CN106526369B - A kind of on-off testing system and method based on programmable controller - Google Patents

A kind of on-off testing system and method based on programmable controller Download PDF

Info

Publication number
CN106526369B
CN106526369B CN201610954128.0A CN201610954128A CN106526369B CN 106526369 B CN106526369 B CN 106526369B CN 201610954128 A CN201610954128 A CN 201610954128A CN 106526369 B CN106526369 B CN 106526369B
Authority
CN
China
Prior art keywords
test
programmable controller
testing
time
timer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610954128.0A
Other languages
Chinese (zh)
Other versions
CN106526369A (en
Inventor
钱文秀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xiaode Network Cloud Technology Co., Ltd.
Original Assignee
Shanghai Feixun Data Communication Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Feixun Data Communication Technology Co Ltd filed Critical Shanghai Feixun Data Communication Technology Co Ltd
Priority to CN201610954128.0A priority Critical patent/CN106526369B/en
Publication of CN106526369A publication Critical patent/CN106526369A/en
Application granted granted Critical
Publication of CN106526369B publication Critical patent/CN106526369B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere

Abstract

The invention discloses a kind of on-off testing system and method based on programmable controller, the system include the end PC, programmable controller, insert row, and the end PC is used for input control information;Programmable controller is used to receive the control information of the end PC transmission, thereby executing test;Programmable controller include for setting runing time, ping leads to time, the timer of switch closure times and counter for setting testing time, the frequency of failure, number of success.Insert row is used for the connection of programmable controller and product.The present invention carries out switching on and shutting down test using programmable controller, and function is strong, high reliablity, strong antijamming capability, maintenance load are small, easy to maintenance, small in size, and low energy consumption saves the time, effectively improves testing efficiency.

Description

A kind of on-off testing system and method based on programmable controller
Technical field
The present invention relates to switching on and shutting down testing field more particularly to a kind of on-off testing systems based on programmable controller And method.
Background technique
With the progress of computer technology, gradually use information equipment replaces traditional manual work to people, daily In work, the state that height relies on has been presented to information equipment by people.It is raw in order to provide reliable and stable equipment to client Manufacturer is produced after the production work for completing equipment, can also carry out a series of tests to the equipment.Wherein, switching on and shutting down test is to survey Test-manufacture an important tests of quality.
Switching on and shutting down test is to verify the power on/off function of product by powering on/off to product progress is frequently multiple.
Current existing method for testing open/close machine mainly uses switching on and shutting down jig and its matched switching on and shutting down to control software Come carry out.
Switching on and shutting down jig be realized using relay circuit power on and power down.Relay coil in switching on and shutting down jig It is powered, by galvanomagnetic-effect adhesive armature, so that contact closure, power on circuitry.After coil blackout, armature is returned by springback Position originally, so that contact disconnects, down circuitry.And the movement of relay is to control software by switching on and shutting down to control. Switching on and shutting down control software can to IP address, runing time, testing time, set by the parameter of some keys such as ratio It sets, and the on-off of relay is controlled by serial ports realization.
However, in actual operation, discovery switching on and shutting down jig not power down can occurs regularly and obtain phenomenon, lead to the test Item can not be successfully progress.The main reason for phenomenon occur is the spring aging inside the electromagnetic relay in switching on and shutting down jig, Cause in coil blackout, spring can not be bounced normally.
In existing patent document, some technical solutions about switching on and shutting down test are also related to.
As provided by Publication No. CN201510940964 " a kind of method for testing open/close machine and system ", which includes Switch machine controller, image information acquisition device and server.Switch machine controller for control display device starting-up to be tested, Shutdown is standby;Image information acquisition device is used in the display device starting-up to be tested, obtains display equipment to be tested Start-up picture information, and the start-up picture information is uploaded into the server, start-up picture information includes start-up picture.Clothes Business device be used for receive image information acquisition device upload start-up picture information, and by start-up picture information start-up picture with Default start-up picture is compared, and determines the start-up picture of display equipment to be tested with the presence or absence of abnormal.The system is opened in equipment By being compared the start-up picture in start-up picture information with default start-up picture with determination display equipment to be tested after machine Start-up picture be inaccurate with the presence or absence of abnormal method, and not can be carried out when exception occurs in equipment after completely record and Abnormal conditions are performed corresponding processing.
For another example provided by Publication No. CN 201210131715 " a kind of on-off test device and method ", the device Including an input module, a control module, a switch module, an AC DC conversion module and a detection module, switch module It is connected between control module and AC DC conversion module, switch module is for connecting an AC power source, AC DC conversion Module inputs mould for being connected between control module and computer main board for connecting a computer main board to be measured, detection module Block link control module is used for control module input test parameter, and detection module is used to detect the power-up state of computer main board, And will test result and be sent to control module, control module is used for after receiving test parameter according to testing result to control The on-off of switch module, to control power supply or power-off of the AC power source to computer main board.The system needs that AC DC is arranged Conversion module, and test process is cumbersome, is not suitable for the switching on and shutting down test for carrying out a large amount of repeatability.
For another example provided by Publication No. CN200810169159 " a kind of method for testing open/close machine and switching on and shutting down test system System " is it is suitable for testing test system through network and remote power control device by distance host, wherein this test system With baseboard management controller and operating system.This method includes that control remote power control device is connected to remote power supply control Power supply line between device processed and test system becomes channel status and initializes baseboard management controller, and this method further includes Test system is activated through baseboard management controller and executes the boot program of the operating system of test system, and this method is also wrapped The shutdown programm that test system execution operating system is controlled after completing boot program is included to close test system and control Remote power control device makes power supply line become off state.The on-off testing system needs network connection, when the switch The failed opening operation system of machine test macro or not it is predetermined be re-closing off shutoff operation system in number when, can be automatic defeated Malfunction error signal, need to artificially solve, and when the error occurs, will increase the testing time.
Summary of the invention
In view of the above-mentioned problems existing in the prior art, the present invention provides a kind of, and the switching on and shutting down based on programmable controller are surveyed Test system and method, the present invention carry out switching on and shutting down test to product using the timing and tally function of programmable controller, save Time improves testing efficiency.
To reach above-mentioned technical purpose, the present invention is adopted the following technical scheme that:
A kind of on-off testing system based on programmable controller, it includes the end PC, programmable controller, insert row, PC End is used for input control information, and programmable controller is used to receive the control information of the end PC transmission, and thereby executing test, insert row is used In connection programmable controller and product.
Further, programmable controller includes for setting determining for runing time, ping logical time, switch closure times When device.
Further, programmable controller further includes the counting for setting testing time, the frequency of failure, number of success Device.
The invention also discloses a kind of method for testing open/close machine based on programmable controller, it includes the following steps:
The end information input PC will be controlled;Control information is sent to programmable controller, and programmable controller receives control Start to execute test after information processed;The test process includes that testing time counts test, runs timing test, frequency of failure meter Number test, ping lead to timing test, and number of success counts test, and switch closes timing test;Programmable controller passes through insert row It is connected to product.
Further, if testing time counts test and completes, then it represents that testing time reaches presumptive test number, terminates to survey Examination;If not completing, the judgement whether operation timing is completed is carried out.
Further, if operation timing test is completed, then it represents that test process is not fully completed in runing time, and test is lost It loses, the frequency of failure adds one;If not completing, the judgement whether completed when ping is amounted to is carried out.
Further, it is completed if ping leads to timing test, then it represents that be successfully tested, number of success counter adds one, goes forward side by side Row switch closes the judgement whether timing is completed.
Further, it is completed if switch closes timing test, carries out reset work.
Further, resetting work includes running timer, and ping leads to timer and switch closes the reset of timer.
Further, after the completion of resetting work, testing time counter adds one, and repeats the above test process, under starting Primary test.
The present invention is based on the on-off testing system of programmable controller and method, technical solution utilizes PLC technology The timing of device and tally function carry out switching on and shutting down test to product, can save the time, improve testing efficiency.
Detailed description of the invention
Fig. 1 is structural framing schematic diagram of the invention.
Fig. 2 is testing process schematic diagram of the invention.
Specific embodiment
Following is a specific embodiment of the present invention in conjunction with the accompanying drawings, technical scheme of the present invention will be further described, However, the present invention is not limited to these examples.
Embodiment 1
The present embodiment provides a kind of on-off testing system based on programmable controller as shown in Figure 1, the system packets Include the end PC 100, programmable controller 200, insert row 300.
Staff inputs pre-set control information by the end PC 100.Programmable controller 200 receives the end PC The 100 control information sent, and automatically begin to execute test.Programmable controller 200 is connected by insert row 300 and test product It connects.
Programmable controller is a kind of electronic system of digital operation, specially applies and designs in industrial settings, It is used to executing storage logical operation and sequential control, timing, counting and arithmetic fortune using the memory that can be programmed The instruction of the operations such as calculation, and by the input (I) and output (O) interface of number or simulation, control various types of mechanical equipments Or production process.The present invention is mainly the timing using programmable controller and counts this two big function to carry out switching on and shutting down control System.
Using programmable controller as control unit, its advantage is the present embodiment:
Firstly, PLC function is strong, the ratio of performance to price is high, and user is easy to use, adaptable.
Have in one PLC it is thousands of can programmed element for users to use, extremely complex control function may be implemented Energy.Compared with the relay system of identical function, there is the very high ratio of performance to price.
In addition, PLC can also be networked by communication, decentralised control, centralized management are realized.
Secondly, PLC high reliablity, strong antijamming capability.
Traditional relay control system has used a large amount of intermediate relay, the time relay.Not due to contact contact It is good, it is easy to appear failure.PLC replaces intermediate relay and the time relay with software, only be left with output and input it is related A small amount of hardware element, wiring may decrease to 1/10th of relay control system hereinafter, greatly reducing because of contact contact not Failure caused by good.PLC has used a series of hardware and software interference protection measures, has very strong anti-interference ability.
Also, PLC maintenance load is small, easy to maintenance.
The failure rate of PLC is very low, and has perfect fault diagnosis functions.PLC or the input unit and execution machine of outside When structure breaks down, it can quickly and easily be looked into according to the information of light emitting diode or programming software offer on signaling module The reason of bright failure, can promptly be debugged with the method for replacement module.
Finally, PLC is small in size, low energy consumption.
Complicated control system uses after PLC, it is possible to reduce a large amount of intermediate relay and the time relay.PLC control For system compared with relay control system, wiring dosage is few, and installation wiring working hour is short, in addition the diminution of switchgear volume.Therefore, A large amount of expense can be saved.
In the present invention, 200 internal structure of programmable controller includes for setting runing time, ping logical time, switch The timer of shut-in time.
Runing time refers to the scheduled product single testing time.
Ping is logical to refer to that network is connected state between two equipment, sends a data packet, other end energy from one end Enough receive, just represent two equipment can ping it is logical.
Switch, which is closed, indicates that single test terminates.
When carrying out switching on and shutting down test, leading to that time, switch closure times are configured to runing time, ping can be by can The timing function of programmable controller is completed.
There are many type of timer in programmable controller, and different timers is selected to have a little difference in programming Not, but its purpose is the same.
Timer can be divided into three kinds in S7-200 series of PLC: connect back off timer (On-Delay Timer, abbreviation TON), off delay timer (Off-Delay Timer, abbreviation TOF), maintenance connect back off timer TONR.
Connect back off timer TON working principle are as follows: when instruction is true, the timer as unit of time base value into Row counts.
The working principle of off delay timer TOF are as follows: when instruction be fictitious time, the timer as unit of time base value into Row counts.
Maintenance connection back off timer TONR working principle are as follows: when instruction is true, as unit of time base value into Row counts, and instructs when becoming false or re-powering, and accumulated value is constant.
The timer that the present invention uses connects delay timer TON between the single time to connect back off timer TON Every timing, when power up cycle or first scan, locator position is OFF, current value 0.When input terminal is connected, timer position For OFF, current value timing since 0, when current value reaches setting value, timer position is ON, and current value still continuous counter arrives 32767.Input terminal disconnects, and timer automatically resets, i.e., timer position is OFF, current value 0.
Connect the instruction format of back off timer TON are as follows: TON Txxxx, PT.It needs to provide in the use of TON instruction Once parameter:
1) timer (Timer): timer element used in indicating;
2) Shi Ji (Time Base): increment value when timer, it determines the precision of timer;
3) preset value (Preset): for setting delay time.
4) aggregate-value (Accum): it is a dynamic value, indicates timer current delay time.
It is respectively runing time timer that the present invention uses three connection back off timers during the test, when ping leads to Between timer, switch closure times timer, specific testing procedure is as follows:
T1: after circuit is connected, runing time timer starts timing;
T2: after runing time timer starts timing, ping leads to time timer and starts timing;
After T3:ping leads to time timer timing, switch closure times timer starts timing;Switch closure times After timer timing, all timers reset, and start to test next time, repeat step T1 and T2.
In PLC control system, typical counter function has:
1) product for manufacturing or detecting is counted;
2) it calculates and is pumped into the material position for maintaining storage tank with the gallonage of let-down vessel;
3) timer is used in combination and tracks one section of long time.
There are three counters can be used for programmable controller: counting up device CTU, down counter CTD, up-down counter CTUD.
Need to use programmable controller in the present invention counts up device CTU to realize to testing time, number of success, mistake Lose the counting of number.
When counting up device CTU first scan, counter position is OFF, current value 0.Counting the every of pulse input end CU A rising edge, counter count 1 time, and current value increases a unit.When current value reaches setting value, counter position is ON, when Preceding value can continue to stop counting after counting down to 32 767.The RESET input effectively or to counter executes reset instruction, counter It automatically resets, i.e., counter position is OFF, current value 0.
Testing time counting refers to the total testing time of product.
Number of success refers to the successful number of product test.
The frequency of failure refers to the number of product test failure.
Needing to count up device CTU using three in invention is respectively testing time counter, frequency of failure counter, success Number counter, the specific steps are as follows:
N1: after switch closure times timer timing, testing time counter adds one;
N2: after runing time timer timing, frequency of failure counter adds one;
After N3:ping leads to time timer timing, number of success counter adds one;
N4: if testing time counter reaches defined testing time, test terminates.
The present embodiment is during the test only comprising the runing time timer in three timers, and test detailed process is such as Under:
After test starts, first determine whether that testing time counting tests whether to complete, if testing time counts test and completes, i.e., The standard testing number for reaching expected setting, terminates to test at this time.If testing time counts test and do not complete, continue next Step.
After judging that testing time counting test does not complete, then judge to run whether timing test is completed.
If running timing test to complete, then it represents that test process is not fully completed in runing time, test crash, failure time Number plus one;If running timing test not completing, number of success counter adds one, and carries out reset work to runing time timer Make.
After the completion of resetting work, the above testing process is repeated, starts to test next time.
Embodiment 2
This embodiment differs from embodiment 1 in that: the present embodiment includes in three timers during the test Runing time timer and ping lead to time timer, and test detailed process is as follows:
After test starts, first determine whether that testing time counting tests whether to complete, if testing time counts test and completes, i.e., The standard testing number for reaching expected setting, terminates to test at this time.If testing time counts test and do not complete, continue next Step.
After judging that testing time counting test does not complete, then judge to run whether timing test is completed.If running timing to survey Examination is completed, then it represents that test process is not fully completed in runing time, and test crash, the frequency of failure adds one;If running timing to survey Examination does not complete, then judges to test whether to complete when ping is amounted to.
It is completed if being tested when ping is amounted to, then it represents that be successfully tested, number of success counter adds one, and right
Runing time timer, ping lead to time timer and carry out reset work.
After the completion of resetting work, the above testing process is repeated, starts to test next time.
The other contents of the present embodiment can refer to embodiment 1.
Embodiment 3
The present embodiment and embodiment 1 or embodiment 2 the difference is that: the present embodiment includes all three during the test A timer.
As shown in Fig. 2, test detailed process is as follows:
Testing time counter controls the beginning and end of test item.After test starts, testing time meter is first determined whether Number tests whether to complete, if testing time counts test and completes, that is, reaches the standard testing number of expected setting, terminates to survey at this time Examination.If testing time counts test and do not complete, continue in next step.
Ping lead to time timer and runing time Timer Controlling number of success counter and frequency of failure counter. After judging that testing time counting test does not complete, then judge to run whether timing test is completed.
If running timing test to complete, then it represents that test process is not fully completed in runing time, test crash, failure time Number plus one;If running timing test not completing, judge to test whether to complete when ping is amounted to.
It is completed if being tested when ping is amounted to, then it represents that be successfully tested, number of success counter adds one, and continues judgement switch Close whether timing test is completed.
If switch close timing test complete, by switch closure times timer complete to runing time timer, Ping leads to the reset work of time timer and switch closure times timer.
After the completion of resetting work, the above process is repeated, starts to test next time.
The other contents of the present embodiment can refer to embodiment 1 or embodiment 2.
In technical solution of the present invention, programmable controller (Programmable Logic Controller, letter are utilized Claim PLC) switching on and shutting down test is carried out to product, it has a characteristic that
1. function is strong, the ratio of performance to price is high, and user is easy to use, adaptable.Have in one PLC it is thousands of for Extremely complex control function may be implemented in the programmed element that user uses.Compared with the relay system of identical function, have The very high ratio of performance to price.PLC can be networked by communication, realize decentralised control, centralized management.
2. high reliablity, strong antijamming capability.Traditional relay control system used a large amount of intermediate relay, when Between relay.Due to poor contact of contacts, it is easy to appear failure.PLC replaces intermediate relay and the time relay with software, only It is remaining with output and input related a small amount of hardware element, wiring may decrease to 1/10th of relay control system hereinafter, Failure caused by greatly reducing because of poor contact of contacts.PLC has used a series of hardware and software interference protection measures, has very Strong anti-interference ability.
3. maintenance load is small, easy to maintenance.The failure rate of PLC is very low, and has perfect fault diagnosis functions.PLC Or external input unit and executing agency be when breaking down, it can be according to the light emitting diode or programming software on signaling module The information of offer, the reason of quickly and easily finding out failure, can promptly be debugged with the method for replacement module.
4. small in size, low energy consumption.Complicated control system uses after PLC, it is possible to reduce a large amount of intermediate relay and when Between relay.For PLC control system compared with relay control system, wiring dosage is few, and installation wiring working hour is short, in addition switchgear The diminution of volume.Therefore, a large amount of expense can be saved.
In conclusion measuring technology scheme of the present invention, uses programmable controller to carry out switching on and shutting down test, it can be effectively It avoids the problem that switching on and shutting down jig not power down during traditional test, so as to save the time, and improves testing efficiency.
Specific embodiment described herein is only an example for the spirit of the invention.The neck of technology belonging to the present invention The technical staff in domain can make various modifications or additions to the described embodiments or replace by a similar method In generation, however, it does not deviate from the spirit of the invention or beyond the scope of the appended claims.

Claims (7)

1. a kind of method for testing open/close machine based on programmable controller, which comprises the steps of:
The end information input PC will be controlled;
Control information is sent to programmable controller, and programmable controller starts to execute test after receiving control information;
The test process includes that testing time counts test, runs timing test, and the frequency of failure counts test, and ping is amounted to When test, number of success count test, switch close timing test;
Programmable controller is connected to product by insert row;
If the testing time counts test and completes, then it represents that testing time reaches presumptive test number, terminates test;If not complete At then carrying out the judgement whether completed of operation timing;
If the operation timing test is completed, then it represents that test process is not fully completed in runing time, test crash, failure time Number plus one;If not completing, the judgement whether completed when ping is amounted to is carried out;
It is completed if the ping leads to timing test, then it represents that be successfully tested, number of success counter adds one, and carries out switch closing The judgement whether timing is completed.
2. a kind of method for testing open/close machine based on programmable controller as described in claim 1, which is characterized in that described to open If closing timing test to complete, reset work is carried out.
3. a kind of method for testing open/close machine based on programmable controller as claimed in claim 2, which is characterized in that described multiple Position work includes running timer, and ping leads to timer and switch closes the reset of timer.
4. a kind of method for testing open/close machine based on programmable controller as claimed in claim 3, which is characterized in that described multiple After the completion of the work of position, testing time counter adds one.
5. a kind of on-off testing system based on programmable controller is opened for realizing claim 1-4 is described in any item Shutdown test method, which is characterized in that including the end PC, programmable controller, insert row;
The end PC is used for input control information;
The programmable controller is used to receive the control information of the end PC transmission, and executes test;
The insert row is for connecting programmable controller and product.
6. a kind of on-off testing system based on programmable controller as claimed in claim 5, which is characterized in that it is described can Programmable controller includes the timer for setting runing time, ping logical time, switch closure times.
7. such as a kind of on-off testing system based on programmable controller described in claim 5 or 6, which is characterized in that institute Stating programmable controller further includes the counter for setting testing time, the frequency of failure, number of success.
CN201610954128.0A 2016-10-27 2016-10-27 A kind of on-off testing system and method based on programmable controller Active CN106526369B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610954128.0A CN106526369B (en) 2016-10-27 2016-10-27 A kind of on-off testing system and method based on programmable controller

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610954128.0A CN106526369B (en) 2016-10-27 2016-10-27 A kind of on-off testing system and method based on programmable controller

Publications (2)

Publication Number Publication Date
CN106526369A CN106526369A (en) 2017-03-22
CN106526369B true CN106526369B (en) 2019-09-13

Family

ID=58325558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610954128.0A Active CN106526369B (en) 2016-10-27 2016-10-27 A kind of on-off testing system and method based on programmable controller

Country Status (1)

Country Link
CN (1) CN106526369B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107765119A (en) * 2017-09-30 2018-03-06 四川九州电子科技股份有限公司 A kind of automatic detection machine starts abnormal method
CN108535563A (en) * 2018-03-28 2018-09-14 四川斐讯信息技术有限公司 A kind of method for testing open/close machine and test system
CN108828442B (en) * 2018-06-22 2021-08-03 中广核核电运营有限公司 Time-delay relay detection device
CN109491368B (en) * 2018-11-30 2021-09-24 邯郸市邯钢集团信达科技有限公司 Method for diagnosing PLC system input signal fault by using counter

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101493500A (en) * 2008-01-24 2009-07-29 中芯国际集成电路制造(上海)有限公司 Electric power on/off automatic control device
CN101982961A (en) * 2010-10-26 2011-03-02 青岛海信移动通信技术股份有限公司 Method and system for testing power on/off reliability of mobile phone
CN203827365U (en) * 2013-12-19 2014-09-10 上海斐讯数据通信技术有限公司 Automatic power on-off testing apparatus
CN104486162A (en) * 2014-12-22 2015-04-01 上海斐讯数据通信技术有限公司 Automatic on-off test system and test method thereof
CN104901848A (en) * 2015-06-02 2015-09-09 上海斐讯数据通信技术有限公司 Automated testing system and method for startup and shutdown of router
CN105116969A (en) * 2015-09-22 2015-12-02 上海斐讯数据通信技术有限公司 Power switch timing method and device
CN105866604A (en) * 2016-06-22 2016-08-17 重庆长安汽车股份有限公司 Automatic on/off testing system and method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101493500A (en) * 2008-01-24 2009-07-29 中芯国际集成电路制造(上海)有限公司 Electric power on/off automatic control device
CN101982961A (en) * 2010-10-26 2011-03-02 青岛海信移动通信技术股份有限公司 Method and system for testing power on/off reliability of mobile phone
CN203827365U (en) * 2013-12-19 2014-09-10 上海斐讯数据通信技术有限公司 Automatic power on-off testing apparatus
CN104486162A (en) * 2014-12-22 2015-04-01 上海斐讯数据通信技术有限公司 Automatic on-off test system and test method thereof
CN104901848A (en) * 2015-06-02 2015-09-09 上海斐讯数据通信技术有限公司 Automated testing system and method for startup and shutdown of router
CN105116969A (en) * 2015-09-22 2015-12-02 上海斐讯数据通信技术有限公司 Power switch timing method and device
CN105866604A (en) * 2016-06-22 2016-08-17 重庆长安汽车股份有限公司 Automatic on/off testing system and method

Also Published As

Publication number Publication date
CN106526369A (en) 2017-03-22

Similar Documents

Publication Publication Date Title
CN106526369B (en) A kind of on-off testing system and method based on programmable controller
CN110716126A (en) Chip aging test system, method and device
CN106152415B (en) The fault determination method and device of air-conditioning system connection wiring
CN103051490A (en) Method for carrying out startup and shutdown testing on blade server
CN106909479B (en) Startup and shutdown test fixture
CN202049222U (en) Electric meter with relay state monitoring function
CN104901848A (en) Automated testing system and method for startup and shutdown of router
CN104394406B (en) A kind of detecting system being applied to the test of TV alternating-current switch machine and method
CN102236054A (en) Power on/off test device and method
CN110173803A (en) Air conditioner and its communication control method, device and electronic equipment
CN105156315B (en) Detection system, device and detection method suitable for multiple compressors
CN103362678B (en) Automatic control device of diesel engine
CN104730365A (en) Household appliance fault detecting device and method
CN105892609B (en) A kind of method and intelligent terminal of terminal booting and identification memory card synchronous operation
CN102915265A (en) BMC (baseboard management controller) loop test method and system
CN205374637U (en) Switching on and shutting down testing arrangement
CN100576744C (en) Test macro
CN204347211U (en) A kind of many relay functions proving installation
CN207588113U (en) Network interface plug-in and pull-off device and network interface insert-pull detection system
CN100539716C (en) The method that a kind of main and standby boards is monitored and switched automatically
CN203310938U (en) Startup/shutdown test system of electronic device
CN107918069B (en) Power failure test system and method
CN102819253B (en) 3G (the third generation telecommunication) network based remote dental air circuit diagnosing and monitoring system
CN110686358B (en) Variable frequency air conditioner fault diagnosis method based on detection tool
CN113946135A (en) Circuit breaker mechanism test monitoring device based on PLC

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20201126

Address after: Room 10242, No. 260, Jiangshu Road, Xixing street, Binjiang District, Hangzhou City, Zhejiang Province

Patentee after: Hangzhou Jiji Intellectual Property Operation Co.,Ltd.

Address before: 201616 Shanghai city Songjiang District Sixian Road No. 3666

Patentee before: Phicomm (Shanghai) Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201214

Address after: 8319 Yanshan Road, Bengbu City, Anhui Province

Patentee after: Bengbu Lichao Information Technology Co.,Ltd.

Address before: Room 10242, No. 260, Jiangshu Road, Xixing street, Binjiang District, Hangzhou City, Zhejiang Province

Patentee before: Hangzhou Jiji Intellectual Property Operation Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210308

Address after: 313000 room 1019, Xintiandi commercial office, Yishan street, Wuxing District, Huzhou, Zhejiang, China

Patentee after: Huzhou YingLie Intellectual Property Operation Co.,Ltd.

Address before: 8319 Yanshan Road, Bengbu City, Anhui Province

Patentee before: Bengbu Lichao Information Technology Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220804

Address after: No. 160 Yunshan South Road, Industrial Development Zone, Tongzhou District, Beijing 101100

Patentee after: Beijing Xiaode Network Cloud Technology Co., Ltd.

Address before: 313000 room 1019, Xintiandi commercial office, Yishan street, Wuxing District, Huzhou, Zhejiang, China

Patentee before: Huzhou YingLie Intellectual Property Operation Co.,Ltd.