CN106446349B - A kind of calculation method of the earthwork original place amortization based on revit software - Google Patents

A kind of calculation method of the earthwork original place amortization based on revit software Download PDF

Info

Publication number
CN106446349B
CN106446349B CN201610787997.9A CN201610787997A CN106446349B CN 106446349 B CN106446349 B CN 106446349B CN 201610787997 A CN201610787997 A CN 201610787997A CN 106446349 B CN106446349 B CN 106446349B
Authority
CN
China
Prior art keywords
cross
landform
model
earthwork
cad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610787997.9A
Other languages
Chinese (zh)
Other versions
CN106446349A (en
Inventor
韩刚平
余红玲
李娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201610787997.9A priority Critical patent/CN106446349B/en
Publication of CN106446349A publication Critical patent/CN106446349A/en
Application granted granted Critical
Publication of CN106446349B publication Critical patent/CN106446349B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The calculation method for the earthwork original place amortization based on revit software that the invention discloses a kind of establishes initial land form model and design relief model by construction site initial land form CAD cross-sectional view, design landform CAD cross-sectional view and revit software.Earthwork excavated volume is calculated by two model volume differences, then landform fine tuning is carried out using the non-construction area to design landform, to achieve the purpose that earthwork balance and amortize on the spot.Whole process can be completed only in software, have preferable Three-dimensional visualizations by the model that software is established, can intuitively check the reasonability of earthwork balance and the new landform formed after amortization on the spot, this method is applicable in various types of topographic features, without limitations.Model the etc. in addition, relief model established can be also used for establishing Ground arrangement model, square is mated formation model, template is led the way, it is applied widely.

Description

A kind of calculation method of the earthwork original place amortization based on revit software
Technical field
It is amortized the present invention relates to construction project management technology more particularly to a kind of earthwork original place based on revit software Calculation method.
Background technique
Construction site earth excavation and backfill amount are efficiently calculated, creation is reasonable new on the basis of the earthwork zero is transported outward Landform is to speed up duration, save the cost, the good solution for avoiding spoir place difficulty from looking for.The earthwork of construction site is opened at present It digs, backfill amount is all manually to carry out "ball-park" estimate using original site elevation and designed elevation.More accurately calculation method It is the contour using software collection initial land form, dividing field zones is carried out to initial land form, arrangement grid calculates again;Or According to engineering experience and specification etc., reasonable side slope is selected than, the earthwork characteristic parameter in determination unit region etc., is constructed corresponding Computation model determines desired technical parameter and then optimizes calculating using software.These methods, respectively there is superiority and inferiority.Manually Rough calculation, data have the property of can refer to, but result and unreliable, also labor intensive;It is accurate to calculate, although as a result reliable, But the inevitable very complicated of calculation method, operability is not strong, does not also have visuality.This method is easy to operate, and principle is understandable, As a result reliable, calculate efficiently and have visuality, can require to optimize change according to site environment at any time, application compared with Height is worthy to be popularized.
Summary of the invention
The technical problem to be solved in the present invention is that for the defects in the prior art, providing a kind of based on revit software The earthwork original place amortization calculation method.
The technical solution adopted by the present invention to solve the technical problems is: a kind of earthwork original place booth based on revit software The calculation method of pin, comprising the following steps:
1) it is reconnoitred according to in-site measurement, draws the initial land form Cross Section CAD figure for obtaining construction site;It is specific as follows: to look into It sees design drawing, finds out within the scope of construction red line, excavate innermost absolute altitude;According to required precision, along longitudinal direction to construction area It is divided, draws an initial land form Cross Section CAD figure every 5m to 10m, draw the initial land form for obtaining construction site Cross Section CAD figure;
2) initial land form Cross Section CAD figure is divided into single cross-sectional view, it is newly-built adaptive public by revit software Each CAD cross-sectional view is successively imported revit software by conventional model processed;The list that initial land form Cross Section CAD figure is divided into A cross-sectional view is regular figure;
3) cross-sectional outling is drawn according to CAD base map with model line, and saves as cross-sectional outling race;
4) metric system scale of construction race is created inside revit, ready-made profile race is loaded into the scale of construction, creates shape, is obtained former The model of beginning landform obtains the volume of initial land form;
5) the Cross Section CAD figure for designing landform is imported into revit software, establishes corresponding design relief model, obtains and set Count the volume of landform;
6) it by initial land form bulking value and design landform bulking value, directly calculates initial land form and designs the body of landform Product moment obtains extra earth volume;
7) the region landform area of pictural surface is amortized by extra earth volume and the earthwork on the spot, the landform after calculating amortization is high Journey.
The beneficial effect comprise that:
The calculation method of earthwork original place amortization of the present invention is solved looks in spoir place difficulty, and haul distance is too far, and construction period is tight It is how simple, quick under equal restrictive conditions, accurately calculate construction site earthwork excavated volume and backfill amount and establish new landform, examine Test the rational problem of newly-built landform.This method principle is simple, and required manpower and material resources are smaller, can effectively save the time, mention High computational accuracy has preferable Three-dimensional visualizations for the new landform of foundation.This method is also applied for earthwork balance, optimization place In landform, optimization field the problems such as transportation route, it is suitable for each intermediate item.
Detailed description of the invention
Present invention will be further explained below with reference to the attached drawings and examples, in attached drawing:
Fig. 1 is the method flow diagram of the embodiment of the present invention;
Fig. 2 is the initial land form schematic cross-sectional view of the embodiment of the present invention;
Fig. 3 is treated initial land form schematic cross-sectional view of the embodiment of the present invention.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, is not used to limit The fixed present invention.
As shown in Figure 1, a kind of calculation method of the earthwork original place amortization based on revit software, comprising the following steps:
1) it is reconnoitred according to in-site measurement, draws the initial land form Cross Section CAD figure for obtaining construction site, as shown in Figure 2;Tool Body is as follows: checking design drawing, finds out within the scope of construction red line, excavate innermost absolute altitude h, since place bottom absolute altitude is infinite It is small, for convenience of calculating and result data, it is assumed that place bottom absolute altitude is (h-5);According to required precision, along longitudinal direction to construction area It is divided, draws an initial land form Cross Section CAD figure every 5m to 10m, draw the initial land form for obtaining construction site Cross Section CAD figure;As shown in Figure 3;
2) initial land form Cross Section CAD figure is divided into single cross-sectional view, it is newly-built adaptive public by revit software Each CAD cross-sectional view is successively imported revit software by conventional model processed;Initial land form Cross Section CAD figure is divided into individually Cross-sectional view be regular figure (Si1To Sim);As shown in Figure 3;
3) to each CAD cross-sectional view for importing revit software in step 2), cross is drawn according to CAD base map with model line Profiled outline, and save as cross-sectional outling race;
4) metric system scale of construction race is created inside revit, ready-made profile race is loaded into the scale of construction, creates shape, is obtained former The model of beginning landform obtains the volume of initial land form;Using integral principle, each cross-sectional outling race is respectively influenced longitudinal Integral in range, final result is cumulative, can be obtained the volume of entire relief model;
5) the Cross Section CAD figure for designing landform is imported into revit software, establishes corresponding design relief model, obtains and set Count the volume of landform;
6) it by initial land form bulking value and design landform bulking value, directly calculates initial land form and designs the body of landform Product moment obtains extra earth volume;
7) the region landform area of pictural surface is amortized by extra earth volume and the earthwork on the spot, the landform after calculating amortization is high Journey.
Pass through formula V=S*H=VIt is former-VIf, the height H for non-construction area backfill that you can get it, wherein S is the earthwork with regard to stall with goods spread out on the ground for sale The area in which the goods are in great demand domain landform area of pictural surface.
The calculation method of earthwork original place amortization based on revit software of the invention, passes through construction site initial land form CAD Cross-sectional view, design landform CAD cross-sectional view and revit software establish initial land form model and design relief model.By two A model volume differences calculate earthwork excavated volume, then landform fine tuning are carried out using the non-construction area to design landform, to reach The purpose amortized to earthwork balance and on the spot.Whole process can be completed only in software, by software establish model have compared with Good Three-dimensional visualizations can intuitively check the reasonability of earthwork balance and the new landform formed after amortization on the spot, the party Method is applicable in various types of topographic features, without limitations.In addition, the relief model established can be also used for establishing Ground arrangement mould Mat formation model, template of type, square is led the way model etc., applied widely.
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (1)

1. a kind of calculation method of the earthwork original place amortization based on revit software, which comprises the following steps:
1) it is reconnoitred according to in-site measurement, draws the initial land form Cross Section CAD figure for obtaining construction site;It is specific as follows: to check and set Drawing is counted, finds out within the scope of construction red line, excavates innermost absolute altitude;According to required precision, construction area is carried out along longitudinal direction It divides, draws an initial land form Cross Section CAD figure every 5m to 10m, the initial land form for drawing acquisition construction site is cross-section Face CAD diagram;
2) initial land form Cross Section CAD figure is divided into single cross-sectional view, it is normal to create adaptive metric system by revit software Each CAD cross-sectional view is successively imported revit software by scale;The list that initial land form Cross Section CAD figure is divided into A cross-sectional view is regular figure;
3) cross-sectional outling is drawn according to CAD base map with model line, and saves as cross-sectional outling race;
4) metric system scale of construction race is created inside revit, ready-made profile race is loaded into scale of construction race, creates shape, is obtained original The model of landform obtains the volume of initial land form;
5) the Cross Section CAD figure for designing landform is imported into revit software, establishes corresponding design relief model, obtain design ground The volume of shape;
6) it by initial land form bulking value and design landform bulking value, directly calculates initial land form and designs the volume of landform Difference obtains extra earth volume;
7) the region landform area of pictural surface is amortized by extra earth volume and the earthwork on the spot, the landform altitude after calculating amortization.
CN201610787997.9A 2016-08-31 2016-08-31 A kind of calculation method of the earthwork original place amortization based on revit software Active CN106446349B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610787997.9A CN106446349B (en) 2016-08-31 2016-08-31 A kind of calculation method of the earthwork original place amortization based on revit software

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610787997.9A CN106446349B (en) 2016-08-31 2016-08-31 A kind of calculation method of the earthwork original place amortization based on revit software

Publications (2)

Publication Number Publication Date
CN106446349A CN106446349A (en) 2017-02-22
CN106446349B true CN106446349B (en) 2019-10-18

Family

ID=58165283

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610787997.9A Active CN106446349B (en) 2016-08-31 2016-08-31 A kind of calculation method of the earthwork original place amortization based on revit software

Country Status (1)

Country Link
CN (1) CN106446349B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107066758B (en) * 2017-05-11 2020-09-29 中国十七冶集团有限公司 Outdoor construction method based on unmanned aerial vehicle photography technology and BIM technology
CN107330140A (en) * 2017-05-19 2017-11-07 河北省电力勘测设计研究院 The method that transformer station is quickly vertically arranged is realized based on BIM technology
CN107392348A (en) * 2017-05-31 2017-11-24 上海市政建设有限公司 The method optimized using BIM technology to cut-fill transition scheme
CN107679337A (en) * 2017-10-20 2018-02-09 浙江煤炭测绘院 A kind of method that irregular earthwork calculates in engineering survey
CN108038269B (en) * 2017-11-19 2021-06-01 上海二十冶建设有限公司 Mountain building group earth-rock square balance blending method based on BIM
CN108121853B (en) * 2017-11-29 2021-03-26 吴先富 System and method for calculating excavation and filling engineering quantity based on AutoCAD
CN108204003B (en) * 2018-02-07 2023-05-05 广州市昊力工具有限公司 Ship with travelling step pile assembly
CN108959824B (en) * 2018-08-06 2020-10-02 上海营邑城市规划设计股份有限公司 BIM design section layer layering generation method for Ying Yi planning pipeline
CN110119596B (en) * 2019-07-05 2019-11-05 广州优比建筑咨询有限公司 A kind of place editing system based on Revit
CN111765867A (en) * 2020-06-12 2020-10-13 中国二十冶集团有限公司 Road effective earth volume calculation method based on oblique photography technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103392192A (en) * 2011-02-28 2013-11-13 莱卡地球系统公开股份有限公司 An integrated terrain modelling system
CN104966154A (en) * 2015-06-09 2015-10-07 广州市水电设备安装有限公司 BIM technology-based temporary water and temporary electricity management method and system
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model
CN105718481A (en) * 2014-12-05 2016-06-29 星际空间(天津)科技发展有限公司 Massive topographic data organization and release method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9189571B2 (en) * 2011-06-11 2015-11-17 Ice Edge Business Solutions, Ltd. Automated re-use of structural components

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103392192A (en) * 2011-02-28 2013-11-13 莱卡地球系统公开股份有限公司 An integrated terrain modelling system
CN105718481A (en) * 2014-12-05 2016-06-29 星际空间(天津)科技发展有限公司 Massive topographic data organization and release method
CN104966154A (en) * 2015-06-09 2015-10-07 广州市水电设备安装有限公司 BIM technology-based temporary water and temporary electricity management method and system
CN105005676A (en) * 2015-08-13 2015-10-28 国网上海市电力公司 Three-dimension design method based on cable engineering information model

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
三维总图设计理论及其应用研究;张圆;《中国优秀硕士学位论文全文数据库》;20091231;全文 *

Also Published As

Publication number Publication date
CN106446349A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106446349B (en) A kind of calculation method of the earthwork original place amortization based on revit software
CN100478996C (en) Three dimension uniform model construction method of water conservancy hydropower engineering geological information
CN108875177B (en) Method for creating inland waterway dredging graph under single beam measuring point based on BIM model
CN110276732B (en) Mountain area point cloud cavity repairing method considering topographic characteristic line elements
CN103806478A (en) Method for measuring deformation of underground diaphragm wall
CN102879820B (en) Based on the three-dimensional table layer model construction method of triangle gridding
CN110929320B (en) Method for calculating construction amount of channel dredging engineering based on Skyline software
CN105118091B (en) A kind of method and system constructing the non-homogeneous geology mesh surface model of more precision
CN111681316B (en) High-precision river terrain interpolation method
CN112100715A (en) Three-dimensional oblique photography technology-based earthwork optimization method and system
CN106934092A (en) The modeling method of the high speed railway prefabricating Liang Chang based on BIM
CN113256809A (en) Engineering earth volume calculation method of seabed immersed tube tunnel foundation trench based on BIM
CN110210135A (en) A kind of slope project entire area quality evaluation technology
CN112395794B (en) Automatic parameterized slope model construction method based on subdivision technology
CN106909740A (en) The computational methods and computing device of a kind of Oil & Gas Storage yard total figure volume of earthwork
CN107391778B (en) A kind of Analytic Calculation Method of circular tunnel seepage discharge
CN113946980B (en) Step earth and stone volume calculation method and system for large strip mine excavation engineering
CN108804780A (en) A kind of method of three dimensional analysis pile-base supporting layer
CN103422463B (en) Step navigation hinge physical model Mathematical Modeling integration test method
CN101303770B (en) Method for constructing triangle gridding as well as application thereof for geotechnical engineer modeling
KR102130922B1 (en) 3D Solid Cut / Fill Terrain and Corridor Structure Objects by Station by Automatic Extraction of Station and Object Information by Location of 3D Surface Terrain and Corridor Structures Automatic conversion and quantity automatic generation system and method
CN106920275A (en) A kind of complex properties border trivector alternative manner and application system
CN113653085B (en) Engineering pile length estimation method and estimation system thereof
CN116226970A (en) Method for establishing slope BIM model based on 3DEXPERIENCE platform
CN110287559B (en) Multi-dimensional information model-based earth stock ground mining planning method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant