter station island fault ride-through control method and system
CN105958554A (en) Flexible direct current coordination stability control method applied to electromagnetic loop network
CN110071499B (en) Method and system for rapidly judging safety loop closing of power distribution network
CN107785921B (en) Urban power grid partition interconnection operation scheduling method based on flexible direct current transmission technology
CN107607885A (en) A kind of variable-frequency power sources pilot system and its experimental control method
CN109301833B (en) AC/DC series-parallel power grid power transmission section overload control method based on path stripping
CN110266032A (en) A kind of feasible zone of HVDC system commutation process describes method
CN112865083B (en) Real-time running state evaluation method for power system containing renewable energy sources
CN106099977B (en) Energy storage control method and system suitable for single-phase micro-capacitance sensor pattern switching
CN106300347B (en) A kind of engineer application method that can quickly determine 10kV distribution line cyclization tune electricity feasibilities

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant