CN106532717B - Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method - Google Patents

Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method Download PDF

Info

Publication number
CN106532717B
CN106532717B CN201610978458.3A CN201610978458A CN106532717B CN 106532717 B CN106532717 B CN 106532717B CN 201610978458 A CN201610978458 A CN 201610978458A CN 106532717 B CN106532717 B CN 106532717B
Authority
CN
China
Prior art keywords
node
cutting load
branch
overload
index
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610978458.3A
Other languages
Chinese (zh)
Other versions
CN106532717A (en
Inventor
张丹丹
杨冬
蒋哲
武乃虎
李文博
邢鲁华
侯燕文
麻常辉
张荻
张一荻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610978458.3A priority Critical patent/CN106532717B/en
Publication of CN106532717A publication Critical patent/CN106532717A/en
Application granted granted Critical
Publication of CN106532717B publication Critical patent/CN106532717B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/30Circuit design
    • G06F30/36Circuit design at the analogue level
    • G06F30/367Design verification, e.g. using simulation, simulation program with integrated circuit emphasis [SPICE], direct methods or relaxation methods
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Primary Health Care (AREA)
  • Public Health (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses the circuit overloads based on comprehensive sensitivity analysis to join cutting load coordination optimizing method, include: node screening: establishing the node overall sensitivity index of meter and branch overload degree according to the sensitivity relation between branch current and node Injection Current, and alternative cutting load node screening is carried out by the calculating of node overall sensitivity index;Scheme search: coordinating cutting load economic cost and harmonious two targets of node cutting load, with the minimum optimization aim of weighted value of economic cost and node cutting load harmony index, establishes circuit overload connection cutting load coordination optimization Controlling model;The weighted value for setting cutting load economic cost and harmonious index calculates the circuit overload connection cutting load coordination optimization Controlling model under different weights, and optimal route overload joining-cutting load coordinates and optimizes control program, finally obtains cutting load node.The present invention substantially increases scheme search efficiency, avoids falling into dimension calamity during Optimum search.

Description

Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method
Technical field
The present invention relates to electric power network technique fields, and in particular to the circuit overload connection cutting load association based on comprehensive sensitivity analysis Adjust optimization method.
Background technique
The continuous development of trans-regional interconnected power grid solves the inverse of energy resources and load center to a certain extent To distribution problem, realize across big area resource distribute rationally with the economical and efficient of operation of power networks, clean and environmental protection, but simultaneously to electricity The safe and stable operation of net brings unprecedented challenge.
In recent years, more large area blackouts show both at home and abroad: in long-distance and large-capacity power transmission system, circuit overload can A series of cascading trip accidents can be will lead to, in turn result in large-area power-cuts.Therefore, reasonable circuit overload connection how is formulated to cut Duty control method quickly eliminates circuit overload, is to prevent the chain power outage of large area, ensures power grid security, stabilization, economy The key of operation.
The circuit overload connection load shedding control method used in real system at present is mainly minute wheel classification cutting load method.It should Method refers to that different according to circuit overload degree, minute wheel grade is cut off according to each load excision round and priority ranking is preset Load.It is rely on related personnel's experience since this method is when presetting each load excision round and priority ranking more, lack The theoretical calculation of system, therefore often result in load in practical operation and owe to cut or cross to cut, and the priority that load is cut off in this method Sequence is overloaded just for uniline, can not be to cutting load measure using this method when route a plurality of in system overloads simultaneously Carry out global optimization.
In short, above-mentioned circuit overload connection cutting load method spininess solves uniline overload, lack to a plurality of line Coordination optimization control when road is overloaded simultaneously;And in Practical Project, electric power enterprise, should when taking overload joining-cutting load measure It pursues economic cost to minimize, considers the harmony of cutting load again, to reduce accident impact, the grading of reduction accident, and show There is method not take in cutting load harmony.
In consideration of it, the application proposes a kind of circuit overload connection cutting load coordination optimization side based on comprehensive sensitivity analysis Method.
Summary of the invention
To solve the shortcomings of the prior art, the invention discloses the circuit overload connection based on comprehensive sensitivity analysis to cut Coordinated optimization method, the purpose of the present invention is: for one or more of routes after failure while overload situations, establish The measure of node cutting load avoids the overall sensitivity index of overload route by the alternative cutting load node of index calculating sifting Calculating falls into dimension calamity;Method constructs circuit overload connection cutting load coordination optimization Controlling model, is cut with economic cost and node The minimum optimization aim of the weighted value of load balancing index, by the active and reactive balance of trend, node voltage, current limiter ginseng Number is not out-of-limit to wait limitations to be included in constraint condition.The method achieve economic cost when overload joining-cutting load control is balanced with cutting load Property coordination optimization control meet different operation of power networks requirements, guarantee quickly disappearing for circuit overload and by the way that different weights are arranged It removes, meets Practical Project demand.
To achieve the above object, concrete scheme of the invention is as follows:
Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method, comprising the following steps:
Node screening: forming network node admittance matrix and incidence matrix, fixed according to nodal voltage equation and incidence matrix Justice obtains the sensitivity relation between branch current and node Injection Current;
The node of meter and branch overload degree is established according to the sensitivity relation between branch current and node Injection Current Overall sensitivity index, and alternative cutting load node screening is carried out by the calculating of node overall sensitivity index;
Scheme search: coordinate cutting load economic cost and harmonious two targets of node cutting load, with economic cost and node The minimum optimization aim of weighted value of cutting load harmony index establishes circuit overload connection cutting load coordination optimization Controlling model;
According to, setting cutting load economic cost and harmonious index different from harmonious requirement to cutting load economic cost Weighted value calculates the circuit overload connection cutting load coordination optimization Controlling model under different weights, and optimal route overload connection is cut Coordinated optimization control scheme finally obtains cutting load node.
Further, defined according to nodal voltage equation and incidence matrix, obtain branch current and node Injection Current it Between sensitivity relation are as follows:
Wherein,For branch current column vector;Y is Nl×NlRank branch admittance matrix,For the inverse of node admittance matrix Battle array,For node Injection Current column vector, flows into node and be positive, outflow is negative, ATFor incidence matrix transposition.
Further, cutting load measure is taken to eliminate ability definition node k to the overcurrent of all overload branches according to node k Sensitivity index considers that branch overload degree is different, definition node overall sensitivity index:
Wherein, δjFor branch j weighted value, for indicating the overload degree of branch j;IjThe practical electricity of respectively branch j Flow valuve and the permission current value upper limit, NsTo overload branch total number, YjFor branch admittance battle array jth row element, the i.e. self-conductance of branch j It receives and transadmittance, ATFor incidence matrix transposition,For the inverse matrix of node admittance matrix.
Further, calculating is normalized in node overall sensitivity index, for intuitively expressing all overload branches pair The overall sensitivity of a certain node cutting load measure.
Further, when carrying out the screening of alternative cutting load node, node overall sensitivity value λ is takenkIt is greater than the set value Node is included in alternative cutting load node collection.
Further, cutting load measure economic cost are as follows:
Wherein, NkFor cutting load node total number;ΔPki、ciThe i-th type load cutting load amount of respectively node k, excision i-th Type load unit-economy cost coefficient.
Further, after calculating cutting load measure economic cost further include the steps that calculating is normalized.
Further, the cutting load harmony index definition is node cutting load rate standard deviation:
Wherein, NkFor cutting load node total number,For k node cutting load rate;For all cutting load node cutting load rates Average value, PkiFor the i-th type load total amount of node k, Δ PkiFor the i-th type load cutting load amount of node k.
Further, the step of node cutting load rate harmony index being normalized.
Further, circuit overload connection cutting load coordinates and optimizes Controlling model are as follows:
Min f=ω1f12f2
Wherein, ω1、ω2The respectively weighted value of cutting load economic cost, node cutting load harmony index carries out normalizing Change the cutting load measure economic cost f after calculating1, the node cutting load rate harmony index f after calculating is normalized2
Further, the constraint condition of circuit overload connection cutting load coordination optimization Controlling model includes that trend is active and reactive Balance, node voltage and line electricity flow valuve be not out-of-limit.
Beneficial effects of the present invention:
(1) circuit overload connection cutting load control is decomposed into node screening and searches for two steps with scheme by the present invention, passes through meter Operator node overall sensitivity carries out alternative cutting load node screening, effectively reduces cutting load node searching range, greatly improves Scheme search efficiency avoids falling into dimension calamity during Optimum search.
(2) previous circuit overload connection load shedding control method relies on related personnel's experience more, often results in load and owes to cut or mistake It cuts, when a plurality of route occurs while overloading, it is difficult to coordination optimization control is carried out, for this purpose, the present invention is established with economic cost With the circuit overload connection cutting load coordination optimization control mould of the minimum optimization aim of weighted value of node cutting load harmony index Type, for the model by the active and reactive balance of trend, constraint condition is included in the limitations such as node voltage, line electricity flow valuve be not out-of-limit, is realized Coordination optimization control when a plurality of route overloads simultaneously.
(3) in Practical Project, electric power enterprise should pursue economic cost minimum when taking overload joining-cutting load, again Consider the harmony of cutting load, reduces accident impact, reduces accident grading and social influence, in the established model of the present invention, lead to The weighted value for crossing adjust economy both cost and node cutting load harmony index, can be calculated under different weights, circuit overload Join cutting load and coordinate and optimize control program, meets the needs of electric power enterprise in Practical Project.
Detailed description of the invention
Fig. 1 is coordination optimizing method flow chart;
Fig. 2 is somewhere Power grid structure figure.
Specific embodiment:
The present invention is described in detail with reference to the accompanying drawing:
As shown in Figure 1, a kind of circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method, including such as Lower step:
(1) it is defined, is derived between branch current and node Injection Current according to nodal voltage equation and incidence matrix Sensitivity relation;
(2) the node overall sensitivity index of meter and branch overload degree is established, which is able to reflect all overload branch Road carries out alternative cutting load to the overall sensitivity of a certain node cutting load measure, and by calculate node overall sensitivity index Node screening;
(3) coordinate cutting load economic cost and harmonious two targets of node cutting load, with economic cost and node cutting load The minimum optimization aim of the weighted value of harmonious index establishes circuit overload connection cutting load coordination optimization Controlling model;
(4) different to cutting load economic cost and harmonious requirements according to policymaker, setting cutting load economic cost with it is equal The weighted value of weighing apparatus property index, calculates under different weights, and optimal route overload joining-cutting load coordinates and optimizes control program.
About the sensitivity relation between branch current and node Injection Current: being built as power grid continues to develop, rack Structure is increasingly complicated, and system interior joint is continuously increased, in carrying out circuit overload connection cutting load scheme optimization solution procedure, if Carry out optimizing in full range of nodes, scheme may be made to fall into dimension calamity in searching process, in system it is certain electrically away from Cutting load measure is taken to influence less on circuit overload is eliminated from node farther out, therefore, the present invention will optimize circuit overload connection and cut Load scheme is divided into alternative cutting load node screening and scheme is searched for two steps and effectively avoided to improve Searching efficiency in side Dimension calamity is fallen into case searching process.
By deriving sensitivity relation between computation overload branch current and node Injection Current, needle can be intuitively obtained More sensitive node is eliminated to a certain overload branch overcurrent, provides theoretical foundation for the screening of alternative cutting load node.
Overload sensitivity relation derivation process between branch current and node Injection Current are as follows:
Wherein, formula (1) is nodal voltage equation;Formula (2) is incidence matrix definition;For node Injection Current column vector, It flows into node to be positive, outflow is negative;YnFor Nb×NbRank node admittance matrix, wherein NbFor number of network node;For node electricity Press column vector;For branch voltage column vector;ATFor incidence matrix transposition.
It can be derived as follows by formula (1), (2):
Sensitivity relation between branch current and node Injection Current can must be overloaded by formula (3), it may be assumed that
Node overall sensitivity index: in Practical Project, failure often results in a plurality of route while overloading, and therefore, is carrying out When alternative cutting load node screening, the present invention proposes node overall sensitivity index, for reflecting the measure of node cutting load to institute There is overload branch to the overall sensitivity of a certain node cutting load measure.
In Practical Project, since circuit overload degree is different, different degrees of power grid accident, social influence, warp are often resulted in Ji influences to influence with electric power enterprise power supply quality, therefore when a plurality of route of generation overloads simultaneously, need to preferentially eliminate overload The more serious branch of degree avoids that even more serious power grid accident occurs.Therefore, the present invention proposes that meter and branch overload degree Node overall sensitivity index.
Certain node takes cutting load measure to eliminate ability to the overcurrent of all overload branches are as follows:
Wherein, NsTo overload branch total number;For the current variation value of branch j after node k cutting load;YjFor branch Admittance battle array jth row element, the i.e. self-admittance of branch j and transadmittance;For its current variation value after node k cutting load.
Definition node k sensitivity are as follows:
The present invention proposes the node overall sensitivity index of meter and branch overload degree, calculation formula are as follows:
Wherein, δjFor branch j weighted value, for indicating the overload degree of branch j;IjThe practical electricity of respectively branch j Flow valuve and the permission current value upper limit.
Calculating is normalized in formula (7) interior joint overall sensitivity index:
Wherein, λk、λ′kRespectively the overall sensitivity normalized value of node k and actual value;λ′max、λ′minRespectively basis Formula (7) calculates gained node overall sensitivity maxima and minima.
Calculating, which is normalized, in node overall sensitivity index can more intuitively express all overload branches to a certain The overall sensitivity of node cutting load measure.When carrying out the screening of alternative cutting load node, it is proposed that take node overall sensitivity value λkAlternative cutting load node collection is included in greater than 0.1 node, it is believed that λkNode less than 0.1 does not have competitiveness.
Circuit overload connection cutting load coordinates and optimizes Controlling model: circuit overload connection cutting load control belongs to complex nonlinear rule The problem of drawing, in Practical Project, electric power enterprise will not only minimize cutting load when taking circuit overload to join cutting load measure Amount is pursued economic cost and is minimized, and the grading of power grid accident caused by cutting load measure, social influence and electric power enterprise are also coordinated Power supply quality influence etc., this requires to be coordinated and optimized, should be chased after from the overall situation when carrying out cutting load control It asks cutting load economic cost to minimize, avoids the excessive unbalanced phenomena of node cutting load as far as possible again, avoid certain sensitive It spends that high node load excision ratio is excessively high or even load complete resection phenomenon, causes major accident to grade, to give electric power enterprise Industry and society bring adverse effect.
Circuit overload joins cutting load and coordinates and optimizes Controlling model are as follows:
Min f=ω1f12f2 (11)
Vi min≤Vi≤Vi maxI=1,2,3 ..., Nb (15)
ΔQkikΔPkiK=1,2,3 ..., Nk (16)
Formula (11) is the minimum optimization aim of model, including cutting load measure economic cost refers to cutting load harmony Mark, cutting load measure economic cost and node cutting load rate harmony dimension difference are excessive, can not directly compare coordinate it is excellent Change, therefore calculating is normalized, in formula, f1、f2Respectively cutting load measure economic cost, cutting load harmony index are returned One change value;ω1、ω2Respectively f1、f2Weight, value is by policymaker depending on real system service requirement.NlIt is total for branch Number;Allow the current value upper limit for branch l;Vi max、Vi minRespectively node i voltage upper and lower limit;σkIt is idle/active for node Scale factor can have economize on electricity power factor to calculate and obtain.Pi、QiThe respectively active and reactive value of node i;Vi、VjRespectively node I, j voltage value;θijFor node i, j phase difference of voltage;Gij、BijRespectively branch lijElectric conductivity value, susceptance value.
Two parts are directed to the active variation of node i.e. in objective function: different cutting load measures, node active power is different, According to the definition of objective function, different target value is calculated.
Formula (12)-(16) are model constraint condition, and formula (16) indicates that node while cutting off active power, cuts off node Corresponding reactive power after taking cutting load measure (variation of node active power), becomes according to formula (16) calculate node reactive power Change, formula (12)-(13) are the active and reactive Constraints of Equilibrium of node, and formula (14) is the constraint of the branch current value upper limit, formula (15) is node Voltage value constraint, wherein the parameters such as voltage, branch current of each node of network can pass through trend according to formula (12), (13) Calculating is found out,, objective function is included in the form of penalty function carrying out model solution up-to-date style (14)-(15).
It is different from harmonious requirement to cutting load economic cost according to policymaker, be set separately in model objective function cut it is negative The weighted value ω of lotus economic cost, node cutting load harmony index1、ω2, by calculating, provided under different weights for policymaker Optimal route overload joining-cutting load coordinates and optimizes control program.
Cutting load measure economic cost and cutting load harmony index derivation process in model are as follows:
Define cutting load measure economic cost are as follows:
Wherein, NkFor cutting load node total number;ΔPki、ciThe i-th type load cutting load amount of respectively node k, excision i-th Type load unit-economy cost coefficient.
Cutting load measure economic cost in formula (17) is normalized and is calculated:
Wherein, NbFor network load node total number;PkiFor the i-th type load total amount of node k.
Definition cutting load harmony index definition is node cutting load rate standard deviation:
Wherein,For k node cutting load rate;For all cutting load node cutting load rate average values.
Formula (19) interior joint cutting load rate harmony index is normalized and is calculated:
Circuit overload connection cutting load coordination optimization control is complicated multiple constraint, a nonlinear optimal problem, therefore, sheet Inequality constraints in model is included in objective function by invention in the form of penalty function, and application is based on the adaptive of nonlinear weight Particle swarm optimization algorithm optimizes.
Real system simulation analysis: by taking the power grid real system of somewhere as an example, validity to the mentioned method of the present invention and Feasibility is verified.Node cutting load percentage range is set as [0,50], one, two, three load cost coefficient of this area Respectively 1,0.4,0.1, this area's power grid total load are 5469MW.Certain planning year this area electric network composition is as shown in Figure 2.Accident Overloading in various degree occurs in route 2-6,11-20, F-24 afterwards.
According to alternative cutting load node screening strategy, overall sensitivity calculating is carried out to nodes all in system, and by drop The preceding N that overall sensitivity is greater than 0.1 is chosen in sequence arrangementkA node is included in alternative cutting load node collection and (thinks that overall sensitivity is small Node in 0.1 does not have competitiveness), higher preceding 10 nodes of overall sensitivity are only listed, as shown in table 1.
The sequence of 1 node overall sensitivity of table
Using the adaptive particle swarm optimization algorithm solving model based on nonlinear weight.Taking particle length is Nk, particle Group's scale is 30, carries out integer coding to particle in population, as shown in table 2 below.
2 particle coding structure table of table
z1 z2 z3 zNk
Wherein, zkFor kth place value, arbitrary integer in [0,50] is taken.If zkArbitrary integer in [1,50] is taken, is indicated in node k Upper excision percentage is zkLoad;If zk0 is taken, indicates that node k does not take cutting load measure.
The asynchronous optimum results of weight coefficient value are as shown in table 3 in formula (11) objective function.
Simulation result under the different design conditions of table 3
By being compared analysis to above-mentioned four kinds of schemes it is found that scheme 1 indicates only to consider when taking cutting load measure Cutting load measure economy cost preferentially cuts off the low node of high sensitivity, economic cost, causes cutting load rate difference between node Greatly, part economic cost lower node loss rate of load condensate is even as high as 40%, aggravates accident grading, to power grid enterprises bring compared with High policy fine, while causing bad social influence;Scheme 2 is indicated when taking cutting load measure, is compared using node etc. Example excision principle, simulation result show that this method causes system cutting load amount excessive, and system performance driving economy is poor, in real system It is undesirable;Scheme 3 and scheme 4, which are all made of, coordinates economic control strategy, can both take into account cutting load economy cost with it is balanced Property require, can effective control node cutting load rate, wherein scheme 4 more emphasizes tactful economy, when using scheme 4, system Node maximum cutting load rate be 17%, comparison scheme 3 it is found that scheme 4 can meet node cutting load rate it is lesser under the premise of, System cutting load amount is substantially reduced, optimal case is obtained.
Above-mentioned simulation result show scheme 3,4 using coordination optimization control strategy can be obviously improved accident grading and To guarantee the economic feasibility of scheme.In real system, Scheme Choice should be carried out according to system service requirement.
Above-mentioned, although the foregoing specific embodiments of the present invention is described with reference to the accompanying drawings, not protects model to the present invention The limitation enclosed, those skilled in the art should understand that, based on the technical solutions of the present invention, those skilled in the art are not Need to make the creative labor the various modifications or changes that can be made still within protection scope of the present invention.

Claims (8)

1. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method, characterized in that the following steps are included:
Node screening: forming network node admittance matrix and incidence matrix, is defined, is obtained according to nodal voltage equation and incidence matrix Sensitivity relation between out branch electric current and node Injection Current;
The node for establishing meter and branch overload degree according to the sensitivity relation between branch current and node Injection Current is comprehensive Sensitivity index, and alternative cutting load node screening is carried out by the calculating of node overall sensitivity index;
Scheme search: coordinating harmonious two targets of cutting load economic cost and node cutting load, is cut with economic cost with node negative The minimum optimization aim of weighted value of lotus harmony index establishes circuit overload connection cutting load coordination optimization Controlling model;
According to, the weight of setting cutting load economic cost and harmonious index different from harmonious requirement to cutting load economic cost Value calculates the circuit overload connection cutting load coordination optimization Controlling model under different weights, optimal route overload joining-cutting load Control program is coordinated and optimized, finally obtains cutting load node;
It takes cutting load measure to eliminate ability definition node k sensitivity index to the overcurrent of all overload branches according to node k, examines It is different to consider branch overload degree, definition node overall sensitivity index:
Wherein, δjFor branch j weighted value, for indicating the overload degree of branch j;IjRespectively branch j actual current value With the permission current value upper limit, NsTo overload branch total number, YjFor branch admittance battle array jth row element, i.e., the self-admittance of branch j with Transadmittance, ATFor incidence matrix transposition,For the inverse matrix of node admittance matrix;
The cutting load harmony index definition is node cutting load rate standard deviation:
Wherein, NkFor cutting load node total number,For k node cutting load rate;It is average for all cutting load node cutting load rates Value, PkiFor the i-th type load total amount of node k, Δ PkiFor the i-th type load cutting load amount of node k.
2. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as described in claim 1, special Sign is defined according to nodal voltage equation and incidence matrix, show that the sensitivity between branch current and node Injection Current is closed System are as follows:
Wherein,For branch current column vector;Y is Nl×NlRank branch admittance matrix,For the inverse matrix of node admittance matrix, For node Injection Current column vector, flows into node and be positive, outflow is negative, ATFor incidence matrix transposition.
3. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as described in claim 1, special Sign is that calculating is normalized in node overall sensitivity index, is cut to a certain node for intuitively expressing all overload branches negative The overall sensitivity of lotus measure.
4. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as claimed in claim 3, special Sign is that, when carrying out the screening of alternative cutting load node, the node for taking node overall sensitivity index value to be greater than the set value is included in standby Select cutting load node collection.
5. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as described in claim 1, special Sign is cutting load economic cost are as follows:
Wherein, NkFor cutting load node total number;ΔPki、ciThe i-th type load cutting load amount, the i-th class of excision of respectively node k is negative Lotus unit-economy cost coefficient;
After calculating cutting load economic cost further include the steps that calculating is normalized.
6. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as described in claim 1, special Sign is to further include the steps that for node cutting load rate harmony index being normalized.
7. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as described in claim 1, special Sign is that circuit overload joins cutting load and coordinates and optimizes Controlling model are as follows:
Min f=ω1f12f2
Wherein, ω1、ω2The respectively weighted value of cutting load economic cost, node cutting load harmony index, is normalized meter Cutting load measure economic cost f after calculation1, the node cutting load rate harmony index f after calculating is normalized2
8. the circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method as claimed in claim 7, special Sign is that the constraint condition that circuit overload joins cutting load coordination optimization Controlling model includes the active and reactive balance of trend, node voltage And line electricity flow valuve is not out-of-limit.
CN201610978458.3A 2016-11-04 2016-11-04 Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method Active CN106532717B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610978458.3A CN106532717B (en) 2016-11-04 2016-11-04 Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610978458.3A CN106532717B (en) 2016-11-04 2016-11-04 Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method

Publications (2)

Publication Number Publication Date
CN106532717A CN106532717A (en) 2017-03-22
CN106532717B true CN106532717B (en) 2018-12-04

Family

ID=58349626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610978458.3A Active CN106532717B (en) 2016-11-04 2016-11-04 Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method

Country Status (1)

Country Link
CN (1) CN106532717B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106953320B (en) * 2017-03-31 2019-05-07 国网江苏省电力公司 A kind of transmission line of electricity overload controlling method based on UPFC
CN107124006B (en) * 2017-05-05 2020-04-14 国电南瑞科技股份有限公司 Equipment overload self-adaptive emergency control method based on measure sensitivity automatic identification
CN107370149B (en) * 2017-08-25 2020-04-14 广州供电局有限公司 Method and system for determining load reduction amount of power system
CN109473991B (en) * 2018-02-12 2022-04-19 国网浙江省电力公司嘉兴供电公司 Regional power grid optimal load control method considering regional balance
CN112994025B (en) * 2021-02-05 2024-04-19 山东大学 Power grid load removal method and system based on linear programming algorithm
CN113363991B (en) * 2021-07-02 2022-12-02 合肥工业大学 Tidal current control method based on comprehensive sensitivity

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1083023A2 (en) * 1999-09-10 2001-03-14 Yoshiaki Kakino Numerical control apparatus for nc machine tool
KR100772984B1 (en) * 2006-04-21 2007-11-02 고수동 electric socket with breaking power supling for loads
CN101299530A (en) * 2007-11-08 2008-11-05 江苏省电力公司 Intelligent joining-cutting method for large electrified wire netting equipment overloading on-line sensitiveness
CN101702524A (en) * 2009-11-12 2010-05-05 华北电力大学 Generator and control method for load adjustment based on optimization model

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1083023A2 (en) * 1999-09-10 2001-03-14 Yoshiaki Kakino Numerical control apparatus for nc machine tool
KR100772984B1 (en) * 2006-04-21 2007-11-02 고수동 electric socket with breaking power supling for loads
CN101299530A (en) * 2007-11-08 2008-11-05 江苏省电力公司 Intelligent joining-cutting method for large electrified wire netting equipment overloading on-line sensitiveness
CN101702524A (en) * 2009-11-12 2010-05-05 华北电力大学 Generator and control method for load adjustment based on optimization model

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
基于功率灵敏度的线路过载划区域紧急控制策略;徐岩等;《电工技术学报》;20150831;第30卷(第15期);第61页-第69页 *
基于综合灵敏度分析的快速控制算法研究;程临燕等;《电力自动化设备》;20090430;第29卷(第4期);第46页-第49页 *

Also Published As

Publication number Publication date
CN106532717A (en) 2017-03-22

Similar Documents

Publication Publication Date Title
CN106532717B (en) Circuit overload based on comprehensive sensitivity analysis joins cutting load coordination optimizing method
WO2018103294A1 (en) Electric reactive power optimization system and method based on double fish-swarm algorithm
CN103020853B (en) Method for checking short-term trade plan safety
CN107103433B (en) Distributed power supply absorption capacity calculation method based on hierarchical partition idea
Sedighizadeh et al. Reconfiguration of distribution systems to improve re-liability and reduce power losses using imperialist com-petitive algorithm
CN108199404A (en) The spectral clustering assemblage classification method of high permeability distributed energy resource system
CN110896231B (en) Distributed photovoltaic capacity receiving calculation method and system for power distribution network in poverty alleviation area
CN105429134B (en) A kind of Network Voltage Stability Forecasting Methodology based on electric power big data
CN109149586A (en) Active power distribution network subregion distributing voltage control method towards intelligent Sofe Switch
CN102738780A (en) Method of optimal configuration of superconducting fault current limiter based on sensitivity technology
CN108183488A (en) High-permeability distributed energy system intelligent pressure regulating method based on cluster division
Gupta et al. A review on optimal sizing and siting of distributed generation system: Integrating distributed generation into the grid
CN108717608A (en) Million kilowatt beach photovoltaic plant accesses electric network synthetic decision-making technique and system
CN105529703B (en) A kind of urban network reconstruction planing method based on power supply capacity bottleneck analysis
CN104484555B (en) The method of assessment 220kV self-healing looped network net capability
CN103560497A (en) Short-circuit current limiting method based on power grid topological adjustment
CN106505576B (en) It is a kind of based on Link-path urban high voltage distribution network load turn for method
CN105337290A (en) Reactive adjustment method applicable to low-frequency oscillation aid decision of electric system
CN110783913A (en) Group-based optimal power grid topology online optimization method considering expected accident set
CN103887823A (en) Micro-grid connection position selection method based on fuzzy hierarchical analysis
CN104300546B (en) A kind of Voltage Stability Constraints idle work optimization method based on wide area measurement information
CN104484832B (en) The method of assessment 220KV handle net net capability
CN107611993B (en) A kind of idle work optimization method suitable for extra-high voltage half-wave power transmission system
CN110649626B (en) Receiving-end power grid layered optimization load shedding method and system
CN105576653B (en) A kind of 220kV sections power network power supply capacity optimization method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant