CN106499417B - Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction - Google Patents

Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction Download PDF

Info

Publication number
CN106499417B
CN106499417B CN201610937859.4A CN201610937859A CN106499417B CN 106499417 B CN106499417 B CN 106499417B CN 201610937859 A CN201610937859 A CN 201610937859A CN 106499417 B CN106499417 B CN 106499417B
Authority
CN
China
Prior art keywords
rock
shape
construction
section
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610937859.4A
Other languages
Chinese (zh)
Other versions
CN106499417A (en
Inventor
黄学军
唐浩峰
殷立达
韩建坤
宫学军
戴润军
王猛
王心毅
陈章林
郭玉山
武相坤
姜永东
米伟
刘辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Zhongche Construction Engineering Co. Ltd.
Woods is with Im international construction consulting (China) Co., Ltd
China Railway Tunnel Group Erchu Co Ltd
Original Assignee
Chongqing Zhongche Construction Engineering Co Ltd
Woods Is With Im International Construction Consulting (china) Co Ltd
China Railway Tunnel Group Erchu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Zhongche Construction Engineering Co Ltd, Woods Is With Im International Construction Consulting (china) Co Ltd, China Railway Tunnel Group Erchu Co Ltd filed Critical Chongqing Zhongche Construction Engineering Co Ltd
Priority to CN201610937859.4A priority Critical patent/CN106499417B/en
Publication of CN106499417A publication Critical patent/CN106499417A/en
Application granted granted Critical
Publication of CN106499417B publication Critical patent/CN106499417B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of extra-large cross-section resistant Capacity of Shallow-buried Subway Station to reserve T word rock beam rock pillar construction, belong to technical field of tunnel construction, comprising steps of 1) left side of excavation project and right side rock mass, section is set to form reserved T word rock beam rock pillar, the double-hole tunnel side wall of formation is using anchor cable filling slurry combining anchor supporting;2) the side wall construction waterproof of the combined supporting in step 1), I-steel and two lining structures are further reinforced, and backfill earth and stone material to fill up, be compacted at excavation, surface construction C20 plain concrete;3) two side areas of T shape rock beam rock pillar is excavated;4) section gap excavates the top area of T shape rock beam rock pillar;5) central region of T shape rock beam rock pillar is excavated, and clears out backfill earth and stone material.The present invention adapts to extra-large cross-section resistant Capacity of Shallow-buried Subway Station or constructing tunnel by the scheme of reserved T shape rock beam rock pillar, can effectively control surrouding rock stress, tunnel arch settling amount and two helps deflection, protection above ground structure, guarantee construction safety.

Description

Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction
Technical field
The invention belongs to technical field of tunnel construction, and in particular to it is a kind of for the shallow embedding engineering with extra-large cross-section (such as Subway station, underground chamber, vcehicular tunnel etc.) take the construction of reserved T word rock beam rock pillar.
Background technique
With being increasing for urban population, the continuous expansion of city size, the congested problem day of urban transportation is more protruded. In order to solve this problem, countries in the world propose in succession and have developed subway transportation.London is to possess ground earliest in the world The city of iron, then, Paris, FRA, Moscow, Russia, Madrid, ESP, Tokyo etc. have started subway engineering in succession Construction and use.Beijing is that China's early start is built and possesses the city of subway.It is Tianjin, Shanghai, wide after Beijing The cities such as state, Shenzhen, Nanjing, Chongqing more early start to build urban light rail and subway.Chengdu, Xi'an, Shenyang, Zhengzhou, Hangzhou, elder brother Multiple cities such as bright start to build subway engineering in recent years, it will be apparent that, city underground there has been very large-scale development in China With use, and its speed of development is higher and higher.
Because China is with a long history, the scenic spots and historical sites are more, and the environment faced in urban light rail and subway construction is more complex, many Ancient building, highway, river, residential area, oil-gas pipeline etc. are worn under track circuit, and track and subway station section are big, According to International Tunnelling Association (ITA) to tunnel cross-section product size definition, it is greater than 100m2Referred to as Super-large-section tunnel, with China The fast development of transport development cause has emerged in large numbers many Super-large-section tunnels, such as No. two line northern station sections of Shenyang Metro are 340m2, Chongqing Light Railway great Ping station section is 430m2, near a river gate bus terminal section be 420.9m2, red flag stream station section be 730m2.Compared with the tunnel built in the past, the construction of Super-large-section tunnel, in the section shape of the mechanical behavior in tunnel, tunnel There is new, higher requirement in formula, tunnel lining structure, preliminary bracing tactic pattern, supporting parameter etc., these will It asks to make construction method and be correspondingly improved, to improve the safety and reliability of engineering.
Mainly there are three steps, seven step excavating load, interval wall approach (CD method), friendship in Construction Method of Super-Large Section Tunnel both at home and abroad Interval wall approach (CRD method), twin side heading method, three pilot tunnel methods etc. are pitched, is provided to improve not by means of the construction method of auxiliary above Especially big section chemical conversion light section construction is made the formation closing or semiclosed carrying knot that outline excavation is as fast as possible by the good soil body Then structure excavates core Rock And Soil again.In recent years, some scientific research institutions, designing unit and construction unit adopt extra-large cross-section tunnel Road construction mentality of designing, optimization of constantly bringing forth new ideas on the basis of conventional Super-large-section tunnel construction, proposes New constructing tunnel engineering method, for example, No. seven line twin-well stations of Beijing Metro be shallow mining method, using two layers of underground twin columns three across Form, station principal length 237.6m, standard paragraphs width 23.1m, height 16.15m, cross-sectional area 320m2, country rock is IV class sand Soil and clay are constructed using PBA engineering method.No. two stations Xian great Ping of Chongqing Light Railway use shallow mining method, main body excavation width 26.3m, height 20.6m, cross-sectional area 430m2, the minimum depth 4m, country rock be III class mud stone, arch flat structure, hole across than for 0.15-0.5, for the first time using " upper half section side heading method, lower half section elder generation bracket groove back side wall are excavated, arch-wall method lining cutting " Constructing tunnel novel construction method.No. two line northern station tunneling sections of Shenyang Metro are that bilayer three encircles two rod structures, and an island platform, platform slab is wide 13.9m, buried depth 6.4m, excavation width 26.3m, height 16.95m, cross-sectional area 340m2, constructed using cavern-pile method.Chongqing Light Railway No. three line red flag streams station Type B section, excavation width 23.753m, height 32.316m, cross-sectional area 730m2, most for Asia The Urban Underground Station of big cross section, using the constructing tunnel new method of reserved cross rock beam rock pillar.
Summary of the invention
In view of this, it is an object of the invention to propose that a kind of extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar Construction takes reserved T word rock beam rock pillar, and structural-load-carrying capacity is strong, can effectively control surrouding rock stress, the sedimentation of tunnel arch Amount and two helps deflection, protects above ground structure, ensures construction safety.
The purpose of the present invention is what is be achieved through the following technical solutions:
A kind of reserved T word rock beam rock pillar construction of extra-large cross-section resistant Capacity of Shallow-buried Subway Station, comprising the following steps:
1) left side of excavation project section and right side rock mass make engineering section form reserved T shape rock beam rock pillar, excavate and are formed Double-hole tunnel side wall using anchor cable add grouted anchor bar carry out combined supporting;
2) the side wall construction waterproof of the combined supporting in step 1), I-steel and two lining structures are further reinforced, and returned The building stones that banket will be filled up at excavation, are compacted, in compacting surface construction C20 plain concrete;
3) the T shape two side areas of T shape rock beam rock pillar is excavated, the two sides side wall at excavation takes grouted anchor bar supporting to add Gu;
4) section gap excavates the T shape top area of T shape rock beam rock pillar, and the vault in subway station takes grouted anchor bar branch Shield is reinforced, and is further reinforced to T shape two sidewalls and vault construction waterproof, I-steel and two lining structures;
5) the T shape central region of T shape rock beam rock pillar is excavated, and clears out backfill earth and stone material;
6) waterproof of construction work bottom, I-steel and two lining structures.
Further, it in step 2), backfills earth and stone material and takes Spaced to construct with C20 plain concrete.
The beneficial effects of the present invention are:
The present invention proposes the scheme of reserved T shape rock beam rock pillar, T shape knot for extra-large cross-section resistant Capacity of Shallow-buried Subway Station engineering Structure bearing capacity is strong, can effectively control engineering surrounding rock stress, arch settling amount and two helps deflection, keeps work progress safer With it is reliable, meanwhile, take backfill earth and stone material and section gap mode can increase the stability of engineering structure, deformation controlling for rock surrounding gateways Amount, further ensures that the safety of construction and the reliability of quality.
Other advantages, target and feature of the invention will be illustrated in the following description to a certain extent, and And to a certain extent, based on will be apparent to those skilled in the art to investigating hereafter, Huo Zheke To be instructed from the practice of the present invention.Target of the invention and other advantages can be realized by following specification and It obtains.
Detailed description of the invention
To make the objectives, technical solutions, and advantages of the present invention clearer, below in conjunction with attached drawing to the present invention make into The detailed description of one step, in which:
Fig. 1 is the working procedure figure of invention;
Fig. 2 is section gap working procedure figure.
Specific embodiment
Hereinafter reference will be made to the drawings, and a preferred embodiment of the present invention will be described in detail.It should be appreciated that preferred embodiment Only for illustrating the present invention, rather than limiting the scope of protection of the present invention.
Fig. 1 is working procedure figure of the invention, and Fig. 2 is section gap working procedure figure, is made by taking metro station as an example detailed It describes in detail bright:
Metro station is 15 meters of an island platform Stations of F3/B3, using drill bursting construction, composite lining.Ground Next layer be station hall layer, two floor of underground be No. four line station layers, F3/B3 be No. nine line station layers, station overall length 237m, Main body excavation width 26.4m, height 28.21m, cross-sectional area 667m2, belong to Super-large-section tunnel.Tunnel surrounding is chiltern mud Rock and sandstone, medium weathering, fender graded are mainly IV grade, and Local topography is V grade.Station buried depth is shallower, and upper overlying strata soil layer is thick Spend about 20m~32.4m, wherein on cover plain fill thickness about 1.2~17.0m, tunnel top medium weathering basement rock thickness is about 9.2~ 26.7m。
Before construction, piecemeal is carried out with width about 6-10m, high about 3-6m to the section at the station, after division comprising 1-13 Block, as shown in Figure 1, its working procedure is as follows:
1) the 1st, 2,3,4 piece of rock mass of tunneling arranged on left and right sides, tunnel cross section form reserved T word rock beam rock pillar, tunnel Wall carries out combined supporting using grouted anchor bar I, anchor cable II;
2) rock mass has been excavated to the 1st, 2,3,4 piece of left and right side and has carried out four backfills, specifically included:
1. construct the 1st, 2,3,4 piece of rock mass waterproof, III II of I-steel and two lining structures IV, inverted arch backfill soil-rock mixture, And be compacted, backfill height is the 4th piece of rock mass absolute altitude, backfill level construction C20 plain concrete;
2. the 3rd piece of soil-rock mixture of backfill, and be compacted, backfill height is the 3rd piece of rock mass absolute altitude, backfill level construction C20 Plain concrete;
3. the 2nd piece of soil-rock mixture of backfill, and be compacted, backfill height is the 2nd piece of rock mass absolute altitude, backfill level construction C20 Plain concrete;
4. the 1st piece of soil-rock mixture of backfill, and be compacted, backfill height is the 1st piece of rock mass absolute altitude, backfill level construction C20 Plain concrete;
3) the 5th, 6 piece of rock mass is excavated, gib is made, tunnel arch uses grouted anchor bar I supporting;
4) excavate the 7th piece of rock mass, step 7 using section gap construction, make preliminary bracing, apply 5,6,7 pieces of rock mass waterproofs, I-steel III and two lining structure IV;
5) the 8th, 9 piece of rock mass is excavated;
6) the 10th, 11,12,13 piece of rock mass is excavated, and clears out backfill body;
7) construction tunnel bottom waterproof, I-steel III and two lining structure IV.
When constructing to the 7th piece of rock mass, the 7th piece of rock mass can be divided into multiple regions by top view, as shown in Fig. 2, being divided into A, tri- pieces of b, c, section gap construct when, can first to serial number a construct, after to serial number b construct, finally again to serial number c construct, and Before subsequent region construction, construction area is subjected to I-steel III and two lining structure IV and is reinforced, the support energy of structure is improved The safety of power and construction.
The present invention proposes the construction of reserved T shape rock beam rock pillar, T for extra-large cross-section resistant Capacity of Shallow-buried Subway Station engineering Shape structure bearing capacity is strong, can effectively control engineering surrounding rock stress, arch settling amount and two helps deflection, makes work progress more It is safe and reliable, meanwhile, take backfill earth and stone material and section gap mode that can increase the stability of engineering structure, control country rock change Shape amount further ensures that the safety of construction and the reliability of quality.
Generally speaking, the present invention adapts to extra-large cross-section resistant Capacity of Shallow-buried Subway Station or constructing tunnel, can effectively control country rock and answer Power, tunnel arch settling amount and two help deflection, protect above ground structure, ensure construction safety.
Finally, it is stated that the above examples are only used to illustrate the technical scheme of the present invention and are not limiting, although referring to compared with Good embodiment describes the invention in detail, those skilled in the art should understand that, it can be to skill of the invention Art scheme is modified or replaced equivalently, and without departing from the objective and range of the technical program, should all be covered in the present invention Scope of the claims in.

Claims (1)

1. a kind of extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction, it is characterised in that: including following step It is rapid:
1) left side of excavation project section and right side rock mass make engineering section form reserved T shape rock beam rock pillar, excavate the double of formation Hole tunnel side wall adds grouted anchor bar to carry out combined supporting using anchor cable;
2) the side wall construction waterproof of the combined supporting in step 1), I-steel and two lining structures are further reinforced, and backfill Building stones will be filled up at excavation, are compacted, and take the mode of Spaced to construct C20 plain concrete in compacting surface;
3) the T shape two side areas of T shape rock beam rock pillar is excavated, the two sides side wall at excavation takes grouted anchor bar support reinforcement;
4) section gap excavates the T shape top area of T shape rock beam rock pillar, and the vault in subway station takes grouted anchor bar supporting to add Gu further being reinforced to T shape two sidewalls and vault construction waterproof, I-steel and two lining structures;
5) the T shape central region of T shape rock beam rock pillar is excavated, and clears out backfill earth and stone material;
6) waterproof of construction work bottom, I-steel and two lining structures.
CN201610937859.4A 2016-10-25 2016-10-25 Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction Active CN106499417B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610937859.4A CN106499417B (en) 2016-10-25 2016-10-25 Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610937859.4A CN106499417B (en) 2016-10-25 2016-10-25 Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction

Publications (2)

Publication Number Publication Date
CN106499417A CN106499417A (en) 2017-03-15
CN106499417B true CN106499417B (en) 2019-01-08

Family

ID=58319114

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610937859.4A Active CN106499417B (en) 2016-10-25 2016-10-25 Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction

Country Status (1)

Country Link
CN (1) CN106499417B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107461201B (en) * 2017-09-30 2019-06-25 中铁二局集团有限公司 The construction method of the damping protection system of hard rock subway station in a kind of middle hole method Blasting Excavation
CN108170988B (en) * 2018-01-23 2021-01-01 成都希盟泰克科技发展有限公司 Three-step seven-step method for tunnel excavation based on BIM technology
CN110924985A (en) * 2019-12-04 2020-03-27 中铁二院贵阳勘察设计研究院有限责任公司 Long rock pillar construction method suitable for overlying thin rock stratum
CN110939472A (en) * 2019-12-24 2020-03-31 中矿金业股份有限公司 Construction method of large-section ultrahigh chamber
CN116480392B (en) * 2023-06-21 2023-09-29 矿冶科技集团有限公司 Rock column reinforcing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006322222A (en) * 2005-05-19 2006-11-30 Metropolitan Expressway Public Corp Construction method of large-sectional tunnel
CN101566064A (en) * 2009-06-01 2009-10-28 中国建筑第八工程局有限公司 Large-section tunnel construction method
CN101858220A (en) * 2010-05-28 2010-10-13 深圳市建设(集团)有限公司 Tunnel double upper sidewall heading construction method
CN102562076A (en) * 2011-12-23 2012-07-11 中铁十九局集团第五工程有限公司 Underground excavation construction technology for large cross-section subway station under geological condition of soft upper layer and hard lower layer
CN104763435A (en) * 2015-03-02 2015-07-08 中国建筑第八工程局有限公司 Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area
CN104847362A (en) * 2015-01-29 2015-08-19 中铁二院工程集团有限责任公司 Large-span subway station underground excavation construction method for hard rock stratum
CN105804760A (en) * 2016-05-17 2016-07-27 中铁十五局集团有限公司 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006322222A (en) * 2005-05-19 2006-11-30 Metropolitan Expressway Public Corp Construction method of large-sectional tunnel
CN101566064A (en) * 2009-06-01 2009-10-28 中国建筑第八工程局有限公司 Large-section tunnel construction method
CN101858220A (en) * 2010-05-28 2010-10-13 深圳市建设(集团)有限公司 Tunnel double upper sidewall heading construction method
CN102562076A (en) * 2011-12-23 2012-07-11 中铁十九局集团第五工程有限公司 Underground excavation construction technology for large cross-section subway station under geological condition of soft upper layer and hard lower layer
CN104847362A (en) * 2015-01-29 2015-08-19 中铁二院工程集团有限责任公司 Large-span subway station underground excavation construction method for hard rock stratum
CN104763435A (en) * 2015-03-02 2015-07-08 中国建筑第八工程局有限公司 Construction method of shallow-buried excavation type large cross section of tunnel in tail slag filling area
CN105804760A (en) * 2016-05-17 2016-07-27 中铁十五局集团有限公司 Super-large section tunnel drilling and blasting method in-situ expansion construction structure and construction method

Also Published As

Publication number Publication date
CN106499417A (en) 2017-03-15

Similar Documents

Publication Publication Date Title
CN106499417B (en) Extra-large cross-section resistant Capacity of Shallow-buried Subway Station reserves T word rock beam rock pillar construction
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN106337686B (en) Three layers of subway station canopy structure of rocky stratum tunneling and construction method
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN106703828B (en) The construction method of subway station is built using prefabricated assembled lining cutting combination PBA
CN105888703B (en) Super Shallow Covered Metro Station construction method under lateral canopy lid is performed in micro- pilot tunnel
CN102296961B (en) Karst tunnel large-scale cavern processing method
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN106014449B (en) The construction method of two-wire small interval big cross section jointed rock mass subway tunnel
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN102606167A (en) Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN105626083A (en) Construction method for permeable ribbed multiple-arch tunnel
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN111206944B (en) Construction method for differential settlement control of pre-supporting excavation of deformation joint of underpass subway station
CN207063982U (en) Mechanical assistance sealing Station structure in a kind of pilot tunnel
CN102287194B (en) Construction method of multi-span gently arc tunnel
CN107288642A (en) PBA construction technologies
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN105909263A (en) Eolian sand stratum highway tunnel structure and construction method thereof
CN102606168A (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN109458185A (en) Overlapping crossing parallel tunneling shield construction method up and down
CN109555527A (en) A kind of five lines small spacing Shallow tunnel with large cross-section group construction method parallel
CN206888990U (en) A kind of Shallow Covered Metro Station separates open type structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Huang Xuejun

Inventor after: Guo Yushan

Inventor after: Wu Xiangkun

Inventor after: Jiang Yongdong

Inventor after: Mi Wei

Inventor after: Liu Hui

Inventor after: Tang Haofeng

Inventor after: Yin Lida

Inventor after: Han Jiankun

Inventor after: Gong Xuejun

Inventor after: Dai Runjun

Inventor after: Wang Meng

Inventor after: Wang Xinyi

Inventor after: Chen Zhanglin

Inventor before: Huang Xuejun

Inventor before: Liu Hui

Inventor before: Tang Haofeng

Inventor before: Han Jiankun

Inventor before: Gong Xuejun

Inventor before: Dai Runjun

Inventor before: Wang Xinyi

Inventor before: Chen Zhanglin

Inventor before: Jiang Yongdong

Inventor before: Mi Wei

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20171030

Address after: 050000 south side of Xueyuan Road street, Yanjiao Development Zone, Shijiazhuang, Hebei, Sanhe

Applicant after: Erchu Co., Ltd. of China Railway Tunnel Group

Applicant after: Woods is with Im international construction consulting (China) Co., Ltd

Applicant after: Chongqing Zhongche Construction Engineering Co. Ltd.

Address before: South side of Xueyuan Road street, Yanjiao Development Zone, Shijiazhuang, Hebei, China

Applicant before: Erchu Co., Ltd. of China Railway Tunnel Group

Applicant before: Woods is with Im international construction consulting (China) Co., Ltd

Applicant before: Chongqing University

GR01 Patent grant
GR01 Patent grant