CN106530131B - A kind of dynamic realtime recording monitoring method - Google Patents

A kind of dynamic realtime recording monitoring method Download PDF

Info

Publication number
CN106530131B
CN106530131B CN201611020140.0A CN201611020140A CN106530131B CN 106530131 B CN106530131 B CN 106530131B CN 201611020140 A CN201611020140 A CN 201611020140A CN 106530131 B CN106530131 B CN 106530131B
Authority
CN
China
Prior art keywords
hydropower unit
real
time
picture
unit runout
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611020140.0A
Other languages
Chinese (zh)
Other versions
CN106530131A (en
Inventor
冯佳男
祁忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NR Electric Co Ltd
Original Assignee
NR Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NR Electric Co Ltd filed Critical NR Electric Co Ltd
Priority to CN201611020140.0A priority Critical patent/CN106530131B/en
Publication of CN106530131A publication Critical patent/CN106530131A/en
Application granted granted Critical
Publication of CN106530131B publication Critical patent/CN106530131B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply

Landscapes

  • Business, Economics & Management (AREA)
  • Health & Medical Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Closed-Circuit Television Systems (AREA)

Abstract

The invention discloses a kind of dynamic realtime recordings to monitor method, Hydropower Unit runout unit address is mapped as multicast address, monitoring screen configuration is by associated all Hydropower Unit runout devices, and the corresponding multicast group of Hydropower Unit runout device is added, more host differentiation recordings are provided using multicast protocol to request, and markers alignment is carried out by the time stamp of real-time recorder data sampling instant, realize picture control synchronous refresh, alleviate network throughput pressure, improve the load capacity of monitoring system, and the switching at runtime that Hydropower Unit runout device realizes supervision object is associated with according to picture configuration, the concurrent capability of the more host data processing of monitoring system is increased while improving real-time, it has a good application prospect.

Description

A kind of dynamic realtime recording monitoring method
Technical field
The present invention relates to Power System Intelligent power network monitoring technical fields, and in particular to a kind of dynamic realtime recording monitoring side Method.
Background technique
With the increasingly raising of monitoring means and inspecting force, for the number such as telemetering, remote signalling of Hydropower Unit conventional Christmas According to not enough meeting the needs of O&M, the diversifications such as real-time curve, orbit of shaft center, space tracking, various dimensions are shown as water The necessary functions of motor group runout monitoring system.Real-time recorder data has high density, high-throughput, low-quality characteristic, but It is that existing substation data acquisition is shares private network channel, and the acquisition of real-time recorder data will increase network load pressure, together When, multimachine picture differentiation data requests the processing capacity of also nationwide examination for graduation qualification check system.Therefore, it is necessary to one kind being capable of dynamic requests, reality When processing, synchronous refresh the acquisition method of real-time recorder data meet monitoring of the operation maintenance personnel to Hydropower Unit runout device Demand.
Currently, for recorder data generally in such a way that unidirectional acquisition forwards again, it is negative that preposition service becomes monitoring system in real time The bottleneck of loading capability also results in and send bring network congestion on more parts of device identical data of Hydropower Unit runout, in real-time With the monitoring requirements that can not meet current Hydropower Unit runout device in terms of load capacity.Moreover, operation maintenance personnel screen operation has There is randomness, the device for needing timely adjustment monitored, and unicast (unidirectional acquisition) opposite multicast in terms of multimachine request of data Not enough efficiently, and the unstable of network flow fluctuation is also resulted in, influences picture control synchronous effect indirectly.Therefore, it also needs A kind of method for wanting dynamic realtime recording monitoring, realizes control network flow, and reduction monitoring system load simultaneously being capable of Real-time and Concurrent Handle the real-time recorder data request of multimachine.
Summary of the invention
The purpose of the present invention is overcoming the existing monitoring system for Hydropower Unit runout device, real-time recorder data is adopted With unidirectionally acquiring the problems of the mode forwarded again.Dynamic realtime recording of the invention monitors method, alleviates network and gulps down Pressure is spat, improves the load capacity of monitoring system, and Hydropower Unit runout device is associated with according to picture configuration and realizes monitoring pair The switching at runtime of elephant increases the concurrent capability of the more host data processing of monitoring system, has good while improving real-time Application prospect.
In order to achieve the above object, the technical scheme adopted by the invention is that:
A kind of dynamic realtime recording monitoring method, it is characterised in that: include the following steps,
Each Hydropower Unit runout unit address is mapped as unique multicast in monitoring system using multicast mode by step (A) Address establishes one-to-one association, and notifies to carry out to corresponding Hydropower Unit runout device by multicast address by unicast messages Binding;
Step (B), establishes real-time recording communication protocol, and real-time recording communication protocol uses electrical power system transient data exchange General format, and increase relevant parameter information;
Step (C), when each host picture of the system of monitoring is opened or when switching, monitoring screen configuration is by associated all water Motor group runout device, and the corresponding multicast group of Hydropower Unit runout device is added;
Step (D), each host for monitoring system monitor the operating status of each Hydropower Unit runout device by heartbeat message, Corresponding Hydropower Unit runout device multicast address binding is released by timeout mechanism;
Step (E), the real-time recorder data that each Hydropower Unit runout device is sent give monitoring system, and monitoring system has been passed through After whole property and correctness verification, the time stamp for extracting sampling instant carries out markers alignment, and presses picture control real-time curve, axle center rail Mark, space tracking association channel difference carry out real-time recorder data secondary treatment after be pushed to the corresponding picture of picture control;
Step (F), sample frequency of the picture control according to real-time recorder data, synchronous adjustment curve movement frequency are kept The linking of picture, realizes picture control synchronous refresh after real-time recorder data refreshes.
A kind of dynamic realtime recording above-mentioned monitors method, it is characterised in that: step (A), by unicast messages by multicast Address notifies to be bound to corresponding Hydropower Unit runout device, and unique multicast address is to dynamically distribute, in water power In the case of unit runout device is monitored without picture, which can cancel in time is tied up It is fixed.
A kind of dynamic realtime recording above-mentioned monitors method, it is characterised in that: step (B), the relevant parameter packet Include analog quantity channel number, sample frequency, sampling number, sampling instant, file totalframes, current frame number and file data.
The beneficial effects of the present invention are: dynamic realtime recording of the invention monitors method, by Hydropower Unit runout device Location is mapped as multicast address, and Hydropower Unit runout is added in associated all Hydropower Unit runout devices by monitoring screen configuration The corresponding multicast group of device provides more host differentiation recordings using multicast protocol and requests, and sampled by real-time recorder data The time stamp at moment carries out markers alignment, realizes picture control synchronous refresh, alleviates network throughput pressure, improve monitoring system Load capacity, and the switching at runtime that Hydropower Unit runout device realizes supervision object is associated with according to picture configuration, improved real-time Property while increase the concurrent capability of monitoring system more host datas processing, have a good application prospect.
Detailed description of the invention
Fig. 1 is the flow chart of dynamic realtime recording monitoring method of the invention.
Specific embodiment
Below in conjunction with Figure of description, the present invention is further illustrated.
Dynamic realtime recording of the invention monitors method, and Hydropower Unit runout unit address is mapped as multicast address, supervises Depending on picture configuration by associated all Hydropower Unit runout devices, and the corresponding multicast group of Hydropower Unit runout device is added, benefit More host differentiation recording requests are provided with multicast protocol, and markers pair is carried out by the time stamp of real-time recorder data sampling instant Together, it realizes picture control synchronous refresh, alleviates network throughput pressure, improve the load capacity of monitoring system, and according to picture Face configuration is associated with the switching at runtime that Hydropower Unit runout device realizes supervision object, and monitoring system is increased while improving real-time The concurrent capability that more host datas of uniting are handled, as shown in Figure 1, following steps are specifically included,
Each Hydropower Unit runout unit address is mapped as unique multicast in monitoring system using multicast mode by step (A) Address establishes one-to-one association, and notifies to carry out to corresponding Hydropower Unit runout device by multicast address by unicast messages Binding, unique multicast address are to dynamically distribute, when Hydropower Unit runout device is monitored without picture, the hydroelectric machine The corresponding unique multicast address of group runout device can cancel binding in time;
Step (B), establishes real-time recording communication protocol, and real-time recording communication protocol uses electrical power system transient data exchange General format, and increase relevant parameter information, the relevant parameter information includes analog quantity channel number, sample frequency, adopts Number of samples, sampling instant, file totalframes, current frame number and file data, as shown in figure the following table 1,
The message format table of the real-time recording communication protocol of table 1
Byte Message content Explanation
11-12 Source device address
13-14 Target plant stand address
15-16 Destination device address
17-18 Data number
19-20 Device type
21-22 Device network state
23-24 Transmission path chopped-off head route device address
25-26 Transmission path final stage route device address
27-28 Reserve bytes 0xFFFF
29-30 Analog quantity channel number
31-32 Sample frequency
33-34 Sampling number
35-38 Sampling instant UTC seconds (4byte, high byte is preceding)
39 File totalframes <0-255>
40 Current frame number <0-255>
41-(41+N-32-1) File data N-32 byte
Wherein, byte 11-28 is the general format of electrical power system transient data exchange, and byte 29- terminates to increase phase Close parameter information;
Step (C), when each host picture of the system of monitoring is opened or when switching, monitoring screen configuration is by associated all water Motor group runout device, and the corresponding multicast group of Hydropower Unit runout device is added;
Step (D), each host for monitoring system monitor the operating status of each Hydropower Unit runout device by heartbeat message, Corresponding Hydropower Unit runout device multicast address binding is released by timeout mechanism;
Step (E), the real-time recorder data that each Hydropower Unit runout device is sent give monitoring system, and monitoring system has been passed through After whole property and correctness verification, the time stamp for extracting sampling instant carries out markers alignment, and presses picture control real-time curve, axle center rail Mark, space tracking association channel difference carry out real-time recorder data secondary treatment after be pushed to the corresponding picture of picture control; Here real-time recorder data secondary treatment belongs to the conventional means of those skilled in the art, is the difference according to picture control requirement The operation such as extracted, converted, being combined, to real-time recorder data to meet picture control data call format;
Step (F), sample frequency of the picture control according to real-time recorder data, synchronous adjustment curve movement frequency are kept The linking of picture, realizes picture control synchronous refresh after real-time recorder data refreshes.
Dynamic realtime recording of the invention monitors method, realizes that the dynamic of real-time recorder data monitoring is asked based on multicast mode Ask, in real time processing and synchronous refresh, Hydropower Unit runout unit address is mapped as multicast address, monitors each host root of system It is dynamically added multicast group according to the associated Hydropower Unit runout device of current picture configuration, provides more host differences using multicast protocol Change recording request, and picture control synchronous refresh is realized by the alignment of recording markers, has reached optimization network performance, improved monitoring The purpose of system real time and oncurrent processing ability.
Basic principles and main features and advantage of the invention have been shown and described above.The technical staff of the industry should Understand, the present invention is not limited to the above embodiments, and the above embodiments and description only describe originals of the invention Reason, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these changes and improvements It all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by appended claims and its equivalent circle It is fixed.

Claims (3)

1. a kind of dynamic realtime recording monitors method, it is characterised in that: include the following steps,
Step (A), using multicast mode, with being mapped in monitoring system unique multicast by each Hydropower Unit runout unit address Location establishes one-to-one association, and notifies to tie up to corresponding Hydropower Unit runout device by multicast address by unicast messages It is fixed;
Step (B) establishes real-time recording communication protocol, and real-time recording communication protocol is using the logical of electrical power system transient data exchange With format, and increase relevant parameter information;
Step (C), when each host picture of the system of monitoring is opened or is switched, monitoring screen configuration is associated with all Hydropower Units vibrations Pendulum device, and the corresponding multicast group of Hydropower Unit runout device is added;
Step (D), each host for monitoring system are monitored the operating status of each Hydropower Unit runout device by heartbeat message, passed through Timeout mechanism releases corresponding Hydropower Unit runout device multicast address binding;
Step (E), each Hydropower Unit runout device send real-time recorder data and give monitoring system, monitoring system by integrality with After correctness verification, the time stamp for extracting sampling instant carries out markers alignment, and presses picture control real-time curve, orbit of shaft center, sky Between Track association channel difference carry out real-time recorder data secondary treatment after be pushed to the corresponding picture of picture control;
Step (F), sample frequency of the picture control according to real-time recorder data, synchronous adjustment curve movement frequency keep real-time The linking of picture after recorder data refreshes, realizes picture control synchronous refresh.
2. a kind of dynamic realtime recording according to claim 1 monitors method, it is characterised in that: step (A) passes through unicast Multicast address is notified to bind to corresponding Hydropower Unit runout device by message, and unique multicast address is to dynamically distribute , in the case that Hydropower Unit runout device without picture monitor, the corresponding unique multicast address of Hydropower Unit runout device and When cancel binding.
3. a kind of dynamic realtime recording according to claim 1 monitors method, it is characterised in that: step (B), the correlation Parameter information includes analog quantity channel number, sample frequency, sampling number, sampling instant, file totalframes, current frame number and text Number of packages evidence.
CN201611020140.0A 2016-11-17 2016-11-17 A kind of dynamic realtime recording monitoring method Active CN106530131B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611020140.0A CN106530131B (en) 2016-11-17 2016-11-17 A kind of dynamic realtime recording monitoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611020140.0A CN106530131B (en) 2016-11-17 2016-11-17 A kind of dynamic realtime recording monitoring method

Publications (2)

Publication Number Publication Date
CN106530131A CN106530131A (en) 2017-03-22
CN106530131B true CN106530131B (en) 2019-06-21

Family

ID=58352784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611020140.0A Active CN106530131B (en) 2016-11-17 2016-11-17 A kind of dynamic realtime recording monitoring method

Country Status (1)

Country Link
CN (1) CN106530131B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116933022B (en) * 2023-09-14 2024-01-23 国网江苏省电力有限公司苏州供电分公司 Intelligent synchronous alignment preprocessing method and system for data of multi-source load equipment

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102222980A (en) * 2011-06-15 2011-10-19 中电普瑞科技有限公司 Transient wave-recording playback system of series capacitor compensation device or fault current limiter device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101062995B1 (en) * 2009-01-19 2011-09-07 충남대학교산학협력단 Key Management Method Effective for SCDA System Communication Environment

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102222980A (en) * 2011-06-15 2011-10-19 中电普瑞科技有限公司 Transient wave-recording playback system of series capacitor compensation device or fault current limiter device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
110kV大侣智能变电站自动化系统的设计与应用;许伟国;《电气技术》;20111215(第12期);第32-36页

Also Published As

Publication number Publication date
CN106530131A (en) 2017-03-22

Similar Documents

Publication Publication Date Title
CN101321367B (en) Monitoring system and method for railway locomotive integration radio communication apparatus
CN105721490A (en) Intelligent collection terminal, master station system and data processing method
CN101965014B (en) Distribution method and distribution control device for Gn interface data
CN102347894A (en) GOOSE message prior forwarding method for industrial Ethernet exchanger
CN110381119B (en) Method, system and device for acquiring log information and storage medium
CN103944671A (en) Method and system for real-time transmission of ultra-wideband airborne data based on multichannel aggregation
CN106530131B (en) A kind of dynamic realtime recording monitoring method
CN104992583A (en) Subway train dispatching simulation training system
CN109104479A (en) A kind of acquisition data flow transmission method and system based on multidiameter delay transmission technology
CN104350488A (en) Systems and methods for selective data redundancy elimination for resource constrained hosts
CN104902243A (en) Unmanned plane line patrolling high-definition video real-time return system based on optical fiber ring network, and return method
CN110233749B (en) Fault processing method, system and device and storage medium
CN104317868B (en) A kind of regulation and control integral method based on single preposition more SCADA applications
CN108614820A (en) The method and apparatus for realizing the parsing of streaming source data
CN106656658A (en) Substation information pushing system
CN105429855A (en) Voice-based communication method
CN104639532A (en) Collection system applied to electricity consumption information and data transmission method collection system
CN110475128A (en) A kind of video transcoding method, device, electronic equipment and storage medium
CN105375626A (en) Distribution network integrated distribution automation terminal on-line monitoring system and method
CN110401683A (en) A kind of mobile command vehicle traveling track display method and system
CN101827026B (en) Method for managing transmission of IEC61850 high layer protocol message
CN204633944U (en) Based on the real-time return system of unmanned plane line walking HD video of optical fiber ring network
CN104980259A (en) Method and device for multilink data transmission
CN102740217A (en) GSM-R (Global System for Mobile Communications for Railway) emergency system and method
CN204361788U (en) Merge the split type network debugging apparatus of intelligent grid of geographic positioning technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant